CN212612342U - Water conservancy dam construction is with blocking dirty device - Google Patents

Water conservancy dam construction is with blocking dirty device Download PDF

Info

Publication number
CN212612342U
CN212612342U CN202021052773.1U CN202021052773U CN212612342U CN 212612342 U CN212612342 U CN 212612342U CN 202021052773 U CN202021052773 U CN 202021052773U CN 212612342 U CN212612342 U CN 212612342U
Authority
CN
China
Prior art keywords
casing
water conservancy
close
shell
welded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021052773.1U
Other languages
Chinese (zh)
Inventor
赵保平
次仁尼玛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021052773.1U priority Critical patent/CN212612342U/en
Application granted granted Critical
Publication of CN212612342U publication Critical patent/CN212612342U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a water conservancy dam construction is with blocking dirty device, including first casing, two second slide rails are installed to the inside both sides of first casing, the inside sliding connection of second slide rail has the second slider, be located inside the first casing and be equipped with the filter plate between two second slide rails, one side that the second slider is close to the filter plate is welded with the filter plate, the welding of the top of second slider has the second connecting rod, first fixed plate has the bolt through first screw hole threaded connection; this device is when using, intercepts the filth in rivers through setting up the filter plate, prevents that it from influencing the construction progress of water conservancy dam, and set up the second slider and slide in the second slide rail, cooperation screw and second screw hole are convenient for the staff and are dismantled the filter plate and take out, are convenient for clear up and change it, prevent that the filter plate from leading to its filter mesh hole to block up because of long-time the use, prolong the life of filter plate, reduce the use cost of this device.

Description

Water conservancy dam construction is with blocking dirty device
Technical Field
The utility model relates to a water conservancy construction technical field specifically is a water conservancy dam construction is with blocking dirty device.
Background
The water conservancy project is a project built for controlling and allocating surface water and underground water in the nature to achieve the purpose of removing harm and benefiting, also called water engineering, water is a valuable resource essential for human production and life, but the naturally existing state of the water does not completely meet the requirements of human, only the water conservancy project is built to control water flow and prevent flood disasters and adjust and distribute water quantity to meet the requirements of people on water resources in life and production, the water conservancy project needs to build different types of water conservancy buildings such as dams, dikes, spillways, sluice gates, water inlets, channels, bunk troughs, rafts, fishways and the like to achieve the aims, the dams, Chinese vocabularies, dam dams for intercepting rivers, water retaining dams of reservoirs, rivers and the like, and the general reservoir dam mainly comprises a main dam, an auxiliary flood dam, a gravity dam, a normal spillway, a very newly added spillway dam, a very newly added spillway, a water diversion dam, a gravity dam, a normal spillway, a very new dam, A smart main canal culvert and a power station.
Current water conservancy dam need set up and block dirty device and intercept sewage in the work progress, prevents that it from influencing the construction progress, and current interception prevents to intercept for setting up the baffle usually, can be with the same interception of rivers, need consume a large amount of baffles, and the cost is higher.
The invention is disclosed in China: CN201920383750.X discloses a power station is with blocking dirty device, and the device blocks it dirty through setting up the interception net, makes rivers pass through, reduces and blocks dirty device atress to block the filth, prevent that it from influencing the construction progress, but the device is when using, and the interception net is blockked up by the filth easily, needs to dismantle clearance or change it, and the device is not convenient for change the clearance to it, for this, provides a water conservancy dam construction is with blocking dirty device.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a water conservancy dam construction is with blocking dirty device.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a water conservancy dam construction is with blocking dirty device, includes first casing, two second slide rails are installed to the inside both sides of first casing, the inside sliding connection of second slide rail has the second slider, the inside filter plate that is located between two second slide rails that is equipped with of first casing, one side and the filter plate welding that the second slider is close to the filter plate, the top welding of second slider has the second connecting rod, the one end welding that the second slider was kept away from to the second connecting rod has first fixed plate, first screw hole has been seted up to one side that first fixed plate is close to first casing, first fixed plate has the bolt through first screw hole threaded connection, two second screw holes have been seted up to one side that first casing is close to the bolt, the bolt passes through second screw hole and first casing threaded connection.
Preferably, two guide blocks are welded to one side of the first housing.
Preferably, the bottom welding of first casing has two bracing pieces, the below of first casing is equipped with the buried block in advance, the bracing piece is close to the one end of buried block in advance and welds with the buried block in advance.
Preferably, two baffles are welded inside the first shell.
Preferably, four first slide rails are installed on one side of the baffle plate inside the first shell, a first sliding block is connected to the inside of the first slide rails in a sliding mode, two scraper plates are arranged on one side of the first slide rail inside the first shell, one side of the first sliding block, which is close to the scraper plates, is welded with the scraper plates, a first connecting rod is welded to the top of each scraper plate, one end, which is far away from the scraper plates, of each first connecting rod penetrates through the first shell, the end, which penetrates through the first shell, of each first connecting rod is welded with the second fixing plate, an electric push rod is installed at the top of the first shell, and the telescopic end of the electric push rod is welded with the second fixing plate.
Preferably, a switch is installed on one side of the top of the first shell, and an electrical output end of the switch is electrically connected with an electrical input end of the electric push rod.
(III) advantageous effects
Compared with the prior art, the utility model provides a water conservancy dam construction is with blocking dirty device possesses following beneficial effect: this device is when using, intercept through setting up the filth of filter plate in to rivers, prevent that it from influencing the construction progress of water conservancy dam, and set up the second slider and slide in the second slide rail, cooperation screw and second screw hole are convenient for the staff and are dismantled filter plate and take out, be convenient for clear up and change it, prevent that filter plate from leading to its filter plate hole to block up because of long-time the use, the life of extension filter plate, reduce the use cost of this device, and set up the baffle and cushion the rivers that get into first casing, prevent that it from directly erodeing filter plate and lead to filter plate to damage.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of a second slide rail of the present invention;
fig. 3 is a schematic structural view of the first slide rail of the present invention.
In the figure: 1. a first fixing plate; 2. a switch; 3. a second fixing plate; 4. an electric push rod; 5. a guide block; 6. a first link; 7. a first slider; 8. pre-burying blocks; 9. a support bar; 10. a first slide rail; 11. a baffle plate; 12. a filter screen plate; 13. a second slide rail; 14. a first housing; 15. a bolt; 16. a first threaded hole; 17. a second link; 18. a second slider; 19. a second threaded hole; 20. a scraper.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Examples
Referring to fig. 1-3, the present invention provides a technical solution: the utility model provides a water conservancy dam construction is with blocking dirty device, including first casing 14, two second slide rails 13 are installed to the inside both sides of first casing 14, the inside sliding connection of second slide rail 13 has second slider 18, first casing 14 is inside to be located and is equipped with filter screen board 12 between two second slide rails 13, one side that second slider 18 is close to filter screen board 12 is welded with filter screen board 12, the welding of the top of second slider 18 has second connecting rod 17, the welding of the one end that second slider 18 was kept away from to second connecting rod 17 has first fixed plate 1, first screw hole 16 has been seted up to one side that first fixed plate 1 is close to first casing 14, first fixed plate 1 has bolt 15 through first screw hole 16 threaded connection, two second screw holes 19 have been seted up to one side that first casing 14 is close to bolt 15, bolt 15 passes through second screw hole 19 and first casing 14 threaded connection.
In this embodiment, specifically: two guide blocks 5 are welded on one side of the first shell 14, the guide blocks 5 are arranged to guide water flow into the first shell 14, the water flow is prevented from directly flushing the baffle 11, and the service life of the baffle 11 is prolonged.
In this embodiment, specifically: the welding of the bottom of first casing 14 has two bracing pieces 9, and the below of first casing 14 is equipped with buried block 8 in advance, and bracing piece 9 is close to buried block 8's one end and buried block 8 welding in advance, sets up buried block 8 cooperation bracing piece 9 and makes this device more stable at the during operation, prevents to be washed away by rivers because of this device and leads to the slope.
In this embodiment, specifically: two baffles 11 are welded inside the first shell 14, and the baffles 11 are arranged to buffer water flow and prevent the water flow from directly scouring the filter screen plate 12.
In this embodiment, specifically: four first slide rails 10 are mounted on one side of the interior of the first shell 14 close to the baffle 11, a first slider 7 is connected to the interior of the first slide rail 10 in a sliding manner, two scrapers 20 are arranged on one side of the interior of the first shell 14 close to the first slide rails 10, one side of the first slider 7 close to the scrapers 20 is welded with the scrapers 20, a first connecting rod 6 is welded on the top of each scraper 20, one end of each first connecting rod 6, which is far away from the corresponding scraper 20, penetrates through the first shell 14, one end of each first connecting rod 6, which penetrates through the first shell 14, is welded with the second fixing plate 3, an electric push rod 4 is mounted on the top of the first shell 14, the electric push rod 4 is CAHB-10, the telescopic end of the electric push rod 4 is welded with the second fixing plate 3, and the scraper 20 is driven by the first connecting rod 6 to clean the baffle 11, so that the normal use of the baffle 11 is prevented from being influenced by the adhesion of sludge.
In this embodiment, specifically: switch 2 is installed to top one side of first casing 14, and the electrical property output of switch 2 and electric putter 4's electrical property input end electrical connection set up switch 2 control electric putter 4's start-up and close.
In summary, the working principle and the working process of the trash device for the water conservancy dam construction are that when the trash device is used, the embedded block 8 is pre-embedded in the working place of the device, the device is installed at the working place through the support rod 9, water flow carries dirt and is guided into the first shell 14 through the guide block 5, the sewage entering the first shell 14 is buffered by the baffle 11 to prevent the sewage from directly scouring the filter screen plate 12, the sewage passes through the filter screen plate 12 and is intercepted by the filter screen plate 12, after the trash device is used for a long time, the filter screen plate 12 and the baffle 11 need to be cleaned, the bolt 15 is rotated to separate the trash device from the second threaded hole 19, the first fixing plate 1 is pulled, the second slide block 18 is driven to slide in the second slide rail 13 through the second connecting rod 17, the second slide block 18 drives the filter screen plate 12 to separate from the first shell 14, the filter screen plate 12 is taken out to be cleaned or replaced, pressing switch 2 and starting electric putter 4, electric putter 4 promotes second fixed plate 3, drives scraper blade 20 upward movement through first connecting rod 6, and scraper blade 20 drives first slider 7 and slides in first slide rail 10, is struck off by the filth of scraper blade 20 adhesion on to baffle 11, prolongs baffle 11's life.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a water conservancy dam construction is with trash device, includes first casing (14), its characterized in that: two second sliding rails (13) are mounted on two sides of the interior of the first shell (14), a second sliding block (18) is connected to the interior of each second sliding rail (13) in a sliding manner, a filter screen plate (12) is arranged between the two second sliding rails (13) in the first shell (14), one side, close to the filter screen plate (12), of each second sliding block (18) is welded with the corresponding filter screen plate (12), a second connecting rod (17) is welded to the top of each second sliding block (18), a first fixing plate (1) is welded to one end, far away from the second sliding block (18), of each second connecting rod (17), a first threaded hole (16) is formed in one side, close to the first shell (14), of each first fixing plate (1), a bolt (15) is connected to each first fixing plate through the corresponding thread of each first threaded hole (16), and two second threaded holes (19) are formed in one side, close to each bolt (15), of each first shell (14), the bolt (15) is in threaded connection with the first housing (14) through the second threaded hole (19).
2. The water conservancy dam construction is with blocking dirty device of claim 1, its characterized in that: two guide blocks (5) are welded on one side of the first shell (14).
3. The water conservancy dam construction is with blocking dirty device of claim 1, its characterized in that: the bottom welding of first casing (14) has two bracing pieces (9), the below of first casing (14) is equipped with buried block (8) in advance, bracing piece (9) are close to the one end and the welding of buried block (8) in advance of buried block (8).
4. The water conservancy dam construction is with blocking dirty device of claim 1, its characterized in that: two baffles (11) are welded inside the first shell (14).
5. The water conservancy dam construction is with blocking dirty device of claim 4, its characterized in that: four first slide rails (10) are installed to the inside one side that is close to baffle (11) of first casing (14), the inside sliding connection of first slide rail (10) has first slider (7), the inside one side that is close to first slide rail (10) of first casing (14) is equipped with two scraper blades (20), one side that is close to scraper blade (20) of first slider (7) welds with scraper blade (20), the top welding of scraper blade (20) has first connecting rod (6), the one end that scraper blade (20) were kept away from in first connecting rod (6) runs through first casing (14), two the one end that first connecting rod (6) run through first casing (14) all welds with second fixed plate (3), electric putter (4) are installed at the top of first casing (14), the flexible end and the welding of second fixed plate (3) of electric putter (4).
6. The water conservancy dam construction is with blocking dirty device of claim 5, its characterized in that: switch (2) are installed to top one side of first casing (14), the electrical property output of switch (2) and the electrical property input electric connection of electric putter (4).
CN202021052773.1U 2020-06-10 2020-06-10 Water conservancy dam construction is with blocking dirty device Active CN212612342U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021052773.1U CN212612342U (en) 2020-06-10 2020-06-10 Water conservancy dam construction is with blocking dirty device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021052773.1U CN212612342U (en) 2020-06-10 2020-06-10 Water conservancy dam construction is with blocking dirty device

Publications (1)

Publication Number Publication Date
CN212612342U true CN212612342U (en) 2021-02-26

Family

ID=74715064

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021052773.1U Active CN212612342U (en) 2020-06-10 2020-06-10 Water conservancy dam construction is with blocking dirty device

Country Status (1)

Country Link
CN (1) CN212612342U (en)

Similar Documents

Publication Publication Date Title
CN113483859A (en) Environment-friendly monitoring platform device for water conservancy management and use method
CN214832820U (en) Foundation ditch drainage support is used in dykes and dams construction
CN212612342U (en) Water conservancy dam construction is with blocking dirty device
CN211989538U (en) Sand screening installation for hydraulic engineering construction
CN210597218U (en) Dam reinforcing structure for hydraulic engineering
CN110528474B (en) Automatic change hydroelectric power generation sluicing floodgate
CN213417721U (en) A breakwater for water conservancy construction
CN213741392U (en) Novel water-saving closestool
CN211340679U (en) Water conservancy water and electricity dam water inlet floater fishing device
CN113373872A (en) Water diversion structure of hydraulic and hydroelectric engineering
CN113565069A (en) River sluice device for hydraulic engineering
CN213143176U (en) Dredging device for urban hydraulic engineering
CN216640514U (en) Pump station that hydraulic engineering used blocks dirty device
CN218492453U (en) Hydraulic engineering is with fence of decontaminating
CN220246844U (en) Sluice rubbish intercepting device
CN215441762U (en) Water conservancy construction water delivery groove for building
CN215633576U (en) Water drainage device for preventing and treating water for coal mine
CN217629719U (en) Earth and rockfill dam sluicing water delivery building stagnant water structure
CN216865047U (en) Sluice cleaning device for hydraulic engineering
CN215888142U (en) Be applied to filter equipment of water conservancy water and electricity dam
CN213926168U (en) Hydraulic engineering is with blocking dirty device
CN220486345U (en) Water conservancy construction is with shelves water weir with reinforced structure
CN216629919U (en) Efficient hydraulic engineering fence of decontaminating
CN214695467U (en) River sluice for hydraulic engineering
CN211143096U (en) Deep foundation pit drainage structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant