CN212896316U - Hydraulic engineering building foundation pile - Google Patents

Hydraulic engineering building foundation pile Download PDF

Info

Publication number
CN212896316U
CN212896316U CN202021760816.1U CN202021760816U CN212896316U CN 212896316 U CN212896316 U CN 212896316U CN 202021760816 U CN202021760816 U CN 202021760816U CN 212896316 U CN212896316 U CN 212896316U
Authority
CN
China
Prior art keywords
foundation pile
protective sleeve
hydraulic engineering
engineering building
lag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021760816.1U
Other languages
Chinese (zh)
Inventor
杜毅治
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021760816.1U priority Critical patent/CN212896316U/en
Application granted granted Critical
Publication of CN212896316U publication Critical patent/CN212896316U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a hydraulic engineering building foundation pile, including the lag, the top of lag is inlayed and is equipped with the roof, the bottom of roof is fixed with the foundation pile that is the matrix distribution, the top of lag is fixed with the supporting station through the gim peg, be connected with a plurality of bracing pieces between the inner wall of foundation pile and lag, the bottom of lag is inlayed and is equipped with about board, about board cover is established on the foundation pile to hydraulic engineering building foundation pile has bigger bearing capacity, and can keep apart rivers and directly erode the pile body, guarantees that the foundation pile can not destroyed by the erosion, makes the bulk strength of foundation pile better, strengthens the wholeness and the stability of foundation pile, makes its better actual demand that satisfies.

Description

Hydraulic engineering building foundation pile
Technical Field
The utility model relates to a hydraulic engineering technical field specifically is a hydraulic engineering building foundation pile.
Background
The hydraulic engineering refers to various engineering (including new construction, extension, reconstruction, reinforcement, restoration, dismantling and other projects) such as flood control, flood drainage, irrigation, hydroelectric generation, water diversion (supply), mud flat treatment, water and soil conservation, water resource protection and the like, and matching and auxiliary projects thereof.
The existing building foundation pile has the advantages that in the actual use process of hydraulic engineering, the phenomena of exposed ribs, insufficient thickness of a protective layer and the like can be generated under the scouring action of water flow on a pile foundation, the pile bearing capacity is affected, in addition, the foundation pile is in direct contact with external water, concrete is damaged and cracked, holes are formed in the pile foundation, the cross section of the pile foundation is seriously weakened, and the corrosion seriously threatens the safety of the structure, so that the hydraulic engineering building foundation pile is provided.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a hydraulic engineering building foundation pile has solved the above-mentioned problem that proposes.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: a foundation pile for a hydraulic engineering building comprises a protective sleeve, wherein a top plate is embedded in the top of the protective sleeve, and foundation piles distributed in a matrix form are fixed at the bottom of the top plate;
a supporting table is fixed at the top of the protective sleeve through a fixing bolt;
a plurality of support rods are connected between the foundation pile and the inner wall of the protective sleeve;
and a restraint plate is embedded at the bottom of the protective sleeve and is sleeved on the foundation pile.
Preferably, the top of the protective sleeve is provided with an installation groove, the top plate is positioned in the installation groove, and the fixing bolt sequentially penetrates through the supporting table and the top plate and is fixed on the inner bottom surface of the installation groove.
Preferably, the bottom of the protective sleeve is provided with a connecting groove, the outside of the restraint plate is sleeved with a connecting plate of an annular structure, and the connecting plate is fixed in the connecting groove.
Preferably, the restraint plate is provided with positioning holes distributed in a matrix shape, the foundation piles extend out of the positioning holes, and the foundation piles are welded in the inner walls of the positioning holes.
Preferably, the outer wall of the protective sleeve is coated with a protective layer, and the bottom of the foundation pile is of a conical structure.
(III) advantageous effects
The utility model provides a hydraulic engineering building foundation pile. The method has the following beneficial effects: under the combined action of each part, hydraulic engineering building foundation pile has bigger bearing capacity, and can keep apart rivers and directly erode the pile body, guarantee that the foundation pile can not be corroded and destroyed, make the bulk strength of foundation pile better, the wholeness and the stability of reinforcing foundation pile make its better satisfy actual demand.
Drawings
FIG. 1 is a schematic sectional view of the present invention;
fig. 2 is a schematic top view of the restraint plate of the present invention;
fig. 3 is a schematic structural diagram of the present invention.
In the figure: 1. a protective sleeve; 2. a protective layer; 3. a top plate; 4. a support table; 5. a fixing bolt; 6. foundation piles; 7. a restraint plate; 8. a connecting plate; 9. connecting grooves; 10. mounting grooves; 11. a support bar; 12. and (7) positioning the holes.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: a hydraulic engineering building foundation pile comprises a protective sleeve 1, wherein a top plate 3 is embedded in the top of the protective sleeve 1, a supporting table 4 is fixed to the top of the protective sleeve 1 through a fixing bolt 5, a mounting groove 10 is formed in the top of the protective sleeve 1, the top plate 3 is located in the mounting groove 10, the top plate 3 is matched with the mounting groove 10, the fixing bolt 5 sequentially penetrates through the supporting table 4 and the top plate 3 and is fixed to the inner bottom surface of the mounting groove 10, the integrity of the supporting table 4, the top plate 3 and the protective sleeve 1 is maintained under the action of the fixing bolt 5, the top surface of the fixing bolt 5 is lower than the top surface of the supporting table 4, foundation piles 6 distributed in a matrix mode are fixed to the bottom of the top plate 3, and the matrix distribution of the foundation piles 6 enables the overall stability to be better;
a plurality of support rods 11 are connected between the foundation pile 6 and the inner wall of the protective sleeve 1, so that the overall connectivity of the protective sleeve is better;
the bottom of lag 1 is inlayed and is equipped with restraint panel 7, the spread groove 9 has been seted up to the bottom of lag 1, the outside cover of restraint panel 7 is equipped with the connecting plate 8 of loop configuration, connecting plate 8 is fixed in spread groove 9, and connecting plate 8 passes through the connecting bolt to be fixed in spread groove 9 or scaffold weldment is in spread groove 9, restraint panel 7 cover is established on foundation pile 6, be equipped with the locating hole 12 that is the matrix distribution on the restraint panel 7, foundation pile 6 stretches out from locating hole 12, foundation pile 6 welds in the inner wall of locating hole 12, makes its relative leakproofness of guaranteeing the inside of lag 1 can not intake.
The outer wall coating of lag 1 has inoxidizing coating 2, increases lag 1's corrosion-resistant characteristic, the bottom of foundation pile 6 is the taper structure, and the convenient grafting of taper structure is used.
Therefore, the whole assembly is convenient during the tooling, the bottom end of the foundation pile 6 can be inserted into a designated position during the use, the supporting effect is achieved, the outer part of the foundation pile 6 is protected in the protective sleeve 1, the foundation pile is prevented from being corroded, the influence on the foundation pile is avoided, the supporting rod 11 is connected between the foundation pile 6 and the protective sleeve 1, the foundation pile has good impact resistance, the whole stability is kept, and the whole rigidity is better;
thereby hydraulic engineering building foundation pile has bigger bearing capacity, and can keep apart rivers and to the direct scouring of pile body, guarantees that the foundation pile can not be corroded the destruction, makes the bulk strength of foundation pile better, strengthens the wholeness and the stability of foundation pile, makes its better satisfied actual demand.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation. The use of the phrase "comprising one of the elements does not exclude the presence of other like elements in the process, method, article, or apparatus that comprises the element.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. A hydraulic engineering building foundation pile is characterized in that: the protective sleeve comprises a protective sleeve (1), wherein a top plate (3) is embedded in the top of the protective sleeve (1), and foundation piles (6) distributed in a matrix form are fixed at the bottom of the top plate (3);
a supporting table (4) is fixed at the top of the protective sleeve (1) through a fixing bolt (5);
a plurality of support rods (11) are connected between the foundation pile (6) and the inner wall of the protective sleeve (1);
and a restraint plate (7) is embedded at the bottom of the protective sleeve (1), and the restraint plate (7) is sleeved on the foundation pile (6).
2. The hydraulic engineering building foundation pile of claim 1, wherein: mounting groove (10) have been seted up at the top of lag (1), roof (3) are arranged in mounting groove (10), gim peg (5) run through supporting bench (4), roof (3) in proper order and fix on the interior bottom surface of mounting groove (10).
3. The hydraulic engineering building foundation pile of claim 1, wherein: the protective sleeve is characterized in that a connecting groove (9) is formed in the bottom of the protective sleeve (1), a connecting plate (8) of an annular structure is sleeved outside the restraint plate (7), and the connecting plate (8) is fixed in the connecting groove (9).
4. The hydraulic engineering building foundation pile of claim 1, wherein: the restraint plate (7) is provided with positioning holes (12) distributed in a matrix mode, the foundation piles (6) extend out of the positioning holes (12), and the foundation piles (6) are welded in the inner walls of the positioning holes (12).
5. The hydraulic engineering building foundation pile of claim 1, wherein: the outer wall coating of lag (1) has inoxidizing coating (2), the bottom of foundation pile (6) is the taper structure.
CN202021760816.1U 2020-08-21 2020-08-21 Hydraulic engineering building foundation pile Expired - Fee Related CN212896316U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021760816.1U CN212896316U (en) 2020-08-21 2020-08-21 Hydraulic engineering building foundation pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021760816.1U CN212896316U (en) 2020-08-21 2020-08-21 Hydraulic engineering building foundation pile

Publications (1)

Publication Number Publication Date
CN212896316U true CN212896316U (en) 2021-04-06

Family

ID=75246815

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021760816.1U Expired - Fee Related CN212896316U (en) 2020-08-21 2020-08-21 Hydraulic engineering building foundation pile

Country Status (1)

Country Link
CN (1) CN212896316U (en)

Similar Documents

Publication Publication Date Title
KR200205765Y1 (en) Reinforcing structure of foundation for pier
CN100535264C (en) Steel boxed cofferdam and recovery method thereof
CN113529589A (en) Plate splicing device applied to reinforcing of underwater bridge piers and reinforcing method thereof
CN110106904B (en) Steel pipe pile structure and jacket foundation construction process
CN212896316U (en) Hydraulic engineering building foundation pile
CN110847167A (en) Combined enhanced uplift anchor rod device and construction method
CN211472481U (en) Combined enhanced uplift anchor rod device
CN212926515U (en) Multifunctional water stop steel plate with double dovetail type prevention, drainage and blocking combination
CN214328954U (en) Cylindrical support node
CN211368731U (en) A foundation ditch construction high strength supporting beam for construction
CN209178914U (en) A kind of exposed throughout type steel pipe sheet pile breakwater
CN210975824U (en) Shaped steel connects combination formula steel support supporting construction that throws to one side
CN213329087U (en) Pipeline support assembled pile foundation structure
CN111962536A (en) Round combined cofferdam of seasonal water area bridge rock-socketed foundation and construction method
CN111778995A (en) Foundation pit protection structure and construction method thereof
CN216839474U (en) Foundation ditch inclined support stake structure
CN218291971U (en) Inner supporting structure for foundation pit
KR20020065661A (en) A Repair ethod and Repair tructure of Bridge Pier Mould Construction
CN218027706U (en) Detachable ramp supporting device
CN219315792U (en) Three-division bottom plate-three-division vertical ring combined concrete bearing platform foundation
CN210917383U (en) Anti-collapse structure of building foundation
CN217781937U (en) Anchoring structure for pit flushing repair
CN212772395U (en) Double-row pile and steel inclined strut deep foundation pit supporting structure and deep foundation pit supporting system
CN217556890U (en) Steel upright post structure with water stop blocking function
CN213204511U (en) Prevention of seepage water wall structure of water works engineering construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210406

Termination date: 20210821

CF01 Termination of patent right due to non-payment of annual fee