Prior art keywords
aerated concrete
concrete wallboard
installed part
wallboard body
supporting beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021156903.6U
Other languages
Chinese (zh)
Inventor
李文富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Hailiang Energy Saving Technology Co ltd
Original Assignee
Shandong Hailiang Energy Saving Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Hailiang Energy Saving Technology Co ltd filed Critical Shandong Hailiang Energy Saving Technology Co ltd
Priority to CN202021156903.6U priority Critical patent/CN212613170U/en
Application granted granted Critical
Publication of CN212613170U publication Critical patent/CN212613170U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The utility model belongs to the technical field of building material structures, in particular to an aerated concrete wallboard mounting structure convenient for assembly, which comprises a ground and a supporting beam, the upper end surface of the ground is provided with a slot, the bottom end inside the slot is provided with a plurality of lower mounting pieces, the inside of the lower mounting pieces is provided with an aerated concrete wallboard body, the lower mounting piece comprises a bottom block, the upper end surface of the bottom block is fixedly connected with two side plates, the front side and the rear side of the upper end surface of the bottom block and the outer side walls of the two side plates can be detachably connected with two first steel nails, a plurality of upper mounting pieces which are symmetrically distributed are arranged on the front side and the rear side of the upper end of the aerated concrete wallboard body, so that the aerated concrete wallboard body is simple and convenient to install and can be used for fixing the ground and the supporting beam at the same time, this kind of connected mode has further increased the ground and the support beam and the aerated concrete wallboard body between the stability.

Description

Aerated concrete wallboard mounting structure convenient to assembly
Technical Field
The utility model relates to a building materials technical field, concretely relates to aerated concrete wallboard mounting structure convenient to assembly.
Background
The aerated concrete has the advantages of high strength, light weight, heat preservation, heat insulation, sound insulation, fire resistance and the like, the early application form of the aerated concrete mainly takes aerated concrete blocks as main materials, along with the aggravation of the market competition of building materials, the improvement of labor cost and the short requirement of construction period, the application of the aerated concrete plates is more and more extensive, the aerated concrete plates have the functions of structural bearing, fire prevention, heat preservation and the like, the aerated concrete plates are mainly used for peripheral retaining walls, inner partition walls, floor slabs, roof slabs and the like of industrial and civil buildings in the international market, the tensile strength of the aerated concrete is very low, when the tensile stress exceeds the tensile strength, the aerated concrete cracks, the performances of heat preservation, fire prevention, sound insulation and the like can be weakened under the action of the external environment, the appearance integrity is damaged, and the structure safety can even be threatened, the tensile stress born by the aerated concrete is mainly caused by foundation settlement displacement, at present, high-rise steel structure houses are increased day by day in the building market, the displacement between steel structure layers is larger than that of a concrete structure, and rigid connection is mostly adopted in the connection mode of aerated concrete slabs and steel beams when the aerated concrete slabs are used as inner walls at the present stage.
The existing aerated concrete wallboard mounting structure has the advantages that the mounting mode is complex when the aerated concrete wallboard body is mounted, the labor burden of workers is increased, the ground and the supporting beam cannot be fixed simultaneously, and the stability after mounting is reduced.
SUMMERY OF THE UTILITY MODEL
For solving the problem that provides in the above-mentioned background art, the utility model provides an aerated concrete wallboard mounting structure convenient to assembly, the simple convenient of mounting means when having aerated concrete wallboard body installation to the convenience is fixed simultaneously to ground and a supporting beam, and this kind of connected mode has further increased the characteristics of ground and a supporting beam and the stability between the aerated concrete wallboard body.
In order to achieve the above object, the utility model provides a following technical scheme: an aerated concrete wallboard mounting structure convenient to assemble comprises a ground and a supporting beam, wherein the supporting beam is positioned right above the ground, a groove is formed in the upper end face of the ground, a plurality of lower mounting pieces are mounted at the bottom end inside the groove, an aerated concrete wallboard body is mounted inside the lower mounting pieces, each lower mounting piece comprises a bottom block, two side plates are fixedly connected to the upper end face of the bottom block, one ends, opposite to the two side plates, of the two side plates are tightly attached to the front end and the rear end of the aerated concrete wallboard body, two first steel nails can be detachably connected to the front side and the rear side of the upper end face of the bottom block and the outer side walls of the two side plates, the lower mounting pieces and the groove as well as the lower mounting pieces and the aerated concrete wallboard body are detachably connected through four first steel nails, and a plurality of symmetrically distributed upper mounting pieces are mounted on the front side and the rear side of the, go up the installed part and be the form of falling L, it is a plurality of go up the up end of installed part and a supporting beam's lower terminal surface can dismantle and be connected.
For convenient with a mounting support beam and aerated concrete wallboard body be connected fixedly, conduct the utility model relates to an aerated concrete wallboard mounting structure is preferred convenient to assembly, it is a plurality of the inside top and the lateral wall of going up the installed part all can dismantle and be connected with two second steel nails, a plurality of go up all can dismantle through four second steel nails between installed part and the aerated concrete wallboard body and the supporting beam and be connected.
For the installed part under convenient first steel nail goes into, conduct the utility model relates to an aerated concrete wall panel mounting structure is preferred convenient to assembly, both sides and the lateral wall of two curb plates all run through set up with first steel nail assorted first mounting hole before the up end of bottom block.
For the convenience nail go into the second steel nail in last installed part, conduct the utility model relates to an aerated concrete wall panel mounting structure is preferred convenient to assembly, a plurality of the up end and the lateral wall of going up the installed part all run through and have seted up two and second steel nail assorted second mounting hole.
In order to make this auxiliary mounting spare have firm, be difficult to rusty characteristics, conduct the utility model relates to an aerated concrete wall panel mounting structure is preferred convenient to assembly, and is a plurality of the material of lower installed part and a plurality of last installed part is the metal material.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the aerated concrete wallboard mounting structure convenient to assemble comprises a bottom block, a plurality of side plates, a plurality of steel nails, an aerated concrete wallboard body, an upper mounting piece, an aerated concrete wallboard body, a plurality of steel nails, a plurality of lower mounting pieces, a plurality of steel nails, a plurality of, and conveniently fix ground and a supporting beam simultaneously, this kind of connected mode has further increased the stability between ground and a supporting beam and the aerated concrete wallboard body.
2. This kind of aerated concrete wallboard mounting structure convenient to assembly, after installation supporting beam and aerated concrete wallboard body butt joint department perpendicular card go into the installed part, two second steel nails are nailed respectively in the installation supporting beam and the aerated concrete wallboard body of last installed part and the punishment of hugging closely of last installed part, and then connect aerated concrete wallboard body and supporting beam fixedly through a plurality of installed parts of going up to reach and conveniently connected fixed effect with installation supporting beam and aerated concrete wallboard body.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention.
In the drawings:
FIG. 1 is a sectional view of an aerated concrete panel installation structure of the present invention, which is convenient for assembly;
fig. 2 is a transverse cross-sectional view of an aerated concrete wall panel mounting structure of the present invention, which is convenient for assembly;
FIG. 3 is a view of the structure of the lower mounting member of the present invention;
FIG. 4 is a structural view of the upper mounting member of the present invention;
fig. 5 is a cross-sectional view at B of the present invention;
fig. 6 is a cross-sectional view taken at a position a of the present invention.
In the figure, 1, the ground; 101. grooving; 2. a lower mounting member; 201. a bottom block; 202. a side plate; 2021. a first mounting hole; 203. a first steel nail; 3. an aerated concrete wall panel body; 4. an upper mounting member; 401. a second steel nail; 402. a second mounting hole; 5. and supporting the beam.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
In the description of the present invention, it is to be understood that the terms "length", "width", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on those shown in the drawings, and are merely for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention. In addition, in the description of the present invention, "a plurality" means two or more unless specifically limited otherwise.
Referring to fig. 1-6, the present invention provides the following technical solutions: an aerated concrete wallboard mounting structure convenient to assemble comprises a ground 1 and a supporting beam 5, wherein the supporting beam 5 is positioned right above the ground 1, the upper end face of the ground 1 is provided with a slot 101, the bottom end inside the slot 101 is provided with a plurality of lower mounting pieces 2, an aerated concrete wallboard body 3 is mounted inside the plurality of lower mounting pieces 2, each lower mounting piece 2 comprises a bottom block 201, the upper end face of each bottom block 201 is fixedly connected with two side plates 202, the opposite ends of the two side plates 202 are tightly attached to the front end and the rear end of the aerated concrete wallboard body 3, the front side and the rear side of the upper end face of each bottom block 201 and the outer side walls of the two side plates 202 can be detachably connected with two first steel nails 203, the lower mounting pieces 2 and the slot 101 as well as the lower mounting pieces 2 and the aerated concrete wallboard body 3 are detachably connected through four first steel nails 203, the front side and the rear side of the upper end of the aerated concrete wallboard body 3 are, the upper mounting members 4 are inverted L-shaped, and the upper end surfaces of the plurality of upper mounting members 4 are detachably connected to the lower end surface of the support beam 5.
In this embodiment: when the aerated concrete wallboard body 3 needs to be installed, firstly, a groove 101 is formed right below a ground 1 and a supporting beam 5, then a plurality of lower installing parts 2 are placed at the bottom end inside the groove 101, first steel nails 203 are respectively nailed into the front side and the rear side of the upper end surface of a bottom block 201 to fix the lower installing parts 2 and the groove 101, then the aerated concrete wallboard body 3 is clamped between two side plates 202, the first steel nails 203 are respectively nailed into the outer side walls of the two side plates 202, further, the lower installing parts 2 and the front side and the rear side of the aerated concrete wallboard body 3 are fixed, after the aerated concrete wallboard body 3 and the ground 1 are installed, the supporting beam 5 and the aerated concrete wallboard body 3 are installed, when in installation, an upper installing part 4 is clamped and fixed at the vertical position of the abutting joint of the supporting beam 5 and the aerated concrete wallboard body 3, therefore, the installation mode of the aerated concrete wallboard body 3 is simple and convenient, and conveniently fix ground 1 and a supporting beam 5 simultaneously, this kind of connected mode has further increased the stability between ground 1 and a supporting beam 5 and aerated concrete wallboard body 3.
As a technical optimization scheme of the utility model, a plurality of inside tops and the lateral wall of going up installed part 4 all can be dismantled and be connected with two second steel nails 401, all can dismantle through four second steel nails 401 between a plurality of installed part 4 and aerated concrete wallboard body 3 and the supporting beam 5 and be connected.
In this embodiment: after installing part 4 is gone into to installation supporting beam 5 and 3 butt joint department card of aerated concrete wallboard body, hug closely punishment at installation supporting beam 5 and aerated concrete wallboard body 3 of last installed part 4 and do not nail into two second steel nails 401, and then connect aerated concrete wallboard body 3 and supporting beam 5 through a plurality of installed parts 4 and fix to reached and conveniently connected fixed effect with installation supporting beam 5 and aerated concrete wallboard body 3.
As a technical optimization scheme of the utility model, both sides and two curb plate 202's lateral wall all run through set up with first steel nail 203 assorted first mounting hole 2021 before the up end of bottom block 201.
In this embodiment: first mounting hole 2021 facilitates driving first steel nail 203 into lower mount 2 when it is desired to screw first steel nail 203 into lower mount 2.
As a technical optimization scheme of the utility model, a plurality of up end and the lateral wall of going up installed part 4 all run through set up two with second steel nail 401 assorted second mounting hole 402.
In this embodiment: second mounting hole 402 facilitates driving second steel nail 401 into upper mounting member 4 when it is desired to screw second steel nail 401 into upper mounting member 4.
As a technical optimization scheme of the utility model, a plurality of material of installed part 2 and a plurality of installed part 4 of going up down is the metal material.
In this embodiment: the material through a plurality of installed part 2 down and a plurality of installed part 4 is the metal material, and then this supplementary installed part has firm, be difficult to rusty characteristics.
The utility model discloses a theory of operation and use flow: when the aerated concrete wallboard body 3 needs to be installed, firstly, a groove 101 is formed in the position right below a ground 1 and a supporting beam 5, then a plurality of lower installing pieces 2 are placed at the bottom end inside the groove 101, first steel nails 203 are respectively nailed into the front side and the rear side of the upper end face of a bottom block 201 to fix the lower installing pieces 2 and the groove 101, then the aerated concrete wallboard body 3 is clamped between two side plates 202, the first steel nails 203 are respectively nailed into the outer side walls of the two side plates 202, further, the front side and the rear side of the lower installing pieces 2 and the aerated concrete wallboard body 3 are fixed, after the aerated concrete wallboard body 3 and the ground 1 are installed, the supporting beam 5 and the aerated concrete wallboard body 3 are installed, when in installation, an upper installing piece 4 is clamped into the vertical position of the abutting position of the supporting beam 5 and the aerated concrete wallboard body 3, and after the upper installing piece 4 is clamped into the vertical position of the abutting position of the supporting beam 5 and the aerated concrete wallboard body, two second steel nails 401 are nailed respectively in the department of hugging closely at the installation supporting beam 5 of last installed part 4 and aerated concrete wallboard body 3 and last installed part 4, and then connect fixed aerated concrete wallboard body 3 and supporting beam 5 through a plurality of upper installed parts 4.
The above description is only exemplary of the present invention and should not be construed as limiting the present invention, and any modifications, equivalents and improvements made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.

Claims (5)

1. The utility model provides an aerated concrete wallboard mounting structure convenient to assembly, includes ground (1) and a supporting beam (5), supporting beam (5) are located ground (1) directly over its characterized in that: fluting (101) has been seted up to the up end on ground (1), a plurality of lower installed part (2) are installed to the inside bottom of fluting (101), and are a plurality of the internally mounted of installed part (2) has aerated concrete wallboard body (3) down, installed part (2) include bottom block (201) down, two curb plates (202) of the up end fixedly connected with of bottom block (201), two both ends are closely laminated around one end that curb plate (202) are relative and aerated concrete wallboard body (3), all can dismantle through four first steel nails (203) and be connected before the up end of bottom block (201) both sides and the lateral wall of two curb plates (202), all can dismantle through four first steel nails (203) and be connected between installed part (2) and fluting (101) and lower installed part (2) and aerated concrete wallboard body (3) down, a plurality of symmetric distributions's last installation of both sides is all installed around the upper end of aerated concrete wallboard body (3), install on the both sides a plurality of symmetric distributions Piece (4), go up installed part (4) and be the form of falling L, it is a plurality of go up the up end of installed part (4) and the lower terminal surface of a supporting beam (5) can dismantle and be connected.
2. An aerated concrete wall panel mounting structure to facilitate assembly according to claim 1 wherein: a plurality of the inside top and the lateral wall of going up installed part (4) all can be dismantled and be connected with two second steel nails (401), a plurality of go up between installed part (4) and aerated concrete wallboard body (3) and the supporting beam (5) all can dismantle through four second steel nails (401) and be connected.
3. An aerated concrete wall panel mounting structure to facilitate assembly according to claim 1 wherein: the front and back sides of the upper end face of the bottom block (201) and the outer side walls of the two side plates (202) are provided with first mounting holes (2021) matched with the first steel nails (203) in a penetrating mode.
4. An aerated concrete wall panel mounting structure to facilitate assembly according to claim 2 wherein: a plurality of the upper end face and the outer side wall of the upper mounting piece (4) are both provided with two second mounting holes (402) matched with the second steel nails (401) in a penetrating way.
5. An aerated concrete wall panel mounting structure to facilitate assembly according to claim 1 wherein: the lower mounting pieces (2) and the upper mounting pieces (4) are all made of metal.
CN202021156903.6U 2020-06-18 2020-06-18 Aerated concrete wallboard mounting structure convenient to assembly Expired - Fee Related CN212613170U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021156903.6U CN212613170U (en) 2020-06-18 2020-06-18 Aerated concrete wallboard mounting structure convenient to assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021156903.6U CN212613170U (en) 2020-06-18 2020-06-18 Aerated concrete wallboard mounting structure convenient to assembly

Publications (1)

Publication Number Publication Date
CN212613170U true CN212613170U (en) 2021-02-26

Family

ID=74755983

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021156903.6U Expired - Fee Related CN212613170U (en) 2020-06-18 2020-06-18 Aerated concrete wallboard mounting structure convenient to assembly

Country Status (1)

Country Link
CN (1) CN212613170U (en)

Similar Documents

Publication Publication Date Title
US7882665B2 (en) Construction configurations and construction methods of steel houses
WO2008113207A1 (en) An exterior wall panel and an assembly method thereof
EP0195662A2 (en) Supporting structure for cladding panels
CN212613170U (en) Aerated concrete wallboard mounting structure convenient to assembly
JPH11256736A (en) Wall face construction method for building and panel unit
CN213296679U (en) Shear wall for enhancing shear resistance
CN209891381U (en) Building structure
JP3029789B2 (en) Wall panels
JP4044411B2 (en) ALC floor / wall structure
CN220150551U (en) Mounting structure of assembled aerated concrete heat preservation external wall panel
CN113789894B (en) Assembly type hollow ceramic brick curtain wall and construction method thereof
CN215759888U (en) Autoclaved aerated concrete floor structure
CN212104563U (en) Prefabricated building element for the top or bottom intermediate position of a building wall
CN214574723U (en) Steel construction assembled wallboard node
CN211665949U (en) Right-angle connection combined steel structure
CN209837459U (en) Environment-friendly area direction constant head tank integral type composite wall panel system
CN108560827B (en) Square tube steel column and steel structure system
JP2642101B2 (en) Structure of mounting part of cantilever floor panel
JPH09268645A (en) Installing structure of rising alc wall corner part
CN118601201A (en) Assembled steel construction floor
JPH0728260Y2 (en) ALC wall panel mounting structure
JPH02101251A (en) Wall material fitting method for alc construction
JPH1171807A (en) Mounting structure and method for verandah handrail wall
JPH0310276Y2 (en)
KR20220163176A (en) Earthquake-proof exterior wall panel assembly

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210226