CN212927003U CN202021137952.5U CN202021137952U CN212927003U CN 212927003 U CN212927003 U CN 212927003U CN 202021137952 U CN202021137952 U CN 202021137952U CN 212927003 U CN212927003 U CN 212927003U
Authority
CN
China
Prior art keywords
plate
board
scaffold
fixedly connected
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021137952.5U
Other languages
Chinese (zh)
Inventor
邓骥
童显祥
田守富
詹安菊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Construction Engineering Second Construction Co ltd
Original Assignee
Hubei Construction Engineering Second Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Construction Engineering Second Construction Co ltd filed Critical Hubei Construction Engineering Second Construction Co ltd
Priority to CN202021137952.5U priority Critical patent/CN212927003U/en
Application granted granted Critical
Publication of CN212927003U publication Critical patent/CN212927003U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model belongs to the technical field of building devices, in particular to a building high-rise scaffold erection plate, which is not convenient for workers to carry aiming at the existing scaffold erection plate, so that the laying and dismounting efficiency of the scaffold erection plate is lower, and the middle of the scaffold can generate an angle slope, so that the scaffold erection plate is difficult to be jointed with the scaffold, thereby generating the problem of potential safety hazard, the utility model provides a proposal which comprises a first erection plate and a second erection plate, wherein one side of the first erection plate is rotationally connected with one side of a connecting plate, the other side of the connecting plate is rotationally connected with one side of the second erection plate, the bottoms of the first erection plate and the second erection plate are respectively provided with two mounting grooves, the utility model is convenient for the workers to carry by a folding mode, improves the laying and dismounting efficiency of the scaffold erection plate, and facilitates the scaffold erection plate to be jointed with the scaffold, the potential safety hazard is reduced.

Description

Building high-rise scaffold erecting plate
Technical Field
The utility model relates to a building technical field especially relates to a building high-rise scaffold erects board.
Background
When a building is built, scaffolds are indispensable to be erected, the importance of erecting the scaffolds can be more and more highlighted along with the improvement of floors, on one hand, the scaffold can prevent falling objects in the building process from causing safety threats to pedestrians, on the other hand, a construction platform can be provided for constructors to facilitate construction of the edge area of the building, the number of the scaffolds is increasing day by day, and at present, most of erection plates among the scaffolds place common flat wood plates on the scaffolds so that constructors can carry out construction operation on the scaffold;
but the present scaffold puts up the board often is not convenient for the workman to carry for the scaffold puts up laying and dismantling efficiency of board is lower, and the centre of scaffold can produce the slope of angle, makes the scaffold put up the board and is difficult to laminate mutually with the scaffold, has produced the potential safety hazard.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving present scaffold and setting up the board and often not being convenient for the workman carry for laying of scaffold and setting up the board and dismantling efficiency are lower, and the centre of scaffold can produce the slope of angle, make scaffold set up the board and be difficult to laminate mutually with the scaffold, have produced the shortcoming of potential safety hazard, and the high-rise scaffold of building that provides sets up the board.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
building high-rise scaffold puts up board, set up the board including first board and the second of setting up, first one side of setting up the board is rotated and is connected with one side of connecting plate, the opposite side of connecting plate is rotated with one side of second setting up the board and is connected, two mounting grooves have all been seted up to the bottom of first board and the second setting up the board, equal fixedly connected with bearing in four mounting grooves, equal fixed mounting has the one end of connecting the round bar in four bearings, four equal fixedly connected with adapter sleeves of the other end of connecting the round bar, equal fixedly connected with connects fixed ear on four adapter sleeves, the opposite side of first board of setting up is opened and is accomodate the groove, accomodate inslot slidable mounting has first connecting element, the opposite side of board is set up to the second rotates and is connected with second connecting element, first connecting element cooperatees with second connecting element.
Preferably, all seted up the spout on the both sides inner wall of accomodating the groove, equal slidable mounting has the slider in two spouts, and two sliders are close to the same horizontal pole of one side fixedly connected with each other, fixedly connected with connecting rod on the horizontal pole, and the one end of connecting rod is rotated with one side of first connecting element and is connected, and the slider can remove along the spout.
Preferably, the first connecting element is provided with a groove, the inner walls of the two sides of the groove are provided with clamping grooves, the two sides of the second erection plate are provided with spring grooves, the two spring grooves are provided with clamping rods, the two clamping rods are respectively matched with the two clamping grooves, and the clamping grooves can lock the second connecting element through the clamping rods.
Preferably, the slide of putting through mutually with two spring slots is seted up respectively to the bottom that the board was set up to the second, and equal slidable mounting has the slide bar in two slides, and the one end of two slide bars extends respectively to two spring slots in and with one side fixed connection of two kellies, the other end of two slide bars extend respectively to the outside that the board was set up to the second and fixedly connected with auxiliary block, and the slide bar can drive the kellies and remove.
Preferably, the one end of equal fixedly connected with spring on the inner wall of one side of two spring grooves, the other end of two springs respectively with the one end fixed connection of two kellies, the spring can drive the kellies and reset.
Compared with the prior art, the utility model has the advantages of:
(1) according to the scheme, the bearing is matched with the connecting round rod, and the first erection plate and the second erection plate are matched with the connecting plate, so that the erection plates can be well attached to a scaffold, and the scaffold is convenient to fold and carry;
(2) according to the scheme, the clamping rod is matched with the clamping groove, and the second connecting element is matched with the groove, so that the erection plates are conveniently connected with each other, and the first erection plate and the second erection plate are conveniently folded and fixed;
the utility model discloses in carry through folding mode workman of being convenient for, promote the efficiency of laying and dismantling of scaffold frame set up board to make scaffold frame set up the board and be convenient for laminate mutually with the scaffold frame, reduced the potential safety hazard.
Drawings
Fig. 1 is a schematic structural view of a building high-rise scaffold erection plate provided by the utility model;
fig. 2 is a schematic structural view of the connection between the connection rod of the high-rise scaffold erection plate and the first connection element;
fig. 3 is a schematic side view of a second connecting element of the high-rise scaffold erection plate of the building provided by the utility model;
fig. 4 is an enlarged schematic structural view of a place a in fig. 1 of the building high-rise scaffold erection plate provided by the utility model;
fig. 5 is an enlarged schematic structural view of B in fig. 1 of the building high-rise scaffold erecting plate of the present invention.
In the figure: the device comprises a first erection plate 1, a second erection plate 2, a connecting plate 3, a bearing 4, a connecting round rod 5, a connecting sleeve 6, a connecting and fixing lug 7, a containing groove 8, a cross rod 9, a connecting rod 10, a first connecting element 11, a clamping groove 12, a second connecting element 13, a groove 14, a sliding block 15, a clamping rod 16, a sliding rod 17, an auxiliary block 18 and a spring 19.
Detailed Description
The technical solutions in the embodiments will be described clearly and completely with reference to the drawings in the embodiments, and it is obvious that the described embodiments are only a part of the embodiments, but not all embodiments.
Example one
Referring to fig. 1-5, a building high-rise scaffold erecting plate comprises a first erecting plate 1 and a second erecting plate 2, one side of the first erecting plate 1 is rotatably connected with one side of a connecting plate 3, the other side of the connecting plate 3 is rotatably connected with one side of the second erecting plate 2, two mounting grooves are formed in the bottoms of the first erecting plate 1 and the second erecting plate 2, bearings 4 are fixedly connected in four mounting grooves, one ends of connecting round rods 5 are fixedly mounted in the four bearings 4, connecting sleeves 6 are fixedly connected with the other ends of the connecting round rods 5, fixing lugs 7 are fixedly connected with the four connecting sleeves 6, a containing groove 8 is formed in the other side of the first erecting plate 1, a first connecting element 11 is slidably mounted in the containing groove 8, a second connecting element 13 is rotatably connected with the other side of the second erecting plate 2, and the first connecting element 11 is matched with the second connecting element 13.
In this embodiment, all seted up the spout on the both sides inner wall of holding groove 8, equal slidable mounting has slider 15 in two spouts, and two sliders 15 are close to the same horizontal pole 9 of one side fixedly connected with each other, fixedly connected with connecting rod 10 on the horizontal pole 9, and the one end of connecting rod 10 rotates with one side of first connecting element 11 to be connected, and slider 15 can remove along the spout.
In this embodiment, a groove 14 is formed in the first connecting element 11, clamping grooves 12 are formed in inner walls of two sides of the groove 14, spring grooves are formed in two sides of the second erection plate 2, clamping rods 16 are slidably mounted in the two spring grooves, the two clamping rods 16 are respectively matched with the two clamping grooves 12, and the clamping grooves 12 can lock the second connecting element 13 through the clamping rods 16.
In this embodiment, the bottom of the second erection plate 2 is respectively provided with a slideway communicated with the two spring grooves, the two slideways are internally provided with a sliding rod 17, one ends of the two sliding rods 17 respectively extend into the two spring grooves and are fixedly connected with one sides of the two clamping rods 16, the other ends of the two sliding rods 17 respectively extend to the outer side of the second erection plate 2 and are fixedly connected with an auxiliary block 18, and the sliding rods 17 can drive the clamping rods 16 to move.
In this embodiment, equal fixedly connected with spring 19's one end on the one side inner wall of two spring grooves, two spring 19's the other end respectively with two kelly 16's one end fixed connection, spring 19 can drive kelly 16 and reset.
Example two
Referring to fig. 1-5, the building high-rise scaffold erecting plate comprises a first erecting plate 1 and a second erecting plate 2, one side of the first erecting plate 1 is rotatably connected with one side of a connecting plate 3, the other side of the connecting plate 3 is rotatably connected with one side of the second erecting plate 2, two mounting grooves are respectively formed at the bottoms of the first erecting plate 1 and the second erecting plate 2, bearings 4 are respectively connected in the four mounting grooves by welding, one end of a connecting round rod 5 is respectively fixedly mounted in the four bearings 4 by welding, the other ends of the four connecting round rods 5 are respectively fixedly connected with connecting sleeves 6 by welding, connecting fixing lugs 7 are respectively fixedly connected on the four connecting sleeves 6 by welding, a receiving groove 8 is formed at the other side of the first erecting plate 1, a first connecting element 11 is slidably mounted in the receiving groove 8, and a second connecting element 13 is rotatably connected at the other side of the second erecting plate 2, the first connecting element 11 cooperates with the second connecting element 13.
In this embodiment, all seted up the spout on the both sides inner wall of holding groove 8, equal slidable mounting has slider 15 in two spouts, and the same horizontal pole 9 of welded fastening connection is passed through to one side that two sliders 15 are close to each other, and through welded fastening connection connecting rod 10 on the horizontal pole 9, the one end of connecting rod 10 is rotated with one side of first connecting element 11 and is connected, and slider 15 can remove along the spout.
In this embodiment, a groove 14 is formed in the first connecting element 11, clamping grooves 12 are formed in inner walls of two sides of the groove 14, spring grooves are formed in two sides of the second erection plate 2, clamping rods 16 are slidably mounted in the two spring grooves, the two clamping rods 16 are respectively matched with the two clamping grooves 12, and the clamping grooves 12 can lock the second connecting element 13 through the clamping rods 16.
In this embodiment, the bottom of second set up board 2 sets up the slide of putting through mutually with two spring slots respectively, and equal slidable mounting has slide bar 17 in two slides, and the one end of two slide bars 17 extends to two spring slots respectively and passes through welded fastening with one side of two kellies 16 to be connected, and the other end of two slide bars 17 extends to the outside of second set up board 2 respectively and is connected with supplementary piece 18 through welded fastening, and slide bar 17 can drive kellies 16 and remove.
In this embodiment, all be connected with the one end of spring 19 through welded fastening on the one side inner wall of two spring grooves, the other end of two springs 19 passes through welded fastening with the one end of two kellies 16 respectively to be connected, and spring 19 can drive kellies 16 and reset.
In the embodiment, when the scaffold connecting device is used, the connecting round rod 5 can be rotated through the bearing 4, so that the angle of the connecting sleeve 6 is convenient to adjust, the connecting sleeve 6 is attached to a scaffold steel pipe, the first erection plate 1 and the second erection plate 2 can be fixed by screwing bolts through the connecting fixing lugs 7, the angle between the first erection plate 1 and the second erection plate 2 can be adjusted through the connecting plate 3, the first erection plate 1 and the second erection plate 2 are convenient to attach to the scaffold steel pipe, then the second connecting element 13 corresponds to the groove 14, the clamping rod 16 corresponds to the clamping groove 12, then the sliding rod 17 is pulled through the auxiliary block 18, the sliding rod 17 drives the clamping rod 16 to displace and deform the spring 19 until the clamping rod 16 is embedded with the clamping groove 12, then the sliding block 15 slides in the sliding groove, so that the first connecting element 11 drives the second connecting element 13 to be hidden in the accommodating groove 8 together, when the use is not needed, the first erection plate 1 can be rotated through the connection plate 3 to achieve the purpose of folding with the second erection plate 2, and finally the first connection element 11 and the second connection element 13 are connected in the same way, so as to facilitate the fixation after folding.
The above descriptions are only preferred embodiments of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the scope of the present invention, and the technical solutions and the utility model concepts of the present invention are equivalent to, replaced or changed.

Claims (5)

1. Building high-rise scaffold puts up board, set up the board including first board and the second of setting up, a serial communication port, first one side of setting up the board is rotated and is connected with one side of connecting plate, the opposite side of connecting plate and one side of second setting up the board are rotated and are connected, two mounting grooves have all been seted up to first board and the bottom of second setting up the board, equal fixedly connected with bearing in four mounting grooves, equal fixed mounting has the one end of connecting the round bar in four bearings, four equal fixedly connected with adapter sleeves of the other end of connecting the round bar, equal fixedly connected with connects fixed ear on four adapter sleeves, first opposite side of setting up the board is opened has and is accomodate the groove, accomodate inslot slidable mounting has first connecting element, the opposite side that the board was set up to the second rotates and is connected with second connecting element, first connecting element cooperatees with second connecting element.
2. The building high-rise scaffold erecting plate according to claim 1, wherein sliding grooves are formed in inner walls of two sides of the receiving groove, sliding blocks are slidably mounted in the two sliding grooves, one side, close to each other, of the two sliding blocks is fixedly connected with a same cross bar, a connecting rod is fixedly connected to the cross bar, and one end of the connecting rod is rotatably connected with one side of the first connecting element.
3. The building high-rise scaffold erecting plate as claimed in claim 1, wherein the first connecting element is provided with a groove, the inner walls of the groove are provided with a clamping groove, the inner walls of the groove are provided with a spring groove, the spring groove is provided with a spring groove, a clamping rod is slidably mounted in each spring groove, and the two clamping rods are respectively matched with the two clamping grooves.
4. The building high-rise scaffold erecting plate of claim 1, wherein the bottom of the second erecting plate is respectively provided with a slideway communicated with the two spring grooves, the two slideways are respectively and slidably provided with a slide bar, one end of each slide bar respectively extends into the two spring grooves and is fixedly connected with one side of each clamping rod, and the other end of each slide bar respectively extends to the outer side of the second erecting plate and is fixedly connected with an auxiliary block.
5. The building high scaffold erection plate of claim 3, wherein one ends of the springs are fixedly connected to one inner wall of each of the two spring grooves, and the other ends of the springs are fixedly connected to one ends of the two clamping rods, respectively.
CN202021137952.5U 2020-06-18 2020-06-18 Building high-rise scaffold erecting plate Active CN212927003U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021137952.5U CN212927003U (en) 2020-06-18 2020-06-18 Building high-rise scaffold erecting plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021137952.5U CN212927003U (en) 2020-06-18 2020-06-18 Building high-rise scaffold erecting plate

Publications (1)

Publication Number Publication Date
CN212927003U true CN212927003U (en) 2021-04-09

Family

ID=75323945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021137952.5U Active CN212927003U (en) 2020-06-18 2020-06-18 Building high-rise scaffold erecting plate

Country Status (1)

Country Link
CN (1) CN212927003U (en)

Similar Documents

Publication Publication Date Title
CN204001647U (en) Demountable combined-type Mobile operating platform
CN212927003U (en) Building high-rise scaffold erecting plate
CN204826593U (en) A portable supplementary operation platform for steel construction support body
CN207194417U (en) A kind of engineering construction scaffold
CN210976538U (en) Foldable scaffold
CN205250939U (en) Portable easel
CN210918316U (en) Elevator shaft opening safety protection device
CN115637839B (en) Quick assembly disassembly structure for building scaffold
CN209620560U (en) A kind of novel climbing frame hanging seat
CN212957716U (en) Safety protection structure of folding assembly joint plate
CN210369828U (en) High temporary support of security for construction
CN112065020B (en) Combined scaffold for civil engineering
CN208363574U (en) A kind of convenient clamping type climbing frame limit safety lock
CN107642232A (en) The horizontal connection structure and system and construction method of a kind of shuttering supporting
CN211736646U (en) Telescopic windproof combined enclosure
CN210659187U (en) Decoration construction platform frame
CN209082712U (en) A kind of movable plank house that stability is high
CN206034872U (en) Folding horse stool
CN220014394U (en) Foldable scaffold for indoor construction
CN207959863U (en) A kind of door-type scaffold
CN207499379U (en) A kind of scaffold with fixed diagonal brace
CN211949494U (en) Foldable scaffold for building construction
CN215331286U (en) Building construction is with slidable regulation's rack of building
CN211229789U (en) Rail guard for building safety
CN215631411U (en) Quick assembly disassembly scaffold frame is used in construction in room

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant