CN212614779U - Utility tunnel construction trolley - Google Patents

Utility tunnel construction trolley Download PDF

Info

Publication number
CN212614779U
CN212614779U CN202020609029.0U CN202020609029U CN212614779U CN 212614779 U CN212614779 U CN 212614779U CN 202020609029 U CN202020609029 U CN 202020609029U CN 212614779 U CN212614779 U CN 212614779U
Authority
CN
China
Prior art keywords
mounting
fixed
connecting rod
plate
roof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020609029.0U
Other languages
Chinese (zh)
Inventor
刘学
王能勇
王绍康
韩伟涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
Third Engineering Co Ltd of Highway Engineering Bureau of CCCC
Original Assignee
CCCC First Highway Engineering Co Ltd
Third Engineering Co Ltd of Highway Engineering Bureau of CCCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, Third Engineering Co Ltd of Highway Engineering Bureau of CCCC filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN202020609029.0U priority Critical patent/CN212614779U/en
Application granted granted Critical
Publication of CN212614779U publication Critical patent/CN212614779U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a utility tunnel construction trolley, which comprises a roof, backup pad and base, the left and right sides of roof lower extreme all is provided with the backup pad, the downside of backup pad all is fixed with the base, the inboard base upper end of backup pad all is provided with the mounting panel, the upper end of mounting panel all is fixed with the connecting plate, the side all is fixed with the connecting rod around the connecting plate upper end middle part, the position department of the corresponding connecting rod of lower extreme of roof all is fixed with an installation section of thick bamboo, the connecting rod upper end sets up in a corresponding installation section of thick bamboo, the mounting groove has all been seted up at the upper end middle part of backup pad, the position department of the corresponding mounting groove of roof lower extreme all is fixed with the installation piece, the side all is fixed with the piece of placing. The utility model discloses a set up installation section of thick bamboo, connecting rod, installation piece and mounting groove, solved the problem that does not possess the function of installation in the utility tunnel construction trolley.

Description

Utility tunnel construction trolley
Technical Field
The utility model relates to a utility tunnel construction technical field specifically is a utility tunnel construction platform truck.
Background
The utility tunnel is the underground city pipeline utility tunnel. The tunnel space is built in the city underground, various engineering pipelines such as electric power, communication, gas, heat supply, water supply and drainage and the like are integrated, a special overhaul port, a lifting port and a monitoring system are arranged, unified planning, unified design, unified construction and management are implemented, the tunnel space is an important infrastructure and a 'life line' for guaranteeing city operation, and at present, the existing comprehensive pipe gallery construction trolley does not have the defects of installation function and the like, so that the prior art needs to be improved to solve the problems.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
An object of the utility model is to provide a utility tunnel construction trolley to solve the problem that proposes among the above-mentioned background art.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a utility tunnel construction trolley, includes roof, backup pad and base, the left and right sides of roof lower extreme all is provided with the backup pad, the downside of backup pad all is fixed with the base, the inboard base upper end of backup pad all is provided with the mounting panel, the upper end of mounting panel all is fixed with the connecting plate, the side all is fixed with the connecting rod around the connecting plate upper end middle part, the position department of the corresponding connecting rod of lower extreme of roof all is fixed with an installation section of thick bamboo, the upper end setting of connecting rod is in a corresponding installation section of thick bamboo, the mounting groove has all been seted up at the upper end middle part of backup pad, the position department of the corresponding mounting groove of lower extreme of roof.
Preferably, the pulley blocks are fixed at the front end and the rear end of one side of the mounting plate corresponding to the support plate, the movable grooves are formed in one ends of the support plate corresponding to the pulley blocks, and the pulley blocks are arranged in the corresponding movable grooves.
Preferably, the front side and the rear side of the left end and the right end of the connecting plate are respectively fixed with a placing block, the corresponding placing blocks of the supporting plate are respectively provided with a placing groove, and the placing blocks are respectively arranged in the corresponding placing grooves.
Preferably, the upper ends of the connecting plates on the left and right sides of the connecting rod are respectively fixed with a mounting frame, the upper ends of the mounting frames are respectively fixed with an air cylinder, and one end of each air cylinder corresponding to the mounting cylinder is respectively fixed with a mounting rod.
Preferably, the left end and the right end of the mounting cylinder are provided with second mounting holes corresponding to the positions of the mounting rods, and the left end and the right end of the connecting rod are provided with first mounting holes corresponding to the positions of the second mounting holes.
(III) advantageous effects
The utility model provides a utility tunnel construction platform truck possesses following beneficial effect:
(1) the utility model arranges the mounting cylinder, the connecting rod, the mounting block and the mounting groove, places the connecting plate at the position between the supporting plate and the supporting plate, places the placing block in the placing groove, thereby leading the pulley block to be placed in the moving groove, then lifts the top plate by an external crane, moves the top plate above the supporting plate, places the mounting block at the lower end of the top plate in the mounting groove at the upper end of the supporting plate, further leads the top plate to stabilize the position of the supporting plate, tightly presses the placing block in the placing groove by the top plate, thereby leading the connecting plate to be mounted and fixed at the position between the supporting plate and the supporting plate, simultaneously leading the connecting rod to move into the mounting cylinder, further leading the second mounting hole of the mounting cylinder to be consistent with the position of the first mounting hole on the connecting rod, then controls the cylinder to work by an external controller, further leading the cylinder to push the mounting rod to move into the mounting, thereby make the roof installation fix in connecting plate and backup pad, solved the problem that does not possess the function of installation in the utility tunnel construction platform truck, possessed simple structure simultaneously, the benefit of the operation of being convenient for.
Drawings
FIG. 1 is a block diagram of the present invention;
FIG. 2 is a block diagram of the mounting plate of FIG. 1 according to the present invention;
FIG. 3 is a schematic view of the connection plate of FIG. 1 according to the present invention;
FIG. 4 is a schematic view of the top plate of FIG. 1 according to the present invention;
FIG. 5 is a schematic view of the support plate of FIG. 1 according to the present invention;
fig. 6 is a structural view of the mounting barrel of fig. 1 according to the present invention.
The reference numbers in the figures are: 1. a top plate; 2. mounting a rod; 3. mounting the cylinder; 4. a cylinder; 5. a mounting frame; 6. a support plate; 7. mounting a plate; 8. a base; 9. a connecting plate; 10. a pulley block; 11. placing the blocks; 12. a connecting rod; 13. a first mounting hole; 14. mounting blocks; 15. mounting grooves; 16. a placement groove; 17. a moving groove; 18. and a second mounting hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-6, the present invention provides a technical solution: a utility tunnel construction trolley comprises a top plate 1, a support plate 6 and a base 8, wherein the left side and the right side of the lower end of the top plate 1 are respectively provided with the support plate 6, the lower side of the support plate 6 is respectively provided with the base 8, the upper end of the base 8 at the inner side of the support plate 6 is respectively provided with the mounting plate 7, the upper end of the mounting plate 7 is respectively provided with the connecting plate 9, the support plate 6 is connected with the support plate 6 through the connecting plate 9, the front side and the rear side of the middle part of the upper end of the connecting plate 9 are respectively provided with a connecting rod 12, the position of the lower end of the top plate 1 corresponding to the connecting rod 12 is respectively provided with a mounting barrel 3, the upper end of the connecting rod 12 is arranged in the corresponding mounting barrel 3, the middle part of the upper end of the support plate 6 is respectively provided with a mounting groove 15, thereby connecting the top plate 1 and the support plate 6 together.
The pulley block 10 is fixed at the front end and the rear end of one side of the mounting plate 7 corresponding to the support plate 6, the movable groove 17 is formed in one end of the support plate 6 corresponding to the pulley block 10, and when the pulley block 10 is placed in the movable groove 17, the device is disassembled again, so that the mounting plate 7 drives the pulley block 10 to move in the movable groove 17, and the pulley block 10 is arranged in the corresponding movable groove 17.
The front and back side of the left and right ends of connecting plate 9 all is fixed with places piece 11, and backup pad 6 has all been seted up standing groove 16 corresponding place piece 11's position department, will place piece 11 and place in standing groove 16, and then makes connecting plate 9 installation fix the position between backup pad 6 and backup pad 6, places piece 11 and all sets up in corresponding standing groove 16.
Mounting bracket 5 all is fixed with on the connecting plate 9 upper end of connecting rod 12 left and right sides, and the upper end of mounting bracket 5 all is fixed with cylinder 4, and through the work of cylinder 4, cylinder 4 can promote installation pole 2 and remove first mounting hole 13 and second mounting hole 18 to make connecting rod 12 erection fixation in installation section of thick bamboo 3, thereby make roof 1 and connecting plate 9 install together, the one end of the corresponding installation section of thick bamboo 3 of cylinder 4 all is fixed with installation pole 2.
The position department that the end corresponds installation pole 2 about installation section of thick bamboo 3 has all seted up second mounting hole 18, places connecting rod 12 in installation section of thick bamboo 3, and then makes the position of first mounting hole 13 unanimous with the position of second mounting hole 18, and the end corresponds the position department of second mounting hole 18 about connecting rod 12 and has all seted up first mounting hole 13.
The working principle is as follows: when the utility model is used, the device is connected with an external power supply, the connecting plate 9 is placed between the supporting plate 6 and the supporting plate 6, the placing block 11 is placed in the placing groove 16, so that the pulley block 10 is placed in the moving groove 17, the top plate 1 is lifted by the external crane, the top plate 1 is moved above the supporting plate 6, the mounting block 14 at the lower end of the top plate 1 is placed in the mounting groove 15 at the upper end of the supporting plate 6, so that the top plate 1 stabilizes the position of the supporting plate 6, the placing block 11 is tightly pressed in the placing groove 16 by the top plate 1, so that the connecting plate 9 is fixedly mounted at the position between the supporting plate 6 and the supporting plate 6, the connecting rod 12 is moved into the mounting cylinder 3, the second mounting hole 18 of the mounting cylinder 3 is consistent with the position of the first mounting hole 13 on the connecting rod 12, and the cylinder 4 is controlled to work by the external controller, and then make cylinder 4 promote installation pole 2 and remove in installation section of thick bamboo 3 and connecting rod 12, thereby make roof 1 erection fixation on connecting plate 9 and backup pad 6, when needs dismantle the device, control cylinder 4 stop work, and then make cylinder 4 take installation pole 2 out from first mounting hole 13 and second mounting hole 18, the rethread loop wheel machine lifts roof 1, and then make roof 1 and backup pad 6 separation, remove backup pad 6 to the opposite direction of mounting panel 7 again, thereby make backup pad 6 and mounting panel 7 separation, thereby reach quick dismounting device's effect.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a utility tunnel construction platform truck, includes roof (1), backup pad (6) and base (8), its characterized in that: the utility model discloses a roof, including roof (1), roof (6), connecting plate (3), mounting block (14), mounting plate (7), connecting plate (9), connecting rod (12) are all fixed with to the downside of roof (6) lower extreme all, the inboard base (8) upper end of backup pad (6) all is provided with mounting panel (7), the upper end of mounting panel (7) all is fixed with connecting plate (9), the front and back side at connecting plate (9) upper end middle part all is fixed with connecting rod (12), the position department of the corresponding connecting rod (12) of roof (1) lower extreme all is fixed with installation section of thick bamboo (3), the upper end setting of connecting rod (12) is in corresponding installation section of thick bamboo (3), mounting groove (15) have all been seted up at the upper end middle part of backup pad (6), the.
2. The utility tunnel construction trolley of claim 1, characterized in that: the pulley block (10) is fixed at the front end and the rear end of one side of the mounting plate (7) corresponding to the support plate (6), a moving groove (17) is formed in one end of the support plate (6) corresponding to the pulley block (10), and the pulley block (10) is arranged in the corresponding moving groove (17).
3. The utility tunnel construction trolley of claim 1, characterized in that: the front side and the rear side of the left end and the right end of the connecting plate (9) are respectively provided with a placing block (11), the corresponding placing block (11) of the supporting plate (6) is provided with a placing groove (16), and the placing blocks (11) are arranged in the corresponding placing grooves (16).
4. The utility tunnel construction trolley of claim 1, characterized in that: the mounting bracket (5) is fixed to the upper end of the connecting plate (9) on the left side and the right side of the connecting rod (12), the air cylinder (4) is fixed to the upper end of the mounting bracket (5), and the mounting rod (2) is fixed to one end of the corresponding mounting cylinder (3) of the air cylinder (4).
5. The utility tunnel construction trolley of claim 4, characterized in that: the left end and the right end of the mounting cylinder (3) correspond to the positions of the mounting rods (2) and are respectively provided with a second mounting hole (18), and the left end and the right end of the connecting rod (12) correspond to the positions of the second mounting holes (18) and are respectively provided with a first mounting hole (13).
CN202020609029.0U 2020-04-21 2020-04-21 Utility tunnel construction trolley Expired - Fee Related CN212614779U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020609029.0U CN212614779U (en) 2020-04-21 2020-04-21 Utility tunnel construction trolley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020609029.0U CN212614779U (en) 2020-04-21 2020-04-21 Utility tunnel construction trolley

Publications (1)

Publication Number Publication Date
CN212614779U true CN212614779U (en) 2021-02-26

Family

ID=74703909

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020609029.0U Expired - Fee Related CN212614779U (en) 2020-04-21 2020-04-21 Utility tunnel construction trolley

Country Status (1)

Country Link
CN (1) CN212614779U (en)

Similar Documents

Publication Publication Date Title
CN212614779U (en) Utility tunnel construction trolley
CN205235774U (en) Hollow fiber curtain formula membrane module detection device
CN203248171U (en) Full fracture surface needle beam trolley without beam frame
CN210623800U (en) Pipe gallery supporting and hanging frame
CN211155059U (en) Connection structure of curtain rail
CN208430648U (en) Passive type builds parapet heat-preserving cover plate
CN115900065A (en) Air energy heat pump outdoor unit
CN203127966U (en) Elevator suspended ceiling assembly
CN214195110U (en) Connecting structure capable of moving building curtain wall
CN206146069U (en) Drier -filter carrier structure
CN201245965Y (en) Hanging scaffold
CN101597956A (en) Suspended scaffold
CN216071799U (en) Small indoor remote control gate replacing trolley
CN218950802U (en) Building equipment cable hoist device
CN213265392U (en) Novel inverted arch piece hoisting accessory
CN213976700U (en) Experimental wall body hoist device
CN214631306U (en) Spinning cake storage rack convenient to install
CN212583138U (en) Intelligent light-operated glass
CN212055291U (en) Integration promotes pump station remote control device
CN211169685U (en) Indoor hanger frock that construction used
CN219297060U (en) Lifting equipment for roller
CN211895678U (en) Electromechanical device installation device
CN210887298U (en) Underground comprehensive pipe gallery die carrier
CN210825084U (en) Hoisting device for box-type substation
CN213115453U (en) Connection structure of integrated form lift protection platform bottom operation layer and stand bar

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210226

CF01 Termination of patent right due to non-payment of annual fee