CN212983756U - Underground reservoir construction device - Google Patents

Underground reservoir construction device Download PDF

Info

Publication number
CN212983756U
CN212983756U CN202020900063.3U CN202020900063U CN212983756U CN 212983756 U CN212983756 U CN 212983756U CN 202020900063 U CN202020900063 U CN 202020900063U CN 212983756 U CN212983756 U CN 212983756U
Authority
CN
China
Prior art keywords
spacing ring
sets
underground reservoir
pouring template
reservoir construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020900063.3U
Other languages
Chinese (zh)
Inventor
胡鹏程
李向通
曹天旭
许崇堃
武文龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020900063.3U priority Critical patent/CN212983756U/en
Application granted granted Critical
Publication of CN212983756U publication Critical patent/CN212983756U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model discloses an underground reservoir construction device, including installation and two sets of first spacing ring of bottom of the reservior top and top of the reservior bottom and second spacing ring, two sets of first spacing ring and second spacing ring, two sets of the equal fixedly connected with fixed column in both sides at first spacing ring and second spacing ring top is two sets of install multiunit fixing device between first spacing ring and the second spacing ring, wherein a set of the main tributary dagger, two are all installed to the both sides at two sets of first spacing ring and second spacing ring top the top of main tributary dagger all is provided with the telescopic link, and is wherein a set of the slip casting hole has been seted up at the top of fixing device front end. The utility model discloses in, this underground reservoir construction device not only design has fixed establishment, and it has support and stop gear still to design, can utilize multiunit fixing device to accomplish the equipment of pouring the template fast, also can accomplish fast to it simultaneously and support and fix to make its work efficiency obtain improving greatly, be worth wideling popularize.

Description

Underground reservoir construction device
Technical Field
The utility model relates to an engineering construction technical field especially relates to underground reservoir construction device.
Background
A water reservoir, which is a water conservancy project building for storing and regulating flood and water flow, can also be used for irrigation, power generation, flood control and fish culture, and is an artificial lake formed by building a barrage at a narrow mouth of a mountain ditch or river, wherein the reservoir can play the roles of flood control, water storage irrigation, water supply, power generation, fish culture and the like after being built, sometimes a natural lake is also called a reservoir (natural reservoir), the scale of the reservoir is generally divided into small, medium and large according to the size of the reservoir, people can fully develop and utilize water resources to adapt to the requirements of water departments in order to solve the problem of redistribution of runoff on time and space, some reservoir projects are often built on rivers, and the beneficial effects of the reservoir are that runoff regulation, flood storage and depletion are carried out, so that natural water can better meet the requirements of water use of departments in time and space, and underground gravel sand and sand pores are formed, The water storage space with a determined range formed by rock cracks or karst caves or by building underground water interception walls and intercepting and storing underground water or subsurface flow can store underground water, and ground water is stored by adopting a recharging mode, so that the water storage device has the advantages of no land occupation, large storage capacity, less investment, small evaporation loss, safety, reliability and the like.
The underground reservoir is also a reservoir, but the construction difficulty of underground reservoir is great relatively, still need use many dedicated construction equipment, the in-process of underground reservoir construction need pour a lot of concrete support columns, some templates need be used to the support column in the process of construction, but present device structural design has certain defect, present concrete placement bounding wall still adopts the plank structure, not only the fastness is relatively poor, and need a large amount of manpower and materials during the construction, the efficiency of construction is lower, for this reason, we have proposed new underground reservoir construction device.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing an underground reservoir construction device.
In order to achieve the above purpose, the utility model adopts the following technical scheme: underground reservoir construction device, including installation and two sets of first spacing ring and second spacing ring in bottom of the reservior top and top of the reservior bottom, two sets of first spacing ring and second spacing ring, two sets of the equal fixedly connected with fixed column in both sides at first spacing ring and second spacing ring top, two sets of install multiunit fixing device between first spacing ring and the second spacing ring, one of them is a set of main tributary dagger, two are all installed to the both sides at two sets of first spacing ring and second spacing ring top the top of main tributary dagger all is provided with the telescopic link, and one of them is a set of the slip casting hole has been seted up at the top of fixing device front end.
As a further description of the above technical solution:
the two groups of first limiting rings and the second limiting rings are rotatably connected, and positioning holes are formed between the two groups of first limiting rings and the two groups of second limiting rings.
As a further description of the above technical solution:
the fixing device comprises a first pouring template and a second pouring template, the first pouring template and the second pouring template are sleeved at the centers of the first limiting ring and the second limiting ring, positioning rings are fixedly connected to the tops of the first pouring template and the second pouring template, and mounting lugs are fixedly connected to one sides of the outer walls of the first pouring template and the second pouring template.
As a further description of the above technical solution:
the first pouring template and the second pouring template are rotatably connected through two rotating shafts.
As a further description of the above technical solution:
two the installation ear is through a plurality of fixing bolt fixed connection, and the multiunit a plurality of mounting holes have all been seted up at the center of installation ear.
As a further description of the above technical solution:
two locking bolts corresponding to the telescopic links are installed at the top of one side of the outer wall of the main support column, and the bottom ends of the main support column and the top ends of the telescopic links are fixedly connected with positioning pipe sleeves corresponding to the fixing columns.
The utility model discloses following beneficial effect has: 1. the utility model provides an underground reservoir construction device compares with traditional device, the device simple structure, and convenient and practical has replaced traditional template structure through the simple fixed and bearing structure of design, and a large amount of manpower and materials have been saved to convenient and fast, have also saved a large amount of engineering time simultaneously.
2. Compared with the traditional device, the device has great innovation and improvement in structure and design, the underground reservoir construction device is provided with the fixing mechanism, the support and the limiting mechanism, the assembling of the pouring template can be rapidly completed by the aid of the multiple groups of fixing devices, and the support and the fixation can be rapidly completed by the aid of the fixing devices, so that the working efficiency is greatly improved, and the underground reservoir construction device is worth vigorously popularizing.
Drawings
Fig. 1 is a schematic view of an installation structure of an underground reservoir construction device according to the present invention;
fig. 2 is a top view structural diagram of the limiting ring of the fixing device of the underground reservoir construction device provided by the utility model;
fig. 3 is a schematic structural view of a second pouring template of the underground reservoir construction device provided by the utility model;
fig. 4 is the utility model provides an overlook the structure chart of underground reservoir construction equipment fixing device.
Illustration of the drawings:
1. a first limit ring; 2. a second stop collar; 3. fixing a column; 4. a first pouring template; 5. a second pouring template; 6. a rotating shaft; 7. a positioning ring; 8. mounting lugs; 9. mounting holes; 10. a main support column; 11. a telescopic rod; 12. locking the bolt; 13. a positioning pipe sleeve; 14. grouting holes; 15. a reservoir bottom; 16. and (6) carrying out warehouse top.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention; the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance, and furthermore, unless otherwise explicitly stated or limited, the terms "mounted," "connected," and "connected" are to be construed broadly and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1-4, the present invention provides an embodiment: underground reservoir construction device, including installation and 15 tops at the bottom of the warehouse and two sets of first spacing ring 1 and second spacing ring 2 in 16 bottoms at the top of the warehouse, two sets of first spacing ring 1 and second spacing ring 2, the equal fixedly connected with fixed column 3 in both sides at two sets of first spacing ring 1 and 2 tops of second spacing ring, install multiunit fixing device between two sets of first spacing ring 1 and the second spacing ring 2, main tributary strut 10 is all installed to the both sides at one of them set of two sets of first spacing ring 1 and 2 tops of second spacing ring, the top of two main tributary struts 10 all is provided with telescopic link 11, grouting hole 14 has been seted up at the top of one of them set of fixing device front end.
Two sets of first spacing rings 1 and second spacing ring 2 all rotate to be connected, and all are provided with the locating hole between two sets of first spacing rings 1 and the second spacing ring 2, thereby first spacing ring 1 and second spacing ring 2 make first spacing ring 1 and second spacing ring 2 can pass the steel reinforcement cage through rotating to the cover is in the outside of steel reinforcement cage.
Fixing device includes that first template 4 and second are pour to the first template 5 of pouring, first template 4 and second are pour to first retaining ring 1 and the spacing center of second have cup jointed, the equal fixedly connected with holding ring 7 in the top of first template 4 and second of pouring 5, the equal fixedly connected with installation ear 8 in one side of first template 4 and the 5 outer walls of second of pouring, first template 4 and the second of pouring are pour and are used for overlapping in the outside of steel reinforcement cage, thereby replace traditional template structure, the equal fixedly connected with holding ring 7 in the top of the first template 4 of pouring of multiunit and second template 5, the inboard of holding ring 7 is provided with the mounting groove, can utilize it to pile up the location to the first template 4 of pouring of multiunit and second template 5, thereby accomplish the equipment fast.
First template 4 and the second of pouring are pour template 5 and are rotated through two axis of rotation 6 and are connected, rotate through axis of rotation 6 and connect more convenient dismantlement and installation, can pour the first outside of 5 quick covers at the steel reinforcement cage of template 4 and the second of pouring.
Two installation ears 8 are through a plurality of fixing bolt fixed connection, and a plurality of mounting holes 9 have all been seted up at the center of multiunit installation ear 8, make its convenient to detach and fixed through a plurality of fixing bolt fixed connection.
Locking bolt 12 corresponding with telescopic link 11 is all installed at the top of two main tributary dagger 10 outer wall one sides, and the equal fixedly connected with in top of two main tributary dagger 10 and two telescopic link 11 and the corresponding locating tube cover 13 of fixed column 3, we utilize locking bolt 12 to lock fast the position of telescopic link 11 fixedly, thereby play support and fixed action to two sets of first spacing ring 1 and second spacing ring 2, locating tube cover 13 is used for the cover on the fixed column 3 of two sets of first spacing ring 1 and 2 both sides of second spacing ring, thereby realize spacing and fixed to two sets of first spacing ring 1 and second spacing ring 2.
The working principle is as follows: the utility model provides an underground reservoir construction device has great improvement innovation with the traditional device, when using the underground reservoir construction device, after the steel reinforcement cage is bound, we can firstly use a group of first spacing ring 1 and second spacing ring 2 to be sleeved at the bottom of the outer wall of the steel reinforcement cage, then stack a plurality of groups of fixing devices in sequence according to the figure, the first pouring template 4 and the second pouring template 5 are used to be sleeved at the outer side of the steel reinforcement cage, thereby replacing the traditional template structure, the top parts of a plurality of groups of first pouring templates 4 and second pouring templates 5 are both fixedly connected with a positioning ring 7, the inner side of the positioning ring 7 is provided with a mounting groove, the mounting groove can be used to stack and position a plurality of groups of first pouring templates 4 and second pouring templates 5, thereby rapidly completing the assembly, after the last group of fixing devices are installed, we can use another group of first spacing ring 1 and second spacing ring 2 to be sleeved at the outer wall of the fixing device at the top part, then reuse to two sets of supporting mechanism to two sets of first spacing ring 1 and second spacing ring 2 support fixed can, we utilize locking bolt 12 to lock fast the position of telescopic link 11 fixedly, thereby play support and fixed action to two sets of first spacing ring 1 and second spacing ring 2, position pipe box 13 is used for the cover on the fixed column 3 of two sets of first spacing ring 1 and second spacing ring 2 both sides, thereby realize spacing and fixed to two sets of first spacing ring 1 and second spacing ring 2, after whole equipment is accomplished, just can pour the concrete through slip casting hole 14.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.

Claims (6)

1. Underground reservoir construction device, including installation and storehouse bottom (15) top and two sets of first spacing ring (1) in storehouse top (16) bottom and second spacing ring (2), its characterized in that: two sets of first spacing ring (1) and second spacing ring (2), two sets of equal fixedly connected with fixed column (3) in both sides at first spacing ring (1) and second spacing ring (2) top, two sets of install multiunit fixing device between first spacing ring (1) and second spacing ring (2), wherein a set of main tributary strut (10), two are all installed to the both sides at two sets of first spacing ring (1) and second spacing ring (2) top main tributary strut (10)'s top all is provided with telescopic link (11), wherein a set of slip casting hole (14) have been seted up at the top of fixing device front end.
2. The underground reservoir construction apparatus according to claim 1, wherein: the two sets of first limiting rings (1) and the second limiting rings (2) are rotatably connected, and positioning holes are formed between the two sets of first limiting rings (1) and the second limiting rings (2).
3. The underground reservoir construction apparatus according to claim 1, wherein: the fixing device comprises a first pouring template (4) and a second pouring template (5), the first pouring template (4) and the second pouring template (5) are sleeved at the centers of the first limiting ring (1) and the second limiting ring, the top parts of the first pouring template (4) and the second pouring template (5) are fixedly connected with positioning rings (7), and the first pouring template (4) and the second pouring template (5) are fixedly connected with mounting lugs (8).
4. The underground reservoir construction apparatus according to claim 3, wherein: the first pouring template (4) and the second pouring template (5) are rotatably connected through two rotating shafts (6).
5. The underground reservoir construction apparatus according to claim 3, wherein: two installation ear (8) are through a plurality of fixing bolt fixed connection, and the multiunit a plurality of mounting holes (9) have all been seted up at the center of installation ear (8).
6. The underground reservoir construction apparatus according to claim 1, wherein: two locking bolts (12) corresponding to the telescopic rods (11) are installed at the top of one side of the outer wall of the main support column (10), and the bottom ends of the main support column (10) and the top ends of the telescopic rods (11) are fixedly connected with positioning pipe sleeves (13) corresponding to the fixing columns (3).
CN202020900063.3U 2020-05-26 2020-05-26 Underground reservoir construction device Expired - Fee Related CN212983756U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020900063.3U CN212983756U (en) 2020-05-26 2020-05-26 Underground reservoir construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020900063.3U CN212983756U (en) 2020-05-26 2020-05-26 Underground reservoir construction device

Publications (1)

Publication Number Publication Date
CN212983756U true CN212983756U (en) 2021-04-16

Family

ID=75421289

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020900063.3U Expired - Fee Related CN212983756U (en) 2020-05-26 2020-05-26 Underground reservoir construction device

Country Status (1)

Country Link
CN (1) CN212983756U (en)

Similar Documents

Publication Publication Date Title
CN101775809B (en) Construction method of marine self-floating type steel soleplate single-wall suspension box cofferdam and single-wall suspension box cofferdam
CN106049525A (en) Polygonal offshore wind power barrel-shaped foundation
CN104389318B (en) Reinforced concrete-steel structure hybrid gravity foundation for offshore wind power and construction method thereof
CN103510529A (en) Steel hanging box system for underwater high-rise pile cap construction and construction technology thereof
CN110468833A (en) Drilled grouting piles under water constructing device and its application method for cruiseway
CN105863042A (en) All-steel structure building and construction method thereof
CN110453714B (en) Offshore wind power jacket gravity type cylindrical foundation structure and construction method thereof
CN101429761A (en) Deep sea bare rock pier protection barrel, positioning pile, underwater cofferdam integrated platform and construction method
CN102644274A (en) Pile-forming construction method for penetrating through existing structure by fender post
CN212983756U (en) Underground reservoir construction device
CN103321212A (en) One-column-one-pile post inserting method construction process
CN203113336U (en) Locating and perpendicularity adjusting device of rotary-drilling pile concrete-filled steel tubular column reverse construction method
CN218667670U (en) Scour prevention construction device
CN103981894A (en) Multi-cylindrical foundation combined foundation structure system
CN103981889B (en) A kind of three bucket foundation combined type foundation structure systems with support
CN110468870A (en) One kind can have enough to meet the need Tower Crane Foundation by Steel Lattice Column structure
CN114635427B (en) Underwater guide frame
CN107119687B (en) Inter-tidal zone pile sinking limit frame capable of rotating greatly and construction method thereof
CN202706019U (en) Foundation steel column of solar photovoltaic power station
CN203007965U (en) Steel hanging box system for underwater high-rise pile cap construction
CN105443311A (en) Tidal current energy generating device fixed to water bottom
CN202164862U (en) Tower barrel type structure suitable for ocean engineering
CN205776423U (en) A kind of levelling device for offshore wind farm catheterostat basis
CN213328897U (en) Slope protection device for water conservancy construction
CN211197581U (en) Mobile mixing station

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210416