CN212957659U - Embedded flower bed prefabricated mould - Google Patents

Embedded flower bed prefabricated mould Download PDF

Info

Publication number
CN212957659U
CN212957659U CN202022201442.6U CN202022201442U CN212957659U CN 212957659 U CN212957659 U CN 212957659U CN 202022201442 U CN202022201442 U CN 202022201442U CN 212957659 U CN212957659 U CN 212957659U
Authority
CN
China
Prior art keywords
flange
flower bed
mold
baffle
top surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022201442.6U
Other languages
Chinese (zh)
Inventor
雷顺颐
张志文
粟光胜
郑智贤
张友能
屈国建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Dongfang Hongzhuang Construction Technology Co ltd
Hunan Dongfanghong Residential Industry Co ltd
Original Assignee
Hunan Dongfang Hongzhuang Construction Technology Co ltd
Hunan Dongfanghong Residential Industry Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Dongfang Hongzhuang Construction Technology Co ltd, Hunan Dongfanghong Residential Industry Co ltd filed Critical Hunan Dongfang Hongzhuang Construction Technology Co ltd
Priority to CN202022201442.6U priority Critical patent/CN212957659U/en
Application granted granted Critical
Publication of CN212957659U publication Critical patent/CN212957659U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Cultivation Receptacles Or Flower-Pots, Or Pots For Seedlings (AREA)

Abstract

The utility model discloses an embedded flower bed prefabricating mould, which comprises an external mould, an internal mould and a connecting cantilever; the inner mold is arranged in the outer mold, and the top surface of the inner mold is connected with the top surface of the outer mold through the connecting cantilever to form a mold cavity. Reserving flower bed holes on a building matrix when in use; manufacturing a flower bed by utilizing a prefabricated mould, wherein the flower bed comprises a flower bed main body and an overlapping beam, and the overlapping beam comprises a connecting reinforcing steel bar which extends out; filling the flower bed into the hole of the flower bed; and pouring concrete to cover the connecting reinforcing steel bars on the assembling surface of the flower bed and the flower bed hole to form a whole. And the on-site die binding is not needed, so that the operation strength is reduced, the operation safety and the construction efficiency are improved, and the construction period is shortened. And the flower bed is embedded into the building matrix to form a whole after construction is finished, so that the flower bed has reliable safety performance and can be used for high-rise buildings.

Description

Embedded flower bed prefabricated mould
Technical Field
The utility model belongs to the assembly type structure field especially relates to an embedded prefabricated mould of flower pond.
Background
The existing flower bed is mostly placed with the combination flower bed on ground, adopts plastic mold production, then assembles the concatenation, and in the work progress, at the outlying medium and large-scale flower bed of building, can't implement through the combination scheme. Traditional building flower bed mould adopts the artifical wooden template bundle mould disposable that uses in scene more, consumes timber and manual work, and the cost is great, and work efficiency is lower, and high altitude construction has certain construction risk. On the other hand, the flower bed is used as a component for planting plants overhanging the periphery of a building, has higher requirements on waterproofness on the premise of ensuring stable structure, and needs additional complex procedures to ensure waterproofness after various flower beds are assembled at present.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a convenient embedded flower bed prefabrication mould of dismouting to prior art's weak point.
The utility model provides an embedded flower bed prefabricating mould, which comprises an external mould, an internal mould and a connecting cantilever; the inner mold is arranged in the outer mold, and the top surface of the inner mold is connected with the top surface of the outer mold through the connecting cantilever to form a mold cavity.
The outer mold comprises an inner flange, an outer flange, a corner flange and a main rib fixing baffle; the outer flange and the inner flange have the same structure and are both strip flanges, and the length of the inner flange is greater than that of the outer flange; the corner flange is an L-shaped flange; the main rib fixing baffle is a rectangular plate; outer flange and interior flange parallel arrangement, a pair of corner flange is located outer flange both ends, the other end and main muscle fixed stop are continuous, and main muscle fixed stop's the other end links to each other with interior flange.
The inner flange is a rectangular frame, one side of the inner flange in the length direction is provided with an opening, a plurality of vertical rib plates are arranged in the opening, and the top surface of the inner flange is provided with a mounting hole.
The internal mold is a rectangular mold and comprises a long sinking platform baffle, a short sinking platform baffle and a connecting plate; two heavy platform corner baffles are respectively arranged at two ends of the same diagonal line of the internal mold and detachably connected between the two heavy platform long baffles, and the connecting plate is connected in the long side top surface of the heavy platform long baffle.
The long baffle plate of the sinking platform is L-shaped and comprises a long side and a short side, and the outer end faces of the long side and the short side are inclined planes; the sinking platform corner baffle is an L-shaped plate and comprises two short sides, and the outer end surfaces of the two short sides are inclined surfaces; the connecting plate is a rectangular plate, and a plurality of assembling holes are formed in the connecting plate.
The connecting cantilever comprises a cross beam, an outer vertical rod, an inner vertical rod and a bottom plate; the pair of outer vertical rods are respectively arranged at two ends of the cross beam and are in a door shape; the inner vertical rod is connected to the lower part of the middle part of the cross beam; the bottom plates are provided with connecting holes and are respectively arranged at the bottoms of the outer upright stanchion and the inner upright stanchion; the connection cantilever is connected with the outer mold through a bottom plate below the outer vertical rod, and is connected with the inner mold through a bottom below the inner vertical rod.
The utility model discloses arrange the centre form in the die cavity of external mold, encorbelment through the connection and can dismantle the connection, enclose into the pouring die cavity. The inner mold and the outer mold are connected by adopting a cantilever process, the concrete can be demolded after reaching the strength, the prefabricated flower bed can be obtained through maintenance, the mold removal time is early, the production period is short, and the mold is convenient to disassemble and assemble.
Drawings
Fig. 1 is an assembly diagram of a prefabricated mold according to a preferred embodiment of the present invention.
Fig. 2 is an enlarged perspective view of the outer mold in the preferred embodiment.
Fig. 3 is a schematic perspective view of the inner mold in the preferred embodiment.
Fig. 4 is an enlarged perspective view of the connection cantilever in the preferred embodiment.
Sequence numbers of the drawings:
1-outer mold, 11-inner flange, 12-outer flange, 13-corner flange, 14-main rib fixed flange;
2-internal mold, 21-long sinking platform baffle, 22-short sinking platform baffle and 23-connecting plate;
3-connecting cantilever, 31-crossbeam, 32-outer upright rod, 33-inner force rod and 34-bottom plate;
Detailed Description
As shown in fig. 1, the embedded prefabricated flower bed die disclosed in this embodiment includes an external die 1, an internal die 2 and a connection cantilever 3; the inner mold 2 is arranged in the outer mold 1, the top surface of the inner mold is connected with the top surface of the outer mold through the connecting cantilever 3 to form a mold cavity, then concrete is not poured into the mold cavity, and the curing and demolding are carried out. Meanwhile, the outer die 1, the inner die 2 and the connecting cantilever 3 are designed to be assembled for the convenience of assembly and demolding.
As shown in fig. 2, the outer mold 1 includes an inner rib 11, an outer rib 12, a corner rib 13, and a main rib fixing baffle 14. Wherein, the outer flange 11 and the inner flange 12 have the same structure and are rectangular frames, one side of the outer flange in the length direction is provided with an opening, a plurality of vertical rib plates are arranged in the opening, and the top surface of the outer flange is provided with a mounting hole. The corner flange 12 is an L-shaped flange and comprises two sections, and the length of one end of the L-shaped flange is equal to the length difference between the outer flange and the inner flange. The main rib fixing baffle 14 is a rectangular plate. During assembly, the outer flanges and the inner flanges are arranged in parallel, the two ends of the outer flanges are respectively arranged on the pair of corner flanges, the other ends of the pair of corner flanges are connected with the main rib fixing baffle, and the other ends of the main rib fixing baffle are connected with the inner flanges. Compensate the length difference of interior flange and outer flange through the corner flange, form the bar region between corner flange and interior flange, during the pouring, pre-buried connecting reinforcement in the bar region, the outer end of practicing level reinforcing bar extends outside the main muscle fixed stop for form the overlap beam 42 in the bar region. And the other side of the corner rib, the main area surrounded by the outer rib and the inner rib is used for installing the inner mold 2, so as to form a mold cavity for pouring the flower bed main body 41.
As shown in fig. 3, the inner mold 2 is a rectangular mold, and includes a long sinking platform baffle 21, a short sinking platform baffle 22 and a connecting plate 23; the long baffle plate 21 of the sinking platform is L-shaped and comprises a long side and a short side, and the outer end faces of the long side and the short side are inclined planes; the sinking platform corner baffle 22 is an L-shaped plate and comprises two short sides, and the outer end surfaces of the two short sides are inclined surfaces; the connecting plate 23 is a rectangular plate, and a plurality of assembling holes are arranged on the connecting plate. When assembling. The two sinking platform corner baffles are respectively arranged at two ends of the same diagonal line of the internal mold and detachably connected between the two sinking platform long baffles, and the connecting plate is connected in the top surface of the long edge of the sinking platform long baffle. Because the concatenation face of sinking the platform long baffle and sinking the platform short baffle is the inclined plane to in the form removal, and when the form removal, adopt diagonal concatenation scheme, can with the heavy platform short baffle of diagonal both ends drawing of patterns earlier, take off the long baffle of sinking platform and further improve the convenient degree of form removal, the equipment of being convenient for, and can be according to the operation requirement of different length, choose for use the heavy platform long baffle of different length can, do benefit to and improve the commonality, realize the modularization. The inner die 2 is arranged in the die cavity of the outer die 1 after being assembled, and can be detachably connected through the connection cantilever 3 to form a pouring die cavity.
As shown in fig. 4, the connection cantilever 3 includes a cross member 31, an outer upright 32, an inner upright 33, and a bottom plate 34; the pair of outer vertical rods are respectively arranged at two ends of the cross beam and are in a door shape; the inner vertical rod is connected to the lower part of the middle part of the cross beam; the bottom plates are provided with connecting holes and are respectively arranged at the bottoms of the outer upright stanchion and the inner upright stanchion; the connection cantilever is connected with the outer mold through a bottom plate below the outer vertical rod, and is connected with the inner mold through a bottom below the inner vertical rod. The inner mold and the outer mold are connected by adopting a cantilever process, and the concrete can be demoulded after reaching the strength and maintained to obtain the prefabricated flower bed. The concrete is directly poured in one step in the flower bed, and the waterproof performance can be guaranteed while the requirement for strength is met.
By adopting the embodiment to manufacture the flower bed, the on-site die binding is not needed, the operation intensity is reduced, the operation safety and the construction efficiency are improved, and the construction period is shortened conveniently. And the mould can reuse, can material saving. On the other hand, after the construction is finished, the flower bed is embedded into the building matrix to form a whole, so that the flower bed has reliable safety performance and can be used for high-rise buildings.

Claims (5)

1. The utility model provides an embedded flower bed prefabricated mould which characterized in that: it comprises an external mold, an internal mold and a connecting cantilever; the inner die is arranged in the outer die, and the top surface of the inner die is connected with the top surface of the outer die through the connecting cantilever to form a die cavity; the connecting cantilever comprises a cross beam, an outer vertical rod, an inner vertical rod and a bottom plate; the pair of outer vertical rods are respectively arranged at two ends of the cross beam and are in a door shape; the inner vertical rod is connected to the lower part of the middle part of the cross beam; the bottom plates are provided with connecting holes and are respectively arranged at the bottoms of the outer upright stanchion and the inner upright stanchion; the connection cantilever is connected with the outer mold through a bottom plate below the outer vertical rod, and is connected with the inner mold through a bottom below the inner vertical rod.
2. The embedded type flower bed prefabrication mold of claim 1, wherein: the outer mold comprises an inner flange, an outer flange, a corner flange and a main rib fixing baffle; the outer flange and the inner flange have the same structure and are both strip flanges, and the length of the inner flange is greater than that of the outer flange; the corner flange is an L-shaped flange; the main rib fixing baffle is a rectangular plate; outer flange and interior flange parallel arrangement, a pair of corner flange is located outer flange both ends, the other end and main muscle fixed stop are continuous, and main muscle fixed stop's the other end links to each other with interior flange.
3. The embedded type flower bed prefabrication mold of claim 2, wherein: the inner flange is a rectangular frame, one side of the inner flange in the length direction is provided with an opening, a plurality of vertical rib plates are arranged in the opening, and the top surface of the inner flange is provided with a mounting hole.
4. The embedded type flower bed prefabrication mold of claim 1, wherein: the internal mold is a rectangular mold and comprises a long sinking platform baffle, a short sinking platform baffle and a connecting plate; two heavy platform corner baffles are respectively arranged at two ends of the same diagonal line of the internal mold and detachably connected between the two heavy platform long baffles, and the connecting plate is connected in the long side top surface of the heavy platform long baffle.
5. The pre-fabricated mold for embedded flower bed of claim 4, wherein: the long baffle plate of the sinking platform is L-shaped and comprises a long side and a short side, and the outer end faces of the long side and the short side are inclined planes; the sinking platform corner baffle is an L-shaped plate and comprises two short sides, and the outer end surfaces of the two short sides are inclined surfaces; the connecting plate is a rectangular plate, and a plurality of assembling holes are formed in the connecting plate.
CN202022201442.6U 2020-09-30 2020-09-30 Embedded flower bed prefabricated mould Active CN212957659U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022201442.6U CN212957659U (en) 2020-09-30 2020-09-30 Embedded flower bed prefabricated mould

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022201442.6U CN212957659U (en) 2020-09-30 2020-09-30 Embedded flower bed prefabricated mould

Publications (1)

Publication Number Publication Date
CN212957659U true CN212957659U (en) 2021-04-13

Family

ID=75371329

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022201442.6U Active CN212957659U (en) 2020-09-30 2020-09-30 Embedded flower bed prefabricated mould

Country Status (1)

Country Link
CN (1) CN212957659U (en)

Similar Documents

Publication Publication Date Title
CN213174446U (en) Assembled UHPC superimposed sheet shear force wall prefabricated construction with mandrel
CN201872232U (en) Vertical cable channel formwork
CN207110166U (en) A kind of prefabricated PC close rib building roof composite plate
CN112976249B (en) Manufacturing template of laminated slab bottom plate with grooves in plate edges and production method
CN212957659U (en) Embedded flower bed prefabricated mould
CN109267585A (en) Assembled prismoid shaped basis and rod structure and assembly method
CN105946099B (en) Fill the method for construction of core assembly concrete beam
CN202595984U (en) Cast-in-place concrete hollow floor system box die
CN207647033U (en) A kind of precast reinforced basket structure
CN112065049A (en) Construction method of embedded flower bed
CN209227579U (en) Assembled prismoid shaped basis and rod structure
CN111663695A (en) Assembly type template-free box-type floor system and construction process thereof
CN111391112B (en) Production method of prefabricated reinforced concrete hollow template with internal crossed holes
CN220945881U (en) General mould of assembled prefabricated shear force wall side forms
CN211993469U (en) Processing die of alloy net combined ecological plate
CN208343115U (en) A kind of prefabricated components formwork erection production equipment
CN206718140U (en) A kind of mould for producing pre-stressed concrete hollow support pile
CN206123901U (en) Mould for prefabricated staircase
CN213654867U (en) One-step casting and forming die frame system for small-section tunnel
CN217621230U (en) Flexible assembling die of precast concrete post girder steel
CN219430506U (en) Combined assembly type bent cap
CN216543857U (en) Hollow concrete block mould
CN220972745U (en) Precast concrete stake wall mould and precast concrete stake wall mould group
CN217353124U (en) Prefabricated assembled reinforced concrete superimposed sheet structure
CN217372753U (en) Steel form is used in processing of concrete prefabricated section

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant