CN213013938U - Bridge erects with supplementary interfacing apparatus convenient to align - Google Patents

Bridge erects with supplementary interfacing apparatus convenient to align Download PDF

Info

Publication number
CN213013938U
CN213013938U CN202021095027.0U CN202021095027U CN213013938U CN 213013938 U CN213013938 U CN 213013938U CN 202021095027 U CN202021095027 U CN 202021095027U CN 213013938 U CN213013938 U CN 213013938U
Authority
CN
China
Prior art keywords
butt joint
plate
bridge body
bridge
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021095027.0U
Other languages
Chinese (zh)
Inventor
秦先文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Wuqiao Bridge Steel Structure Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021095027.0U priority Critical patent/CN213013938U/en
Application granted granted Critical
Publication of CN213013938U publication Critical patent/CN213013938U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a bridge erects with supplementary interfacing apparatus convenient to align, includes fixed pontic, removes pontic, first butt joint board, second butt joint board and locating plate, fixed pontic lower extreme is connected with the pontic stopper, and the pontic stopper installs the upper end at fixed pier, remove pontic lower extreme and the pontic stopper and laminate each other, and remove the pontic and laminate each other with fixed pontic to remove pontic and bearing wire rope interconnect, first butt joint board and fixed pontic laminate each other, and first butt joint board internal surface mounting has electric telescopic handle, second butt joint board and the laminating each other of removal pontic, and second butt joint board internal surface mounting has electric telescopic handle. This bridge erects with supplementary interfacing apparatus convenient to align realizes laminating fixedly the position of first butt joint board and second butt joint board through electric telescopic handle to be convenient for follow-up splice, can realize restricting the position of bridge through first butt joint board and connecting plate.

Description

Bridge erects with supplementary interfacing apparatus convenient to align
Technical Field
The utility model relates to a bridge erects technical field, specifically is a bridge erects and uses supplementary interfacing apparatus convenient to align.
Background
The bridge erection generally refers to the construction of structures through which vehicles and pedestrians normally pass on rivers, lakes and seas, so that convenience is brought to the life of people.
But also have some problems when splicing the bridge, for example, when will remove the pontic and splice to fixed pontic, the condition that very easily appears rocking to cause the influence to the concatenation effect, in case the error is great, will need splice once more, very waste time and energy.
SUMMERY OF THE UTILITY MODEL
The utility model aims at: the utility model provides a bridge erects and uses supplementary interfacing apparatus convenient to align to easy the appearance rocks when proposing the concatenation in solving above-mentioned background art, the great problem that will need the concatenation once more of error.
The technical scheme of the utility model is that: an auxiliary butt joint device convenient for alignment for bridge erection comprises a fixed bridge body, a movable bridge body, a first butt joint plate, a second butt joint plate and a positioning plate, wherein the lower end of the fixed bridge body is connected with a bridge body limiting block, the bridge body limiting block is arranged at the upper end of the fixed bridge pier, the fixed bridge pier and the fixed bridge body are mutually attached, the lower end of the movable bridge body and the bridge body limiting block are mutually attached, the movable bridge body and the fixed bridge body are mutually attached, the movable bridge body and a bearing steel wire rope are mutually connected, a butt joint rod is arranged on the movable bridge body at the same time, the first butt joint plate and the fixed bridge body are mutually attached, an electric telescopic rod is arranged on the inner surface of the first butt joint plate, a fixing device is arranged at the lower end of the electric telescopic rod, the fixing device and the fixed bridge body are mutually attached, the second butt joint plate and the, and the connecting plate is installed to second butt joint board lower extreme, has seted up the block hole on the connecting plate simultaneously, the locating plate laminates with first butt joint board each other, and first butt joint board laminates with the connecting plate each other to install positioning spring on the first butt joint board, positioning spring and locating plate interconnect simultaneously.
Preferably, the bridge limiting block is arranged to be a square block structure, and the bridge limiting block is connected with the fixed bridge body through a long strip-shaped groove formed in the lower end of the fixed bridge body.
Preferably, the first butt plate is symmetrically distributed about the center of the fixed bridge body, and the inner surface of the first butt plate is smooth.
Preferably, the fixing device comprises a joint plate and a movable sliding block, the lower end of the fixing device is connected with the joint plate, the movable sliding block is mounted on the fixing device, and the movable sliding block is jointed with the first joint plate.
Preferably, the attaching plate is made of rubber, and the attaching plate is connected with the first attaching plate in a sliding mode through the movable sliding block.
Preferably, the outer surface of the positioning plate is smooth, and one end of the positioning plate is triangular.
Compared with the prior art, the beneficial effects of the utility model are that: according to the auxiliary butt joint device for bridge erection, the positions of the first butt joint plate and the second butt joint plate are jointed and fixed through the electric telescopic rod, so that subsequent splicing is facilitated, and the position of a bridge can be limited through the first butt joint plate and the connecting plate;
1. the electric telescopic rod starts to work, so that the attaching plate moves downwards, namely the attaching plate and the fixed bridge body are attached to each other, and the friction force between the attaching plate and the fixed bridge body is large at the moment, so that the position of the first attaching plate can be fixed;
2. through connecting plate downstream, set up the effect of recess on first butt joint board under, realize leading the direction of motion of connecting plate to restrict the range of motion of second butt joint board through the locating plate, thereby realize assisting the concatenation process.
Drawings
FIG. 1 is a schematic view of a main sectional structure of a mobile bridge according to the present invention;
FIG. 2 is a schematic view of the cross-sectional structure of the fixed bridge and the movable bridge in the same horizontal plane;
FIG. 3 is a schematic view of the top view cross-sectional structure of the movable bridge of the present invention;
fig. 4 is a schematic side view, sectional structure view of the first butt plate of the present invention;
fig. 5 is an enlarged schematic view of a portion a in fig. 1 according to the present invention.
In the figure: 1. fixing the bridge body; 2. a bridge body limiting block; 3. fixing a bridge pier; 4. moving the bridge body; 5. a load-bearing wire rope; 6. a first butt plate; 7. an electric telescopic rod; 8. a fixing device; 801. attaching a plate; 802. moving the slide block; 9. a second butt joint plate; 10. a connecting plate; 11. clamping the hole; 12. positioning a plate; 13. a positioning spring; 14. a docking rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-5, an auxiliary butt-joint device for bridge erection convenient for alignment comprises a fixed bridge body 1, a bridge body stopper 2, a fixed bridge pier 3, a movable bridge body 4, a bearing steel wire rope 5, a first butt-joint plate 6, an electric telescopic rod 7, a fixing device 8, a joint plate 801, a movable slider 802, a second butt-joint plate 9, a connecting plate 10, a clamping hole 11, a positioning plate 12, a positioning spring 13 and a butt-joint rod 14, wherein the lower end of the fixed bridge body 1 is connected with the bridge body stopper 2, the bridge body stopper 2 is installed at the upper end of the fixed bridge pier 3, the fixed bridge pier 3 is mutually jointed with the fixed bridge body 1, the lower end of the movable bridge body 4 is mutually jointed with the bridge body stopper 2, the movable bridge body 4 is mutually jointed with the fixed bridge body 1, the movable bridge body 4 is mutually jointed with the bearing steel wire rope 5, the butt-joint rod 14 is installed on the movable bridge body 4, the first butt, and 6 internal surface mounting of first butt joint board has electric telescopic handle 7, and fixing device 8 is installed to electric telescopic handle 7 lower extreme, fixing device 8 laminates with fixed pontic 1 each other simultaneously, second butt joint board 9 laminates with removal pontic 4 each other, and 9 internal surface mounting of second butt joint board has electric telescopic handle 7, and connecting plate 10 is installed to 9 lower extremes of second butt joint board, block hole 11 has been seted up on the connecting plate 10 simultaneously, locating plate 12 laminates with first butt joint board 6 each other, and first butt joint board 6 laminates with connecting plate 10 each other, and install positioning spring 13 on the first butt joint board 6, positioning spring 13 and locating plate 12 interconnect simultaneously.
In the embodiment, the bridge body limiting block 2 is arranged to be a square block structure, the bridge body limiting block 2 is connected with the fixed bridge body 1 through a long strip-shaped groove formed in the lower end of the fixed bridge body 1, the bridge body limiting block 2 is arranged to be a square block structure, so that the fixed bridge body 1 and the fixed bridge pier 3 can be limited preliminarily, the bridge body limiting block 2 is connected with the fixed bridge body 1 through a long strip-shaped groove formed in the lower end of the fixed bridge body 1, and the movable bridge body 4 can be moved left and right during splicing conveniently;
the first butt plate 6 is symmetrically distributed about the center of the fixed bridge body 1, the inner surface of the first butt plate 6 is smooth, the first butt plate 6 is symmetrically distributed about the center of the fixed bridge body 1, so that the movement of the fixed bridge body 1 is limited from two ends at the same time, and the inner surface of the first butt plate 6 is smooth, so that the friction force between the first butt plate 6 and the fixed bridge body 1 is reduced;
the fixing device 8 comprises an attaching plate 801 and a movable sliding block 802, the lower end of the fixing device 8 is connected with the attaching plate 801, the movable sliding block 802 is installed on the fixing device 8, and meanwhile, the movable sliding block 802 is attached to the first attaching plate 6, and by means of the structure, the first attaching plate 6 is installed on the fixed bridge body 1 conveniently;
the attachment plate 801 is made of rubber, the attachment plate 801 is in sliding connection with the first butt plate 6 through the movable slider 802, the attachment plate 801 is made of rubber, friction between the attachment plate 801 and the fixed bridge body 1 can be effectively increased, and the attachment plate 801 is in sliding connection with the first butt plate 6 through the movable slider 802, so that the attachment plate 801 can freely move when stressed;
the outer surface of the positioning plate 12 is set to be smooth, one end of the positioning plate 12 is set to be triangular, the outer surface of the positioning plate 12 is set to be smooth, the positioning plate 12 can move left and right conveniently, and one end of the positioning plate 12 is set to be triangular, so that the positioning plate can be attached to the connecting plate 10 conveniently.
When a bridge needs to be spliced, a first butt plate 6 and a second butt plate 9 in fig. 2 are respectively placed on a fixed bridge body 1 and a movable bridge body 4, then an electric telescopic rod 7 in fig. 5 starts to work, because the lower end of the electric telescopic rod 7 is provided with a fixing device 8, the fixing device 8 starts to move downwards under the action of a movable sliding block 802, because the lower end of the fixing device 8 is provided with an attaching plate 801, the attaching plate 801 also starts to move downwards, namely, the attaching plate 801 and the fixed bridge body 1 are attached to each other, so that the first butt plate 6 is installed on the fixed bridge body 1, the process is equal to the process, the second butt plate 9 in fig. 2 is installed on the movable bridge body 4, the bearing steel wire rope 5 in fig. 1 drops the movable bridge body 4, then the movable bridge body 4 moves downwards, and moves downwards along with the movable bridge body 4 in fig. 4, the second butt plate 9 attached and installed on the movable bridge 4 also starts to move downwards, because the lower end of the second butt plate 9 is provided with the connecting plate 10, the connecting plate 10 also starts to move downwards, along with the downward movement of the connecting plate 10, the groove formed on the first butt plate 6 guides the movement direction of the connecting plate 10, then along with the continuous downward movement of the connecting plate 10, the connecting plate 10 starts to be attached to the positioning plate 12 and pushes the positioning plate 12, the positioning spring 13 installed on the positioning plate 12 is stretched and deformed, then under the action of the deformation recovery of the positioning spring 13, the positioning plate 12 recovers to the original position, namely, the positioning plate 12 is attached to the clamping hole 11, the clamping hole 11 is a long strip-shaped groove formed on the connecting plate 10 and then reaches the position in fig. 2, so that the bearing steel wire rope 5 drives the movable bridge 4 to move leftwards, the butt-joint rod 14 on the movable bridge body 4 is mutually attached to the groove formed in the fixed bridge body 1, and then the pouring treatment is carried out on the butt-joint position of rivers and lakes, namely the fixed bridge body 1 and the movable bridge body 4 are spliced.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a bridge erection is with supplementary interfacing apparatus convenient to align, includes fixed pontic (1), removal pontic (4), first butt joint board (6), second butt joint board (9) and locating plate (12), its characterized in that: the lower end of the fixed bridge body (1) is connected with a bridge body limiting block (2), the bridge body limiting block (2) is installed at the upper end of the fixed bridge pier (3), the fixed bridge pier (3) is mutually attached to the fixed bridge body (1), the lower end of the movable bridge body (4) is mutually attached to the bridge body limiting block (2), the movable bridge body (4) is mutually attached to the fixed bridge body (1), the movable bridge body (4) is mutually connected to a bearing steel wire rope (5), a butt joint rod (14) is installed on the movable bridge body (4), the first butt joint plate (6) is mutually attached to the fixed bridge body (1), an electric telescopic rod (7) is installed on the inner surface of the first butt joint plate (6), a fixing device (8) is installed at the lower end of the electric telescopic rod (7), the fixing device (8) is mutually attached to the fixed bridge body (1), the second butt joint plate (9) is mutually attached to the movable bridge body (4), and electric telescopic rod (7) is installed to second butt joint board (9) internal surface to connecting plate (10) are installed to second butt joint board (9) lower extreme, have seted up block hole (11) simultaneously on connecting plate (10), locating plate (12) and first butt joint board (6) are laminated each other, and first butt joint board (6) and connecting plate (10) are laminated each other, and install positioning spring (13) on first butt joint board (6), and positioning spring (13) and locating plate (12) interconnect simultaneously.
2. The auxiliary docking device for bridge erection convenient to align of claim 1, wherein: the bridge body limiting block (2) is arranged to be a square block-shaped structure, and the bridge body limiting block (2) is connected with the fixed bridge body (1) through a long-strip-shaped groove formed in the lower end of the fixed bridge body (1).
3. The auxiliary docking device for bridge erection convenient to align of claim 1, wherein: the first butt plate (6) is symmetrically distributed relative to the center of the fixed bridge body (1), and the inner surface of the first butt plate (6) is smooth.
4. The auxiliary docking device for bridge erection convenient to align of claim 1, wherein: fixing device (8) are including laminating board (801) and removal slider (802), and fixing device (8) lower extreme and laminating board (801) interconnect to install on fixing device (8) and remove slider (802), remove slider (802) and laminate each other with first butt joint board (6) simultaneously.
5. The auxiliary butt joint device for bridge erection convenient to align of claim 4, wherein: the attaching plate (801) is made of rubber, and the attaching plate (801) is connected with the first attaching plate (6) in a sliding mode through the movable sliding block (802).
6. The auxiliary docking device for bridge erection convenient to align of claim 1, wherein: the outer surface of the positioning plate (12) is smooth, and one end of the positioning plate (12) is triangular.
CN202021095027.0U 2020-06-15 2020-06-15 Bridge erects with supplementary interfacing apparatus convenient to align Active CN213013938U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021095027.0U CN213013938U (en) 2020-06-15 2020-06-15 Bridge erects with supplementary interfacing apparatus convenient to align

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021095027.0U CN213013938U (en) 2020-06-15 2020-06-15 Bridge erects with supplementary interfacing apparatus convenient to align

Publications (1)

Publication Number Publication Date
CN213013938U true CN213013938U (en) 2021-04-20

Family

ID=75494614

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021095027.0U Active CN213013938U (en) 2020-06-15 2020-06-15 Bridge erects with supplementary interfacing apparatus convenient to align

Country Status (1)

Country Link
CN (1) CN213013938U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114775455A (en) * 2022-05-20 2022-07-22 安徽省公路桥梁工程有限公司 Integral bridge deck installation construction device and use method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114775455A (en) * 2022-05-20 2022-07-22 安徽省公路桥梁工程有限公司 Integral bridge deck installation construction device and use method thereof

Similar Documents

Publication Publication Date Title
CN213013938U (en) Bridge erects with supplementary interfacing apparatus convenient to align
CN102514976B (en) Laminated cell side surface adhesive tape sticking device
CN113155830A (en) Pier underwater structure detection device and method integrated with self-propelled fixed platform
CN208869949U (en) A kind of bridge installation jacking apparatus based on bridge security performance
CN210002244U (en) bridge anti-seismic support
CN109973793A (en) A kind of comprehensive bridge machinery machine
CN206947448U (en) A kind of battery core is secondary to be pressed into housing apparatus
CN200950470Y (en) Automatic connecting device for mobile power supply sliding wire
KR100465628B1 (en) installation apparatus and method in one united body for prefabrication upper part of bridge using lifting system with push pull mechanism
CN210134356U (en) Bridge displacement adjusting device
CN213267539U (en) Supporting structure for bridge construction
CN213460873U (en) Patrol robot system running on cable
CN211390142U (en) Laminating device of curved surface part
CN112792764A (en) Clamping device
CN113735009A (en) Bridge machine for lifting prefabricated part
CN212779825U (en) Bridge detection device simple to operate
CN220509401U (en) Keyboard cleaning device for computer
CN213867303U (en) Light composite structure bridge
CN219862411U (en) Assembled short T roof beam construction protection device
CN212452277U (en) Vibration damper in splicing construction of highway bridge
CN217176073U (en) Industrial building construction fence
CN203030806U (en) Industrial filter screen strip steel buckle joint manufacture device
CN211547360U (en) Variable cross-section pier climbing and gathering roller device
CN215668964U (en) Bridge anti-seismic device
CN212128815U (en) Quick joint for erecting floating bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230614

Address after: No. 777 Zhuankou Road, Caidian District, Wuhan City, Hubei Province, 430000

Patentee after: Wuhan Wuqiao Bridge Steel Structure Co.,Ltd.

Address before: 1213, Huachen international business center, 399 Lushan Road, Tianyuan District, Zhuzhou City, Hunan Province, 412007

Patentee before: Qin Xianwen