CN212772372U - Synchronous riprap rammer - Google Patents
Synchronous riprap rammer Download PDFInfo
- Publication number
- CN212772372U CN212772372U CN202021521703.6U CN202021521703U CN212772372U CN 212772372 U CN212772372 U CN 212772372U CN 202021521703 U CN202021521703 U CN 202021521703U CN 212772372 U CN212772372 U CN 212772372U
- Authority
- CN
- China
- Prior art keywords
- synchronous
- track
- ship
- chute
- riprap
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Machines For Laying And Maintaining Railways (AREA)
Abstract
The utility model discloses a synchronous stone rammer that throws of immersed tube construction usefulness belongs to construction technical field under water. The synchronous riprap ramming ship is characterized in that a first rail and a second rail are respectively arranged on the port and the starboard of a main deck, and the first rail and the second rail extend along the direction of a ship body and are parallel to each other; the first track is provided with two chute trolleys, and the second track is provided with a tamping platform trolley. The elephant trunk stone throwing system and the vibration tamping system of the synchronous stone throwing tamping ship are respectively arranged on the left side and the right side of a ship, and have respective trolley running tracks, so that construction is not interfered with each other, stone throwing and tamping operations can be carried out simultaneously, and the construction efficiency is greatly improved.
Description
Technical Field
The utility model belongs to the technical field of the construction under water, especially, relate to a synchronous stone rammer that throws of immersed tube construction usefulness.
Background
When the immersed tube foundation is constructed, the foundation trench needs to be excavated, and then the foundation bed is subjected to throwing filling, leveling and dredging operations. The method comprises the following steps that a throwing and filling ship is used for throwing and filling a foundation bed, a barge carries stones to a designated area and then berths the throwing and filling ship, the materials are supplied to the throwing and filling ship through modes of throwing by a belt or an excavator and the like, and the throwing and filling ship throws materials at the bottom of the water to finish throwing and filling operation; the leveling ship is needed to be used for leveling the foundation bed, the original rugged blocks are rearranged and combined by the vibration of the vibration hammer arranged on the leveling ship by utilizing the principle of vibration tamping, and the surface of the foundation bed is leveled.
In order to solve the problems of complex operation and safety caused by the approach construction of various ships, patent application CN102758439A discloses a sinking pipe foundation construction barge, wherein one side of a deck of the barge is provided with a track, the track is provided with a travelling mechanism, the travelling mechanism comprises a pipe sliding vehicle and a tamping vehicle, the pipe sliding vehicle is connected with a pipe sliding system, the tamping vehicle is loaded with a vibration hammer and a vibration hammer lifting system, the functions of stone throwing and tamping are integrated on one ship, and the types of the ships are reduced. However, the chute stone throwing system and the vibrating ramming system are arranged on the same side of the ship and share the same trolley running track, only single stone throwing or ramming construction can be carried out, the synchronous construction conditions of stone throwing and ramming are not provided, the construction efficiency is low, and the requirements of high efficiency and construction period cannot be met.
SUMMERY OF THE UTILITY MODEL
The utility model provides an above-mentioned technical problem, provide a possess and throw the stone and tamp the ship with ramming the synchronous construction condition in step.
In order to achieve the above object, the utility model discloses a technical scheme be:
the synchronous riprap ramming ship is characterized by comprising a main deck, a main; the first track is provided with two chute trolleys, and the second track is provided with a tamping platform trolley.
Preferably, the chute trolley and the tamper platform trolley are respectively driven by a plurality of winches, so that independent movement and operation on the rails can be realized.
Preferably, a fixed docking pier is arranged at the outboard bow and stern of the first rail.
Preferably, two sets of chute retracting mechanisms are further arranged on one side of the first track, each chute retracting mechanism comprises a retracting winch, and the retracting winches control the retraction of the chutes through traction cables; the chute retracting mechanism further comprises two groups of supporting mechanisms arranged outside the ship board on one side of the first track.
Preferably, the supporting mechanism comprises two supporting frames, when the chute works, the supporting frames are tightly attached to a ship board, and when the chute is folded, the supporting frames can rotate 90 degrees along the horizontal direction to play a role in supporting the chute.
Preferably, a control container is disposed between the first rail and the second rail.
Compared with the prior art, the utility model discloses an advantage lies in with positive effect:
1. the elephant trunk stone throwing system and the vibration tamping system of the synchronous stone throwing tamping ship are respectively arranged on the left side and the right side of a ship, and have respective trolley running tracks, so that construction is not interfered with each other, conditions for simultaneous operation are met, and construction efficiency is greatly improved.
2. The synchronous stone throwing tamping ship is provided with two fixed fender boats on the side of the elephant trunk, the stone transport ship can be directly berthed on the fixed fender boats on one side of the elephant trunk, and the excavator can directly throw and fill stones into a hopper of the elephant trunk on the stone ship, so that secondary transportation of stones is avoided, and the stone throwing work efficiency is greatly improved.
Drawings
Fig. 1 is a schematic structural view of a main deck of a synchronous riprap ramming vessel provided by an embodiment of the present invention;
fig. 2 is a schematic side structure view of the synchronous riprap ramming vessel provided by the embodiment of the present invention;
in the figure, 1: first rail, 2: second rail, 3: chute trolley, 4: ramming platform car, 5: control container, 6: winch, 7: receive and release winch, 8: support frame, 9: pier 9
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely below, and it should be understood that the described embodiments are only some embodiments of the present invention, but not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
As shown in fig. 1, an embodiment of the present invention provides a synchronous riprap ramming vessel, which is provided with a first rail 1 and a second rail 2 on the port and starboard side of a main deck, respectively, where the first rail 1 and the second rail 2 extend in a hull direction and are parallel to each other; two chute trolleys 3 are arranged on the first track 1, and a tamping platform trolley 4 is arranged on the second track 2. The elephant trunk trolley 3 and the tamping platform trolley 4 are respectively driven by a plurality of winches 6, and can independently move and operate on respective tracks. Specifically, two ends of the first track 1 are respectively provided with 2 winches, and two elephant trunk trolleys 3 are controlled to walk on the first track 1 through steel cables; two ends of the second track 2 are respectively provided with 1 winch, and the tamping platform car 4 is controlled to travel on the second track 2 through a steel cable; in addition, four winches are arranged on the elephant trunk trolley 3 to control the elephant trunk to stretch, and two winches are arranged on the tamping platform trolley to control the vibration hammer to lift.
In the embodiment, the chute stone throwing system and the vibration tamping system of the synchronous stone throwing tamping vessel are respectively arranged on the left side and the right side of the vessel, have respective trolley running tracks and are controlled by different winches to move and work, the construction is not interfered with each other, and the synchronous stone throwing tamping vessel has the condition of simultaneous operation. And only carrying out stone throwing operation on the vessel position before entering each time, and after the vibration tamping system of the subsequent vessel position enters a preset construction area, simultaneously carrying out stone throwing and vibration tamping operation, thereby greatly improving the construction efficiency.
Specifically, 2 stands of 1.5m are used3The excavator with bucket capacity is matched with two sets of riprap elephant trunks for construction, and the construction efficiency is 1800m3D, the single immersed tube riprap amount is 15209m3(average), the required time was 9 days; the ramming area of a single immersed tube foundation is 8580m2And the time for completing the ramming construction of the single immersed tube foundation is 3 days. The construction of the synchronous stone throwing and tamping ship is adopted, the stone throwing and tamping construction is carried out synchronously, the tamping time of 3 days can be saved, and the construction efficiency is improved.
As further shown in fig. 1 and 2, two sets of chute retracting and releasing mechanisms are further arranged on one side of the first track 1, each chute retracting and releasing mechanism comprises a retracting and releasing winch 7, and the retracting and releasing winches 7 control the retraction of a chute through a traction rope; the chute retracting mechanism further comprises two groups of supporting mechanisms arranged outside the ship board on one side of the first track 1. The supporting mechanism comprises two supporting frames 8, when the elephant trunk works, the supporting frames 8 are tightly attached to a ship board, and when the elephant trunk is folded, the supporting frames 8 can rotate 90 degrees in the horizontal direction to play a role in supporting the elephant trunk.
The outer bow and stern of the side of the ship on the first track 1 are respectively provided with a fixed berth pier 9, the stone material transport ship can be directly berthed on the fixed berth pier 9 on one side of the elephant trunk, and the excavator can directly throw and fill stone materials into a chute hopper on the stone material ship, so that secondary transportation of the stone materials is avoided, the stone throwing work efficiency is greatly improved, and the effect of protecting the chute can be achieved. Because need not keep in the building stones on the riprap ramming ship, usable area is showing the increase on its main deck, consequently can carry out more reasonable arrangement to all kinds of auxiliary facilities on the ship. A control container 5 may be arranged between said first track 1 and second track 2, e.g. for more convenient viewing and manoeuvring of the equipment.
Claims (6)
1. The synchronous riprap ramming ship is characterized in that a first rail and a second rail are respectively arranged on the port and the starboard of a main deck, and extend along the ship body direction and are parallel to each other; the first track is provided with two chute trolleys, and the second track is provided with a tamping platform trolley.
2. The synchronous riprap ramming platform vessel of claim 1, wherein said chute carriage and said ramming platform carriage are each driven by a respective plurality of winches to allow independent movement and operation on respective tracks.
3. The synchronous riprap rammer flattening vessel according to claim 1, wherein a fixed docking block is provided at each of the outboard bow and stern on the first track side.
4. The synchronous riprap ramming platform according to claim 1, wherein two sets of elephant trunk retraction mechanisms are further arranged on one side of the first track, each elephant trunk retraction mechanism comprises a retraction winch, and the retraction winches control retraction of elephant trunks through traction cables; the chute retracting mechanism further comprises two groups of supporting mechanisms arranged outside the ship board on one side of the first track.
5. The synchronous riprap ramming and flattening ship according to claim 4, wherein the supporting mechanism comprises two supporting frames, when the chute is in operation, the supporting frames are tightly attached to the side of the ship, and when the chute is retracted, the supporting frames can rotate 90 degrees in the horizontal direction to play a role of supporting the chute.
6. The synchronous riprap ramming vessel of claim 1, wherein a control container is disposed between the first track and the second track.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021521703.6U CN212772372U (en) | 2020-07-28 | 2020-07-28 | Synchronous riprap rammer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021521703.6U CN212772372U (en) | 2020-07-28 | 2020-07-28 | Synchronous riprap rammer |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212772372U true CN212772372U (en) | 2021-03-23 |
Family
ID=75040030
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021521703.6U Active CN212772372U (en) | 2020-07-28 | 2020-07-28 | Synchronous riprap rammer |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212772372U (en) |
-
2020
- 2020-07-28 CN CN202021521703.6U patent/CN212772372U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6802684B2 (en) | Container tranfer terminal system and method | |
US7370768B2 (en) | Crane apparatus for direct transshipment of marine containers between transportation modes without need of ground placement | |
CN111891296A (en) | Submersible transport and distribution recovery system and method | |
KR100940795B1 (en) | Method for launching and transporting heavy weight structures using air bags | |
CN112573113A (en) | Riprap leveling ship | |
CN101941510A (en) | Method for improving ship handling efficiency of containers (or bulk cargo) and equipment thereof | |
AU2005306106B2 (en) | Device for the offshore loading and unloading of ships | |
CN212772372U (en) | Synchronous riprap rammer | |
CN104060592B (en) | Method for 1/4 land territory preassembling and overwater dispersion of large cylinder main grids of cellular steel sheet piles | |
CN101725162B (en) | Well-type grab bucket sand dredging and desilting ship | |
CN112810762A (en) | Ship is restoreed to cross sea bridge pier pile foundation | |
CN212711257U (en) | Riprap leveling ship | |
CN1143138A (en) | Launching method for laud region prefabricated sinking caisson | |
US3561617A (en) | Means for the transportation of goods | |
CN213625592U (en) | Lifting, placing and anchoring device for leveling frame in riprap leveling ship | |
CN114032897A (en) | Waterborne wheel-rail type remote control piling platform and method | |
CN216739456U (en) | Wharf construction device | |
CN213323580U (en) | Posture adjusting device of leveling frame device of riprap leveling ship | |
CN212714952U (en) | Leveling frame device of riprap leveling ship | |
CN211494398U (en) | Stone sliding pipe device of riprap leveling ship | |
CN213324785U (en) | Hopper device of riprap leveling ship | |
CN218579106U (en) | Multipurpose bank ship unloader | |
CN213805183U (en) | Novel gravity cylinder type beam plate wharf structure | |
CN211169577U (en) | Cable reel storage device for shore power connection | |
CN212531453U (en) | Full-track loading and unloading transportation system for cable car wharf marker ship |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |