CN212957766U - Wall construction breaker - Google Patents

Wall construction breaker Download PDF

Info

Publication number
CN212957766U
CN212957766U CN202021001120.0U CN202021001120U CN212957766U CN 212957766 U CN212957766 U CN 212957766U CN 202021001120 U CN202021001120 U CN 202021001120U CN 212957766 U CN212957766 U CN 212957766U
Authority
CN
China
Prior art keywords
fixed block
lead screw
water pipe
cylinder
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021001120.0U
Other languages
Chinese (zh)
Inventor
吴懿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Quanzhu Decoration Co ltd
Original Assignee
Shanghai Quanzhu Decoration Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Quanzhu Decoration Co ltd filed Critical Shanghai Quanzhu Decoration Co ltd
Priority to CN202021001120.0U priority Critical patent/CN212957766U/en
Application granted granted Critical
Publication of CN212957766U publication Critical patent/CN212957766U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a wall construction breaker, including PMKD, PMKD's rear end is provided with the backup plate, the backup plate internal rotation is connected with the lead screw, one side of lead screw and PMKD's surface are provided with actuating mechanism, the elevating platform has been cup jointed on the surface of lead screw, the front end fixedly connected with slip table of elevating platform, the top of elevating platform is provided with the fixed block, and the fixed block cup joints in the surface of lead screw, the both sides of fixed block all are provided with the support frame, and the fixed block passes through support frame and elevating platform fixed connection, the front end fixed mounting of fixed block has the cylinder, the bottom of cylinder is provided with the mount, and the cylinder is connected with. The utility model discloses a be provided with water spray mechanism at the top of rig, at the rig during operation, water spray mechanism just can spray water to drilling department, also can cool down the rig when playing the dust fall effect to be provided with the collecting box in the bottom of rig, sewage just can fall into in the collecting box along the swash plate with the rubble.

Description

Wall construction breaker
Technical Field
The utility model relates to a construction field, specific is a wall body construction breaker.
Background
The building is a structure built by all available materials such as soil, stone, wood, steel, glass, reed, plastic, ice blocks and the like. The purpose of the building is not itself, but is to obtain the "space" that the building forms. The artificial environment is created by people by using the grasped substance technical means and applying certain scientific laws, geomantic omen and aesthetic rules in order to meet the needs of social life.
In the construction, often need carry out broken handle to the wall body, the broken rig that mainly adopts of current wall body carries out the operation, and it is carrying out the operation in-process, can cause a large amount of dust in traditional broken rig, causes construction environment's pollution, causes the influence to staff's health, and simultaneously, the rig can produce a large amount of heats after long-time work, causes the influence to rig itself.
SUMMERY OF THE UTILITY MODEL
For solving the not enough that mentions in the above-mentioned background art, the utility model aims to provide a wall body construction breaker, the utility model discloses a be provided with water spray mechanism at the top of rig, at rig during operation, water spray mechanism just can spray water to drilling department, also can cool down the rig when playing the dust fall effect to be provided with the collecting box in the bottom of rig, in sewage just can drop into the collecting box along the swash plate with the rubble.
The purpose of the utility model can be realized by the following technical scheme:
a wall construction crushing device comprises a fixed base plate, wherein a backup plate is arranged at the rear end of the fixed base plate, a lead screw is rotationally connected in the backup plate, and a driving mechanism is arranged on one side of the lead screw and on the surface of the fixed base plate;
the surface of the lead screw is sleeved with a lifting table, the front end of the lifting table is fixedly connected with a sliding table, a fixed block is arranged at the top end of the lifting table and sleeved on the surface of the lead screw, two sides of the fixed block are both provided with supporting frames, and the fixed block is fixedly connected with the lifting table through the supporting frames;
the front end fixed mounting of fixed block has the cylinder, and the bottom of cylinder is provided with the mount, and the cylinder is connected with the fixed block through the mount, and the expansion end of cylinder is provided with the push pedal, and push pedal and slip table sliding connection, and one side that the cylinder was kept away from to the push pedal is provided with the rig, and the top of push pedal is provided with water spray mechanism, is provided with the collecting box on PMKD's surface and water spray mechanism's bottom, and the swash plate has all been welded to the both.
Further, the driving mechanism comprises a driving motor, an output shaft of the driving motor is sleeved with a driving roller, a transmission belt is sleeved on the surface of the driving roller, a driven roller is sleeved on the surface of the bottom of the lead screw, and the driving roller is connected with the driven roller through the transmission belt.
Further, the water spraying mechanism comprises a supporting table, a water tank is arranged at the top end of the supporting table, a first water pipe is arranged at one end, close to the drilling machine, of the water tank, a second water pipe is arranged at one end, far away from the water tank, of the first water pipe, and water spraying guns are distributed at the bottom end of the second water pipe in an array mode.
Furthermore, a first bracket is sleeved on the surface of the first water pipe, the first water pipe is fixedly connected with the supporting table through the first bracket, a second bracket is arranged at the center of the surface of the second water pipe, and the second water pipe is connected with the supporting table through the second bracket.
Further, the one end that the slip table was kept away from to the elevating platform is provided with the connecting rod, and the one end welding that the slip table was kept away from to the connecting rod has the removal slider, and the spout has been seted up on the surface of backup plate, and the elevating platform is through removing slider and backup plate sliding connection.
The utility model has the advantages that:
the utility model discloses a be provided with water spray mechanism at the top of rig, at the rig during operation, water spray mechanism just can spray water to drilling department, also can cool down the rig when playing the dust fall effect to be provided with the collecting box in the bottom of rig, sewage just can fall into in the collecting box along the swash plate with the rubble.
Drawings
The present invention will be further described with reference to the accompanying drawings.
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic view of the connection between the cylinder and the drilling machine of the present invention;
FIG. 3 is a schematic view of the driving mechanism of the present invention;
fig. 4 is a schematic structural view of the water spraying mechanism of the present invention.
In the figure: 1. fixing the bottom plate; 2. a backup plate; 3. a lead screw; 31. a driven roller; 4. a drive mechanism; 41. a drive motor; 42. a drive roll; 43. a drive belt; 5. a lifting platform; 6. a sliding table; 7. a fixed block; 8. a support frame; 9. a cylinder; 10. a fixed mount; 11. pushing the plate; 12. a drilling machine; 13. a water spraying mechanism; 131. a support table; 132. a water tank; 133. a first water pipe; 134. a first bracket; 135. a second water pipe; 136. a second bracket; 137. a water spray gun; 14. a collection box; 15. a sloping plate; 16. a connecting rod; 17. the slider is moved.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "open hole", "upper", "lower", "thickness", "top", "middle", "length", "inner", "around", and the like, indicate positional or positional relationships, are merely for convenience in describing the present invention and to simplify the description, and do not indicate or imply that the components or elements referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore should not be construed as limiting the present invention.
A wall construction crushing device is shown in figures 1 and 2 and comprises a fixing base plate 1, a backup plate 2 is arranged at the rear end of the fixing base plate 1, a lead screw 3 is connected to the backup plate 2 in a rotating mode, and a driving mechanism 4 is arranged on one side of the lead screw 3 and the surface of the fixing base plate 1.
Elevating platform 5 has been cup jointed on lead screw 3's surface, and elevating platform 5's front end fixedly connected with slip table 6, and elevating platform 5's top is provided with fixed block 7, and fixed block 7 cup joints in lead screw 3's surface, and the both sides of fixed block 7 all are provided with support frame 8, and fixed block 7 passes through support frame 8 and elevating platform 5 fixed connection.
The front end fixed mounting of fixed block 7 has cylinder 9, the bottom of cylinder 9 is provided with mount 10, and cylinder 9 is connected with fixed block 7 through mount 10, the expansion end of cylinder 9 is provided with push pedal 11, and push pedal 11 and 6 sliding connection of slip table, one side that cylinder 9 was kept away from to push pedal 11 is provided with rig 12, the top of push pedal 11 is provided with water spray mechanism 13, surface and the bottom of water spray mechanism 13 at PMKD 1 are provided with collecting box 14, swash plate 15 has all been welded to the both sides of collecting box 14.
The one end that slip table 6 was kept away from to elevating platform 5 is provided with connecting rod 16, and the one end welding that slip table 6 was kept away from to connecting rod 16 has a removal slider 17, and the spout has been seted up on the surface of backup plate 2, and elevating platform 5 is through removing slider 17 and backup plate 2 sliding connection, guarantees that elevating platform 5 is more stable at the lift in-process.
As shown in fig. 3, the driving mechanism 4 includes a driving motor 41, an output shaft of the driving motor 41 is sleeved with a driving roller 42, a driving belt 43 is sleeved on a surface of the driving roller 42, a driven roller 31 is sleeved on a bottom surface of the lead screw 3, the driving roller 42 is connected with the driven roller 31 through the driving belt 43, the driving motor 41 drives the driving roller 42 to rotate, and the lead screw 3 can be driven to rotate through the matching of the driving belt 43 and the driven roller 31.
As shown in fig. 4, the water spraying mechanism 13 includes a support table 131, a water tank 132 is disposed at the top end of the support table 131, a first water pipe 133 is disposed at one end of the water tank 132 close to the drilling machine 12, a second water pipe 135 is disposed at one end of the first water pipe 133 far from the water tank 132, water spraying guns 137 are distributed at the bottom end of the second water pipe 135 in an array manner, the water spraying guns 137 are aligned to the drill holes of the drilling machine 12, dust can be effectively prevented from flying, meanwhile, the drilling machine 12 can also be cooled, and the service life of the.
The surface of the first water pipe 133 is sleeved with a first bracket 134, the first water pipe 133 is fixedly connected with the support table 131 through the first bracket 134, the center of the surface of the second water pipe 135 is provided with a second bracket 136, and the second water pipe 135 is connected with the support table 131 through the second bracket 136.
When using, through hugging closely collecting box 14 in the wall, start driving motor 41, driving motor 41 passes through under the cooperation of drive roll 42 and driven voller 31, drive lead screw 3 rotates, make elevating platform 5 be elevating movement, start cylinder 9 and rig 12, cylinder 9 promotes rig 12 and removes towards the wall, and carry out broken drilling to the wall, and simultaneously, start spray gun 137, spray gun 137 is just to drilling department, can effectively prevent the raise dust, and can cool down rig 12, the rubble piece that sewage and drilling produced falls along the wall, make sewage and rubble piece can drop in collecting box 14.
In the description herein, references to the description of "one embodiment," "an example," "a specific example," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention.

Claims (5)

1. A wall construction crushing device comprises a fixed base plate (1), and is characterized in that a backup plate (2) is arranged at the rear end of the fixed base plate (1), a lead screw (3) is rotatably connected to the backup plate (2), and a driving mechanism (4) is arranged on one side of the lead screw (3) and the surface of the fixed base plate (1);
the surface of the lead screw (3) is sleeved with a lifting table (5), the front end of the lifting table (5) is fixedly connected with a sliding table (6), a fixed block (7) is arranged at the top end of the lifting table (5), the fixed block (7) is sleeved on the surface of the lead screw (3), two sides of the fixed block (7) are provided with supporting frames (8), and the fixed block (7) is fixedly connected with the lifting table (5) through the supporting frames (8);
the utility model discloses a pneumatic water spraying device, including fixed block (7), the front end fixed mounting of fixed block (7) has cylinder (9), the bottom of cylinder (9) is provided with mount (10), and cylinder (9) are connected with fixed block (7) through mount (10), the expansion end of cylinder (9) is provided with push pedal (11), and push pedal (11) and slip table (6) sliding connection, one side that cylinder (9) were kept away from in push pedal (11) is provided with rig (12), the top of push pedal (11) is provided with water spray mechanism (13), the surface of PMKD (1) and the bottom of water spray mechanism (13) are provided with collecting box (14), swash plate (15) have all been welded to the both sides of collecting box.
2. The wall construction crushing device according to claim 1, wherein the driving mechanism (4) comprises a driving motor (41), an output shaft of the driving motor (41) is sleeved with a driving roller (42), a transmission belt (43) is sleeved on the surface of the driving roller (42), a driven roller (31) is sleeved on the bottom surface of the lead screw (3), and the driving roller (42) is connected with the driven roller (31) through the transmission belt (43).
3. The wall construction crushing device as claimed in claim 1, wherein the water spraying mechanism (13) comprises a support table (131), a water tank (132) is arranged at the top end of the support table (131), a first water pipe (133) is arranged at one end, close to the drilling machine (12), of the water tank (132), a second water pipe (135) is arranged at one end, far away from the water tank (132), of the first water pipe (133), and water spraying guns (137) are distributed at the bottom end of the second water pipe (135) in an array mode.
4. A wall construction crushing device according to claim 3, wherein a first bracket (134) is sleeved on the surface of the first water pipe (133), the first water pipe (133) is fixedly connected with the support platform (131) through the first bracket (134), a second bracket (136) is arranged at the center of the surface of the second water pipe (135), and the second water pipe (135) is connected with the support platform (131) through the second bracket (136).
5. A wall construction crushing device according to claim 1, wherein a connecting rod (16) is arranged at one end of the lifting platform (5) far away from the sliding table (6), a movable sliding block (17) is welded at one end of the connecting rod (16) far away from the sliding table (6), a sliding groove is formed in the surface of the backup plate (2), and the lifting platform (5) is connected with the backup plate (2) in a sliding manner through the movable sliding block (17).
CN202021001120.0U 2020-06-03 2020-06-03 Wall construction breaker Expired - Fee Related CN212957766U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021001120.0U CN212957766U (en) 2020-06-03 2020-06-03 Wall construction breaker

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021001120.0U CN212957766U (en) 2020-06-03 2020-06-03 Wall construction breaker

Publications (1)

Publication Number Publication Date
CN212957766U true CN212957766U (en) 2021-04-13

Family

ID=75384726

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021001120.0U Expired - Fee Related CN212957766U (en) 2020-06-03 2020-06-03 Wall construction breaker

Country Status (1)

Country Link
CN (1) CN212957766U (en)

Similar Documents

Publication Publication Date Title
CN207970915U (en) A kind of broken scraper bowl of soil remediation
CN212003029U (en) Drilling device that punches that highway maintenance was used
CN116397501A (en) Road surface sampling device and sampling method for road detection
CN110586592B (en) High-efficient cleaning device of cement bucket for building
CN212957766U (en) Wall construction breaker
CN109797979B (en) Wall skin ash shoveling robot
CN211564559U (en) Intelligent drilling equipment is used in construction
CN211313470U (en) Ground floor paint repairing device
CN209849356U (en) Production equipment of flame-retardant wall brick forming machine with leftover material recycling mechanism
CN215060759U (en) Real-time monitoring device for electric power engineering
CN112974353B (en) Cleaning device for building curtain wall and using method thereof
CN215164912U (en) Warning sign is used in civil engineering construction
CN214749036U (en) Quick drilling and coring device for pavement detection
CN211184446U (en) Cutting device for electronic board processing
CN211417350U (en) Multi-use architecture trolley
CN113734896A (en) Water pipe coiling mechanism that agricultural irrigation used
CN215291232U (en) Plastering tool for building construction
CN212074139U (en) Building material transfer device with high adaptability
CN219359387U (en) Auxiliary support for drilling holes in top plate of electric hammer
CN215051849U (en) Road construction is with leveling device
CN212827027U (en) Special portable rubbish compression equipment of environmental protection
CN211842287U (en) Processing device for polyethylene foam adhesive tape base material
CN218406663U (en) Wall putty cleaning device is used to office building fitment
CN215276208U (en) High-efficient recycle device of cement dust waste material
CN212453766U (en) Strutting arrangement is used in prefabricated house construction

Legal Events

Date Code Title Description
GR01 Patent grant