CN2128276Y - Column head for early dismantling system - Google Patents

Column head for early dismantling system Download PDF

Info

Publication number
CN2128276Y
CN2128276Y CN 92230018 CN92230018U CN2128276Y CN 2128276 Y CN2128276 Y CN 2128276Y CN 92230018 CN92230018 CN 92230018 CN 92230018 U CN92230018 U CN 92230018U CN 2128276 Y CN2128276 Y CN 2128276Y
Authority
CN
China
Prior art keywords
corbel
joint
lock
shape
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 92230018
Other languages
Chinese (zh)
Inventor
戴红妹
程剑兵
张理明
仇铭华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beixin Construction Tech. Inst., Beijing City
Original Assignee
戴红妹
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 戴红妹 filed Critical 戴红妹
Priority to CN 92230018 priority Critical patent/CN2128276Y/en
Application granted granted Critical
Publication of CN2128276Y publication Critical patent/CN2128276Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model relates to a column head for an early disassembling system, which belongs to a building tool. The column head for an early disassembling system is composed of a supporting plate, a beam support, T-shaped pins, a column body, a connecting pipe and a round pin, wherein, two steel plates are bent to be opposite to form the column body, and the column body is weld with the supporting plate and the connecting pipe. The middle of the column body is provided with a pin opening. The beam support is composed of a beam ear, a support and a square sleeve pipe. The front part and the rear part of the square sleeve pipe are provided with T-shaped pin openings which are corresponding with each other. When a template beam is additionally added, the beam support is upwards lifted. The T-shaped pins are knocked into the T-shaped pin openings and pin openings, the wide surfaces of the T-shaped pins are just positioned on both ends of the T-shaped pin openings of the beam support to be used as supporting surfaces, and the contact surfaces of the column head for an early disassembling system are the wide surfaces of the T-shaped pins. The stability of the column head for an early disassembling system is high. The column head for an early disassembling system is suitable for a small steel mould system. The column head for an early disassembling system has the advantages of high stability, convenient use, simple processing and low cost.

Description

Column head for early dismantling system
The utility model belongs to the building frock
In builing industry, quote little punching block from the seventies since, development has basically formed system rapidly, becomes the main template of using in the present building operations of China.
Along with the develop rapidly of highrise building industry, it is more and more incompatible that the form of construction work of little punching block has seemed.One of them important deficiency is the early removing system that its support system also lacks a kind of practicality.
Early tearing column cap open, is to be contained in to regulate on the column, and its corbel is hung with Form beam, and two shoulders of Form beam are laid little punching block, can cast-in-situ concrete on little punching block.
Be that column cap is early torn in 89208032.9 hot investment casting open as the patent No. in the prior art, its main defective is:
When its supporting plate 4 places between corbel 3 and the following backing pin 5 with location corbel height, because the contact surface of supporting plate 4 and following backing pin 5 very little (promptly descend the thickness of backing pin 5 very little), when setting up Form beam and little punching block, rock back and forth easily, stability is not high, can cause the of low quality of cast-in-situ floor, in addition because it is hot investment casting processing, the processing cost height, the weight of whole column cap is also heavier.
The purpose of this utility model is: provide a kind of being applicable to tear column cap morning little punching block system, that stability is high, that process simply, save steel and weight open.
The utility model is made up of supporting plate 1, corbel 2, shaft 4, tube connector 5, it is characterized in that:
Shaft 4 is formed after by two block plate bendings relatively, open with lock-joint 11 centre, shaft 4 upper ends and supporting plate 1 welding, weld mutually with tube connector 5 lower end, corbel 2 is welded by beam ear 7, support 8 and square casing 9, square casing 9 front and back have corresponding T shape lock-joint 10, and corbel 2 places the supporting plate 1 and 5 of the tube connectors of shaft 4 and can move up and down.When setting up Form beam, corbel 2 is upwards carried by foot, make the T shape lock-joint 10 and the lock-joint 11 of shaft 4 be in same position, T shape pin 3 is squeezed into from T shape lock-joint 10 by having of garden lock-joint 13, make a wide 14(A to B of T shape pin 3) be in two ends of the T shape lock-joint 10 of corbel 2, and insert with pin 6 at garden lock-joint 13 places, make corbel 2 be positioned the certain altitude of shaft 4, be the height 55mm that certain value is little punching block with the distance H on the last plane of the last plane that guarantees corbel 2 and supporting plate 1.Because the height of corbel 2 of the present utility model location is to depend in the T shape lock-joint 10 that T shape pin 3 is inserted in the lock-joint 7 of shaft 4 and corbel 2, its contact surface is wide 14 of T shape pin 3, it is long to be (A to B), and this just makes it that high stability is arranged, and can not produce the phenomenon of rocking.
When early stripping formwork system, T shape pin 3 is hit the back side that the A end that makes T shape pin 3 surpasses corbel 2 forward, narrow 15 centre joint 11 places that are positioned at shaft 4 of T shape pin 3, corbel 2 promptly falls voluntarily.
The utility model compared with prior art has the following advantages:
(1). because the height of corbel 2 location is to realize that with the lock-joint 7 of shaft 4 its contact surface is very big by the T shape lock-joint 11 of T shape pin 3 insertion corbels 2, can produce and rock back and forth, stability is very high.
(2). early tear several critical pieces of column cap open, as corbel 2, shaft 4 etc. by the sheet material bending and be welded.Therefore technology is simple, and material economy, weight are light approximately by 25%, and price is lower.
Accompanying drawing is described in conjunction with the embodiments
The utility model is to be used for the little punching block early removing system that the cast-in-place concrete floor building is used.For regulating column, on a plane of lower support system, an one direction is the interval with the length of Form beam in the bottom of early tearing column cap open, and other direction is the interval with the length of little punching block, forms a support system.Hang with Form beam on the beam ear 7, two Form beam structure of an essay are with little punching block.Behind the fluid concrete, when its intensity reaches the 5C% left and right sides, beat T shape pin 3, corbel 2 is fallen, take off Form beam, template, mould support etc. and drop into it in order to save cost with hammer.
Description of drawings:
Fig. 1 is a general assembly drawing of the present utility model
1. supporting plate 2. corbels
3.T shape lock-joint 4. shafts
5. tube connector 6. pins
Fig. 2 is the part figure in addition of corbel 2 of the present utility model
7. beam ear 8. supports
9. square casing 10.T shape lock-joint
Fig. 3 is the part figure in addition of shaft 4 of the present utility model
11. lock-joint 12. centres joint
Fig. 4 is the part figure in addition of T shape pin 3 of the present utility model
13. wide of garden lock-joint 14.T shape pin
15.T narrow of shape pin

Claims (2)

1, a kind of column cap of early removing system is made up of supporting plate (1), corbel (2), shaft (4) and tube connector (5), it is characterized in that:
(1) shaft (4) is formed after by two block plate bendings relatively, and open with lock-joint (11) centre, upper end and supporting plate (1) welding, and weld mutually with tube connector (5) lower end;
(2) corbel (2) by beam ear (7), support (8) and square casing (9) is welded, have corresponding T shape lock-joint (10) before and after the square casing (9), corbel (2) places between the supporting plate (1) of shaft (4) and tube connector (5) and also can move up and down;
When (3) setting up Form beam, corbel (2) is upwards carried by foot, make the T shape lock-joint (10) and the lock-joint (11) of shaft (4) be in same position, T shape pin (3) is squeezed into from T shape lock-joint (10) by having of garden lock-joint (13), wide (14) (A to B) that makes T shape sell (3) is in two ends of the T shape lock-joint (10) of corbel (2), and locate slotting at garden lock-joint (13) with pin, making corbel (2) be positioned the certain altitude of shaft (4), is certain value with the distance H on the last plane of the last plane that guarantees corbel (2) and supporting plate (1);
(4) during the delivery plate-girder, T shape pin (3) is hit the back side that the A end that makes T shape pin (3) surpasses corbel (2) forward, narrow (15) of T shape pin (3) are positioned at the centre joint (12) of shaft (4) to be located, and corbel (2) i.e. is whereabouts voluntarily.
2, according to the column cap of the said early removing system of claim 1, it is characterized in that: the distance H that last plane of corbel (2) and supporting plate (1) are gone up the plane is 55mm.
CN 92230018 1992-08-11 1992-08-11 Column head for early dismantling system Expired - Lifetime CN2128276Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 92230018 CN2128276Y (en) 1992-08-11 1992-08-11 Column head for early dismantling system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 92230018 CN2128276Y (en) 1992-08-11 1992-08-11 Column head for early dismantling system

Publications (1)

Publication Number Publication Date
CN2128276Y true CN2128276Y (en) 1993-03-17

Family

ID=33773240

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 92230018 Expired - Lifetime CN2128276Y (en) 1992-08-11 1992-08-11 Column head for early dismantling system

Country Status (1)

Country Link
CN (1) CN2128276Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195241A (en) * 2013-04-18 2013-07-10 深圳市广胜达建筑工程有限公司 Early removal support device for constructional engineering

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195241A (en) * 2013-04-18 2013-07-10 深圳市广胜达建筑工程有限公司 Early removal support device for constructional engineering
CN103195241B (en) * 2013-04-18 2014-04-02 深圳市广胜达建筑工程有限公司 Early removal support device for constructional engineering

Similar Documents

Publication Publication Date Title
CN102720293B (en) Assembly method of inverted-triangular steel tube intersected spatial truss
CN2128276Y (en) Column head for early dismantling system
CN113737987A (en) Prefabricated high-strength fiber cement formwork superposed shear wall
CN208472949U (en) A kind of integrated-type steel moald-cavity convenient for site operation
CN202936919U (en) Fabricated steel bar truss deck
CN2561868Y (en) Triangular stud scaffold
CN210067191U (en) Assembled aluminum plate wall
CN202689334U (en) Inverted triangular steel tube intersecting spatial truss
CN210080614U (en) Quick processingequipment of soil nail locator card
CN208718359U (en) A kind of aluminum alloy mould plate BB clamping plate
CN2532176Y (en) Fish stomach shape steel truss
CN208810851U (en) A kind of small-sized I-steel bending device
CN208686064U (en) A kind of shear wall casting mold
CN216195708U (en) Prefabricated high-strength fiber cement formwork superposed shear wall
CN216196699U (en) Cloth machine entrance to a cave reinforcing apparatus
CN215907143U (en) Exempt from to tear open die block truss floor carrier plate
CN213539682U (en) Concrete building template for civil engineering
CN220058813U (en) Arc back edge of aluminum alloy template
CN214721804U (en) Shear force nail welding position mould
CN2128280Y (en) Form beam for early dismantling system
CN2161666Y (en) Adjustable height removing shore
CN212614107U (en) Water injection guardrail piece for building construction
CN218090532U (en) Tool for straightening hinge joint reinforcing steel bars at wet joint of hollow slab beam
CN2401592Y (en) Combined formwork for artificial formed slot hole steel bar concrete bulkhead of underground continuous wall
CN213105308U (en) Welding structure for box-type component inclined partition plate

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C53 Correction of patent for invention or patent application
COR Change of bibliographic data

Free format text: CORRECT: PATENTEE; FROM: DAI HONGMEI TO: BEIXIN CONSTRUCTION TECHNIQUE INST., BEIJING

CP03 Change of name, title or address

Address after: 100083 No. 30, Haidian District, Beijing, Xueyuan Road

Patentee after: Beixin Construction Tech. Inst., Beijing City

Address before: 100083 No. 16, No. four, gate 29, No. 303, spring, Beijing, Xueyuan Road

Patentee before: Dai Hongmei

C17 Cessation of patent right
CX01 Expiry of patent term