CN212983813U - Preliminary edulcoration clarification plant of sewage - Google Patents

Preliminary edulcoration clarification plant of sewage Download PDF

Info

Publication number
CN212983813U
CN212983813U CN202021480473.3U CN202021480473U CN212983813U CN 212983813 U CN212983813 U CN 212983813U CN 202021480473 U CN202021480473 U CN 202021480473U CN 212983813 U CN212983813 U CN 212983813U
Authority
CN
China
Prior art keywords
sewage
rake teeth
garbage
base
impurity removal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021480473.3U
Other languages
Chinese (zh)
Inventor
马向宇
刘嘉颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Hanwei City Construction Co ltd
Original Assignee
Guangdong Hanwei City Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Hanwei City Construction Co ltd filed Critical Guangdong Hanwei City Construction Co ltd
Priority to CN202021480473.3U priority Critical patent/CN212983813U/en
Application granted granted Critical
Publication of CN212983813U publication Critical patent/CN212983813U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The utility model relates to a sewage treatment field, to the problem of winding rubbish easily on the rake teeth of grid machine among the preliminary edulcoration clarification plant of sewage, a preliminary edulcoration clarification plant of sewage is provided, set up the grid machine on the bilge tank including the slope, the grid machine includes the frame of fixed connection in the bilge tank, install slewing belt in the frame and a plurality of groups of rake teeth on slewing belt, the preliminary edulcoration clarification plant of sewage is still including locating the cleaning assembly under the bilge tank one end is kept away from to the grid machine, cleaning assembly includes first base and locates the flexible member on the first base, it has a plurality of spouts to open on the flexible member, when the rake teeth passes the flexible member, the lateral wall and the rake teeth butt of a plurality of spouts, still be equipped with the garbage collection board under the cleaning assembly, the one end that the flexible member was kept away from to the garbage collection board is equipped. This application has the effect that the rake teeth of grid machine are difficult to the winding rubbish among the preliminary edulcoration clarification plant of messenger's sewage.

Description

Preliminary edulcoration clarification plant of sewage
Technical Field
The application relates to the technical field of sewage purification, in particular to preliminary impurity removal and purification equipment for sewage.
Background
In the process of rapid development of human society, a lot of environmental problems are brought, people often find various pollutions accompanied with the development of science and technology today, the water pollution is the most serious of various pollutions, people pay attention to the problem of sewage treatment along with the continuous aggravation of the water pollution, and the modern sewage treatment technology can be divided into primary treatment, secondary treatment and tertiary treatment according to the treatment degree. Wherein primary treatment mainly gets rid of the solid pollutant who is the suspended state who collects in the sewage tank, and the solid pollutant in the sewage tank is cleared up to the preliminary edulcoration clarification plant of sewage often adopts to the tradition.
The conventional preliminary impurity removal and purification equipment for sewage usually comprises a grating machine placed in a sewage tank and a garbage collection tank for collecting obtained garbage on the grating machine, wherein the grating machine comprises a rack, a rotary rotating belt installed on the rack, rake teeth fixedly connected to the rotary conveying belt, a driving device for driving the rotary conveying belt and the like. The grid machine utilizes drive arrangement drive slewing belt, drives the rake teeth on the slewing belt and salvages the clearance to the rubbish in the sewage tank, utilizes the rake teeth to take out the upward transportation with the solid waste in the sewage, and after reacing the frame top, slewing belt drives the certain angle of rake teeth slope, and rubbish on the rake teeth can fall into the rubbish collecting pit under the effect of gravity.
Aiming at the related technology, as the rake teeth of the grating machine are easy to wind various kinds of garbage in the operation process, when the rake teeth transport the garbage to reach the top end of the rack, the garbage wound on the rake teeth can not be separated from the rake teeth through gravity, and the subsequent garbage cleaning condition of the rake teeth is easily influenced. The inventor believes that the rake teeth of the traditional grating machine are easy to be wound with garbage and cannot be cleaned.
SUMMERY OF THE UTILITY MODEL
In order to reduce the rake teeth of grid machine at clearance solid waste in-process, the condition that is difficult to the clearance on the rake teeth is twined easily to partial rubbish, and this application provides a preliminary edulcoration clarification plant of sewage.
The application provides a pair of preliminary edulcoration clarification plant of sewage adopts following technical scheme:
a primary impurity removal and purification device for sewage comprises a grating machine obliquely arranged on a sewage tank, wherein the grating machine comprises a rack fixedly connected in the sewage tank, a rotary conveyor belt arranged on the rack and a plurality of groups of rake teeth fixedly connected on the rotary conveyor belt, the sewage primary impurity removal and purification equipment also comprises a cleaning component which is arranged right below one end of the grating machine far away from the sewage tank, the cleaning component comprises a first base and a flexible piece arranged on the first base, a plurality of sliding grooves are arranged on the flexible piece, when the rake teeth penetrate through the flexible part, the side walls of the sliding grooves are abutted against the rake teeth, a garbage collecting plate is arranged right below the cleaning component, one side that the garbage collection board is close to ground is connected with the second support, the one end fixed connection that the garbage collection board was kept away from to the second support is in ground, the one end that the flexible piece was kept away from to the garbage collection board is equipped with the garbage collection pond.
Through adopting above-mentioned technical scheme, because contain solid rubbish such as rotten cloth, disposal bag in the sewage, when the rake teeth cleared up, rubbish such as rotten cloth and disposal bag twines easily on the rake teeth, when the rake teeth moves grid machine peak, the rubbish of winding on the rake teeth can't fall through gravity for subsequent rake teeth receives the influence to the clearance effect of the rubbish in the sewage. When the rake teeth which have been cleaned up the garbage pass through the flexible part, the side wall of the chute is abutted against the rake teeth, the solid garbage wound around the rake teeth can be pulled out to the flexible part through the clamping of the flexible part, and the cleaned garbage falls into the garbage collection tank through the garbage collection plate, so that the cleaned rake teeth are not easy to be wound with the garbage, and the condition that the solid garbage in the sewage is cleaned up by the grating machine due to the garbage wound on the rake teeth is favorably reduced; simultaneously, through the setting of flexible piece for clean the subassembly and be difficult to damage the rake teeth when clearing up the rubbish of winding on the rake teeth, be favorable to prolonging the life of rake teeth.
Preferably, the preliminary edulcoration clarification plant of sewage still includes sliding connection in the first support on ground, first support orientation is close to the grid machine and is slided towards the direction of keeping away from the grid machine, first base is located on the first support, the preliminary edulcoration clarification plant of sewage still including locating the subaerial locking Assembly who is used for locking first support.
Through adopting above-mentioned technical scheme, when we need to change the flexible piece, because the flexible piece is located under the grid machine and with the rake teeth looks butt that passes through, operating space is comparatively compact, the change of inconvenient flexible piece, through first support sliding connection in ground for when needs change the flexible piece, slide through the direction that makes first support keep away from the grid machine, thereby make the cleaning assembly keep away from the grid machine, make the space of operatable grow, be favorable to reducing the degree of difficulty of changing the flexible piece.
Preferably, the first support is further provided with a flat nozzle air gun, and an air outlet of the flat nozzle air gun faces to the upper surface of the flexible part.
Through adopting above-mentioned technical scheme, after the flexible piece clearance rake teeth, the rubbish of clearing up can gather on the flexible piece, through the setting of flat mouth air gun for gather the solid rubbish on the flexible piece and can be blown off, thereby be difficult to gather rubbish on making the flexible piece, be favorable to reducing the condition that the flexible piece is clean rake teeth is influenced to the rubbish of gathering on the flexible piece.
Preferably, the garbage collection plate is arranged from one end far away from the garbage collection pool to one end close to the garbage collection pool in an inclined and downward mode, and the width of the garbage collection plate is larger than the length of the flexible member.
Through adopting above-mentioned technical scheme for rubbish that washs and drop on the garbage collection board through the flexible piece can get into the rubbish collecting pit better through gravity, is favorable to reducing the condition that rubbish is piled up on the garbage collection board.
Preferably, the one end that refuse collection pond was kept away from to the refuse collection board still is equipped with the brush, the brush is including locating the second base on the refuse collection board and being fixed in the brush hair on the second base, the one end that the second base was kept away from to the brush hair and the rotary conveyor who keeps away from the bilge sump of grid machine butt.
Through adopting above-mentioned technical scheme, because the flexible piece when the rubbish on the clearance rake teeth, partial rubbish can remain in the spout of flexible piece, and subsequent rake teeth can take the rubbish in the spout out when the flexible piece, through the setting of brush for outside the rubbish that is taken out through the rake teeth is difficult to fall out the garbage collection board, be favorable to reducing the rubbish that the rake teeth was beaten and fall out the garbage collection board and lead to the secondary pollution's the condition outward.
Preferably, the two sides of the garbage collecting plate along the width direction are integrally connected with a baffle.
Through adopting above-mentioned technical scheme, through the setting of baffle for the rubbish that falls into the refuse collection board is difficult to fall out the refuse collection board when sliding into the rubbish collecting pit, is favorable to reducing because of rubbish falls out the refuse collection board and causes secondary pollution's the condition outward.
Preferably, the second base is detachably connected to the garbage collecting plate.
Through adopting above-mentioned technical scheme, when the brush wearing and tearing, only need change first brush and need not change a whole brush, be favorable to resources are saved.
Preferably, the first base is detachably connected to the first bracket.
By adopting the technical scheme, when the flexible part is worn and needs to be replaced, only the flexible part on the first support needs to be replaced, and a whole cleaning assembly does not need to be replaced, so that the resource is saved.
Preferably, the outer side walls of the baffles are provided with vibrators.
Through adopting above-mentioned technical scheme, through the vibrations of electromagnetic shaker for solid waste on the garbage collection board can get into the garbage collection pond better, is favorable to reducing the accumulational condition of garbage collection board rubbish, makes solid waste can get into the garbage collection pond through the garbage collection board more smoothly.
Preferably, a buffer member is arranged at the joint of the garbage collecting plate and the second bracket.
Through adopting above-mentioned technical scheme, be favorable to reducing because the vibrator vibrations lead to the not hard up condition in junction of garbage collection board and second support, be favorable to improving the stability of second support.
In summary, the present application includes at least one of the following beneficial technical effects:
1. through the setting of washing subassembly for the rubbish of winding on the rake teeth can be cleared up, makes the rake teeth be difficult to the winding have rubbish, is favorable to the rake teeth to salvage the solid waste in the sewage better. Therefore, the sewage treated by the grating machine does not easily contain solid garbage, and the condition that the solid garbage is mistakenly remained after the treatment of the grating machine to influence equipment for subsequent sewage treatment is favorably reduced;
2. through the arrangement of the first support, when the cleaning assembly needs to be replaced, the cleaning assembly can be moved to a position far away from the grating machine from the position close to the grating machine, so that the operable space is larger, and the cleaning assembly is more convenient to replace;
3. through the arrangement of the flat nozzle air gun, garbage accumulated on the flexible part can be blown off, and the flexible part is favorable for better cleaning the garbage wound on the rake teeth.
Drawings
FIG. 1 is a schematic diagram of an overall structure of a preliminary sewage impurity removal and purification apparatus according to an embodiment of the present application;
FIG. 2 is a schematic diagram of an internal structure of a preliminary sewage impurity removal and purification apparatus according to an embodiment of the present application;
fig. 3 is an enlarged schematic view of a portion a in fig. 2.
Description of reference numerals: 1. a ground surface; 11. a refuse collection tank; 2. a sewage tank; 21. a first fixing lever; 3. a grid machine; 31. a drive member; 32. a rotating conveyor belt; 33. rake teeth; 34. a frame; 4. a first bracket; 41. a sleeve; 42. a slide bar; 43. a vertical rod; 44. a beam rod; 5. cleaning the assembly; 51. a flexible member; 511. a chute; 52. a first base; 521. a first locking bolt; 53. a flat nozzle air gun; 54. a connecting rod; 55. an air tube; 56. an air compressor; 6. a second bracket; 61. a first connecting rod; 62. a second connecting rod; 63. a buffer member; 64. a refuse collection plate; 65. a baffle plate; 66. a vibrator; 68. A brush; 682. a second base; 681. brushing; 6821. and a second locking bolt.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
Referring to fig. 1, the embodiment of the application discloses a preliminary edulcoration clarification plant of sewage. Including being fixed in the sewage tank 2 and being used for clearing up the grid machine 3 of solid rubbish, the preliminary edulcoration clarification plant of sewage still includes the first support 4 that is fixed in ground 1, is equipped with on the first support 4 and washs subassembly 5, washs subassembly 5 and includes first base 52 and is used for cleaning the flexible 51 of the winding solid rubbish on the rake teeth 33. A garbage collecting plate 64 is arranged right below the first support 4, and a garbage collecting pool 11 is further arranged at one end, far away from the cleaning component 5, of the garbage collecting plate 64.
Referring to fig. 2 and 3, the grid machine 3 includes a frame 34, a rotary conveyor 32 disposed on the frame 34, a plurality of groups of rake teeth 33 fixedly connected to the rotary conveyor 32, and a driving member 31 for driving the rotary conveyor 32, in this embodiment, the driving member 31 is a motor. In the present embodiment, ten sets of rake teeth 33 are provided. One end of the frame 34 far away from the ground 1 is fixedly connected with a first fixing rod 22, and one end of the first fixing rod 22 far away from the frame 34 is fixedly connected with the ground 1.
Referring to fig. 2 and 3, the first bracket 4 includes a sleeve 41 fixed to the ground 1, which, in this embodiment, the two sleeves 41 are arranged, the two sleeves 41 are opposite to each other, the two sleeves 41 are both connected with the sliding rods 42 in a sliding manner, the two sleeves 41 are also provided with locking components (not marked in the figure) for locking the positions of the sliding rods, each locking component comprises a third locking threaded hole (not marked in the figure) penetrating through the sleeves 41, the third locking threaded hole is also in threaded connection with a third locking bolt (not marked in the figure), the third locking bolt is abutted against the outer side wall of the sliding rod 42, the ends, far away from the sleeves 41, of the two sliding rods 42 are both fixed with vertical rods 43, the length directions of the vertical rods 43 are perpendicular to the ground 1, the end, far away from the sliding rods 42, of each vertical rod 43 is fixedly connected with a cross, in this embodiment, two ends of the cross beam 44 are fixedly connected to one ends of the two vertical rods 43 away from the sliding rod 42.
Referring to fig. 2 and 3, the cleaning assembly 5 includes a first base 52 detachably connected to the beam rod 44 and a flexible member 51 fixed to the first base 52, the flexible member 51 is provided with a plurality of sets of sliding grooves 511, and when the rake teeth 33 of the grating machine 3 pass through the flexible member 51, the rake teeth 33 abut against the side walls of the sliding grooves 511. In this embodiment, the flexible member 51 is a sponge, and in other embodiments, it may be a brush or the like. The first base 52 is provided with first through holes (not shown), the beam rod 44 is recessed with first locking screw holes (not shown), and the first locking screw holes are in threaded connection with first locking bolts 521. The first locking screw holes are provided in two corresponding to the first through holes, and when the first base 52 is fixed to the beam rod 44, the first locking bolt 521 passes through the first through holes and is in threaded connection with the first locking screw holes.
Referring to fig. 2 and 3, the beam rod 44 is further fixedly connected with third connecting rods 54, in this embodiment, two third connecting rods 54 are provided, one ends of the two third connecting rods 54, which are far away from the beam rod 44, are both fixedly connected with flat nozzle air guns 53, the flat nozzle air guns 53 are connected with air pipes 55, and one ends of the air pipes 55, which are far away from the flat nozzle air guns 53, are connected with air compressors 56. In this embodiment, the coverage area of the two sets of flat nozzle air guns 53 when spraying air is larger than the cross-sectional area of the flexible member 51 on the side close to the garbage collection tank 11.
Referring to fig. 2 and 3, the preliminary impurity removal and purification equipment for sewage further comprises a second support 6 fixed on the ground 1, the second support 6 comprises four first connecting rods 61 fixed on the ground 1, a second connecting rod 62 is connected between adjacent first connecting rods 61, and the length directions of the four first connecting rods 61 are all perpendicular to the ground 1. The second bracket 6 is fixed with four buffering members 63, in this embodiment, the buffering members 63 are springs, the number of the buffering members 63 in this embodiment is four, the four buffering members 63 are respectively and fixedly connected to ends of the four first connecting rods 61 far away from the ground 1, and ends of the four buffering members 63 far away from the first connecting rods 61 are fixedly connected to the garbage collecting plate 64.
Referring to fig. 2 and 3, in the present embodiment, the width of the garbage collection plate 64 is greater than the length of the flexible member 51, the two sides of the garbage collection plate 64 in the width direction are further integrally connected with the blocking plate 65, and the height of the blocking plate 65 is greater than the thickness of the garbage collection plate 64. The garbage collection plate 64 is disposed to be inclined downward from an end far from the garbage collection chamber 11 toward an end close to the garbage collection chamber 11. A vibrator 66 is also fixedly connected to the side wall of the baffle 65.
Referring to fig. 2 and 3, the end of the garbage collecting plate 64 away from the garbage collecting tank 11 is detachably connected with a brush 68, the brush 68 comprises a second base 682 detachably connected to the garbage collecting plate 64 and bristles 681 fixedly connected to the second base 682, and the end of the bristles 681 away from the second base 682, which is far away from the grill machine 3, is abutted by the end of the revolving conveyor belt 32 away from the sewage tank 2. The second base 682 is provided with a second through hole (not shown), one side of the garbage collecting plate 64 close to the second base 682 is recessed with a second locking threaded hole (not shown), and the second locking threaded hole is in threaded connection with a second locking bolt 6821. The number of the second locking screw holes is two corresponding to the number of the second through holes, and when the brush 68 is fixed to the garbage collection plate 64, the second locking bolt 6821 penetrates through the second through hole to be in threaded connection with the second locking screw holes.
The implementation principle of the preliminary impurity removal and purification equipment for sewage in the embodiment of the application is as follows: when the solid garbage in the sewage needs to be cleaned, the grating machine 3 is started, the rotary conveyor belt 32 starts to operate to drive the rake teeth 33 to start to do rotary motion, the rake teeth 33 fish the solid garbage in the sewage out of the sewage in the motion process and drive the garbage to be transported upwards, after the tines 33 have traveled to the highest point, the tines 33 are tilted by the carousel 32, so that the garbage on the rake teeth 33 falls into the garbage collecting plate 64 by gravity, the rake teeth 33 moving downward pass through the chute 511 of the flexible member 51, when the rake teeth 33 abut against the side wall of the flexible member 51, the solid waste wound around the rake teeth 33 cannot pass through the chute 511 of the flexible member 51, by the clamping of the flexible member 51, the garbage wound around the rake teeth 33 is torn out to the side of the flexible member 51 away from the grating machine 3 and falls into the garbage collecting plate 64, and falls into the garbage collecting tank 11 through the garbage collecting plate 64. The condition that the efficiency of the rake teeth 33 for fishing up the solid waste from the sewage is influenced by winding the waste on the rake teeth 33 is favorably reduced, and the rake teeth 33 are favorably kept in a clean state, so that the rake teeth 33 can better fish up the solid waste, the grid machine 3 can better separate the solid waste in the sewage, and the solid waste is not easy to flow into subsequent sewage treatment equipment to cause the fault and the damage of the sewage treatment equipment.
Through the arrangement of the sliding rod 42 slidably connected in the sleeve 41, the flexible part 51 can slide towards the direction close to the grille machine 3 and towards the direction far away from the grille machine 3, which is beneficial to reducing the situation that the operation space of the flexible part 51 arranged under the grille machine 2 is compact, and when the flexible part 51 needs to be replaced, the flexible part 51 is beneficial to being replaced more conveniently by making the flexible part 51 far away from the grille machine 2 to obtain larger operation space.
Through the setting of brush 68, because flexible piece 51 is when the rubbish on the clearance rake teeth 33, some rubbish can block in the spout 511 of flexible piece 51, when follow-up rake teeth 33 passed flexible piece 51, can take the rubbish of block in spout 511 out, the rubbish of taking out may fall outside the rubbish collection board 64, cause the pollution easily, through set up brush 68 on rubbish collection board 64, make the rubbish of taking out can be blockked by brush 68 and fall into on rubbish collection board 64, be favorable to reducing because of the rubbish that is taken out spout 511 by rake teeth 33 falls outside the rubbish collection board 64 and causes the condition of secondary pollution.
By providing the first base 52 to be removably attached to the beam 44, only the cleaning assembly 5 need be replaced when the flexible member 51 is worn to be replaced, rather than replacing an entire first rack 4.
The second base 682 is detachably connected to the garbage collecting plate 64, so that when the brush 68 is worn and needs to be replaced, only the brush 68 needs to be replaced, and the whole garbage collecting plate 64 does not need to be replaced, which is beneficial to saving resources.
Through the setting of flat mouth air gun 53 for solid waste that is cleared up by flexible member 51 can be blown to the rubbish collecting plate 64 on, is favorable to reducing because of rubbish gathers on flexible member 51 and leads to the condition of the rubbish on the flexible member 51 can't clear up rake teeth 33 better.
Through the setting that refuse collection board 64 has baffle 65 along width direction's both ends an organic whole for refuse collection board 64 is difficult to fall out when on refuse collection board 64 from the rubbish that drops on rake teeth 33 and the rubbish of clearing up out through flexible piece 51, is favorable to reducing the condition that causes secondary pollution because of rubbish falls out refuse collection board 64.
And is inclined toward one end of the waste collection tank 11 by a waste collection plate 64. The garbage on the garbage plate can be easily scratched into the garbage collection tank 11, the garbage accumulation on the garbage plate 64 can be reduced, and the garbage can smoothly enter the garbage collection tank 11 through the garbage plate 64.
Through the arrangement of the vibrator 66 fixedly connected to the baffle 65, the garbage on the garbage collecting plate 64 can enter the garbage collecting tank 11 more smoothly through the vibration of the vibrator 66.
The buffer member 63 is provided to reduce the loosening of the connection between the second bracket 6 and the garbage collecting plate 64 caused by the vibration of the vibrator 66.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (10)

1. The utility model provides a preliminary edulcoration clarification plant of sewage, sets up grid machine (3) on bilge water tank (2) including the slope, grid machine (3) include frame (34) of fixed connection in bilge water tank (2), install slewing belt (32) on frame (34) and a plurality of groups of rake teeth (33) of fixed connection on slewing belt (32), its characterized in that: the preliminary impurity removal and purification equipment for sewage also comprises a cleaning component (5) which is arranged right below one end of the grating machine (3) far away from the sewage tank (2), the cleaning component (5) comprises a first base (52) and a flexible piece (51) arranged on the first base (52), a plurality of sliding grooves (511) are formed in the flexible piece (51), when the rake teeth (33) pass through the flexible member (51), the side walls of the plurality of slide grooves (511) abut against the rake teeth (33), a garbage collecting plate (64) is arranged under the cleaning component (5), one side of the garbage collecting plate (64) close to the ground (1) is connected with a second bracket (6), one end of the second bracket (6) far away from the garbage collecting plate (64) is fixedly connected with the ground (1), and a garbage collecting pool (11) is arranged at one end of the garbage collecting plate (64) far away from the flexible part (51).
2. The primary impurity removal and purification equipment for sewage according to claim 1, which is characterized in that: preliminary edulcoration clarification plant of sewage still includes sliding connection in first support (4) on ground (1), first support (4) orientation is close to grid machine (3) and the orientation is kept away from the direction of grid machine (3) and is slided, first base (52) are located on first support (4), preliminary edulcoration clarification plant of sewage still is including locating the locking Assembly who is used for locking first support (4) on ground (1).
3. The primary impurity removal and purification equipment for sewage according to claim 2, which is characterized in that: the first support (4) is further provided with a flat nozzle air gun (53), and an air outlet of the flat nozzle air gun (53) faces towards the upper surface of the flexible part (51).
4. The primary impurity removal and purification equipment for sewage according to claim 1, which is characterized in that: the garbage collection plate (64) is arranged from one end far away from the garbage collection pool (11) to one end close to the garbage collection pool (11) in an inclined and downward mode, and the width of the garbage collection plate (64) is larger than the length of the flexible piece (51).
5. The preliminary impurity removal and purification equipment for sewage according to claim 4, wherein the equipment comprises: one end of the garbage collection plate (64) far away from the garbage collection pool (11) is further provided with a brush (68), the brush (68) comprises a second base (682) arranged on the garbage collection plate (64) and brush bristles (681) fixed on the second base (682), and one end of the brush bristles (681) far away from the second base (682) is abutted to a rotary conveyor belt (32) far away from one end of the sewage tank (2) with the grating machine (3).
6. The preliminary impurity removal and purification equipment for sewage according to claim 5, characterized in that: the two sides of the garbage collecting plate (64) in the width direction are integrally connected with baffle plates (65).
7. The preliminary impurity removal and purification equipment for sewage according to claim 5, characterized in that: the second base (682) is removably connected to the waste collection plate (64).
8. The primary impurity removal and purification equipment for sewage according to claim 2, which is characterized in that: the first base (52) is detachably connected to the first bracket (4).
9. The preliminary impurity removal and purification equipment for sewage according to claim 6, characterized in that: the outer side walls of the baffles (65) are provided with vibrators (66).
10. The primary impurity removal and purification equipment for sewage according to claim 9, which is characterized in that: and a buffer member (63) is arranged at the joint of the garbage collecting plate (64) and the second bracket (6).
CN202021480473.3U 2020-07-23 2020-07-23 Preliminary edulcoration clarification plant of sewage Active CN212983813U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021480473.3U CN212983813U (en) 2020-07-23 2020-07-23 Preliminary edulcoration clarification plant of sewage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021480473.3U CN212983813U (en) 2020-07-23 2020-07-23 Preliminary edulcoration clarification plant of sewage

Publications (1)

Publication Number Publication Date
CN212983813U true CN212983813U (en) 2021-04-16

Family

ID=75429118

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021480473.3U Active CN212983813U (en) 2020-07-23 2020-07-23 Preliminary edulcoration clarification plant of sewage

Country Status (1)

Country Link
CN (1) CN212983813U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112876006A (en) * 2021-04-22 2021-06-01 福建沛泰环境工程有限公司 Municipal sewage treatment method based on rotary grating machine
CN114195289A (en) * 2021-12-13 2022-03-18 许海兵 Rural escape canal domestic sewage treatment device
CN114949974A (en) * 2022-04-07 2022-08-30 深圳市滨特尔环保设备有限公司 Low-energy-consumption domestic sewage treatment device
CN117282163A (en) * 2023-11-27 2023-12-26 广州中科碧疆环保科技有限公司 Sewage treatment grid and sewage pretreatment process

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112876006A (en) * 2021-04-22 2021-06-01 福建沛泰环境工程有限公司 Municipal sewage treatment method based on rotary grating machine
CN114195289A (en) * 2021-12-13 2022-03-18 许海兵 Rural escape canal domestic sewage treatment device
CN114949974A (en) * 2022-04-07 2022-08-30 深圳市滨特尔环保设备有限公司 Low-energy-consumption domestic sewage treatment device
CN117282163A (en) * 2023-11-27 2023-12-26 广州中科碧疆环保科技有限公司 Sewage treatment grid and sewage pretreatment process
CN117282163B (en) * 2023-11-27 2024-02-23 广州中科碧疆环保科技有限公司 Sewage treatment grid and sewage pretreatment process

Similar Documents

Publication Publication Date Title
CN212983813U (en) Preliminary edulcoration clarification plant of sewage
CN110813749A (en) Raw materials cleaning plant is used in glutinous rice wine production
CN216497890U (en) Filter equipment for sewage treatment
CN114100237A (en) Chain plate filtering type solid-liquid separation device
CN212855060U (en) High-efficiency energy-saving industrial filter drum dust removal equipment
CN212914707U (en) Domestic sewage treatment device with large water volume
CN111450599A (en) Papermaking sewage high efficiency treatment equipment
CN217220337U (en) Online cleaning device of circulating water pool
CN216445942U (en) Environment-friendly water surface scum clearing device
CN214486025U (en) Urban and rural sewage discharge system
CN214598020U (en) Waste gas conveying pipeline with cleaning mechanism
CN212052660U (en) River course device of decontaminating for environmental protection
CN2495121Y (en) Machine for removing hair or impurities for raw material of soft food
CN210248305U (en) Vegetable cleaning system's garbage collection device
CN212757465U (en) Muddy water recovery system
CN112023495A (en) Sewage treatment plant convenient to use
CN212856513U (en) Desulfurization gypsum edulcoration device
CN220097384U (en) Intelligent garbage classification device
CN216302725U (en) Conveyer is used in chicken feed production
CN218743258U (en) Integrative cleaning and sorting machine of air screen for seed processing
CN206082622U (en) System is tentatively cleared up to wheat of flour production in -process
CN216837384U (en) Dirt separator for sewage
CN220561698U (en) Waste recycling mechanism of high-speed circular cutting machine
CN220909636U (en) Drilling mud purifying treatment device
CN217200017U (en) Garbage classification collection device for hydraulic engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant