CN212836706U - Template supporting structure at floor discharge pit of warehouse prefabricated reinforced concrete integral casting structure - Google Patents

Template supporting structure at floor discharge pit of warehouse prefabricated reinforced concrete integral casting structure Download PDF

Info

Publication number
CN212836706U
CN212836706U CN202021019862.6U CN202021019862U CN212836706U CN 212836706 U CN212836706 U CN 212836706U CN 202021019862 U CN202021019862 U CN 202021019862U CN 212836706 U CN212836706 U CN 212836706U
Authority
CN
China
Prior art keywords
warehouse
reinforced concrete
precast
beams
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021019862.6U
Other languages
Chinese (zh)
Inventor
郭晓康
钟修华
彭松生
刘兆东
杨基亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Changjiang Shipping Planning And Design Institute Co ltd
Original Assignee
Wuhan Changjiang Shipping Planning And Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Changjiang Shipping Planning And Design Institute Co ltd filed Critical Wuhan Changjiang Shipping Planning And Design Institute Co ltd
Priority to CN202021019862.6U priority Critical patent/CN212836706U/en
Application granted granted Critical
Publication of CN212836706U publication Critical patent/CN212836706U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型公开了一种仓库预制钢筋砼整浇结构楼面卸货坑处的模板支撑结构,其包括设置在二层预制梁上的两个卡具、设置在装卸平台上的两个砖墩,以及两个主梁和多根钢管。本实用新型所述仓库预制钢筋砼整浇结构楼面卸货坑处的模板支撑结构施工便捷、迅速,施工周期短,重复利用性强,经济安全。

Figure 202021019862

The utility model discloses a formwork support structure at a floor unloading pit of a prefabricated reinforced concrete cast-in-place structure of a warehouse, which comprises two clamps arranged on a second-floor prefabricated beam, and two brick piers arranged on a loading and unloading platform. As well as two main beams and multiple steel pipes. The formwork support structure at the unloading pit on the floor of the warehouse prefabricated reinforced concrete cast-in-place structure of the utility model is convenient and rapid in construction, has short construction period, strong reusability, and is economical and safe.

Figure 202021019862

Description

Template supporting structure at floor discharge pit of warehouse prefabricated reinforced concrete integral casting structure
Technical Field
The utility model belongs to the technical field of double-deck commodity circulation warehouse construction, concretely relates to double-deck ramp storehouse unloading pit department template bearing structure of structure is wholly watered for prefabricated reinforced concrete to two-deck floor.
Background
When a double-layer logistics warehouse is built, a two-layer unloading pit and a two-layer beam plate are usually constructed simultaneously, a high formwork support is used as a support structure, and a lifting plate is formed at the unloading pit by adjusting the elevation of the top of a frame body. However, for the prefabricated reinforced concrete integral casting structure floor double-layer ramp warehouse, firstly, the prefabricated beam is hoisted in place, then the steel bearing plate is laid on the prefabricated beam to serve as a floor slab template, and as the unloading pit is positioned between the warehouse and the loading and unloading platform and is a descending plate, the integrated template system cannot be directly formed with the two floors.
Disclosure of Invention
In order to solve the problem that exists among the prior art, the utility model provides a template bearing structure of storehouse precast reinforced concrete monolithic structure floor discharge pit department that waters, this structural design is simple, the construction is convenient.
In order to achieve the purpose, the template supporting structure at the floor unloading pit of the prefabricated reinforced concrete integral casting structure of the warehouse provided by the utility model comprises two fixtures arranged on a second-layer precast beam, two brick piers arranged on a loading and unloading platform, two main beams and a plurality of steel pipes;
each fixture comprises a jackscrew, a screw rod, a cross beam and two vertical beams, wherein the upper ends of the two vertical beams are connected with the cross beam; the two vertical beams and the cross beam are clamped on a two-layer precast beam in an inverted U-shaped structure, a sizing block is arranged at the position, corresponding to the cross beam, of the two-layer precast beam, the jackscrew vertically penetrates through the cross beam to abut against the sizing block, and the rest gap between the sizing block and the clamp is filled by using a sizing block; the lead screw is positioned below the two layers of precast beams and is vertically connected with the two vertical beams;
each main beam is connected with the vertical beam on the corresponding side by one end, and the other end is placed on the brick pier on the corresponding side;
and a plurality of steel pipes are horizontally laid on the two main beams in parallel.
In one embodiment, the fixture further comprises an opening supporting plate and a rib plate for supporting the opening supporting plate, and one end of the main beam is mounted on the opening supporting plate through a limiting pin.
In another embodiment, a sleeve for connecting a jackscrew is arranged on the cross beam.
In yet another embodiment, the lead screw is secured to the vertical beam by a nut.
Has the advantages that:
prefabricated reinforced concrete of warehouse waters the on-the-spot earlier of template bearing structure make full use of structure floor unloading pit department and waters the component, the simple and easy truss support system of local design unloading pit department, simple manufacture, construction are convenient, rapid, and construction cycle is short, and reuse nature is strong, economic safety.
Drawings
Fig. 1 is the prefabricated reinforced concrete of warehouse waters the template bearing structure's of structure floor unloading pit department axle side schematic diagram entirely.
Fig. 2 is a schematic structural view of the fixture of fig. 1.
Fig. 3 is the plan view of the template bearing structure of warehouse precast reinforced concrete integral casting structure floor unloading pit department.
Fig. 4 is a cross-sectional view taken along the line a-a in fig. 3.
Wherein: the device comprises a fixture 1, a jackscrew 1.1, a sleeve 1.2, a screw rod 1.3, a nut 1.4, a cross beam 1.5, a vertical beam 1.6, an opening supporting plate 1.7, a rib plate 1.8, a sizing block 2, a sizing block 3, a main beam 4, a steel pipe 5, a brick pier 6, a two-layer precast beam 7, a loading and unloading platform 8, a concrete wall 9, a wood veneer 10 and a loading and unloading platform precast beam 11.
Detailed Description
The following template bearing structure of the prefabricated reinforced concrete integral casting structure floor discharge pit of the warehouse of the utility model is described in further detail with reference to the accompanying drawings and specific examples, but the examples should not be construed as limiting the utility model:
as shown in fig. 1 to 4, the formwork support structure at the discharge pit of the floor of the prefabricated reinforced concrete integral casting structure of the warehouse comprises two fixtures 1, two main beams 4, two brick piers 6 and a plurality of steel pipes 5.
Each fixture 1 is a main force transmission component and a bearing component, and comprises a jackscrew 1.1 for elevation adjustment, a sleeve 1.2, a screw rod 1.3, a nut 1.4, a cross beam 1.5 and two parallel vertical beams 1.6. The upper ends of the two vertical beams 1.6 are connected with the cross beam 1.5 to form an inverted U-shaped structure and are clamped on the two layers of precast beams 7. The sizing block 2 is put on the cement face that two layers of precast beam 7 correspond to crossbeam 1.5, crossbeam 1.5 is equipped with the pinhole, sleeve 1.2 welding is in pinhole department (the sleeve center aligns with the pinhole center), jackscrew 1.1 passes sleeve 1.2 and pinhole and sizing block 2 offset from last to down in proper order, adjusts the top elevation of girder 4 through rotatory jackscrew 1.1, the elevation adjustment back of finishing, the intermediate space of fixture 1 and two layers of precast beam is filled up with the sizing block 3 and is real. The lead screw 1.3 is connected with the two vertical beams 1.6 to balance and stabilize the fixture 1, specifically, holes for the lead screw 1.3 to vertically pass through are formed in the lower portions of the two vertical beams 1.6, and the lead screw 1.3 passes through the lower portion of the two-layer precast beam 7 and is fixed through the nut 1.4.
One side web plate of each vertical beam 1.6 facing the loading platform 8 is provided with an opening supporting plate 1.7 and a ribbed plate 1.8 for supporting the opening supporting plate 1.7. The main beam 4 rests with one end on the perforated pallet 1.7 and is connected by a limit pin 1.8, and with the other end through a concrete wall 9 on a brick pier 6 on which the landing platform 8 has been cast, in particular, the concrete wall 9 is anchored to a landing platform precast beam 11. The steel pipe 5 is fully laid on the main beam 4, the wood plywood 10 is laid on the steel pipe 5, the construction load is transmitted to the fixture 1 through the steel pipe 5 and the main beam 4, and finally the force is transmitted to the two-layer precast beam 7 through the skid 3.
The template supporting structure at the floor discharge pit of the warehouse precast reinforced concrete integral casting structure can effectively and fully utilize the early casting components such as the two-layer precast beam 7, the loading and unloading platform 8, the concrete wall 9, the loading and unloading platform precast beam 11 and the like, according to the principle of a shear-resistant support, the fixture 1 is designed to be reliably connected with the two-layer precast beam 7, and a simple truss supporting system at the discharge pit is locally designed on the basis. The formwork support structure of the embodiment is utilized to transfer the construction operation of erecting the high formwork full framing on the original ground to the installation operation of a simple truss support system on the floor, a scaffold does not need to be erected, the hoisting times of a tower crane (truck crane) are reduced, and three-dimensional construction can be realized, so that the construction progress can be effectively accelerated.

Claims (4)

1. Template bearing structure of warehouse precast reinforced concrete integral casting structure floor discharge pit department, its characterized in that: the device comprises two clamps (1) symmetrically arranged on a second-layer precast beam (7), two brick piers (6) arranged on a loading and unloading platform (8), two main beams (4) and a plurality of steel pipes (5);
each fixture (1) comprises a jackscrew (1.1), a screw (1.3), a cross beam (1.5) and two vertical beams (1.6) which are connected with the cross beam (1.5) by the upper ends thereof; the two vertical beams (1.6) and the transverse beam (1.5) are clamped on a two-layer precast beam (7) in an inverted U-shaped structure, a sizing block (2) is arranged at the position, corresponding to the transverse beam (1.5), of the two-layer precast beam (7), the jackscrew (1.1) vertically penetrates through the transverse beam (1.5) to abut against the sizing block (2), and a rest gap between the sizing block (2) and the clamping block (1) is filled by using a sizing block (3); the lead screw (1.3) is positioned below the two layers of precast beams (7) and is vertically connected with the two vertical beams (1.6);
each main beam (4) is connected with the vertical beam (1.6) on the corresponding side by one end, and the other end is placed on the brick pier (6) on the corresponding side;
and a plurality of steel pipes (5) are horizontally laid on the two main beams (4) in parallel.
2. The formwork support structure at the floor discharge pit of the warehouse precast reinforced concrete monolithic structure according to claim 1, characterized in that: the fixture (1) further comprises an opening supporting plate (1.7) and a rib plate (1.8) used for supporting the opening supporting plate (1.7), and one end of the main beam (4) is mounted on the opening supporting plate (1.7) through a limiting pin.
3. The formwork support structure at the floor discharge pit of the warehouse precast reinforced concrete monolithic structure according to claim 1, characterized in that: the cross beam (1.5) is provided with a sleeve (1.2) used for connecting the jackscrew (1.1).
4. The formwork support structure at the floor discharge pit of the warehouse precast reinforced concrete monolithic structure according to claim 1, characterized in that: the lead screw (1.3) is fixed on the vertical beam (1.6) through a nut (1.4).
CN202021019862.6U 2020-06-05 2020-06-05 Template supporting structure at floor discharge pit of warehouse prefabricated reinforced concrete integral casting structure Expired - Fee Related CN212836706U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021019862.6U CN212836706U (en) 2020-06-05 2020-06-05 Template supporting structure at floor discharge pit of warehouse prefabricated reinforced concrete integral casting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021019862.6U CN212836706U (en) 2020-06-05 2020-06-05 Template supporting structure at floor discharge pit of warehouse prefabricated reinforced concrete integral casting structure

Publications (1)

Publication Number Publication Date
CN212836706U true CN212836706U (en) 2021-03-30

Family

ID=75170769

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021019862.6U Expired - Fee Related CN212836706U (en) 2020-06-05 2020-06-05 Template supporting structure at floor discharge pit of warehouse prefabricated reinforced concrete integral casting structure

Country Status (1)

Country Link
CN (1) CN212836706U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116556694A (en) * 2023-04-21 2023-08-08 中国五冶集团有限公司 A construction method for unloading platform of prefabricated logistics workshop

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116556694A (en) * 2023-04-21 2023-08-08 中国五冶集团有限公司 A construction method for unloading platform of prefabricated logistics workshop

Similar Documents

Publication Publication Date Title
CN110965470A (en) A main tower transverse brace structure system and construction method capable of bearing three-way loads
CN110453613B (en) Full-section one-step suspension casting construction method for large-span beam bridge box girder
CN103452126B (en) Light combined hanging box with recyclable baseplate steels and construction technology thereof
CN208055880U (en) A kind of crane's major girder hoisting frame
CN101781878A (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN110409319B (en) Bracket for large-span steel-concrete composite beam cast-in-place bridge deck and construction method
CN112575948A (en) Truss string beam and cantilever truss combined roof truss and construction method
CN102080384B (en) Construction Method of Installing Lift on the Roof of Underground Garage
CN110847050A (en) Large-span prefabricated corrugated steel web composite beam top and bottom plate synchronous pouring template and application method thereof
CN109881587B (en) Integral installation method of beam support on main tower in strong wind environment
CN102777044B (en) Hoisting method of steel-structured spraying layer of urea prilling tower
CN212077660U (en) Large-span wide width bridge girder rhombus hanging basket construction structure
CN212836706U (en) Template supporting structure at floor discharge pit of warehouse prefabricated reinforced concrete integral casting structure
CN113279582A (en) Hanging construction method for overhanging and hanging type cast-in-place plate
CN206902913U (en) A kind of high-altitude long-span overhung structure
CN211420881U (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam
CN110512776B (en) Construction method of assembled steel structure multi-cavity steel plate composite shear wall
CN112443040A (en) Multi-layer assembly type industrial factory building precast beam step-by-step hoisting construction method
CN111847272A (en) Supporting method of tower crane for renovation of existing buildings
CN208039864U (en) The attached lift-type discharging platform of Guiding Support Elevating Scaffold
CN212375721U (en) Double-hoop supporting system for single-column bent cap construction
CN111335183A (en) A double-hoop support system for single-column cover-beam construction
CN218815294U (en) Steel construction platform of unloading
CN108019040B (en) A construction method for the Bailey frame platform of the transfer floor of a high-rise building
CN215717067U (en) Construction platform suitable for concrete composite shear wall structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210330