CN212613190U - Aggregate sun-proof greenhouse assembled construction partition wall - Google Patents
Aggregate sun-proof greenhouse assembled construction partition wall Download PDFInfo
- Publication number
- CN212613190U CN212613190U CN202020743076.4U CN202020743076U CN212613190U CN 212613190 U CN212613190 U CN 212613190U CN 202020743076 U CN202020743076 U CN 202020743076U CN 212613190 U CN212613190 U CN 212613190U
- Authority
- CN
- China
- Prior art keywords
- aggregate
- partition wall
- prefabricated
- greenhouse
- sun
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Greenhouses (AREA)
Abstract
The utility model relates to a civil engineering technical field, concretely relates to aggregate sun-proof big-arch shelter assembled construction partition wall, it is including base member, a plurality of stand and a plurality of prefabricated dog, a plurality of the stand equidistant side by side fixed setting is in on the base member, the straight flute has been seted up on two relative side of stand, and is adjacent be provided with between the straight flute of stand prefabricated dog, be provided with on the prefabricated dog and lift by crane the groove and lift by crane the hook, it sets up to lift by crane the groove on the up end of prefabricated dog, it is fixed to set up to lift by crane the hook in the groove. The utility model provides a sun-proof big-arch shelter assembled construction partition wall of aggregate just can be under construction after the sun-proof big-arch shelter base place of aggregate is confirmed for partition wall construction progress has improved partition wall concrete efficiency of construction.
Description
Technical Field
The utility model relates to a civil engineering technical field, concretely relates to sun-proof big-arch shelter assembled construction partition wall of aggregate.
Background
With the development of modern industrial technology, buildings can be manufactured in batches as machines are produced. The prefabricated building components are transported to the construction site and assembled. The fabricated building is interesting in the beginning of the 20 th century and is realized in the end of the sixties, and the fabricated building is rapidly constructed and low in production cost and is rapidly popularized and developed all over the world.
In the concrete construction of a hydropower station gravel aggregate greenhouse, according to the structural characteristics, partition walls are required to be arranged inside the aggregate greenhouse to separate gravel aggregates with different particle sizes, the existing traditional construction is generally that after a greenhouse foundation is built, the construction of the concrete partition walls is carried out, reinforcement construction is firstly carried out through reinforcement and formwork erection, a construction scaffold platform is then erected, finally, the construction of a concrete wall is carried out through means of hoisting and pouring by a crane, each circulating construction procedure is many in link, the construction speed is slow, the construction platform is erected with time and labor consumption, and a certain time is occupied in the construction arrangement of the aggregate greenhouse partition walls.
Disclosure of Invention
In view of this, the utility model provides a sun-proof big-arch shelter assembled construction partition wall of aggregate just can be under construction after the sun-proof big-arch shelter base place of aggregate is confirmed for partition wall construction progress has improved partition wall concrete efficiency of construction.
In order to achieve the purpose, the utility model is realized by the following technical scheme:
the utility model provides a sun-proof big-arch shelter assembled construction partition wall of aggregate, including base member, a plurality of stand and a plurality of prefabricated dog, it is a plurality of the equidistant fixed setting side by side of stand is in on the base member, the straight flute has been seted up on two relative sides of stand, and is adjacent be provided with between the straight flute of stand prefabricated dog, be provided with on the prefabricated dog and lift by crane the groove and lift by crane the lifting hook, it sets up to lift by crane the groove on the up end of prefabricated dog, it is in to lift by crane the fixed setting of lifting hook in the groove.
In the assembled construction partition wall of the aggregate sun-proof greenhouse, as an optimal scheme, a plurality of stacked prefabricated stop blocks are arranged between adjacent upright columns, and the prefabricated stop blocks are poured and molded.
In the assembly type construction partition wall of the aggregate sunscreen greenhouse, as a preferred scheme, the prefabricated stop block is cuboid, angle steel is arranged at the top point of the prefabricated stop block, the angle steel is poured in the prefabricated stop block, and the outer surface of the angle steel is flush with the side face of the prefabricated stop block.
In the aggregate sunscreen greenhouse fabricated construction partition wall, as a preferred scheme, the inner surface of the angle steel is fixedly welded with a clip hook.
In the assembly type construction partition wall of the aggregate sunscreen greenhouse, as a preferred scheme, the lifting hook is in an inverted U shape, the top end of the lifting hook does not exceed the upper end face of the prefabricated stop block, and the bottom end of the lifting hook is poured into the prefabricated stop block.
In the assembled construction partition wall of the aggregate sun-proof greenhouse, as a preferred scheme, the bottom of the lifting hook is provided with a transversely-arranged extension part which is in a long strip shape and is integrally arranged with the lifting hook.
In foretell sun-proof big-arch shelter assembled construction partition wall of aggregate, as preferred scheme, the inside steel reinforcement cage that is equipped with of prefabricated dog, the steel reinforcement cage includes a plurality of vertically-arranged first reinforcing bars and a plurality of horizontal second reinforcing bars that set up, first reinforcing bar with the cage form is spliced into each other to the second reinforcing bar, first reinforcing bar with the connected mode between the second reinforcing bar is welding or ligature.
In the assembled construction partition wall of the aggregate sunscreen greenhouse, as a preferred scheme, the extension part of the lifting hook is positioned below at least one second steel bar and is connected with the second steel bar through welding or binding.
In the assembled construction partition wall of the aggregate sunscreen greenhouse, as a preferred scheme, the upright is an i-shaped steel, the lower end of the upright is poured in the base body, and the opening direction of the straight groove of the upright points to the adjacent upright.
In the assembly type construction partition wall of the aggregate sunscreen greenhouse, as a preferred scheme, the lower portion of each upright is fixedly connected with a connecting plate and an inclined strut, the connecting plates are perpendicular to the uprights, the lower ends of the uprights are located below the connecting plates, the inclined struts are arranged in an inclined mode, one ends of the inclined struts are fixedly connected to the side faces of the uprights, the other ends of the inclined struts are fixedly connected to the surfaces of the connecting plates, and the connecting plates and the inclined struts are poured in the base body.
The utility model provides a sun-proof big-arch shelter assembled construction partition wall of aggregate has following beneficial effect:
the utility model provides a sun-proof big-arch shelter assembled construction partition wall of aggregate just can be under construction after the sun-proof big-arch shelter base place of aggregate is confirmed, at first fixes the I-steel on the base place through pouring, places prefabricated dog through the crane in the groove between two adjacent I-steels, and the angle steel and the I-steel welding of prefabricated dog have strengthened the steadiness of partition wall for the partition wall construction progress has improved partition wall concrete efficiency of construction.
Drawings
Fig. 1 is a schematic view of an overall structure of an aggregate sunscreen greenhouse fabricated construction partition wall provided in an embodiment of the present invention;
fig. 2 is a schematic view of an overall structure of a prefabricated stop block of an aggregate sun-proof greenhouse fabricated construction partition wall provided by the embodiment of the present invention;
fig. 3 is a schematic view of a front view and a half-section structure of a prefabricated stop block of an assembled construction partition wall of an aggregate sun-proof greenhouse provided by the embodiment of the utility model;
fig. 4 is a schematic top view of a cross-sectional structure of a prefabricated stop block of an assembled construction partition wall of an aggregate sunscreen greenhouse provided in the embodiment of the present invention;
fig. 5 is a schematic view of a sectional structure of an upright post of an assembled construction partition wall of an aggregate sunscreen greenhouse provided in an embodiment of the present invention.
Description of reference numerals:
1-base body, 2-prefabricated stop block, 201-angle steel, 202-lifting groove, 203-lifting hook, 204-first steel bar, 205-second steel bar, 206-clip hook, 3-upright post, 4-connecting plate and 5-inclined strut.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Exemplary embodiments of the present invention are described below in conjunction with specific situations:
referring to fig. 1 and fig. 2, fig. 1 is a schematic diagram of an overall structure of an assembled construction partition wall of an aggregate sunscreen greenhouse provided in an embodiment of the present invention, and fig. 2 is a schematic diagram of an overall structure of a prefabricated stop 2 of the assembled construction partition wall of the aggregate sunscreen greenhouse provided in an embodiment of the present invention; the utility model provides a sun-proof big-arch shelter assembled construction partition wall of aggregate, including base member 1, a plurality of stands 3 and a plurality of prefabricated dog 2, a plurality of stands 3 equidistant parallel fixation sets up on base member 1, has seted up the straight flute on two opposite flanks of stand 3, is provided with prefabricated dog 2 between the straight flute of adjacent stand 3, is provided with on the prefabricated dog 2 and lifts by crane groove 202 and lifting hook 203, lifts by crane groove 202 and sets up on prefabricated dog 2's up end, and lifting hook 203 is fixed to be set up in lifting by crane groove 202. The two lifting grooves 202 are symmetrically distributed on two sides of the upper end face along the central line of the prefabricated stop block 2, a lifting hook 203 is fixedly arranged in each lifting groove 202, the two lifting hooks 203 are also symmetrical relative to the central line of the prefabricated stop block 2, when a crane is used for lifting the prefabricated stop block 2 through the two lifting hooks 203, the balance of the prefabricated stop block 2 can be ensured, and the prefabricated stop block is not only inclined to cause the straight groove which is not easy to be placed into the upright post 3.
The utility model discloses an among the concrete implementation mode, as preferred embodiment, base member 1 sets up on aggregate sun-proof big-arch shelter foundation, and aggregate sun-proof big-arch shelter foundation adopts concrete ground or cement ground, and base member 1 can select as foundation ground an organic whole, and the lower extreme of stand 3 directly immerses in the foundation ground promptly, regards as base member 1 with the foundation ground, also can pour a concrete piece that is higher than the foundation ground plane on the plane in foundation ground as base member 1.
In foretell sun-proof big-arch shelter assembled construction partition of aggregate, as preferred scheme, be provided with a plurality of prefabricated dog 2 that pile up between adjacent stand 3, prefabricated dog 2 pours the shaping. According to the height requirement of the partition wall, a plurality of prefabricated blocks 2 are stacked between two adjacent upright posts 3.
In the specific embodiment of the utility model, as an optimal solution, prefabricated dog 2's length is 2m, highly is 1m, and the stand 3 surpasss the height of base member 1 and is 2.5m, consequently, places two prefabricated dogs 2 between per two adjacent stands 3, and effectual partition wall height is 2 m.
In other embodiments, different numbers of prefabricated blocks 2 can be arranged between different adjacent upright columns 3, for example, the number of the prefabricated blocks 2 is adjusted to make the whole aggregate sunscreen greenhouse prefabricated construction partition wall present a step shape.
More specifically, the distance between the centers of the two lifting grooves 202 of one precast block 2 is 1m, the width of the lifting groove 202 is 20mm, and the distances between the two lifting grooves 202 and the side surface of the precast block 2 are both 40 mm.
In the above aggregate sun-proof greenhouse fabricated construction partition wall, as a preferred scheme, the prefabricated stop block 2 is rectangular, an angle steel 201 is arranged at the vertex of the prefabricated stop block 2, the angle steel 201 is poured in the prefabricated stop block 2, and the outer surface of the angle steel 201 is flush with the side surface of the prefabricated stop block 2. And angle steel 201 is respectively arranged at eight vertexes or four vertexes above the prefabricated stopper 2, and the angle steel 201 is arranged along the height direction of the prefabricated stopper 2. Specifically, the width dimension of the angle steel 201 is 50 × 50mm, the thickness dimension is 5-10mm, and the length dimension is 100 mm.
Referring to fig. 4, fig. 4 is a schematic top sectional view of a prefabricated stop block 2 of an assembled construction partition wall of an aggregate sunscreen greenhouse according to an embodiment of the present invention; in the aggregate sunscreen greenhouse fabricated construction partition wall, as a preferable scheme, a clip hook 206 is fixedly welded to the inner surface of the angle steel 201. One end of the clip hook 206 is a straight edge, the other end is a circular hook, the straight edge of the clip hook 206 is welded on the inner surface of the angle steel 201, the included angle between the straight edge and the two side surfaces of the angle steel 201 is an acute angle, and the circular hook of the clip hook 206 faces the inside of the prefabricated block. When the precast block is poured, the connection tightness and stability between the angle steel 201 and the precast block can be enhanced by the existence of the clip hook 206.
When the prefabricated stop blocks 2 are installed, the angle steel 201 of the prefabricated stop blocks 2 is welded in the straight groove of the upright post 3 when one layer of the prefabricated stop blocks 2 is installed.
Referring to fig. 3, fig. 3 is a schematic front view and a half-sectional structure view of a prefabricated stop block 2 of an assembled construction partition wall of an aggregate sunscreen greenhouse according to an embodiment of the present invention; in the above aggregate sunscreen greenhouse fabricated construction partition wall, as a preferred scheme, the lifting hook 203 is in an inverted U shape, the top end of the lifting hook 203 does not exceed the upper end surface of the prefabricated stop block 2, and the bottom end of the lifting hook 203 is poured into the prefabricated stop block 2.
In the above aggregate sunscreen greenhouse fabricated construction partition wall, as a preferable scheme, the bottom of the lifting hook 203 is provided with a horizontally arranged extension part, and the extension part is long and is integrally arranged with the lifting hook 203.
In the above-mentioned assembled construction partition wall of aggregate sun-proof greenhouse, as preferred scheme, prefabricated dog 2 is inside to be equipped with the steel reinforcement cage, and the steel reinforcement cage includes a plurality of vertically arranged first reinforcing bars 204 and a plurality of horizontal second reinforcing bars 205 that set up, and first reinforcing bar 204 splices into the cage form with second reinforcing bar 205 each other, and the connected mode between first reinforcing bar 204 and the second reinforcing bar 205 is welding or ligature.
The utility model discloses an among the concrete implementation mode, as an optimal solution, first reinforcing bar 204 and second reinforcing bar 205 all adopt the 5mm reinforcing bar, first reinforcing bar 204 is along prefabricated block body length direction equidistant vertical setting, second reinforcing bar 205 is respectively along the direction of height and the equidistant parallel arrangement of length direction of prefabricated block body, first reinforcing bar 204 and second reinforcing bar 205 are two-layer around all having, connect through the second reinforcing bar 205 along length direction setting between the front and back layer, at all junctions of first reinforcing bar 204 and second reinforcing bar 205, all weld or ligature.
In the above-mentioned aggregate sunscreen greenhouse fabricated construction partition wall, preferably, the extension part of the lifting hook 203 is located below the at least one second steel bar 205, and is connected with the second steel bar 205 by welding or binding.
In the specific embodiment of the utility model, as an optimal solution, lifting hook 203 can adopt the reinforcing bar to buckle and form, and the diameter scope of reinforcing bar is 5-10mm, and lifting hook 203's whole shape is omega shape, and first U type for invering, the lower half be for being long banding extension promptly, and lifting hook 203 of shape like this pours in prefabricated block, strengthens the degree of stability of being connected between lifting hook 203 and the prefabricated block.
In the above embodiment, the extending portions of the two ends of the lifting hook 203 are respectively disposed below at least one second steel bar 205 distributed along the length direction of the prefabricated block, and the contact portions are welded or bound to fix the lifting hook 203 on the steel bar cage. The lifting hook 203 is installed when the reinforcement cage is manufactured, and then the prefabricated block is poured.
In the assembled construction partition wall of the aggregate sunscreen greenhouse, as a preferred scheme, the upright columns 3 are i-shaped steel, the lower ends of the upright columns 3 are poured in the base body 1, and the opening directions of the straight grooves of the upright columns 3 point to the adjacent upright columns 3.
Referring to fig. 5, fig. 5 is a schematic front view cross-sectional structure view of an upright post 3 of an assembled construction partition wall of an aggregate sunscreen greenhouse according to an embodiment of the present invention; in the above-mentioned sun-proof big-arch shelter assembled construction partition of aggregate, as preferred scheme, the lower part fixedly connected with connecting plate 4 and bracing 5 of stand 3, connecting plate 4 perpendicular to stand 3, the lower extreme of stand 3 is in the below of connecting plate 4, bracing 5 have two and all slope the setting, the one end fixed connection of bracing 5 is on the side of stand 3, other end fixed connection is on the surface of connecting plate 4, connecting plate 4 and bracing 5 are all pour in base member 1.
The utility model discloses an among the concrete implementation mode, as an optimal scheme, set up the I-shaped groove unanimous with I-steel cross sectional shape in advance on connecting plate 4, cup joint connecting plate 4 on the I-steel through the I-shaped groove, weld connecting plate 4 on the I-steel after fixing in advance, treat stable back, weld the both ends of bracing 5 respectively on the side that the I-steel does not have the groove and connecting plate 4 upper surface, the inclination of bracing 5 is 40-50. After welding, the I-steel is poured into the matrix 1 together with the connecting plate 4.
Finally, it should also be noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
The detailed description of the embodiments provided by the present invention is provided above, and the principles and embodiments of the present invention are explained herein by using specific examples, and the descriptions of the above examples are only used to help understand the method and the core ideas of the present invention; meanwhile, for the general technical personnel in the field, according to the idea of the present invention, there are changes in the specific implementation and application scope, and in summary, the content of the present specification should not be understood as the limitation of the present invention.
Claims (10)
1. The utility model provides a sun-proof big-arch shelter assembled construction partition wall of aggregate, its characterized in that includes base member, a plurality of stand and a plurality of prefabricated dog, and is a plurality of the stand equidistant fixed setting side by side is in on the base member, the straight flute has been seted up on two opposite flank of stand, and is adjacent be provided with between the straight flute of stand prefabricated dog, be provided with on the prefabricated dog and lift by crane groove and lifting hook, the groove of lifting by crane is seted up on the up end of prefabricated dog, lifting hook is fixed to be set up in the groove of lifting by crane.
2. The assembled construction partition wall of the aggregate sunscreen greenhouse as claimed in claim 1, wherein a plurality of the prefabricated blocks are stacked and formed by pouring between adjacent columns.
3. The aggregate sun-proof greenhouse fabricated construction partition wall as claimed in claim 2, wherein the prefabricated block is rectangular, angle steel is arranged at the vertex of the prefabricated block, the angle steel is poured in the prefabricated block, and the outer surface of the angle steel is flush with the side surface of the prefabricated block.
4. The aggregate sunscreen greenhouse fabricated construction partition wall as claimed in claim 3, wherein the inner surface of the angle steel is fixedly welded with a clip hook.
5. The assembled construction partition wall of the aggregate sunscreen greenhouse as claimed in claim 2, wherein the lifting hook is in an inverted U shape, the top end of the lifting hook does not exceed the upper end surface of the prefabricated block, and the bottom end of the lifting hook is poured into the prefabricated block.
6. The assembled construction partition wall of the aggregate sunscreen greenhouse as claimed in claim 5, wherein the bottom of the lifting hook is provided with a transversely arranged extension part, and the extension part is long and is integrally arranged with the lifting hook.
7. The assembled construction partition wall of the aggregate sun-proof greenhouse as claimed in claim 6, wherein a reinforcement cage is arranged inside the prefabricated block, the reinforcement cage comprises a plurality of longitudinally arranged first reinforcements and a plurality of transversely arranged second reinforcements, the first reinforcements and the second reinforcements are spliced into a cage shape, and the first reinforcements and the second reinforcements are connected by welding or binding.
8. The assembled construction partition wall of the aggregate sunscreen greenhouse as claimed in claim 7, wherein the extension part of the lifting hook is positioned below at least one second steel bar and is connected with the second steel bar by welding or binding.
9. The aggregate sun-proof greenhouse fabricated construction partition wall as claimed in claim 1, wherein the vertical columns are i-shaped steel, the lower ends of the vertical columns are poured in the matrix, and the opening directions of the straight grooves of the vertical columns point to the adjacent vertical columns.
10. The assembled construction partition wall of the aggregate sunscreen greenhouse as claimed in claim 9, wherein a connecting plate and two inclined struts are fixedly connected to the lower portions of the vertical columns, the connecting plate is perpendicular to the vertical columns, the lower ends of the vertical columns are located below the connecting plate, the two inclined struts are obliquely arranged, one ends of the inclined struts are fixedly connected to the side surfaces of the vertical columns, the other ends of the inclined struts are fixedly connected to the upper surfaces of the connecting plate, and the connecting plate and the inclined struts are both poured in the matrix.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020743076.4U CN212613190U (en) | 2020-05-08 | 2020-05-08 | Aggregate sun-proof greenhouse assembled construction partition wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020743076.4U CN212613190U (en) | 2020-05-08 | 2020-05-08 | Aggregate sun-proof greenhouse assembled construction partition wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212613190U true CN212613190U (en) | 2021-02-26 |
Family
ID=74725482
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020743076.4U Active CN212613190U (en) | 2020-05-08 | 2020-05-08 | Aggregate sun-proof greenhouse assembled construction partition wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212613190U (en) |
-
2020
- 2020-05-08 CN CN202020743076.4U patent/CN212613190U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111576619A (en) | Production method of high-strength concrete post-cast assembled frame system | |
US4050213A (en) | Method of erecting a multi-story building | |
CN212053673U (en) | Tower construction operation platform of dome | |
CN212656384U (en) | High-strength concrete connecting piece, high-strength concrete post-cast assembled frame system and support frame | |
CN206722216U (en) | A kind of prefabricated girder of laminated floor slab | |
CN212052355U (en) | Bent cap formwork structure | |
CN209760597U (en) | Precast concrete shear connector and self-supporting precast member thereof | |
CN212613190U (en) | Aggregate sun-proof greenhouse assembled construction partition wall | |
CN112359659A (en) | Construction method for cast-in-place box girder support door opening of anti-seismic intercommunication area | |
CN112144412A (en) | Construction method of prefabricated assembled intercolumnar tie beam | |
CN109397522B (en) | Universal precast beam pedestal suitable for soft soil geology and construction method thereof | |
CN107012985A (en) | A kind of prefabricated girder and the laminated floor slab construction technology containing the prefabricated girder | |
CN214994078U (en) | Large-diameter pile column structure for reverse construction method engineering | |
CN215715478U (en) | Lattice formula steel column tower crane basis | |
CN215759633U (en) | Concrete beam and wall, post connected node | |
CN110552430B (en) | Steel pipe column structure house | |
CN110004969B (en) | Tower crane foundation structure | |
CN212562162U (en) | Prefabricated slab | |
CN213509708U (en) | Ring beam underpinning and reinforcing structure of brick-concrete structure building | |
CN218170789U (en) | Prefabricated steel construction cushion cap template | |
CN217679033U (en) | Frame-type rod iron steel reinforcement cage installation device | |
CN215630962U (en) | Semi-fabricated concrete floor | |
CN217257066U (en) | A hollow inner membrance of loose formula for in prefabricated bridge construction | |
CN215252626U (en) | Cast-in-place surface course construction reverse hoisting system suitable for high-pile wharf | |
CN215367366U (en) | Assembled hollow foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |