Template supporting structure at floor discharge pit of warehouse prefabricated reinforced concrete integral casting structure
Technical Field
The utility model belongs to the technical field of double-deck commodity circulation warehouse construction, concretely relates to double-deck ramp storehouse unloading pit department template bearing structure of structure is wholly watered for prefabricated reinforced concrete to two-deck floor.
Background
When a double-layer logistics warehouse is built, a two-layer unloading pit and a two-layer beam plate are usually constructed simultaneously, a high formwork support is used as a support structure, and a lifting plate is formed at the unloading pit by adjusting the elevation of the top of a frame body. However, for the prefabricated reinforced concrete integral casting structure floor double-layer ramp warehouse, firstly, the prefabricated beam is hoisted in place, then the steel bearing plate is laid on the prefabricated beam to serve as a floor slab template, and as the unloading pit is positioned between the warehouse and the loading and unloading platform and is a descending plate, the integrated template system cannot be directly formed with the two floors.
Disclosure of Invention
In order to solve the problem that exists among the prior art, the utility model provides a template bearing structure of storehouse precast reinforced concrete monolithic structure floor discharge pit department that waters, this structural design is simple, the construction is convenient.
In order to achieve the purpose, the template supporting structure at the floor unloading pit of the prefabricated reinforced concrete integral casting structure of the warehouse provided by the utility model comprises two fixtures arranged on a second-layer precast beam, two brick piers arranged on a loading and unloading platform, two main beams and a plurality of steel pipes;
each fixture comprises a jackscrew, a screw rod, a cross beam and two vertical beams, wherein the upper ends of the two vertical beams are connected with the cross beam; the two vertical beams and the cross beam are clamped on a two-layer precast beam in an inverted U-shaped structure, a sizing block is arranged at the position, corresponding to the cross beam, of the two-layer precast beam, the jackscrew vertically penetrates through the cross beam to abut against the sizing block, and the rest gap between the sizing block and the clamp is filled by using a sizing block; the lead screw is positioned below the two layers of precast beams and is vertically connected with the two vertical beams;
each main beam is connected with the vertical beam on the corresponding side by one end, and the other end is placed on the brick pier on the corresponding side;
and a plurality of steel pipes are horizontally laid on the two main beams in parallel.
In one embodiment, the fixture further comprises an opening supporting plate and a rib plate for supporting the opening supporting plate, and one end of the main beam is mounted on the opening supporting plate through a limiting pin.
In another embodiment, a sleeve for connecting a jackscrew is arranged on the cross beam.
In yet another embodiment, the lead screw is secured to the vertical beam by a nut.
Has the advantages that:
prefabricated reinforced concrete of warehouse waters the on-the-spot earlier of template bearing structure make full use of structure floor unloading pit department and waters the component, the simple and easy truss support system of local design unloading pit department, simple manufacture, construction are convenient, rapid, and construction cycle is short, and reuse nature is strong, economic safety.
Drawings
Fig. 1 is the prefabricated reinforced concrete of warehouse waters the template bearing structure's of structure floor unloading pit department axle side schematic diagram entirely.
Fig. 2 is a schematic structural view of the fixture of fig. 1.
Fig. 3 is the plan view of the template bearing structure of warehouse precast reinforced concrete integral casting structure floor unloading pit department.
Fig. 4 is a cross-sectional view taken along the line a-a in fig. 3.
Wherein: the device comprises a fixture 1, a jackscrew 1.1, a sleeve 1.2, a screw rod 1.3, a nut 1.4, a cross beam 1.5, a vertical beam 1.6, an opening supporting plate 1.7, a rib plate 1.8, a sizing block 2, a sizing block 3, a main beam 4, a steel pipe 5, a brick pier 6, a two-layer precast beam 7, a loading and unloading platform 8, a concrete wall 9, a wood veneer 10 and a loading and unloading platform precast beam 11.
Detailed Description
The following template bearing structure of the prefabricated reinforced concrete integral casting structure floor discharge pit of the warehouse of the utility model is described in further detail with reference to the accompanying drawings and specific examples, but the examples should not be construed as limiting the utility model:
as shown in fig. 1 to 4, the formwork support structure at the discharge pit of the floor of the prefabricated reinforced concrete integral casting structure of the warehouse comprises two fixtures 1, two main beams 4, two brick piers 6 and a plurality of steel pipes 5.
Each fixture 1 is a main force transmission component and a bearing component, and comprises a jackscrew 1.1 for elevation adjustment, a sleeve 1.2, a screw rod 1.3, a nut 1.4, a cross beam 1.5 and two parallel vertical beams 1.6. The upper ends of the two vertical beams 1.6 are connected with the cross beam 1.5 to form an inverted U-shaped structure and are clamped on the two layers of precast beams 7. The sizing block 2 is put on the cement face that two layers of precast beam 7 correspond to crossbeam 1.5, crossbeam 1.5 is equipped with the pinhole, sleeve 1.2 welding is in pinhole department (the sleeve center aligns with the pinhole center), jackscrew 1.1 passes sleeve 1.2 and pinhole and sizing block 2 offset from last to down in proper order, adjusts the top elevation of girder 4 through rotatory jackscrew 1.1, the elevation adjustment back of finishing, the intermediate space of fixture 1 and two layers of precast beam is filled up with the sizing block 3 and is real. The lead screw 1.3 is connected with the two vertical beams 1.6 to balance and stabilize the fixture 1, specifically, holes for the lead screw 1.3 to vertically pass through are formed in the lower portions of the two vertical beams 1.6, and the lead screw 1.3 passes through the lower portion of the two-layer precast beam 7 and is fixed through the nut 1.4.
One side web plate of each vertical beam 1.6 facing the loading platform 8 is provided with an opening supporting plate 1.7 and a ribbed plate 1.8 for supporting the opening supporting plate 1.7. The main beam 4 rests with one end on the perforated pallet 1.7 and is connected by a limit pin 1.8, and with the other end through a concrete wall 9 on a brick pier 6 on which the landing platform 8 has been cast, in particular, the concrete wall 9 is anchored to a landing platform precast beam 11. The steel pipe 5 is fully laid on the main beam 4, the wood plywood 10 is laid on the steel pipe 5, the construction load is transmitted to the fixture 1 through the steel pipe 5 and the main beam 4, and finally the force is transmitted to the two-layer precast beam 7 through the skid 3.
The template supporting structure at the floor discharge pit of the warehouse precast reinforced concrete integral casting structure can effectively and fully utilize the early casting components such as the two-layer precast beam 7, the loading and unloading platform 8, the concrete wall 9, the loading and unloading platform precast beam 11 and the like, according to the principle of a shear-resistant support, the fixture 1 is designed to be reliably connected with the two-layer precast beam 7, and a simple truss supporting system at the discharge pit is locally designed on the basis. The formwork support structure of the embodiment is utilized to transfer the construction operation of erecting the high formwork full framing on the original ground to the installation operation of a simple truss support system on the floor, a scaffold does not need to be erected, the hoisting times of a tower crane (truck crane) are reduced, and three-dimensional construction can be realized, so that the construction progress can be effectively accelerated.