CN212601324U CN202020853865.3U CN202020853865U CN212601324U CN 212601324 U CN212601324 U CN 212601324U CN 202020853865 U CN202020853865 U CN 202020853865U CN 212601324 U CN212601324 U CN 212601324U
Authority
CN
China
Prior art keywords
fastening block
stand
pipeline
block
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020853865.3U
Other languages
Chinese (zh)
Inventor
金社伟
张景森
曾扬刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Huaran Energy Construction Co Ltd
Original Assignee
Foshan Huaran Energy Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Huaran Energy Construction Co Ltd filed Critical Foshan Huaran Energy Construction Co Ltd
Priority to CN202020853865.3U priority Critical patent/CN212601324U/en
Application granted granted Critical
Publication of CN212601324U publication Critical patent/CN212601324U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a zinc-plating pipe installation is with no flower bench pincers, which comprises a bracket, with the pipe clamping mechanism of fixed mounting in the support top, pipe clamping mechanism includes the stand, first holding block, the second holding block, stand fixed mounting is at the up end of support, first holding block is the style of calligraphy of falling V, first holding block sets up the top at the stand, the left end of first holding block and the left end of stand are articulated each other, the right-hand member of first holding block is equipped with locking device, first holding block passes through locking device and stand interconnect, the second holding block is the V style of calligraphy, the below at the middle of the stand is installed to the second holding block. The utility model has the advantages that: through setting up pipeline clamping mechanism, use through the cooperation between first fastening block, the second fastening block, can avoid causing the damage of certain degree to the anticorrosive coating and the pipeline surface of tubular product in the installation to the pipeline, increase the life of tubular product, reduce the extra maintenance cost of pipeline.

Description

Non-flower bench clamp for installation of galvanized pipeline
Technical Field
The utility model belongs to the technical field of pipeline installation mechanism and specifically relates to a zinc-plating pipeline installation is with no flower bench vice is related to.
Background
With the increasing requirements of people on the quality of life, the application of gas in various fields is more and more extensive. In order to guarantee the safety of gas delivery and use, the selection of pipeline materials has important meaning. Compared with other traditional gas pipelines, the galvanized pipeline has better tolerance and corrosion resistance, thereby having higher safety and economical efficiency in installation engineering. When the galvanized pipe is used as a gas pipeline, the galvanized pipe is usually installed by adopting a welding or wire connection mode, and the wire connection mode is widely adopted due to the advantages of convenience in installation and the like.
Galvanized pipe thread joint adopts the breakout tongs to install usually, thereby traditional breakout tongs drive the pipeline rotation with the help of the bite-force between tong tooth and the pipeline and realize the screw-thread fit between pipeline and the pipe fitting and accomplish the installation process with the tong power conversion for torsion, inevitably can cause certain damage to the anticorrosive coating and the pipeline surface of tubular product at the in-process of installation, thereby lead to the life of tubular product to descend, thereby the destruction of pipeline outward appearance increases extra maintenance cost.
SUMMERY OF THE UTILITY MODEL
The utility model discloses an it is not enough to overcome above-mentioned condition, provides a technical scheme that can solve above-mentioned problem.
The utility model provides a zinc-plating pipe installation is with no flower bench vice, which comprises a bracket, with the pipe clamping mechanism of fixed mounting in the support top, pipe clamping mechanism includes the stand, first holding shoe, the second holding shoe, stand fixed mounting is at the up end of support, first holding shoe is the style of calligraphy of falling V, first holding shoe sets up the top at the stand, the left end of first holding shoe and the left end of stand are articulated each other, the right-hand member of first holding shoe is equipped with locking device, first holding shoe passes through locking device and stand interconnect, the second holding shoe is the V style of calligraphy, the below at the middle of the stand is installed to the second holding shoe.
As a further aspect of the present invention: the locking device comprises a lock catch and a lock block, the lock catch is hinged with the right end of the first fastening block, the lock block is arranged at the right end of the upright post corresponding to the lock catch, and the lock catch and the lock block are matched with each other.
As a further aspect of the present invention: the middle of support is equipped with the mounting bracket, installs the jack on the mounting bracket, has seted up the through-hole between the up end of support and the stand, and the telescopic link of jack passes the mutual fixed connection of lower terminal surface of through-hole and second fastening block.
As a further aspect of the present invention: the inboard shaping of stand has the spout, and the corresponding spout shaping in both sides has the slider about the second fastening block, and the slider is established in the spout, and the second fastening block slides from top to bottom in the middle of the stand.
As a further aspect of the present invention: silica gel is installed on the working surfaces of the first fastening block and the second fastening block.
Compared with the prior art, the beneficial effects of the utility model are that: through setting up pipeline clamping mechanism, use through the cooperation between first fastening block, the second fastening block, can avoid causing the damage of certain degree to the anticorrosive coating and the pipeline surface of tubular product in the installation to the pipeline, increase the life of tubular product, reduce the extra maintenance cost of pipeline.
Additional aspects and advantages of the invention will be set forth in part in the description which follows and, in part, will be obvious from the description, or may be learned by practice of the invention.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic view of the pipe clamp mechanism in an open configuration.
Figure 3 is a schematic view of the construction of the second fastening block.
Shown in the figure: 1. a support; 11. a mounting seat; 12. a through hole; 2. a pipe clamping mechanism; 21. a column; 22. a first fastening block; 23. a second fastening block; 24. the locking device 25 and the lock catch; 26. a locking block; 27. silica gel; 28. a chute; 29. a slider; 3. a jack.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, a pair of non-flower bench clamp for installation of galvanized pipelines comprises a support 1 and a pipeline clamping mechanism 2 fixedly installed above the support 1, wherein the pipeline clamping mechanism 2 comprises an upright post 21, a first fastening block 22 and a second fastening block 23, the upright post 21 is fixedly installed on the upper end face of the support 1, the first fastening block 22 is of an inverted V shape, the first fastening block 22 is arranged above the upright post 1, the left end of the first fastening block 22 is hinged with the left end of the upright post 21, the right end of the first fastening block 22 is provided with a locking device 24, the first fastening block 22 is connected with the upright post 21 through the locking device 24, the second fastening block 23 is of a V shape, and the second fastening block 23 is installed below the middle of the upright post 21. When the pipeline fastening device is used, a pipeline to be installed is placed on the second fastening block 23, then the first fastening block 22 is covered, the pipeline is locked between the first fastening block 22 and the second fastening block 23 through the locking device 24 at the right end of the first fastening block 22, and then the pipeline is connected.
As a further aspect of the present invention: the locking device 24 comprises a lock catch 25 and a lock block 26, the lock catch 25 is hinged with the right end of the first fastening block 22, the lock block 26 is arranged at the right end of the upright post 21 corresponding to the lock catch 25, and the lock catch 25 is matched with the lock block 26. By the cooperation between the catches 25 and the locking blocks 26, the pipe is locked between the first fastening block 22 and the second fastening block 23,
as a further aspect of the present invention: the middle of support 1 is equipped with mounting bracket 11, installs jack 3 on mounting bracket 11, has seted up through-hole 12 between the up end of support 1 and stand 21, and the telescopic link of jack 3 passes through-hole 12 and the mutual fixed connection of lower terminal surface of second fastening block 23. The pipe is locked between the first fastening block 22 and the second fastening block 23 by the upward force of the jack 3 below the second fastening block 23.
As a further aspect of the present invention: the inner side of the upright post 21 is formed with a sliding groove 28, the left and right sides of the second fastening block 23 are formed with sliding blocks 29 corresponding to the sliding groove 28, the sliding blocks 29 are arranged in the sliding groove 28, and the second fastening block 23 slides up and down in the middle of the upright post 21. The second fastening block 23 can slide up and down between the uprights 21 by providing the slide grooves 28 and the slide blocks 29.
As a further aspect of the present invention: the silicone rubber 27 is mounted on the working surfaces of the first fastening block 22 and the second fastening block 23. By utilizing the flexibility of the silica gel 27, the surface of the pipeline can be perfectly attached when the first fastening block 22 and the second fastening block 23 are used for locking the pipeline, and the pipeline can be more stably fixed between the first fastening block 22 and the second fastening block 23.
The utility model discloses a theory of operation is: when the pipeline fixing device is used, a pipeline to be installed is placed on the second fastening block 23, then the first fastening block 22 is covered, the pipeline is locked between the first fastening block 22 and the second fastening block 23 through the matching between the lock catches 25 and the locking blocks 26, and then the pipeline is connected.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (5)

1. The utility model provides a galvanized pipe installation is with no flower bench vice which characterized in that: the support is included, with the pipeline clamping mechanism of fixed mounting in the support top, pipeline clamping mechanism includes the stand, first fastening block, the second fastening block, stand fixed mounting is at the up end of support, first fastening block is the style of calligraphy of falling V, first fastening block sets up the top at the stand, the left end of first fastening block and the left end of stand are articulated each other, the right-hand member of first fastening block is equipped with locking device, first fastening block passes through locking device and stand interconnect, the second fastening block is the V style of calligraphy, the below in the middle of the stand is installed to the second fastening block.
2. The flower-free bench clamp for installation of the galvanized pipeline as claimed in claim 1, wherein: the locking device comprises a lock catch and a lock block, the lock catch is hinged with the right end of the first fastening block, the lock block is arranged at the right end of the upright post corresponding to the lock catch, and the lock catch and the lock block are matched with each other.
3. The flower-free bench clamp for installation of the galvanized pipeline as claimed in claim 1, wherein: the middle of support is equipped with the mounting bracket, installs the jack on the mounting bracket, has seted up the through-hole between the up end of support and the stand, and the telescopic link of jack passes the mutual fixed connection of lower terminal surface of through-hole and second fastening block.
4. The flower-free bench clamp for installation of the galvanized pipeline as claimed in claim 3, wherein: the inboard shaping of stand has the spout, and the corresponding spout shaping in both sides has the slider about the second fastening block, and the slider is established in the spout, and the second fastening block slides from top to bottom in the middle of the stand.
5. The flower-free bench clamp for installation of the galvanized pipeline as claimed in claim 1, wherein: silica gel is installed on the working surfaces of the first fastening block and the second fastening block.
CN202020853865.3U 2020-05-20 2020-05-20 Non-flower bench clamp for installation of galvanized pipeline Expired - Fee Related CN212601324U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020853865.3U CN212601324U (en) 2020-05-20 2020-05-20 Non-flower bench clamp for installation of galvanized pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020853865.3U CN212601324U (en) 2020-05-20 2020-05-20 Non-flower bench clamp for installation of galvanized pipeline

Publications (1)

Publication Number Publication Date
CN212601324U true CN212601324U (en) 2021-02-26

Family

ID=74724946

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020853865.3U Expired - Fee Related CN212601324U (en) 2020-05-20 2020-05-20 Non-flower bench clamp for installation of galvanized pipeline

Country Status (1)

Country Link
CN (1) CN212601324U (en)

Similar Documents

Publication Publication Date Title
CN109473795B (en) Novel gravity locking anti-drop universal ground rod
CN212601324U (en) Non-flower bench clamp for installation of galvanized pipeline
CN205904737U (en) Arm horizontal adjusting device is held to square pipe clamp
CN208011632U (en) A kind of lamps and lanterns aluminium frame of Anti-fall
CN111791207A (en) Side wall stores pylon frock
CN208996435U (en) A kind of construction scaffold assembly connector
CN208890286U (en) A kind of novel power cable support device
CN220839786U (en) Assembling tool for aluminum alloy pipe fitting
CN206971598U (en) A kind of floor guard rail support
CN217882788U (en) Cable hanging rack
CN214820958U (en) Hot melting device is used in processing of plastic accessory
CN214402506U (en) Aluminum alloy railing capable of adjusting glass height
CN214204856U (en) Anchor ear of acting as go-between
CN211936997U (en) Reagent frame joint formula spliced pole
CN214868373U (en) Car seat welding jig
CN218290300U (en) Gallows structure is used in building engineering construction
CN220033789U (en) Socket steel pipe with lifting lugs
CN214785774U (en) Lifting type construction platform for house building engineering
CN213257799U (en) Bucket elevator connecting pipe tool
CN217882662U (en) Cable bracket
CN209294969U (en) A kind of adjustable type lamps and lanterns hanging apparatus suitable for assembled subway station
CN211622564U (en) Connect stable pole setting connecting piece
CN212802335U (en) Angle-adjustable color steel tile roof stand
CN214785088U (en) Dry-hanging curtain wall connecting piece
CN217272427U (en) Flexible hanging device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210226