CN212968815U - Convenient portable job site uses interim cable support - Google Patents

Convenient portable job site uses interim cable support Download PDF

Info

Publication number
CN212968815U
CN212968815U CN202021753866.7U CN202021753866U CN212968815U CN 212968815 U CN212968815 U CN 212968815U CN 202021753866 U CN202021753866 U CN 202021753866U CN 212968815 U CN212968815 U CN 212968815U
Authority
CN
China
Prior art keywords
steel bar
cable support
reinforcing bar
inclined strut
bracing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021753866.7U
Other languages
Chinese (zh)
Inventor
王龙
陈刚
陈鹏
田小亮
王楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Civil Engineering Co Ltd
Original Assignee
China Construction Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Civil Engineering Co Ltd filed Critical China Construction Civil Engineering Co Ltd
Priority to CN202021753866.7U priority Critical patent/CN212968815U/en
Application granted granted Critical
Publication of CN212968815U publication Critical patent/CN212968815U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The utility model relates to a convenient portable job site is with interim cable support, including the reinforcing bar stand, the position that reinforcing bar stand surface bottom is close to the middle section welds respectively and sets up around and is located bracing one and bracing two on right side, and the right side on reinforcing bar stand surface just is located and welds between bracing one and bracing two and the reinforcing bar stand and has the reinforcing bar snap ring, and the inner chamber of reinforcing bar snap ring is provided with the upper reinforcing bar of structural bottom plate. The utility model discloses convenient portable job site can select cable job site hanging position with interim cable support in a flexible way, and the dead weight is light, can remove in a flexible way, can have enough to meet the need convenient operation, safe and reliable, convenient portable job site passes through the insulating plastic tubing of parcel with interim cable support, plays insulating effect, guarantees interim power consumption safety, fine solution job site interim cable erection problem.

Description

Convenient portable job site uses interim cable support
Technical Field
The application relates to the field of side slope protection tools, in particular to a temporary cable support for a convenient and movable construction site.
Background
At present, in the foundation slab work progress before the major structure construction, the in-process is laid to interim power consumption cable, and power tool is terminal to be far away with the electric connection point distance, and the circuit is longer, and the cable can't be erect, adopts to lay the scaffold board to fill up the cable mostly, in the constructor work progress, tramples the cable easily, causes the damage, is unfavorable for the interim power consumption safety control of job site.
At present in the foundation slab work progress, interim power consumption is mostly through laying the scaffold board and having filled up the cable, in the constructor work progress, tramples the cable easily, causes the damage, is unfavorable for the interim power consumption safety control of job site.
SUMMERY OF THE UTILITY MODEL
Based on the circumstances, the utility model discloses can guarantee in the foundation slab work progress, interim power consumption safety, and the support has the dead weight light, and the flexibility is good, can have enough to meet the need, and advantages such as safe and reliable reliably solve the job site cable and can't erect the problem, loads ecological stick technical problem with low efficiency in order to solve current shovel, and this application provides a convenient portable job site uses interim cable support.
The application provides a pair of convenient portable job site uses interim cable support adopts following technical scheme:
the utility model provides a convenient portable job site uses interim cable support, including the reinforcing bar stand, the position that reinforcing bar stand surface bottom is close to the middle section welds respectively and sets up and be located the bracing one and bracing two on right side around, the right side on reinforcing bar stand surface just is located the welding between bracing one and bracing two and the reinforcing bar stand has the reinforcing bar snap ring, the inner chamber of reinforcing bar snap ring is provided with the upper reinforcing bar of structure bottom plate, the bottom of the upper reinforcing bar of structure bottom plate is provided with the cover and establishes at the reinforcing bar stand, the structure bottom plate on bracing one and bracing two surfaces, the reinforcing bar stand, the bottom of bracing one and bracing two all contradicts on the ground bottom plate, the top welding on reinforcing bar stand surface right side has the short reinforcement, the right-hand member welding of short reinforcement has the link, it.
Preferably, couple mechanism is including articulating the couple on the link, and the one end welding of couple has the fixed block, and the bottom of fixed block is rotated and is connected with the turning block, and the right side welding of turning block has the rotating tube, and the welding of one side of rotating tube inner chamber has the spring, and the one end welding that the rotating tube was kept away from to the spring has the sliding block, and the one end welding that the spring was kept away from to the sliding block has the pothook of lock joint on the.
Preferably, the hook is S-shaped, and the bent end at the top of the hook is hung on the hanging ring.
Preferably, the bottom ends of the first inclined strut and the second inclined strut are inclined towards the right side of the steel bar upright post, and the inclination angle of the bottom ends of the first inclined strut and the second inclined strut is forty-five degrees.
By adopting the technical scheme: the insulating effect can be played, and the construction safety is improved.
Preferably, the surfaces of the hook mechanism, the steel bar upright post, the first inclined strut and the second inclined strut are all sleeved with insulating plastic pipes.
By adopting the technical scheme: when the steel bar snap ring contacts with the upper steel bar of the structural bottom plate, the upper steel bar of the structural bottom plate can be prevented from sliding, and therefore the stability of the whole support is guaranteed.
Preferably, the curved internal surface of reinforcing bar snap ring is provided with anti-skidding line, and anti-skidding line is the intensive surface that distributes at the reinforcing bar snap ring of slope.
By adopting the technical scheme: the bottom that can prevent the reinforcing bar stand slides, improves the stability of whole support.
Preferably, the bottom of the steel bar upright is provided with a non-slip mat, and the diameter of the non-slip mat is the same as that of the bottom of the steel bar upright.
Preferably, the notch of the hook is the size of a quarter of a circular ring.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the utility model discloses convenient portable job site can select cable job site hanging position with interim cable support in a flexible way, and the dead weight is light, can remove in a flexible way, can have enough to meet the need convenient operation, safe and reliable.
2. The convenient and fast movable temporary cable support for the construction site plays an insulating role by wrapping an insulating plastic pipe, guarantees the temporary power utilization safety, and well solves the construction site temporary cable erection problem.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a perspective view of the present invention.
Fig. 3 is a rear perspective view of the present invention.
Fig. 4 is a perspective view of the hook mechanism of the present invention.
Fig. 5 is a front sectional view of the hook mechanism of the present invention.
Description of reference numerals: 1. a steel bar upright post; 2. a first inclined strut; 3. a steel bar snap ring; 4. upper steel bars of the structural bottom plate; 5. a structural floor; 6. short reinforcing steel bars; 7. hanging a ring; 8. a hooking mechanism; 9. a second inclined strut; 81. hooking; 82. a fixed block; 83. rotating the tube; 84. a hook; 85. rotating the block; 86. a spring; 87. and a slider.
Detailed Description
The present application is described in further detail below with reference to figures 1-5.
A temporary wire and cable support for a convenient and movable construction site comprises a steel bar upright post 1, wherein a first inclined strut 2 and a second inclined strut 9 which are arranged in the front and at the back and are positioned on the right side are respectively welded at the position, close to the middle section, of the bottom of the surface of the steel bar upright post 1, a steel bar snap ring 3 is welded at the position, on the right side of the surface of the steel bar upright post 1, between the first inclined strut 2 and the second inclined strut 9 and the steel bar upright post 1, an upper-layer steel bar 4 of a structural bottom plate is arranged in an inner cavity of the steel bar snap ring 3, a structural bottom plate 5 which is sleeved on the surfaces of the steel bar upright post 1, the first inclined strut 2 and the second inclined strut 9 is arranged at the bottom of the upper-layer steel bar 4 of the structural bottom plate, the bottom ends of the steel bar upright post 1, the first inclined strut 2 and the second inclined strut 9 are all abutted against a ground bottom plate, one end of a hook 81 is welded with a fixed block 82, the bottom of the fixed block 82 is rotatably connected with a rotating block 85, the right side of the rotating block 85 is welded with a rotating pipe 83, one side of the inner cavity of the rotating pipe 83 is welded with a spring 86, one end of the spring 86 far away from the rotating pipe 83 is welded with a sliding block 87, one end of the sliding block 87 far away from the spring 86 is welded with a clamping hook 84 buckled on the hook 81, the hook 81 is S-shaped, the bent end of the top of the hook 81 is hung on a hanging ring 7, the bottom ends of a first inclined strut 2 and a second inclined strut 9 are both inclined towards the right side of a steel bar upright post 1, the inclination angles of the bottom ends of the first inclined strut 2 and the second inclined strut 9 are forty-five degrees, the whole support is welded by steel bars with nominal diameter larger than phi 25, the surfaces of the hook mechanism 8, the steel bar upright post 1, the first inclined strut, improve construction safety, it is preferred, the 3 crooked internal surface of reinforcing bar snap ring is provided with anti-skidding line, anti-skidding line is the intensive distribution in reinforcing bar snap ring 3 surface of slope, setting through anti-skidding line, when reinforcing bar snap ring 3 contacts with structural bottom plate upper reinforcing bar 4, can prevent that structural bottom plate upper reinforcing bar 4 from sliding, thereby guarantee the stability of whole support, it is preferred, reinforcing bar stand 1's bottom is provided with the slipmat, the diameter of slipmat is the same with the diameter of reinforcing bar stand 1 bottom, setting through the slipmat, can prevent that reinforcing bar stand 1's bottom from sliding, improve the stability of whole support, it is preferred, pothook 84's breach department is the size of a quarter ring.
Before using, a user prepares a long steel bar upright post 1 and a short diagonal brace I2 and a short diagonal brace II 9, the diagonal brace I2 and the diagonal brace II 9 are welded at the lower position of the right side of the steel bar upright post 1, then a short steel bar 6 is welded at the position of the right side of the steel bar upright post 1 close to the top, a hanging ring 7 is welded on the short steel bar 6, a hook mechanism 8 is hung on the hanging ring 7, a steel bar snap ring 3 is welded on the steel bar upright post 1 to form a complete bracket, the bracket is placed on a structural bottom plate 5, the steel bar snap ring 3 is clamped on an upper layer steel bar 4 of the structural bottom plate fixed on the structural bottom plate 5, the bottom ends of the steel bar upright post 1, the diagonal brace I2 and the diagonal brace II 9 are abutted against the floor ground, the placement and installation of the bracket are completed, the electric wires are placed on a hook 81 during construction, the electric wires are combed, and thus the electric wires can be prevented, thereby guarantee user's construction safety, whole support can also adjust the turnover at structure bottom plate 5 moreover, and the flexibility is strong, and the person of facilitating the use uses.
To sum up, this interim wire and cable support is used to convenient portable job site can select wire and cable job site hanging position in a flexible way through interim wire and cable support is used to convenient portable job site, and the dead weight is light, can remove in a flexible way, can have enough to meet the need convenient operation, safe and reliable, and interim wire and cable support is used to convenient portable job site passes through parcel insulating plastic tubing, plays the insulating effect, guarantees interim power consumption safety, fine solution job site interim wire and cable erect the problem.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a convenient portable job site is with interim cable support which characterized in that: comprises a steel bar stand column (1), a first inclined strut (2) and a second inclined strut (9) which are arranged at the front and the back and are positioned at the right side are welded at the position, close to the middle section, of the bottom of the surface of the steel bar stand column (1) respectively, a steel bar clamping ring (3) is welded at the right side of the surface of the steel bar stand column (1) and between the first inclined strut (2) and the second inclined strut (9) and the steel bar stand column (1), an upper-layer steel bar (4) of a structural bottom plate is arranged at the inner cavity of the steel bar clamping ring (3), a structural bottom plate (5) sleeved on the surfaces of the steel bar stand column (1), the first inclined strut (2) and the second inclined strut (9) is arranged at the bottom of the upper-layer steel bar (4) of the structural bottom plate, short steel bars (6) are welded at the top of the right side of the surface of the steel bar stand column (1), and hanging rings (7, and a hook mechanism (8) is hung on the hanging ring (7).
2. The temporary cable support for the portable construction site according to claim 1, wherein: couple mechanism (8) are including hanging couple (81) on link (7), the one end welding of couple (81) has fixed block (82), the bottom of fixed block (82) is rotated and is connected with rotating block (85), the right side welding of rotating block (85) has rotating tube (83), one side welding of rotating tube (83) inner chamber has spring (86), the one end welding that rotating tube (83) were kept away from in spring (86) has sliding block (87), the one end welding that spring (86) were kept away from in sliding block (87) has pothook (84) of lock joint on couple (81).
3. The temporary cable support for the portable construction site according to claim 2, wherein: the hook (81) is S-shaped, and the bent end of the top of the hook (81) is hung on the hanging ring (7).
4. The temporary cable support for the portable construction site according to claim 1, wherein: the bottom of bracing one (2) and bracing two (9) all inclines to the right side of reinforcing bar stand (1), the inclination of bracing one (2) and bracing two (9) bottom is forty-five degrees.
5. The temporary cable support for the portable construction site according to claim 1, wherein: and insulating plastic pipes are sleeved on the surfaces of the hook mechanism (8), the steel bar upright post (1), the first inclined strut (2) and the second inclined strut (9).
6. The temporary cable support for the portable construction site according to claim 1, wherein: the inner surface of the bend of the steel bar clamping ring (3) is provided with anti-slip grains which are distributed on the surface of the steel bar clamping ring (3) in an inclined and dense mode.
7. The temporary cable support for the portable construction site according to claim 1, wherein: the bottom of the steel bar upright post (1) is provided with an anti-slip pad, and the diameter of the anti-slip pad is the same as that of the bottom of the steel bar upright post (1).
8. The temporary cable support for the portable construction site according to claim 2, wherein: the gap of the hook (84) is the size of a quarter of a ring.
CN202021753866.7U 2020-08-20 2020-08-20 Convenient portable job site uses interim cable support Expired - Fee Related CN212968815U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021753866.7U CN212968815U (en) 2020-08-20 2020-08-20 Convenient portable job site uses interim cable support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021753866.7U CN212968815U (en) 2020-08-20 2020-08-20 Convenient portable job site uses interim cable support

Publications (1)

Publication Number Publication Date
CN212968815U true CN212968815U (en) 2021-04-13

Family

ID=75357127

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021753866.7U Expired - Fee Related CN212968815U (en) 2020-08-20 2020-08-20 Convenient portable job site uses interim cable support

Country Status (1)

Country Link
CN (1) CN212968815U (en)

Similar Documents

Publication Publication Date Title
CN207700821U (en) A kind of upright bar stringer
CN212968815U (en) Convenient portable job site uses interim cable support
CN210029819U (en) Cantilever crane stand reinforcing apparatus
CN210788730U (en) Portable bender is used in building site construction
CN109830917B (en) Device and method for erecting temporary cable
CN110593309B (en) Construction method of full-hall scaffold supporting system with slope comprehensive pipe gallery
CN217642639U (en) Pre-buried tub of protection architecture
CN215212188U (en) Floor type scaffold with side position locking structure
CN214401814U (en) Good foundation ditch side slope supporting construction of stability
CN215290258U (en) Connecting node structure of concrete wall and basic raft
CN210629041U (en) Basement cable overhead support
CN211475059U (en) Municipal works are with pipeline shop line frame
CN220335646U (en) Concrete polishing trowelling machine
CN209071978U (en) A kind of cable bearer and cable protecting device of roller
CN112779917A (en) Good foundation ditch side slope supporting construction of stability
CN202509750U (en) Height-adjustable type scaffold
CN214329991U (en) Walking channel of construction protection roof reinforcing bar
US20100025152A1 (en) Scaffolding platform with materials ledge
CN210608340U (en) Novel convenient couple of interim power cable
CN218324207U (en) Locator is used in wire pole construction
CN218059919U (en) Safe supporting roof is erect to beam slab
CN214116306U (en) Bent cap reinforcing bar bed-jig and bridge construction equipment
CN221568488U (en) Support, construction platform and construction platform for subway shield segment
CN214615213U (en) PVC panel transitional coupling stable structure
CN220619714U (en) Convenient and reliable side form fixing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210413

CF01 Termination of patent right due to non-payment of annual fee