CN212841646U - Boiler convenient to clean and clear away cinder - Google Patents

Boiler convenient to clean and clear away cinder Download PDF

Info

Publication number
CN212841646U
CN212841646U CN202021059784.2U CN202021059784U CN212841646U CN 212841646 U CN212841646 U CN 212841646U CN 202021059784 U CN202021059784 U CN 202021059784U CN 212841646 U CN212841646 U CN 212841646U
Authority
CN
China
Prior art keywords
boiler
cinder
welded
main body
welding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021059784.2U
Other languages
Chinese (zh)
Inventor
黄凤梅
盛叶盛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yichang Hengkun New Material Technology Co.,Ltd.
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021059784.2U priority Critical patent/CN212841646U/en
Application granted granted Critical
Publication of CN212841646U publication Critical patent/CN212841646U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a boiler convenient to clean clearance cinder, including boiler main part and right angle gear box, the top welding of boiler main part has the water tank, and water tank and boiler main part formula structure as an organic whole, first cell body has been seted up to boiler main part's inside, and has seted up the second cell body in the planar left side in first cell body bottom, first spout has all been seted up at the middle part on both sides surface around the second cell body, and the block has the cardboard in the first spout, three supporting legs of group have been welded in the outside of boiler main part's bottom. The utility model provides a current boiler all clear up when not using when clearing up the cinder, when the incessant long term of boiler is used, inside has a large amount of cinder, if needs the clearance need stop the burning with the boiler, leads to the boiler to work, and the problem of clearance cinder needs a large amount of time has improved the device's work efficiency and practicality.

Description

Boiler convenient to clean and clear away cinder
Technical Field
The utility model relates to the technical field of boilers, in particular to a boiler convenient for cleaning coal cinder.
Background
Although the existing electric heating boilers have higher cost, the traditional coal-fired boilers still occupy the absolute position of the market, and coal slag is generated after the coal is fired and needs to be cleaned regularly. Existing boilers substantially meet the needs of people, but still have some problems.
The first problem is that: the existing boiler is cleaned when not used when the coal cinder is cleaned, a large amount of coal cinder is arranged inside the boiler when the boiler is used uninterruptedly for a long time, the boiler cannot work due to the fact that the boiler needs to be stopped to burn if the boiler needs to be cleaned, a large amount of time is needed for cleaning the coal cinder, and the working efficiency and the practicability of the device are reduced.
The second problem is that: the boiler need spill water to inside when the clearance cinder, produce a large amount of dusts when avoiding the clearance cinder, but current boiler all sprinkles water in the boiler inside when the clearance cinder, may damage the inner wall of boiler in the past for a long time, perhaps sprinkles water to inside when inside temperature is higher sometimes, can produce a large amount of vapor, may make the boiler blast, great reduction the device's practicality and security, consequently need for a boiler convenient to clean clearance cinder urgently to solve above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a boiler convenient to clean clearance cinder to the boiler that proposes in solving above-mentioned background art carries out the burning during operation, if a large amount of cinder are deposited to inside collection, can't carry out the problem of clearing up to inside cinder.
In order to achieve the above object, the utility model provides a following technical scheme: a boiler convenient for cleaning coal cinder comprises a boiler main body and a right-angle gear box, wherein a water tank is welded at the top of the boiler main body, the water tank and the boiler main body are of an integral structure, a first groove body is formed in the boiler main body, a second groove body is formed in the left side of the bottom plane of the first groove body, first sliding grooves are formed in the middle of the front side surface and the rear side surface of the second groove body, clamping plates are clamped in the first sliding grooves, three supporting foot frames are welded on the outer side of the bottom of the boiler main body, mounting plates are welded in the middle of the supporting foot frames, a bottom plate is welded at the bottom of the supporting foot frames, rotating blades are attached to the bottom surface of the first groove body, a first rotating shaft is welded on the lower surface of each rotating blade, the first rotating shaft penetrates through the bottom of the first groove body, the bottom surface of the first rotating shaft is welded with the output end of, and the second pivot registrates and has supported the boss, support the upper surface of boss bottom and mounting panel and pass through welded connection, and the front end welding that supports the boss has the carousel, the outside welding of carousel front side surface has the handle.
Preferably, the left end welding on boiler main part bottom surface has the unloading pipe, and the inside and the second cell body intercommunication of unloading pipe, the bottom welding of unloading pipe has the collecting box main part, and the lower extreme on collecting box main part right side surface passes through welded connection with the left side surface of bottom plate, the inside last skin weld of collecting box main part has Y shape water pipe, and the right side of Y shape water pipe runs through the right side inner wall of collecting box main part and extends to the outside, the apopore has been seted up to the inboard of Y shape water pipe, and the inside block of collecting box main part has the cinder to deposit the case, both sides all seted up around the inside bottom plane of collecting box main part deposit the bottom portion second spout of mutually supporting with the cinder, and the left side skin weld that the cinder was deposited the case has the handle.
Preferably, the right side welding of cardboard upper surface has the fixed block, and fixed block thickness size is less than the distance size of cardboard upper surface to first cell body bottom surface.
Preferably, the length of the clamping plate is greater than that of the first sliding groove.
Preferably, the shape of the top view partial profile of the rotating blade is an arc shape.
Preferably, a supporting plate is welded at the bottom of the left side surface of the cinder storage box, and the lower surface of the supporting plate and the lower surface of the collecting box main body are on the same horizontal plane.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the boiler convenient for cleaning the coal slag is provided with a water tank, a first tank body, a second tank body, a first sliding groove, a clamping plate, a rotating blade, a first rotating shaft, a right-angle gear box, a second rotating shaft, a supporting boss, a rotating disk and a handle, wherein the clamping plate is drawn out from the first sliding groove until a foot rest reaches the inner wall of a boiler main body, the rotating handle rotates the rotating disk, the rotating disk rotates to drive the second rotating shaft to rotate, the rotating force is transmitted to the first rotating shaft through the right-angle gear box, the first rotating shaft rotates to drive the rotating blade to rotate anticlockwise, the coal slag at the bottom of the boiler is driven to fall into the second tank body, the problem that the existing boiler can not be cleaned when the boiler is not used when the coal slag is cleaned is solved, a large amount of coal slag can be generated inside the boiler when the boiler is used for a long time, if the boiler needs to be cleaned, the boiler needs, the problem that a large amount of time is needed for cleaning the coal slag is solved, and the working efficiency and the practicability of the device are improved;
2. this boiler convenient to clean clearance cinder is provided with the unloading pipe, the collection box main part, Y shape water pipe, the apopore, the case is deposited to the cinder, second spout and handle, insert the water source with the right-hand member of Y shape water pipe, make water continuously spout from the apopore, drench on the cinder that falls down from the unloading pipe, and spray water to the inner space that the case was deposited to the cinder, the boiler need spill water to inside when clearing up the cinder, produce a large amount of dusts when avoiding clearing up the cinder, but current boiler all sprinkles water inside the boiler when clearing up the cinder, can damage the inner wall of boiler in the past for a long time, perhaps spill water to inside when inside temperature is higher sometimes, can produce a large amount of vapor, can make the boiler problem that explodes, the practicality and the security of the device have been improved.
Drawings
Fig. 1 is a schematic perspective view of the present invention;
fig. 2 is a schematic front sectional view of fig. 1 according to the present invention;
FIG. 3 is a schematic top sectional view of the boiler main body, the first tank body, the second tank body and the feeding pipe of the present invention;
FIG. 4 is a schematic view of the three-dimensional structure of the clamping plate of the present invention;
FIG. 5 is a schematic perspective view of the rotary blade, the first rotary shaft, the right-angle gear box, the second rotary shaft, the supporting boss, the rotary disk and the handle of the present invention;
FIG. 6 is a schematic perspective view of the collecting box body, the cinder containing box, the handle and the support plate of the present invention;
fig. 7 is a schematic left side sectional view of fig. 6 according to the present invention.
In the figure: 1. a boiler main body; 2. a water tank; 3. a first tank body; 4. a second tank body; 5. a first chute; 6. clamping a plate; 7. a foot rest; 8. mounting a plate; 9. a base plate; 10. rotating the leaf; 11. a first rotating shaft; 12. a right angle gear box; 13. a second rotating shaft; 14. supporting the boss; 15. a turntable; 16. a grip; 17. a discharging pipe; 18. a collection box main body; 19. a Y-shaped water pipe; 20. a water outlet hole; 21. a coal cinder storage box; 22. a second chute; 23. a handle; 24. and a support plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-7, the present invention provides an embodiment: a boiler convenient for cleaning coal cinder comprises a boiler main body 1 and a right-angle gear box 12, a water tank 2 is welded at the top of the boiler main body 1, a blanking pipe 17 is welded at the left end of the bottom surface of the boiler main body 1, the interior of the blanking pipe 17 is communicated with a second groove body 4, a collecting box main body 18 is welded at the bottom end of the blanking pipe 17, the lower end of the right side surface of the collecting box main body 18 is connected with the left side surface of a bottom plate 9 in a welding manner, a Y-shaped water pipe 19 is welded at the upper surface of the interior of the collecting box main body 18, the right side of the Y-shaped water pipe 19 penetrates through the right inner wall of the collecting box main body 18 and extends to the outside, a water outlet hole 20 is formed in the inner side of the Y-shaped water pipe 19, a coal cinder storage box 21 is clamped in the collecting box main body 18, a supporting plate 24 is welded at the, the supporting plate 24 serves to keep the cinder keeping box 21 stable when the cinder keeping box 21 is drawn out of the collection box main body 18.
Both sides all have been seted up around the inside bottom plane of collecting box main part 18 and have been deposited case 21 bottom second spout 22 of mutually supporting with the cinder, and the cinder is deposited case 21's left side skin weld and has handle 23, its effect is handled and is collected for carrying out the dust fall to the cinder, and water tank 2 and boiler main part 1 formula structure as an organic whole, first cell body 3 has been seted up to boiler main part 1's inside, and second cell body 4 has been seted up to the planar left side in first cell body 3 bottom, first spout 5 has all been seted up at the middle part on both sides surface around the second cell body 4, and the block has cardboard 6 in the first spout 5, the length of cardboard 6 is greater than the length of first spout 5, its effect is for conveniently taking out cardboard 6, the outside welding of boiler main part 1's bottom has three group foot rests 7, and the middle part welding of foot rest.
The right side of the upper surface of the clamping plate 6 is welded with a fixed block, the thickness of the fixed block is smaller than the distance from the upper surface of the clamping plate 6 to the bottom surface of the first tank body 3, the fixed block is used for preventing the rotating blade 10 from colliding with the fixed block, the bottom of the foot support 7 is welded with a bottom plate 9, the bottom surface of the first tank body 3 is attached with the rotating blade 10, the overlooking local contour of the rotating blade 10 is arc-shaped and can drive the coal cinder in the middle to the outside during rotation, the lower surface of the rotating blade 10 is welded with a first rotating shaft 11, the first rotating shaft 11 penetrates through the bottom of the first tank body 3, the bottom surface of the first rotating shaft 11 is welded with the output end of the right-angle gear box 12, the input end of the right-angle gear box 12 is welded with a second rotating shaft 13, the model of the right-angle gear box 12 can be PW075, the right-angle gear box 12 transmits, and the second rotating shaft 13 is sleeved with a supporting boss 14, the bottom end of the supporting boss 14 is connected with the upper surface of the mounting plate 8 through welding, the front end of the supporting boss 14 is welded with a rotating disc 15, and the outer side of the front side surface of the rotating disc 15 is welded with a handle 16.
The working principle is as follows: when the coal cinder needs to be cleaned, the clamping plate 6 is drawn out from the first chute 5 until the foot rest 7 reaches the inner wall of the boiler main body 1, the handle 16 is rotated to rotate the turntable 15, the turntable 15 rotates to drive the second rotating shaft 13 to rotate, the rotating force is transmitted to the first rotating shaft 11 through the right-angle gear box 12 to rotate the first rotating shaft 11, so as to drive the rotating blades 10 to rotate anticlockwise, the coal cinder at the bottom of the boiler is driven to fall into the second tank body 4, the coal cinder falls into the coal cinder storage box 21 through the foot rest 7, the right end of the Y-shaped water pipe 19 is connected to a water source, so that water is continuously sprayed out from the water outlet hole 20 and is sprayed onto the coal cinder falling from the blanking pipe 17, the water is sprayed into the inner space of the coal cinder storage box 21, after the cleaning of the inner coal cinder is finished, the water source is closed, the clamping plate 6 is inserted into the first chute 5, the coal cinder storage box 21 is drawn out from the collecting box main body 18 through, the coal cinder in the coal cinder storage box 21 is cleaned.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. The utility model provides a boiler convenient to clean clearance cinder, includes boiler main part (1) and right angle gear box (12), its characterized in that: the boiler comprises a boiler main body (1), a water tank (2) is welded at the top of the boiler main body (1), the water tank (2) and the boiler main body (1) are of an integral structure, a first groove body (3) is arranged inside the boiler main body (1), a second groove body (4) is arranged on the left side of the bottom plane of the first groove body (3), first sliding grooves (5) are formed in the middle parts of the front side surface and the rear side surface of the second groove body (4), clamping plates (6) are clamped in the first sliding grooves (5), three groups of supporting feet (7) are welded on the outer side of the bottom of the boiler main body (1), mounting plates (8) are welded in the middle parts of the supporting feet (7), a bottom plate (9) is welded at the bottom of the supporting feet (7), rotating leaves (10) are attached to the bottom surface of the first groove body (3), first rotating shafts (11) are welded on the lower surfaces of the rotating leaves (10), and the first, and the bottom surface of first pivot (11) is in the same place with the output welding of right angle gear box (12), the input welding of right angle gear box (12) has second pivot (13), and second pivot (13) registrate has support boss (14), support boss (14) bottom and the upper surface of mounting panel (8) and pass through welded connection, and the front end welding of supporting boss (14) has carousel (15), the outside welding of carousel (15) front side surface has handle (16).
2. The boiler for facilitating clean up of coal cinder as claimed in claim 1, wherein: the boiler is characterized in that a discharging pipe (17) is welded at the left end of the bottom surface of the boiler main body (1), the interior of the discharging pipe (17) is communicated with a second groove body (4), a collecting box main body (18) is welded at the bottom end of the discharging pipe (17), the lower end of the right side surface of the collecting box main body (18) is connected with the left side surface of the bottom plate (9) in a welding mode, a Y-shaped water pipe (19) is welded on the upper surface of the interior of the collecting box main body (18), the right side of the Y-shaped water pipe (19) penetrates through the right inner wall of the collecting box main body (18) and extends to the outside, water outlet holes (20) are formed in the inner side of the Y-shaped water pipe (19), a cinder storing box (21) is clamped in the interior of the collecting box main body (18), second sliding grooves (22) matched with the bottom of the cinder storing box (21) are formed in the, and a handle (23) is welded on the left surface of the cinder storage box (21).
3. The boiler for facilitating clean up of coal cinder as claimed in claim 1, wherein: the right side welding of cardboard (6) upper surface has the fixed block, and fixed block thickness size is less than the distance size of cardboard (6) upper surface to first cell body (3) bottom surface.
4. The boiler for facilitating clean up of coal cinder as claimed in claim 1, wherein: the length of the clamping plate (6) is greater than that of the first sliding groove (5).
5. The boiler for facilitating clean up of coal cinder as claimed in claim 1, wherein: the shape of the local contour of the rotating blade (10) in the top view is arc.
6. A boiler for facilitating clean up of coal slag according to claim 2, wherein: the bottom of the left side surface of the cinder storage box (21) is welded with a support plate (24), and the lower surface of the support plate (24) and the lower surface of the collection box body (18) are on the same horizontal plane.
CN202021059784.2U 2020-06-11 2020-06-11 Boiler convenient to clean and clear away cinder Active CN212841646U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021059784.2U CN212841646U (en) 2020-06-11 2020-06-11 Boiler convenient to clean and clear away cinder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021059784.2U CN212841646U (en) 2020-06-11 2020-06-11 Boiler convenient to clean and clear away cinder

Publications (1)

Publication Number Publication Date
CN212841646U true CN212841646U (en) 2021-03-30

Family

ID=75171830

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021059784.2U Active CN212841646U (en) 2020-06-11 2020-06-11 Boiler convenient to clean and clear away cinder

Country Status (1)

Country Link
CN (1) CN212841646U (en)

Similar Documents

Publication Publication Date Title
CN212311672U (en) Surface treatment device for groove pipe fitting
CN212841646U (en) Boiler convenient to clean and clear away cinder
CN212585563U (en) Flue gas heat exchanger with good dust removal effect
CN115518802A (en) Water curtain type water-spinning paint spray booth and use method thereof
CN214903536U (en) A roasting machine for tea production
CN115057158A (en) Transmission structure for precision machinery transmission
CN210884325U (en) Ash cleaning device
CN207552369U (en) A kind of comprehensive cooling equipment of aluminum products
CN112208016A (en) Gypsum wire rod processingequipment with clearance gypsum piece mechanism
CN218225771U (en) Friction disc machining table convenient to clean
CN213436142U (en) Recovery plant for residual heat and pressure
CN209960523U (en) Boiler plenum slag removal device
CN215390996U (en) Casting cleaning device for stainless steel pipe fitting
CN218168175U (en) Quick disassembling device for lithium battery
CN217667008U (en) High-efficient nitrogen protection device that fills of wave soldering stove
CN211823864U (en) Lithium battery material production sintering matching cooling device
CN213164397U (en) Engineering material cutting device for construction
CN212339386U (en) Environment-friendly high heat accumulation heating stove
CN218914983U (en) Economizer with wear-resistant structure
CN217453169U (en) Double-column plane milling machine convenient for collecting scraps
CN216159033U (en) High-efficient clean sectional combustion device of coal layer combustion boiler
CN110295336A (en) A kind of galvanizing recycling residual heat system
CN213411429U (en) High-efficient safe circuit board edging device
CN220911679U (en) Biomass organic heat carrier boiler
CN214516260U (en) Air can water heater cleaning device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230410

Address after: 443000 No. 8 Huaxin Road, Lou Zihe Village, Zhicheng Town, Yidu City, Yichang City, Hubei Province

Patentee after: Yichang Hengkun New Material Technology Co.,Ltd.

Address before: No.21 Bawang street, Baiyun District, Guangzhou City, Guangdong Province 510080

Patentee before: Sheng Yesheng

TR01 Transfer of patent right