CN212802155U - Firm formula mounting structure is used to building curtain bright frame - Google Patents
Firm formula mounting structure is used to building curtain bright frame Download PDFInfo
- Publication number
- CN212802155U CN212802155U CN202021263871.XU CN202021263871U CN212802155U CN 212802155 U CN212802155 U CN 212802155U CN 202021263871 U CN202021263871 U CN 202021263871U CN 212802155 U CN212802155 U CN 212802155U
- Authority
- CN
- China
- Prior art keywords
- mounting structure
- building curtain
- fixed
- deflector
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000003466 welding Methods 0.000 claims abstract description 6
- 239000007787 solid Substances 0.000 claims abstract description 4
- 229910001220 stainless steel Inorganic materials 0.000 claims description 9
- 239000010935 stainless steel Substances 0.000 claims description 9
- 230000007246 mechanism Effects 0.000 description 11
- 238000009434 installation Methods 0.000 description 7
- 239000011521 glass Substances 0.000 description 3
- 238000010276 construction Methods 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000003908 quality control method Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
The utility model discloses a building curtain sees frame with firm formula mounting structure, including mounting panel, movable clamp plate and solid fixed splint, the welding of the preceding terminal surface middle section rigidity of mounting panel has the deflector, movable clamp plate has seted up sliding through hole, and cup joints the outer wall at the deflector through sliding through hole slides, gu fixed splint is located movable clamp plate's front side, and the fixed welding is at the most advanced lateral wall of deflector. The utility model relates to a building curtain sees firm formula mounting structure for frame can rationally set up whole mounting structure's position, the bright frame of the quick fixed mounting curtain of being convenient for, simple and practical according to the curtain area size.
Description
Technical Field
The utility model relates to a building curtain sees frame specifically is a building curtain sees frame with firm formula mounting structure with installation relevant technical field.
Background
The glass curtain wall is used as a novel wall body, and is widely applied to large-scale and high-rise buildings such as shopping malls, office buildings, airports, stadiums, convention and exhibition centers, railway station houses and the like by virtue of the advantages of attractive appearance, light dead weight, good lighting, standardization, high industrialization degree and the like; at present, the mounting and dismounting processes of the glass curtain wall which is transversely exposed and vertically hidden must be completed in outdoor construction, and the problems of inconvenient construction, difficult quality control, low system safety and the like exist; in addition, for cross-line station houses and overpass buildings such as cross-railway tracks, the glass curtain wall has the safety risks that the decorative cover plate is easy to fall off and the connection is unreliable, so that the stable mounting structure for the exposed frame of the building curtain wall is designed and produced, and the problems are solved conveniently.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building curtain sees frame with firm formula mounting structure to solve the problem that proposes among the above-mentioned background art.
In order to solve the technical problem, the utility model provides a following technical scheme: the utility model provides a building curtain sees frame with firm formula mounting structure, includes mounting panel, movable clamp plate and solid fixed splint, the fixed welding in preceding terminal surface middle section position of mounting panel has the deflector, movable clamp plate has seted up sliding through hole, and slides through sliding through hole and cup joint the outer wall at the deflector, gu fixed splint is located movable clamp plate's front side, and the fixed welding is at the most advanced lateral wall of deflector.
Preferably, four settlement mounting holes which are rectangular and evenly distributed at intervals are formed in the mounting plate.
Preferably, the rubber anti-skid pads are adhered to the front end face of the movable clamping plate and the rear end face of the fixed clamping plate, and a corrugated wire groove is formed in the surface of each rubber anti-skid pad.
Preferably, two tensioning mechanisms are arranged between the mounting plate and the movable clamping plate and are respectively positioned on the left side and the right side of the guide plate, and each tensioning mechanism comprises an oval stainless steel ring and two connecting columns.
Preferably, every two spliced poles of straining device weld respectively at the both ends of the long semi-axis of every oval stainless steel ring, two the rear end face of two spliced poles of straining device respectively with the preceding terminal surface left and right sides fixed weld of mounting panel, two the preceding terminal surface of two spliced poles of straining device respectively with the preceding terminal surface left and right sides fixed weld of movable clamp plate.
Preferably, the mounting plate, the movable clamping plate and the fixed clamping plate are equal in height, width and thickness.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model relates to a building curtain sees firm formula mounting structure for frame can rationally set up whole mounting structure's position, the bright frame of the quick fixed mounting curtain of being convenient for, simple and practical according to the curtain area size.
2. The utility model discloses, all paste through the preceding terminal surface at movable splint and the rear end face of solid fixed splint and have the rubber slipmat, and the surface of every rubber slipmat all is equipped with the ripple wire casing, the contact friction of increase and bright frame to the phenomenon that sideslips appears, simple and practical.
Drawings
Fig. 1 is a schematic structural diagram of an embodiment of the present invention;
fig. 2 is a sectional view of the top view structure of the embodiment of the present invention.
In the figure: 1. mounting a plate; 11. settling the mounting hole; 2. a tensioning mechanism; 21. connecting columns; 22. an elliptical stainless steel ring; 3. moving the clamping plate; 4. a guide plate; 5. and fixing the splint.
Detailed Description
In order to facilitate the use, the embodiment of the utility model provides a building curtain is firm formula mounting structure for bright frame. The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
Referring to fig. 1-2, the present embodiment provides a stable mounting structure for a building curtain wall exposed frame, including a mounting plate 1, a movable clamping plate 3 and a fixed clamping plate 5, wherein a guide plate 4 is fixedly welded at a middle section of a front end surface of the mounting plate 1, the movable clamping plate 3 is provided with a sliding through hole and is slidably sleeved on an outer wall of the guide plate 4 through the sliding through hole, and the fixed clamping plate 5 is located at a front side of the movable clamping plate 3 and is fixedly welded on a side wall of a tip end of the guide plate 4.
Four settlement mounting holes 11 which are distributed in a rectangular shape at even intervals are formed in the mounting plate 1.
Two tensioning mechanisms 2 are arranged between the mounting plate 1 and the movable clamping plate 3, the two tensioning mechanisms 2 are respectively positioned at the left side and the right side of the guide plate 4, and each tensioning mechanism 2 comprises an oval stainless steel ring 22 and two connecting columns 21.
The two connecting columns 21 of each tensioning mechanism 2 are respectively welded at two ends of the long half shaft of each oval stainless steel ring 22, the rear end faces of the two connecting columns 21 of the two tensioning mechanisms 2 are respectively fixedly welded with the left side and the right side of the front end face of the mounting plate 1, and the front end faces of the two connecting columns 21 of the two tensioning mechanisms 2 are respectively fixedly welded with the left side and the right side of the front end face of the movable clamping plate 3.
In the embodiment, the position of the whole installation structure can be reasonably set according to the area of the curtain wall, and then the installation structure penetrates through four settlement installation holes 11 of the installation plate 1 through bolts respectively to realize that the installation plate 1 is fixedly installed firstly, then the movable clamping plate 3 and the fixed clamping plate 5 are unfolded by bare hands, namely the movable clamping plate 3 slides to one side of the installation plate 1 along the guide plate 4, so that the clamping gap between the movable clamping plate 3 and the fixed clamping plate 5 is increased, the oval stainless steel rings 22 of the two tensioning mechanisms 2 are deformed, namely the upper end and the lower end are elongated, the exposed frame to be fixed is placed in the clamping gap between the movable clamping plate 3 and the fixed clamping plate 5, the movable clamping plate 3 is loosened, the oval stainless steel rings 22 of the two tensioning mechanisms 2 recover the deformation and jack up the movable clamping plate 3 to one end of the fixed clamping plate 5 along the guide plate 4, the exposed frame of, is simple and practical.
Example 2
Referring to fig. 1-2, a further improvement is made on the basis of embodiment 1:
rubber anti-slip pads are adhered to the front end face of the movable clamping plate 3 and the rear end face of the fixed clamping plate 5, corrugated wire grooves are formed in the surface of each rubber anti-slip pad, and the rubber anti-slip pads with the corrugated wire grooves are arranged to increase the contact friction force with the exposed frame so as to avoid the phenomenon of sideslip;
the mounting plate 1, the movable clamping plate 3 and the fixed clamping plate 5 are equal in height, width and thickness, so that the size deviation can not be generated during mounting, and the fixed mounting and the attractiveness of the curtain wall are not influenced.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (6)
1. The utility model provides a building curtain sees frame with firm formula mounting structure, includes mounting panel (1), movable clamp plate (3) and solid fixed splint (5), its characterized in that: the fixed welding in preceding terminal surface middle section position of mounting panel (1) has deflector (4), sliding through hole has been seted up in movable clamp plate (3), and slides through sliding through hole and cup joint the outer wall in deflector (4), fixed clamp plate (5) are located the front side of movable clamp plate (3), and the fixed welding is at the most advanced lateral wall of deflector (4).
2. The stable mounting structure for the exposed frame of the building curtain wall as claimed in claim 1, wherein: four settlement mounting holes (11) which are distributed at equal intervals in a rectangular shape are formed in the mounting plate (1).
3. The stable mounting structure for the exposed frame of the building curtain wall as claimed in claim 1, wherein: the rubber anti-skid mat is adhered to the front end face of the movable clamping plate (3) and the rear end face of the fixed clamping plate (5), and a corrugated wire groove is formed in the surface of each rubber anti-skid mat.
4. The stable mounting structure for the exposed frame of the building curtain wall as claimed in claim 1, wherein: be equipped with two straining device (2), two between mounting panel (1) and movable clamp plate (3) straining device (2) are located the left and right sides of deflector (4) respectively, every straining device (2) all are including oval stainless steel ring (22) and two spliced poles (21).
5. The stable mounting structure for the exposed frame of the building curtain wall as claimed in claim 4, wherein: every two spliced poles (21) of straining device (2) weld respectively at the both ends of the major axis of every oval stainless steel ring (22), two the rear end face of two spliced poles (21) of straining device (2) respectively with the preceding terminal surface left and right sides fixed weld of mounting panel (1), two the preceding terminal surface of two spliced poles (21) of straining device (2) respectively with the preceding terminal surface left and right sides fixed weld of removal splint (3).
6. The stable mounting structure for the exposed frame of the building curtain wall as claimed in claim 1, wherein: the mounting plate (1), the movable clamping plate (3) and the fixed clamping plate (5) are equal in height, width and thickness.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021263871.XU CN212802155U (en) | 2020-07-02 | 2020-07-02 | Firm formula mounting structure is used to building curtain bright frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021263871.XU CN212802155U (en) | 2020-07-02 | 2020-07-02 | Firm formula mounting structure is used to building curtain bright frame |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212802155U true CN212802155U (en) | 2021-03-26 |
Family
ID=75099236
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021263871.XU Expired - Fee Related CN212802155U (en) | 2020-07-02 | 2020-07-02 | Firm formula mounting structure is used to building curtain bright frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212802155U (en) |
-
2020
- 2020-07-02 CN CN202021263871.XU patent/CN212802155U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111934254A (en) | Polyurethane bridge frame with embedded channel structure and rapid assembling method thereof | |
CN211306781U (en) | Concrete test piece bears frame for concrete curing room | |
CN212802155U (en) | Firm formula mounting structure is used to building curtain bright frame | |
CN214952597U (en) | Pressure-bearing detection device for production of gypsum plaster boards | |
CN214423855U (en) | Assembled building wallboard | |
CN203499074U (en) | Glass curtain wall facilitating replacement of glass panels | |
CN211690968U (en) | Composite curtain wall structure | |
CN210092810U (en) | Firm supporting structure for cable bus duct bridge | |
CN206844423U (en) | Glass curtain wall attachment structure positioner optimizes structure | |
CN211428814U (en) | Cable support | |
CN213897638U (en) | Green building glass wall body of convenient concatenation | |
CN210122776U (en) | Glass curtain wall erection joint stand | |
CN210827851U (en) | Assembled splicing structure of mobile sunlight room | |
CN210669347U (en) | Make things convenient for welding-free gallows of steel construction building electromechanical pipeline installation | |
CN216587487U (en) | Light-transmitting marble mounting rack convenient to disassemble | |
CN216713562U (en) | Aluminum veneer convenient to installation | |
CN214574973U (en) | Assembled curtain wall assembling device for building design | |
CN214117933U (en) | Glass plate with detachable performance for mounting sunlight room | |
CN217150837U (en) | Safer environment-friendly energy-saving exposed frame curtain wall end | |
CN209847059U (en) | Fixed window machine of wiping of parapet | |
CN116044077B (en) | Aluminum structure top surface glass daylighting roof mounting system | |
CN214574990U (en) | Installation positioning device of glass curtain wall | |
CN214255221U (en) | Inflatable looped netowrk cabinet that side is provided with anticollision protective structure | |
CN215802504U (en) | A connection structure for glass curtain wall | |
CN218894255U (en) | Novel high-rise curtain wall mounting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210326 |