CN212866619U - Building engineering is with prefabricated post of convenient dismouting - Google Patents

Building engineering is with prefabricated post of convenient dismouting Download PDF

Info

Publication number
CN212866619U
CN212866619U CN202021637275.3U CN202021637275U CN212866619U CN 212866619 U CN212866619 U CN 212866619U CN 202021637275 U CN202021637275 U CN 202021637275U CN 212866619 U CN212866619 U CN 212866619U
Authority
CN
China
Prior art keywords
cylinder
steel bar
assembly
cage
steel reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021637275.3U
Other languages
Chinese (zh)
Inventor
吴轶强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou Zhongyang Yantong Building Technology Co ltd
Original Assignee
Fuzhou Zhongyang Yantong Building Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou Zhongyang Yantong Building Technology Co ltd filed Critical Fuzhou Zhongyang Yantong Building Technology Co ltd
Priority to CN202021637275.3U priority Critical patent/CN212866619U/en
Application granted granted Critical
Publication of CN212866619U publication Critical patent/CN212866619U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model discloses a building engineering is with prefabricated post of making things convenient for dismouting, the electric iron comprises a cylinder body, the cylinder upper end is connected with the hoist and mount subassembly, the cylinder lower extreme is connected with the installation component, be provided with the steel reinforcement skeleton subassembly in the cylinder, simple structure, the structure is clear and easy to understand, is provided with outer steel reinforcement skeleton cage and interior steel reinforcement skeleton cage in the cylinder, all wears to be equipped with a plurality of reinforcing bars outside outer steel reinforcement skeleton cage and the interior steel reinforcement skeleton cage, and skeleton strength is high, easy dismounting, and the cylinder of being convenient for lifts by crane the removal, is worth promoting.

Description

Building engineering is with prefabricated post of convenient dismouting
Technical Field
The utility model relates to a building engineering technical field specifically is a building engineering is with prefabricated post of making things convenient for dismouting.
Background
With the increasing importance of modern buildings and the increasing height of buildings, higher requirements are put on the performance of the building foundation. In the higher area of requirement of earthquake fortification, building foundation not only reaches the requirement of vertical compressive load, still satisfy the requirement of earthquake fortification, this is required that the stake in the building foundation satisfies vertical compressive load and antidetonation requirement simultaneously, the prefabricated prestressing force high strength concrete centrifugation stake of mill, have high vertical bearing capacity, construction period is short, the preparation is convenient with transporting, the cost is lower, relatively be fit for being used for only to the area of vertical bearing requirement, however traditional precast column is not convenient for remove the transport, the dismouting is inconvenient, intensity is not high, therefore, need a building engineering with the precast column of convenient dismouting.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building engineering is with prefabricated post of making things convenient for dismouting to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
the utility model provides a building engineering is with prefabricated post of convenient dismouting, includes the cylinder, the cylinder upper end is connected with hoisting assembly, the cylinder lower extreme is connected with the installation component, be provided with the framework of steel reinforcement subassembly in the cylinder.
Preferably, the steel reinforcement framework assembly comprises a plurality of outer steel reinforcement framework cages, inner steel reinforcement framework cages are arranged in the outer steel reinforcement framework cages, a plurality of outer reinforcing steel bars are arranged outside the outer steel reinforcement framework cages, a plurality of middle reinforcing steel bars are arranged between the outer steel reinforcement framework cages and the inner steel reinforcement framework cages, and a plurality of inner reinforcing steel bars are arranged in the inner steel reinforcement framework cages.
Preferably, the transverse cross section of the cylinder is elliptical.
Preferably, the hoisting assembly comprises a hoisting sleeve, the hoisting sleeve is sleeved on the outer surface of the upper end face of the cylinder, a plurality of compression bolts are connected between the hoisting sleeve and the cylinder, and the upper end face of the hoisting sleeve is fixedly connected with a hoisting ring.
Preferably, the installation component comprises a plurality of installation grooves, the installation grooves are evenly formed in the outer surface of the lower portion of the cylinder, installation holes are formed in the installation grooves, and installation nuts and installation bolts are arranged on the upper side and the lower side of the installation holes.
Preferably, the column body is cast concrete.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses simple structure, the structure is clear understandable, is provided with outer framework of steel cage and interior framework of steel cage in the cylinder, all wears to be equipped with a plurality of reinforcing bars outside outer framework of steel cage and the interior framework of steel cage, and skeleton strength is high, easy dismounting, and the cylinder of being convenient for lifts by crane the removal, is worth promoting.
Drawings
FIG. 1 is a schematic structural view of a prefabricated column for construction engineering, which is convenient to disassemble and assemble;
FIG. 2 is a schematic structural view of a steel bar skeleton assembly of a prefabricated column for construction engineering, which is convenient to disassemble and assemble;
fig. 3 is a schematic view of a horizontal cross-section structure of a prefabricated column for construction engineering, which is convenient to disassemble and assemble.
In the figure: 1-column body, 2-external reinforcing steel bar, 3-external reinforcing steel bar framework cage, 4-middle reinforcing steel bar, 5-internal reinforcing steel bar framework cage, 6-internal reinforcing steel bar, 7-hoisting ring, 8-compression bolt, 9-hoisting sleeve, 10-installation groove, 11-installation nut, 12-installation bolt, 13-installation hole, 14-hoisting component, 15-installation component and 16-reinforcing steel bar framework component.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1 to 3, the present invention provides a technical solution: the utility model provides a building engineering is with prefabricated post of convenient dismouting, includes cylinder 1, 1 upper end of cylinder is connected with hoist and mount subassembly 14, 1 lower extreme of cylinder is connected with installation component 15, be provided with steel reinforcement framework subassembly 16 in the cylinder 1, cylinder 1 is concreting.
The utility model provides a prefabricated post includes cylinder 1, is provided with steel reinforcement framework subassembly 16 in the cylinder 1, and as prefabricated post skeleton, 1 upper end of cylinder is connected with hoisting assembly 14 for 1 hoist and mount of cylinder remove, and 1 lower extreme of cylinder is connected with installation component 15, is used for the installation of cylinder 1.
The steel reinforcement framework assembly 16 comprises a plurality of outer steel reinforcement framework cages 3, an inner steel reinforcement framework cage 5 is arranged in each outer steel reinforcement framework cage 3, a plurality of outer reinforcing steel bars 2 are arranged outside each outer steel reinforcement framework cage 3, a plurality of middle reinforcing steel bars 4 are arranged between each outer steel reinforcement framework cage 3 and each inner steel reinforcement framework cage 5, and a plurality of inner reinforcing steel bars 6 are arranged in each inner steel reinforcement framework cage 5.
An outer steel reinforcement framework cage 3 and an inner steel reinforcement framework cage 5 are arranged in the column body 1, a plurality of reinforcing steel bars are arranged inside and outside the outer steel reinforcement framework cage 3 and the inner steel reinforcement framework cage 5 in a penetrating mode, and the framework strength is high.
The transverse section of the column body 1 is oval, and the strength is high.
The hoisting assembly 14 comprises a hoisting sleeve 9, the hoisting sleeve 9 is sleeved on the outer surface of the upper end face of the column body 1, a plurality of compression bolts 8 are connected between the hoisting sleeve 9 and the column body 1, and a hoisting ring 7 is fixedly connected to the upper end face of the hoisting sleeve 9, so that the prefabricated column can be hoisted and moved conveniently and transported conveniently.
The installation component 15 includes a plurality of mounting grooves 10, and a plurality of mounting grooves 10 evenly set up at 1 below surface of cylinder, be provided with mounting hole 13 in the mounting groove 10, the lower side is provided with mounting nut 11 and mounting bolt 12 about mounting hole 13, makes things convenient for the installation of prefabricated post, makes things convenient for the dismouting.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (6)

1. The utility model provides a building engineering is with prefabricated post of convenient dismouting, includes cylinder (1), its characterized in that: the cylinder (1) upper end is connected with hoist and mount subassembly (14), cylinder (1) lower extreme is connected with installation component (15), be provided with framework of steel reinforcement subassembly (16) in cylinder (1).
2. The prefabricated column convenient for disassembly and assembly for constructional engineering as claimed in claim 1, wherein: the steel bar framework assembly (16) comprises a plurality of outer steel bar framework cages (3), an inner steel bar framework cage (5) is arranged in the outer steel bar framework cage (3), a plurality of outer reinforcing steel bars (2) are arranged outside the outer steel bar framework cage (3), a plurality of middle reinforcing steel bars (4) are arranged between the outer steel bar framework cage (3) and the inner steel bar framework cage (5), and a plurality of inner reinforcing steel bars (6) are arranged in the inner steel bar framework cage (5).
3. The prefabricated column convenient for disassembly and assembly for constructional engineering as claimed in claim 2, wherein: the transverse section of the cylinder (1) is oval.
4. The prefabricated column convenient for disassembly and assembly for constructional engineering as claimed in claim 3, wherein: the hoisting assembly (14) comprises a hoisting sleeve (9), the hoisting sleeve (9) is sleeved on the outer surface of the upper end face of the cylinder (1), a plurality of compression bolts (8) are connected between the hoisting sleeve (9) and the cylinder (1), and a hoisting ring (7) is fixedly connected to the upper end face of the hoisting sleeve (9).
5. The prefabricated column convenient for disassembly and assembly for constructional engineering as claimed in claim 4, wherein: the mounting component (15) comprises a plurality of mounting grooves (10), the mounting grooves (10) are evenly formed in the outer surface of the lower portion of the column body (1), mounting holes (13) are formed in the mounting grooves (10), and mounting nuts (11) and mounting bolts (12) are arranged on the upper side and the lower side of the mounting holes (13).
6. The prefabricated column convenient for disassembly and assembly for constructional engineering as claimed in claim 5, wherein: the column body (1) is made of pouring concrete.
CN202021637275.3U 2020-08-10 2020-08-10 Building engineering is with prefabricated post of convenient dismouting Active CN212866619U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021637275.3U CN212866619U (en) 2020-08-10 2020-08-10 Building engineering is with prefabricated post of convenient dismouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021637275.3U CN212866619U (en) 2020-08-10 2020-08-10 Building engineering is with prefabricated post of convenient dismouting

Publications (1)

Publication Number Publication Date
CN212866619U true CN212866619U (en) 2021-04-02

Family

ID=75220417

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021637275.3U Active CN212866619U (en) 2020-08-10 2020-08-10 Building engineering is with prefabricated post of convenient dismouting

Country Status (1)

Country Link
CN (1) CN212866619U (en)

Similar Documents

Publication Publication Date Title
CN101886468B (en) Construction method of suspension type template support in high-position conjoined structure
CN102287029A (en) High-strength reinforcement built-in ultra high performance concrete (UHPC) beam member
CN211498526U (en) Self-lifting type corrugated steel web cast-in-situ box girder hanging basket
CN212866619U (en) Building engineering is with prefabricated post of convenient dismouting
CN113107127A (en) Reinforced composite floor slab
CN203007933U (en) Compound reinforcing bar non-round concrete precast pile
CN214785334U (en) Prefabricated section steel-concrete column unit structure
CN211646026U (en) General type mould number formula bearing truss
CN211596824U (en) Construction elevator foundation capable of being circulated
CN211920627U (en) Light lifting appliance for dismantling cantilever box girder segment
CN210049486U (en) Concrete precast beam
CN210507768U (en) Novel prefabricated balcony
CN113737966A (en) Assembled RCS lotus root beam column connecting node and application thereof
CN209837074U (en) Assembled additional elevator combination basis
CN217580551U (en) Partially-assembled self-resetting friction energy dissipation node capable of being installed quickly
CN219491788U (en) Face limit protection architecture of convenient, turnover use of installation in assembled building
CN218813150U (en) Prefabricated pier stud
CN215053872U (en) Assembled frame system
CN213569284U (en) Lifting upper hanging point for connecting and fixing sensor and electric hoist
CN204898701U (en) Prefabricated post of elliptic type
CN215715981U (en) Template-free and support-free assembled integral frame system for storage type logistics building
CN207078863U (en) Large-tonnage large span machine-roomless lift spandrel girder
CN217105130U (en) Precast concrete bearing structure for foundation pit
CN218538899U (en) Stand column structure and elevator shaft
CN217420170U (en) Load-bearing type large-span prestressed double-T plate

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant