CN212716681U CN202021545206.XU CN202021545206U CN212716681U CN 212716681 U CN212716681 U CN 212716681U CN 202021545206 U CN202021545206 U CN 202021545206U CN 212716681 U CN212716681 U CN 212716681U
Authority
CN
China
Prior art keywords
matched
gasket
auxiliary
central
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021545206.XU
Other languages
Chinese (zh)
Inventor
王晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Zhongkai Weiye Equipment Manufacturing Co ltd
Original Assignee
Wuhan Zhongkai Weiye Equipment Manufacturing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Zhongkai Weiye Equipment Manufacturing Co ltd filed Critical Wuhan Zhongkai Weiye Equipment Manufacturing Co ltd
Priority to CN202021545206.XU priority Critical patent/CN212716681U/en
Application granted granted Critical
Publication of CN212716681U publication Critical patent/CN212716681U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a shield constructs construction section of jurisdiction hoist device, including the section of jurisdiction, the both sides on section of jurisdiction top all are equipped with rather than the fixed knot of matched with function, the intermediate position of section of jurisdiction bottom is equipped with rather than matched with central function gasket, the bottom of central function gasket is equipped with rather than matched with central fixed block, the inside symmetry of central fixed block is equipped with rather than matched with function hole, the inside in function hole is equipped with rather than matched with hoist and mount rope, the both sides of central function gasket all are equipped with rather than section of jurisdiction matched with supplementary gasket, the bottom of supplementary gasket is equipped with rather than matched with supplementary fixed block, the inside of supplementary fixed block is equipped with rather than matched with supplementary rope. The beneficial effects are that: the effectual equipment of having guaranteed can carry out better atress during whole use by equipment to can guarantee the steady of whole hoist and mount process, thereby make equipment nimble more and practical.

Description

Shield constructs construction section of jurisdiction hoist device
Technical Field
The utility model relates to a hoist and mount field particularly, relates to a shield constructs construction section of jurisdiction hoist device.
Background
The hoisting refers to the general name of the installation and the positioning of equipment by a crane or a hoisting mechanism, and various hoisting tools are utilized to hoist the equipment, workpieces, appliances, materials and the like in the process of maintenance or repair so as to cause the equipment, the workpieces, the appliances, the materials and the like to generate position change, and the shield segment is a main assembly member of shield construction, is an outermost barrier of a tunnel and plays a role in resisting soil layer pressure, underground water pressure and some special loads. The shield segment is a permanent lining structure of a shield tunnel, and the quality of the shield segment is directly related to the overall quality and safety of the tunnel, so that the waterproof performance and the durability of the tunnel are influenced. At present, shield constructs hoisting tool of shield segment in the construction and generally all uses traditional canvas suspender, and in hoisting process, if appearing rocking, do not have sufficient atress strong point and good stable structure that keeps, when can not hoist a plurality of segments simultaneously, still appear hoist and mount position unbalance easily moreover, the final phenomenon that drops appears.
An effective solution to the problems in the related art has not been proposed yet.
SUMMERY OF THE UTILITY MODEL
To the problem in the correlation technique, the utility model provides a shield constructs construction section of jurisdiction hoist device to overcome the above-mentioned technical problem that current correlation technique exists.
Therefore, the utility model discloses a specific technical scheme as follows:
the utility model provides a shield constructs construction section of jurisdiction hoist device, includes the section of jurisdiction, the both sides on section of jurisdiction top all are equipped with rather than the fixed knot of matched with function, the intermediate position of section of jurisdiction bottom is equipped with rather than matched with central function gasket, the bottom of central function gasket is equipped with rather than matched with central fixed block, the inside symmetry of central fixed block is equipped with rather than matched with function hole, the inside in function hole is equipped with rather than matched with hoist and mount rope, the both sides of central function gasket all be equipped with section of jurisdiction matched with supplementary gasket, the bottom of supplementary gasket is equipped with rather than matched with supplementary fixed block, the inside of supplementary fixed block is equipped with rather than matched with supplementary rope.
Furthermore, the top end of the function fixing buckle is provided with an auxiliary hoisting reinforcing rope matched with the function fixing buckle.
Furthermore, a plurality of connecting reinforcing ropes are arranged between the auxiliary gasket and the functional fixing buckles.
Furthermore, an anti-skid connecting strip is arranged between the auxiliary fixing block and the auxiliary gasket.
Furthermore, a connecting rope is arranged between the auxiliary gasket and the central functional gasket.
Furthermore, the auxiliary rope and the end, far away from the segment, of the hoisting rope are provided with a connecting lifting ring matched with the auxiliary rope.
Furthermore, a connecting and fixing strip is arranged between the central fixing block and the central functional gasket.
The utility model has the advantages that: the effectual equipment of having guaranteed can carry out better atress during whole use by equipment to can guarantee the steady of whole hoist and mount process, thereby make equipment nimble more and practical.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required to be used in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural diagram of a shield construction segment hoisting device according to an embodiment of the present invention;
fig. 2 is a structural schematic diagram of a central functional gasket of a shield construction segment hoisting device according to the embodiment of the utility model.
In the figure:
1. a duct piece; 2. a functional fixing buckle; 3. a central functional spacer; 4. a central fixed block; 5. a functional hole; 6. hoisting a rope; 7. an auxiliary pad; 8. an auxiliary fixing block; 9. an auxiliary rope; 10. auxiliary hoisting of reinforcing ropes; 11. connecting a reinforcing rope; 12. an anti-slip connecting strip; 13. connecting ropes; 14. connecting a lifting ring; 15. and connecting the fixing strips.
Detailed Description
For further explanation of the embodiments, the drawings are provided as part of the disclosure and serve primarily to illustrate the embodiments and, together with the description, to explain the principles of operation of the embodiments, and to provide further explanation of the invention and advantages thereof, it will be understood by those skilled in the art that various other embodiments and advantages of the invention are possible, and that elements in the drawings are not to scale and that like reference numerals are generally used to designate like elements.
According to the utility model discloses an embodiment provides a shield constructs construction section of jurisdiction hoist device.
The first embodiment is as follows:
as shown in fig. 1-2, according to the utility model discloses shield constructs construction section of jurisdiction hoist device, including section of jurisdiction 1, the both sides on section of jurisdiction 1 top all are equipped with rather than the fixed knot 2 of matched with function, the intermediate position of section of jurisdiction 1 bottom is equipped with rather than matched with central function gasket 3, the bottom of central function gasket 3 is equipped with rather than matched with central fixed block 4, the inside symmetry of central fixed block 4 is equipped with rather than matched with function hole 5, the inside of function hole 5 is equipped with rather than matched with hoist and mount rope 6, the both sides of central function gasket 3 all be equipped with section of jurisdiction 1 matched with auxiliary gasket 7, the bottom of auxiliary gasket 7 is equipped with rather than matched with auxiliary fixed block 8, the inside of auxiliary fixed block 8 is equipped with rather than matched with auxiliary rope 9.
The specific arrangement and function of the duct piece 1, the auxiliary gasket 7, the central fixing block 4, the auxiliary rope 9 and the functional hole 5 are described in detail below.
As shown in fig. 1-2, when the device is used, the central functional gasket 3 is firstly placed at the middle position of the bottom end of the segment 1, then the auxiliary gasket 7 connected with the central functional gasket is placed at the middle position, then the central fixing block 4 is fixed with the central functional gasket 3 through the connecting fixing strip 15, the central fixing block and the central functional gasket 3 are ensured to be stressed together, then the auxiliary fixing block 8 is installed and fixed in the same way, after the auxiliary fixing block 8 is connected with the auxiliary gasket 7 and stressed, the connecting reinforcing rope 11 bypasses the lateral source of the segment 1 and is connected and fixed with the functional fixing buckle 2, at this time, the device is basically installed, after the auxiliary fixing block is connected with a hoisting power machine through the connecting hoisting ring 14, the hoisting starts, the auxiliary ropes 9, the hoisting rope 6 and the auxiliary hoisting reinforcing rope 10 start to be stressed simultaneously, the auxiliary gasket 7 can slowly deviate from the central functional gasket 3 due to the, in the period, the connecting ropes 13 can ensure the offset distance and can simultaneously communicate with the stress of the central function gasket 3 to achieve simultaneous stress and disperse the force in a single direction, in the whole stress pulling period, the auxiliary hoisting reinforcing ropes 10 can further enhance the strength and simultaneously can ensure the hoisting stability and the opposite force to be dispersed again, the two sides of the duct piece 1 can be simultaneously stressed to avoid the structural collapse, the connecting reinforcing ropes 11 can connect the stress points on the two sides, the similar hoisting stress area distribution is enlarged, the edges are uniform and the stress can be more stable,
example two:
as shown in fig. 1-2, the top end of the function fixing buckle 2 is provided with an auxiliary hoisting reinforcing rope 10 matched with the function fixing buckle 2, the auxiliary gasket 7 is provided with a plurality of connecting reinforcing ropes 11 between the function fixing buckle 2, the auxiliary fixing block 8 is provided with an anti-slip connecting strip 12 between the auxiliary gasket 7, the auxiliary gasket 7 is provided with a connecting rope 13 between the central function gaskets 3, the auxiliary rope 9 and one end of the hoisting rope 6 far away from the duct piece 1 are provided with a connecting lifting ring 14 matched with the auxiliary rope, and a connecting fixing strip 15 is provided between the central fixing block 4 and the central function gaskets 3.
For the convenience of understanding the technical solution of the present invention, the following detailed description is made on the working principle or the operation mode of the present invention in the practical process.
In practical application, the central functional gasket 3 is firstly placed in the middle of the bottom end of the segment 1, then the auxiliary gasket 7 connected with the central functional gasket is placed in the middle, then the central fixing block 4 is fixed with the central functional gasket 3 through the connecting fixing strip 15, the central functional gasket and the auxiliary functional gasket are enabled to bear force together, then the auxiliary fixing block 8 is installed and fixed in the same way, after the auxiliary fixing block 8 is connected with the auxiliary gasket 7 and stressed, the connecting reinforcing rope 11 bypasses the side source of the segment 1 and is connected and fixed with the functional fixing buckle 2, at the moment, the equipment is basically installed, after the auxiliary fixing block is connected with a hoisting power machine through the connecting hoisting ring 14, hoisting starts, the auxiliary ropes 9, the hoisting rope 6 and the auxiliary hoisting reinforcing rope 10 simultaneously start to bear force, the auxiliary gasket 7 slowly deviates from the central functional gasket 3 due to excessive gravity and the shape of the segment 1, and the connecting rope 13 can guarantee the deviation distance, and make it can reach the atress simultaneously and disperse the power of single direction with the atress UNICOM of central function gasket 3 simultaneously, and during whole atress is dragged, when supplementary hoist and mount reinforcing rope 10 can further strengthen intensity, can guarantee the stability of hoist and mount and to the power at this dispersion, section of jurisdiction 1 that is can both sides atress simultaneously, avoid the structure to collapse, and connect reinforcing rope 11 and can connect both sides stress point, the even and more steady atress of draft area distribution grow limit of similar hoist and mount.
To sum up, with the help of the above technical scheme of the utility model, the effectual equipment of having guaranteed can carry out better atress during whole use to can guarantee the steady of whole hoist and mount process, thereby make equipment nimble more and practical.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. A shield construction segment hoisting device is characterized by comprising a segment (1), both sides of the top end of the duct piece (1) are provided with a functional fixing buckle (2) matched with the duct piece, a central functional gasket (3) matched with the middle position of the bottom end of the duct piece (1) is arranged at the middle position of the bottom end of the duct piece, the bottom end of the central functional gasket (3) is provided with a central fixed block (4) matched with the central functional gasket, functional holes (5) matched with the central fixed block (4) are symmetrically arranged in the central fixed block, a hoisting rope (6) matched with the functional hole (5) is arranged in the functional hole, auxiliary gaskets (7) matched with the duct piece (1) are arranged on both sides of the central functional gasket (3), the bottom end of the auxiliary gasket (7) is provided with an auxiliary fixing block (8) matched with the auxiliary gasket, and an auxiliary rope (9) matched with the auxiliary fixing block is arranged in the auxiliary fixing block (8).
2. The shield construction segment hoisting device according to claim 1, wherein the top end of the functional fixing buckle (2) is provided with an auxiliary hoisting reinforcing rope (10) matched with the functional fixing buckle.
3. The shield construction segment hoisting device according to claim 1, wherein a plurality of connecting reinforcing ropes (11) are arranged between the auxiliary gasket (7) and the functional fixing buckle (2).
4. The shield construction segment hoisting device according to claim 1, wherein an anti-slip connecting strip (12) is arranged between the auxiliary fixing block (8) and the auxiliary gasket (7).
5. The shield construction segment hoisting device according to claim 1, wherein a connecting rope (13) is arranged between the auxiliary gasket (7) and the central functional gasket (3).
6. The shield construction segment hoisting device according to claim 1, wherein the auxiliary rope (9) and the hoisting rope (6) are provided with a connecting hoisting ring (14) matched with the auxiliary rope and the hoisting rope at the ends far away from the segment (1).
7. The shield construction segment hoisting device according to claim 1, wherein a connecting fixing strip (15) is arranged between the central fixing block (4) and the central functional gasket (3).
CN202021545206.XU 2020-07-30 2020-07-30 Shield constructs construction section of jurisdiction hoist device Active CN212716681U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021545206.XU CN212716681U (en) 2020-07-30 2020-07-30 Shield constructs construction section of jurisdiction hoist device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021545206.XU CN212716681U (en) 2020-07-30 2020-07-30 Shield constructs construction section of jurisdiction hoist device

Publications (1)

Publication Number Publication Date
CN212716681U true CN212716681U (en) 2021-03-16

Family

ID=74910702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021545206.XU Active CN212716681U (en) 2020-07-30 2020-07-30 Shield constructs construction section of jurisdiction hoist device

Country Status (1)

Country Link
CN (1) CN212716681U (en)

Similar Documents

Publication Publication Date Title
CN203319499U (en) Shaft tube hoisting device
CN212716681U (en) Shield constructs construction section of jurisdiction hoist device
CN108708281A (en) A kind of porous freely-supported approximation arch steel truss beam erection method
CN207192584U (en) A kind of boom hoisting of torsion-bending ratio
CN203513082U (en) Special combined lifting appliance of excavator
CN203066073U (en) Pile-pulling mechanism, pile-pulling machinery and lifting machinery with same
CN202529744U (en) Structure of auxiliary hoist of fixed mast and crawler crane equipped with structure
CN210888296U (en) Electric power warning fence
CN208454359U (en) A kind of portable multifunctional transfer device peculiar to vessel
CN108547647B (en) High-strength supporting structure for underground cavern
CN216336160U (en) Portable multifunctional combined lifting appliance for offshore drilling platform
CN206188260U (en) Hoist top ping lift prevents kinking device and hoist
CN207999218U (en) A kind of mast installation and rotary drilling rig
CN207792472U (en) A kind of thrust wheel of digging machine installation auxiliary mould
CN207645633U (en) A kind of reversal hanger for Rectangular Tunnel combined type section of jurisdiction
CN207063110U (en) A kind of removable gutter of open slope
CN205575425U (en) High strength tower crane attachment structure
CN215762015U (en) Runner blade anti-skid device for axial flow propeller type water turbine generator set
CN211310750U (en) Single hoisting point bridge crane major part hoist and mount sky anchor
CN217676307U (en) Combined stay bar structure for hoisting cable reel
CN213738293U (en) Tower crane without counterweight
CN208684188U (en) A kind of cable winder of elevator cable
CN215755923U (en) Mechanical rope special for Acheson graphitizing furnace unloading lifting appliance
CN216586201U (en) A hoist that is arranged in cable-stay bridge construction to stride to close
CN210178418U (en) Deep well relief drainage hoisting system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant