CN212687348U - Hoist device is used in building engineering construction - Google Patents
Hoist device is used in building engineering construction Download PDFInfo
- Publication number
- CN212687348U CN212687348U CN202021699192.7U CN202021699192U CN212687348U CN 212687348 U CN212687348 U CN 212687348U CN 202021699192 U CN202021699192 U CN 202021699192U CN 212687348 U CN212687348 U CN 212687348U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- cross arm
- circular
- hoist
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 16
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 101
- 239000010959 steel Substances 0.000 claims abstract description 101
- 239000002184 metal Substances 0.000 claims abstract description 23
- 230000007246 mechanism Effects 0.000 claims abstract description 8
- 238000003466 welding Methods 0.000 claims description 3
- 238000010030 laminating Methods 0.000 claims 1
- 230000035515 penetration Effects 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 8
- 230000000149 penetrating effect Effects 0.000 description 3
- 239000004035 construction material Substances 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a hoisting device for construction engineering construction, which relates to the field of buildings, and comprises steel pipe clamps, wherein the steel pipe clamps are provided with a plurality of groups, the plurality of groups of steel pipe clamps are sequentially overlapped along the vertical direction, the steel pipe clamps comprise an upper clamping plate and a lower clamping plate which are laminated up and down, vertical metal screw rods are all inserted in screw rod perforation, the middle parts of steel cables are all tied with circular ring knots, cross arm pipes are all inserted between two corresponding circular ring knots in the front and back, both ends of each cross arm pipe are provided with anti-dropping mechanisms, a lug plate is welded at the upper end of the middle part of each cross arm pipe, a hoisting hole is formed in each lug plate, and a self-locking lifting hook is hooked in each hoisting; the utility model discloses a set up the steel pipe centre gripping that steel pipe anchor clamps are used for will hanging fixed, the centre gripping is stable can not take place the steel pipe phenomenon of droing at the hoist and mount in-process, has avoided the emergence of hoist and mount in-process incident, and once only can hoist more quantity of steel pipes, has improved the efficiency of hoist and mount greatly.
Description
Technical Field
The utility model relates to a building field, in particular to hoist device is used in building engineering construction.
Background
Hoisting refers to the general term of installation and taking place of equipment by a crane or a hoisting mechanism, when a high-rise building is constructed, a crane is needed to hoist construction materials, and round tubular materials are often needed to be hoisted, for example, steel pipes are hoisted, when the steel pipes are not well clamped and fixed, hoisting can be performed by tightening ropes, the outer walls of the steel pipes are smooth, and a plurality of steel pipes are bound together, so that the steel pipes can easily slide off the ropes, and safety accidents are easily caused.
Therefore, it is necessary to provide a hoisting device for construction engineering to solve the above problems.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a hoist device is used in building engineering construction to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a hoisting device for construction engineering construction comprises steel pipe clamps, wherein the steel pipe clamps are provided with a plurality of groups, the plurality of groups of steel pipe clamps are sequentially overlapped along the vertical direction, each steel pipe clamp comprises an upper clamping plate and a lower clamping plate which are vertically attached, a plurality of groups of arc-shaped clamping grooves are respectively formed in the equal separation sections of the lower surface of the upper clamping plate and the upper surface of the lower clamping plate, round steel pipes are respectively clamped between two groups of arc-shaped clamping grooves which are vertically symmetrical, screw rod through holes are vertically formed in the four corners of each steel pipe clamp, vertical metal screw rods are inserted in the screw rod through holes, hidden circular grooves are respectively formed in the four corners of the lower end of the lowermost steel pipe clamp, limiting circular blocks are welded at the lower ends of the vertical metal screw rods and are respectively positioned in the hidden circular grooves, the vertical metal screw rods are respectively locked and fixed at the upper ends of the uppermost steel pipe clamp through locking screw caps, sleeves are respectively fixedly connected at the, the telescopic upper end all welds there is the arc ring, controls and all is provided with a cable wire between two corresponding arc rings, the both ends of cable wire all are connected with the shackle, the shackle all detains on the arc ring that corresponds, the middle part of cable wire all has the ring knot, all alternates between two corresponding ring knots around and have the cross arm pipe, and the both ends of cross arm pipe all are provided with anti-disengaging mechanism, the middle part upper end welding of cross arm pipe has the lug plate, has seted up the lewis hole on the lug plate, the couple has the auto-lock lifting hook in the lewis hole.
Preferably, the opening depth of the hidden circular groove is larger than the thickness of the limiting circular block, and the diameter of the limiting circular block is larger than the aperture of the screw hole.
Preferably, the inner diameter of each sleeve is larger than the diameter of each vertical metal screw, the sleeves are sleeved at the upper ends of the vertical metal screws, and the sleeves and the vertical metal screws are fixedly connected through the transverse penetrating positioning pins.
Preferably, the anti-disengaging mechanism comprises an anti-disengaging circular plate, an inserting rod and a connecting pin shaft, the inserting rod is welded in the middle of one side of the anti-disengaging circular plate, the inserting rod is inserted into the end of the cross arm pipe, the cross arm pipe and the inserting rod are connected and fixed through the penetrating connecting pin shaft, the anti-disengaging circular plate is located on the outer side of the cross arm pipe, and the diameter of the anti-disengaging circular plate is larger than the outer diameter of the circular ring knot.
Preferably, the auto-lock lifting hook includes U shaped steel component and I shaped steel component, the opening part of U shaped steel component is towards one side, the notch has all been seted up to the upper end of U shaped steel component, the middle part of I shaped steel component all blocks in the notch and is articulated with U shaped steel component, the upper end of I shaped steel component all articulates and is connected with rings.
The utility model discloses a technological effect and advantage:
1. the steel pipe clamp is used for clamping and fixing the steel pipe to be hoisted, the steel pipe can not fall off stably in the hoisting process, and the safety accident in the hoisting process is avoided; the single group of steel pipe clamps can clamp a plurality of steel pipes, and the steel pipe clamps can be overlapped into a plurality of groups, so that a large number of steel pipes can be hoisted at one time, and the hoisting efficiency is greatly improved;
2. the steel cable is connected to the front side and the rear side of the upper end of the steel pipe clamp, the two steel cables are connected through the cross arm pipe in the middle, the lug plates on the cross arm pipe are used for hoisting, the whole hoisting is stable, so that the steel pipe clamp or the steel pipe is in a horizontal state in the hoisting process, and the hoisting stability is greatly improved;
3. the utility model relates to a hoist device, it is fixed convenient to the steel pipe centre gripping, it is also very convenient to dismantle steel pipe anchor clamps after the hoist and mount is accomplished, the taking out of steel pipe after the convenient hoist and mount, whole equipment, dismantlement are simple, and the hoist and mount time can be saved in the operation of being convenient for, improves hoist and mount efficiency.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is an enlarged view of a structure a in fig. 1.
Fig. 3 is an enlarged view of the structure at B in fig. 1.
Fig. 4 is a top view of the steel pipe clamp of the present invention.
Fig. 5 is an enlarged view of the structure at C in fig. 4.
Fig. 6 is a schematic view of the self-locking hook of the present invention.
In the figure: the steel pipe clamp comprises a steel pipe clamp 1, an upper clamping plate 101, a lower clamping plate 102, an arc-shaped clamping groove 103, a circular steel pipe 2, a hidden circular groove 104, a vertical metal screw rod 3, a limiting circular block 301, a lock nut 302, a steel cable 4, a sleeve 5, a positioning pin shaft 6, an arc-shaped ring 7, a shackle 8, a circular ring knot 9, a cross arm pipe 10, a lug plate 11, a lifting hole 12, a self-locking lifting hook 13, a U-shaped steel member 1301, an I-shaped steel member 1302, a lifting ring 1303, an anti-falling circular plate 14, an inserted link 15 and a connecting pin shaft 16.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The utility model provides a hoisting device for construction engineering construction as shown in figures 1 to 6, which comprises a plurality of groups of steel pipe clamps 1, wherein the steel pipe clamps 1 are sequentially stacked along the vertical direction, and the number of the steel pipe clamps 1 can be increased or decreased according to the number of steel pipes to be hoisted as required;
the steel pipe clamp 1 comprises an upper clamp plate 101 and a lower clamp plate 102 which are attached up and down, a plurality of groups of arc-shaped clamping grooves 103 are arranged on the lower surface of the upper clamp plate 101 and the upper surface of the lower clamp plate 102 at intervals, round steel pipes 2 are arranged between two groups of arc-shaped clamping grooves 103 which are symmetrical up and down, screw holes are vertically arranged at four corners of the steel pipe clamp 1 in a penetrating way, vertical metal screws 3 are inserted in the screw holes, hidden circular grooves 104 are arranged at four corners of the lower end of the lowermost steel pipe clamp 1, limiting circular blocks 301 are welded at the lower end of each vertical metal screw 3 and are arranged in the hidden circular grooves 104, the depth of each hidden circular groove 104 is larger than the thickness of each limiting circular block 301, the diameter of each limiting circular block 301 is larger than the aperture of each screw hole, the purpose of arranging the limiting circular blocks 301 is to lift the lowermost steel pipe clamp 1 and avoid the vertical metal screws 3 from being pulled out from the upper part, the limiting round block 301 can be hidden in the hiding round groove 104, so that the steel pipe clamp 1 at the bottom can be stably placed on the ground;
the vertical metal screw rods 3 are locked and fixed at the upper ends of the steel pipe clamps 1 positioned at the uppermost part through locking nuts 302, the upper ends of the vertical metal screw rods 3 are fixedly connected with sleeves 5, arc-shaped rings 7 are welded at the upper ends of the sleeves 5, the inner diameters of the sleeves 5 are larger than the diameters of the vertical metal screw rods 3, the sleeves 5 are sleeved at the upper ends of the vertical metal screw rods 3, and the sleeves 5 and the vertical metal screw rods 3 are fixedly connected through positioning pin shafts 6 which transversely penetrate through the sleeves 5;
a steel cable 4 is arranged between the two corresponding arc-shaped rings 7 on the left and the right, two ends of the steel cable 4 are connected with shackles 8, the shackles 8 are respectively buckled on the corresponding arc-shaped rings 7, the middle parts of the steel cable 4 are respectively tied with a circular ring knot 9, a cross arm pipe 10 is respectively inserted between the two circular ring knots 9 corresponding to the front and the back, and both ends of the cross arm pipe 10 are provided with anti-drop mechanisms, each anti-drop mechanism is composed of an anti-drop circular plate 14, an inserted link 15 and a connecting pin 16, the inserted links 15 are all welded at the middle part of one side of the anti-drop circular plate 14, the inserted links 15 are all inserted at the end part of the cross arm pipe 10, the cross arm pipe 10 and the inserted bar 15 are fixedly connected through a through connecting pin 16, the anti-dropping circular plate 14 is positioned at the outer side of the cross arm pipe 10, the diameter of the anti-falling circular plate 14 is larger than the outer diameter of the circular ring knot 9, and the anti-falling circular plate 14 is arranged for preventing the cross arm pipe 10 from falling off from the circular ring knot 9 and ensuring the hoisting safety;
the welding of the middle part upper end of cross arm pipe 10 has lug plate 11, the lewis hole 12 has been seted up on lug plate 11, the couple has self-locking lifting hook 13 in lewis hole 12, self-locking lifting hook 13 includes U shaped steel component 1301 and I shaped steel component 1302, the opening part of U shaped steel component 1301 is towards one side, the notch has all been seted up to the upper end of U shaped steel component 1301, the equal block in middle part of I shaped steel component 1302 is articulated in the notch and with U shaped steel component 1301, the equal articulated rings 1303 that is connected with in upper end of I shaped steel component 1302, during the hoist and mount, the lifting hook of loop wheel machine is on rings 1303 on self-locking lifting hook 13, self-locking lifting hook 13 can pin automatically under the lifting force of heavy object dead weight and hoist, after the hoist and mount, self-locking lifting hook 13 can open automatically under the.
The utility model discloses a theory of operation:
the steel pipe clamp is used for clamping and fixing the steel pipe to be hoisted, the steel pipe can not fall off stably in the hoisting process, and the safety accident in the hoisting process is avoided; the single group of steel pipe clamps can clamp a plurality of steel pipes, and the steel pipe clamps can be overlapped into a plurality of groups, so that a large number of steel pipes can be hoisted at one time, and the hoisting efficiency is greatly improved; the steel cable 4 is connected to the front side and the rear side of the upper end of the steel pipe clamp, the two steel cables 4 are connected through the cross arm pipe 10 at the middle part, the lug plate 11 on the cross arm pipe 10 is used for hoisting, the whole hoisting is stable, so that the steel pipe clamp or the steel pipe is in a horizontal state in the hoisting process, and the hoisting stability is greatly improved; the utility model relates to a hoist device, it is fixed convenient to the steel pipe centre gripping, it is also very convenient to dismantle steel pipe anchor clamps after the hoist and mount is accomplished, the taking out of steel pipe after the convenient hoist and mount, whole equipment, dismantlement are simple, and the hoist and mount time can be saved in the operation of being convenient for, improves hoist and mount efficiency.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.
Claims (5)
1. The utility model provides a hoist device for building engineering construction, includes steel pipe clamp (1), its characterized in that: steel pipe anchor clamps (1) are provided with the multiunit, and multiunit steel pipe anchor clamps (1) superpose in proper order along vertical direction, steel pipe anchor clamps (1) all include punch holder (101) and lower plate (102) of laminating from top to bottom, multiunit arc clamp groove (103) have been seted up to the lower surface of punch holder (101) and the upper surface of lower plate (102) all separate the section, all press from both sides between two sets of arc clamp grooves (103) of longitudinal symmetry and be equipped with circular steel tube (2), the equal vertical penetration of four corners department of steel pipe anchor clamps (1) has been seted up the screw rod and has been perforated, all alternate perpendicular metal screw rod (3) in the screw rod perforation, the lower extreme four corners department that is located below steel pipe anchor clamps (1) has all seted up hidden circular slot (104), the lower extreme of perpendicular metal screw rod (3) all welds spacing circle piece (301), and spacing circle piece (301) all are located hidden circular slot (104), perpendicular metal screw rod (3) all pass through lock nut (302) in the upper end that is located ) Locking is fixed, erect equal fixedly connected with sleeve pipe (5) in upper end of metal screw (3), arc ring (7) have all been welded to the upper end of sleeve pipe (5), all are provided with one cable wire (4) between two arc rings (7) of controlling the correspondence, the both ends of cable wire (4) all are connected with shackle (8), shackle (8) all are detained on corresponding arc ring (7), the middle part of cable wire (4) all has ring knot (9), all alternates between two ring knots (9) that correspond around have cross arm pipe (10), and the both ends of cross arm pipe (10) all are provided with anti-disengaging mechanism, the middle part upper end welding of cross arm pipe (10) has lug plate (11), has seted up lewis hole (12) on lug plate (11), the couple has auto-lock lifting hook (13) in lewis hole (12).
2. The hoisting device for the construction of the building engineering as claimed in claim 1, wherein: the hidden circular groove (104) is deeper than the limiting circular block (301), and the diameter of the limiting circular block (301) is larger than the aperture of the screw hole.
3. The hoisting device for the construction of the building engineering as claimed in claim 1, wherein: the inner diameter of the sleeve (5) is larger than the diameter of the vertical metal screw (3), the sleeve (5) is sleeved on the upper end of the vertical metal screw (3), and the sleeve (5) and the vertical metal screw (3) are fixedly connected through a positioning pin shaft (6) which transversely penetrates through the sleeve.
4. The hoisting device for the construction of the building engineering as claimed in claim 1, wherein: the anti-falling mechanism is composed of an anti-falling circular plate (14), an inserting rod (15) and a connecting pin shaft (16), the inserting rod (15) is welded in the middle of one side of the anti-falling circular plate (14), the inserting rod (15) is inserted into the end of the cross arm pipe (10), the cross arm pipe (10) and the inserting rod (15) are fixedly connected through the connecting pin shaft (16) which penetrates through the inserting rod, the anti-falling circular plate (14) is located on the outer side of the cross arm pipe (10), and the diameter of the anti-falling circular plate (14) is larger than the outer diameter of the circular ring knot (9).
5. The hoisting device for the construction of the building engineering as claimed in claim 1, wherein: the self-locking lifting hook (13) comprises a U-shaped steel member (1301) and an I-shaped steel member (1302), the opening of the U-shaped steel member (1301) faces one side, notches are formed in the upper end of the U-shaped steel member (1301), the middle of the I-shaped steel member (1302) is clamped in the notches and hinged to the U-shaped steel member (1301), and the upper end of the I-shaped steel member (1302) is hinged to a lifting ring (1303).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021699192.7U CN212687348U (en) | 2020-08-15 | 2020-08-15 | Hoist device is used in building engineering construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021699192.7U CN212687348U (en) | 2020-08-15 | 2020-08-15 | Hoist device is used in building engineering construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212687348U true CN212687348U (en) | 2021-03-12 |
Family
ID=74902194
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021699192.7U Expired - Fee Related CN212687348U (en) | 2020-08-15 | 2020-08-15 | Hoist device is used in building engineering construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212687348U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114182950A (en) * | 2021-12-16 | 2022-03-15 | 中铁建工集团有限公司 | Hanging basket attaching and fixing mechanism for high-altitude operation |
CN117342398A (en) * | 2023-09-25 | 2024-01-05 | 张家港嘉园钢铁制品有限公司 | Hoisting jig for steel pipe pickling processing |
-
2020
- 2020-08-15 CN CN202021699192.7U patent/CN212687348U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114182950A (en) * | 2021-12-16 | 2022-03-15 | 中铁建工集团有限公司 | Hanging basket attaching and fixing mechanism for high-altitude operation |
CN117342398A (en) * | 2023-09-25 | 2024-01-05 | 张家港嘉园钢铁制品有限公司 | Hoisting jig for steel pipe pickling processing |
CN117342398B (en) * | 2023-09-25 | 2024-10-01 | 张家港嘉园钢铁制品有限公司 | Hoisting jig for steel pipe pickling processing |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212687348U (en) | Hoist device is used in building engineering construction | |
CN210193173U (en) | Large-scale H shaped steel stand hoist and mount hoist that breaks off relations fast | |
CN109879155B (en) | Device for rapidly hoisting laminated slab | |
CN112707302A (en) | Frame type hoisting balance beam | |
JP2007022789A (en) | Suspension tool and vertical pipe construction method | |
CN218619838U (en) | Steel pipe truss hoist and mount auxiliary device | |
US20020162283A1 (en) | Jacking & tipping restraint apparatus and design of communications towers to enable entire tower erection at ground level | |
CN212334354U (en) | Lifting device for welded steel bar mesh | |
CN215433503U (en) | Large stud mounting device | |
CN215287652U (en) | Lifting appliance | |
CN213475147U (en) | Major diameter pile foundation steel reinforcement cage gallows device | |
CN212799331U (en) | Movable lifting appliance using I-shaped steel as lifting point | |
CN112193984B (en) | Steel reinforcement cage lifting and fixing device and steel reinforcement cage lifting method | |
CN110937496B (en) | Lifting lug for hoisting segmented equipment and hoisting method thereof | |
CN211594756U (en) | Lifting tool for steel pipe | |
CN218715456U (en) | Safe cat ladder of being under construction | |
CN217417880U (en) | Vertical hoisting device of reinforcing bar | |
CN217126641U (en) | Special lifting appliance for hoisting secondary beam of glass kiln | |
CN109987501A (en) | A kind of device threaded off in Quick air in steel structure hoisting and tripping method | |
CN221052395U (en) | Anti-falling device for bridge construction | |
CN219449103U (en) | Secondary beam lifting device | |
CN209758824U (en) | Device for quickly hoisting laminated slab | |
CN220998884U (en) | Assembled superimposed sheet adjustable angle hoist device | |
CN220148971U (en) | Steel bar hoisting device | |
CN219078840U (en) | Hoisting tool for turning over and supporting sling of steel pipe pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210312 |