CN212559145U - Shore bridge - Google Patents

Shore bridge Download PDF

Info

Publication number
CN212559145U
CN212559145U CN202021503974.9U CN202021503974U CN212559145U CN 212559145 U CN212559145 U CN 212559145U CN 202021503974 U CN202021503974 U CN 202021503974U CN 212559145 U CN212559145 U CN 212559145U
Authority
CN
China
Prior art keywords
extension
support
shore bridge
tie bar
connection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021503974.9U
Other languages
Chinese (zh)
Inventor
曾鹏
李义明
郭新林
赵良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhenghua Heavy Industries Co Ltd
Original Assignee
Shanghai Zhenghua Heavy Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zhenghua Heavy Industries Co Ltd filed Critical Shanghai Zhenghua Heavy Industries Co Ltd
Priority to CN202021503974.9U priority Critical patent/CN212559145U/en
Application granted granted Critical
Publication of CN212559145U publication Critical patent/CN212559145U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a shore bridge, including preceding girder, preceding girder includes first portion, second portion and locates the extension between first portion and the second portion, the both ends of extension respectively with first portion and second portion fixed connection, first portion, and/or, be equipped with connecting portion between second portion and the extension, connecting portion are used for strengthening the first portion, and/or, the joint strength between second portion and the extension. The utility model provides a pair of bank bridge has set up the extension through in the front between girder's the first portion and the second portion and has made the length of preceding girder to increase. The first part or the second part is connected with the extension part through the connecting part, a stable triangular supporting structure is formed together, the connecting strength between the first part and the second part is enhanced, the structural strength of the whole front girder is improved, and the extension part can well meet the use safety requirement of the front girder.

Description

Shore bridge
Technical Field
The utility model relates to a container crane technical field particularly, relates to a bank bridge.
Background
Shore bridges, also known as shore container cranes, are equipment used to load and unload containers on container ships on shore. In order to reduce the cost of shipping and circulating goods, more goods are loaded on the ship, the container ship is updated from 2500TEU Panama type container ship to 7000TEU container ship with the fourth generation, fifth generation and sixth generation, so that the large-scale speed of the container ship is accelerated to the current ten thousand-container ship times.
In order to match the upgrading of the container ship, the shore bridge reach is changed. The distance from the original front reach to 35 m, 50 m and 65 m to the maximum distance from the front reach to 80 m. If the active shore bridge can not touch the container far from the side of the wharf, the container can only be adjusted to the head' without any trouble, which wastes time and labor. The quayside usually purchases a shore bridge with larger reach to meet the berthing of a large container ship, but the cost of the new shore bridge is higher, the delivery time of a manufacturer is long, and the like. Therefore, the quayside often excavates the capacity of the active shore bridge, and improves the capacity of the shore bridge for hoisting containers at a farther position by modifying the reach of the active shore bridge.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a bank bridge to solve among the prior art bank bridge's not enough problem of reach.
In order to achieve the above object, the utility model provides a shore bridge, including preceding girder, preceding girder includes first portion, second portion and locates the extension between first portion and the second portion, the both ends of extension respectively with first portion and second portion fixed connection, first portion, and/or, be equipped with connecting portion between second portion and the extension, connecting portion are used for strengthening first portion, and/or, the joint strength between second portion and the extension.
According to another embodiment of the present invention, the first connection point of the extension portion and the first portion is an end of the original reach, and the distance between the first connection point and the second connection point of the extension portion and the second portion is the extended reach.
According to the utility model discloses a further concrete implementation mode, connecting portion include support post, first pull rod and second pull rod, and support post locates the one end that is close to the extension on the first portion, and first pull rod one end is connected with the first portion, and the other end is connected with support post's upper end, and second pull rod one end is connected with support post's upper end, and the other end is connected with the extension.
According to another embodiment of the present invention, a connecting ear plate is disposed between the first pull rod and the first portion, between the second pull rod and the extending portion, and between the first pull rod and the supporting pillar.
According to another embodiment of the present invention, the upper portion of the supporting pillar is provided with a first double-ear plate and a second double-ear plate, the first double-ear plate is connected with the first pull rod, and the second double-ear plate is connected with the second pull rod.
According to another embodiment of the present invention, the first and second double-ear plates are provided with a stress-releasing hole sealing plate at the junction with the support pillar.
According to the utility model discloses a further embodiment, support post's upper end is equipped with the apron, is equipped with the hoist and mount otic placode on the apron.
According to the utility model discloses a further concrete implementation mode, the lower extreme of support post is equipped with the backup pad, and the backup pad is used for fixed the setting on the first portion with the support post.
According to another embodiment of the present invention, the first portion is provided with a beam, and the supporting plate is provided on the beam.
According to the utility model discloses a further embodiment, the lower extreme of support post is equipped with the cylinder shrouding for seal the opening between support post's lower extreme and the backup pad.
As above, the utility model provides a bank bridge makes the length of preceding girder can increase through having set up the extension between the first portion and the second portion of preceding girder. The first part or the second part is connected with the extension part through the connecting part, a stable triangular supporting structure is formed together, the connecting strength between the first part and the second part is enhanced, the structural strength of the whole front girder is improved, and the extension part can well meet the use safety requirement of the front girder.
In order to make the aforementioned and other objects of the present invention comprehensible, preferred embodiments accompanied with figures are described in detail below.
Drawings
The accompanying drawings, which form a part of the present application, are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the invention and not to limit the invention. On the attachment
In the figure:
fig. 1 schematically shows an overall structure diagram of a shore bridge of the present invention;
fig. 2 schematically shows a partial structure diagram of a shore bridge of the present invention;
fig. 3 schematically shows a structural diagram of a support column in a shore bridge of the present invention;
fig. 4 schematically shows a side view distribution diagram of a support post in a shore bridge of the present invention.
Detailed Description
The following description is provided for illustrative embodiments of the present invention, and other advantages and effects of the present invention will be readily apparent to those skilled in the art from the disclosure herein. While the invention will be described in conjunction with the preferred embodiments, it is not intended that features of the invention be limited to only those embodiments. On the contrary, the intention of implementing the novel features described in connection with the embodiments is to cover other alternatives or modifications which may be extended based on the claims of the present invention. In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention. The invention may be practiced without these particulars. Furthermore, some of the specific details are omitted from the description so as not to obscure or obscure the present invention.
It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The present invention will be described in detail below with reference to the accompanying drawings in conjunction with embodiments.
Referring to fig. 1-4, an embodiment of the present invention provides a shore bridge 1, including a front girder 10, the front girder 10 includes a first portion 100, a second portion 101 and an extension portion 11 disposed between the first portion 100 and the second portion 101, both ends of the extension portion 11 are respectively fixedly connected with the first portion 100 and the second portion 101, the first portion 100, and/or a connection portion 12 is disposed between the second portion 101 and the extension portion 11, and the connection portion 12 is used for enhancing the connection strength between the first portion 100, and/or the second portion 101 and the extension portion 11.
That is, the front side member 10 is mainly composed of a first portion 100, a second portion 101, and an extension 11, wherein the extension 11 is disposed between the first portion 100 and the second portion 101, and both ends thereof are fixedly connected to the first portion 100 and the second portion 101, respectively. Meanwhile, in order to enhance the coupling strength between the extension 11 and the first portion 100 or the second portion 101, a coupling portion 12 is provided between the first portion 100 or the second portion 101 and the extension 11.
That is, the present embodiment allows the length of the front girder 10 to be increased by providing the extension 11 between the first portion 100 and the second portion 101 of the front girder 10. The utility model discloses do not injecing to the position and the length that the extension set up, as long as can make preceding girder extension can.
Specifically, in the present embodiment, the second portion 101 is cut from the first portion 100 at the front end of the front side member 10, that is, the first portion 100 and the second portion 101 of the front side member 10 are of an integral structure before the extension 11 is added, in order to extend the front side member 10 by adding the extension, the second portion 101 is cut from the first portion 100, and then the extension 11 and the second portion 101 are sequentially and fixedly connected together along the extension direction (as shown in the X direction in fig. 1) of the front side member 10.
In this embodiment, the first portion 100, the second portion 101 and the extension 11 are fixedly connected by welding, and the joint portion of the first portion 100, the second portion 101 and the extension 11 has the same cross section, so that the first portion 100 and the extension 11 and the second portion 101 and the extension 11 can be welded together well and have sufficient strength. In other embodiments, the three also can be through other forms realization fixed connection in proper order, like forms such as riveting, bolted connection, the utility model discloses do not limit to this, can set up according to actual need, as long as can ensure between the three in proper order reliable and stable link together can.
In addition, the utility model discloses do not restrict yet the position that the extension set up, as long as can make the forward extension distance extension of preceding girder can. Specifically, in the present embodiment, a first connection point of the extension portion 11 and the first portion 100 is an end of the original reach L, and a distance between the first connection point and a second connection point of the extension portion 11 and the second portion 101 is the extended reach W.
That is, the second portion 101 is cut off from the front side member 10 at the end of the original reach L, and then one end of the extension 11 is fixedly connected to the end of the original reach L by welding, and the first connection is formed where the two are butted. And welding the second part 101 at the other end of the extension part 11, wherein the second part 101 is butted with the extension part 11 to form a second connection part. The distance between the first connection and the second connection is the length of the extension 11, i.e., the forward extension W of the front frame 10. By arranging the extension part 11 at the tail end of the original forward extension distance L, the stress condition of the front girder 10 can be reasonably distributed, so that the front girder 10 can better bear the trolley to walk.
Further, in order to enhance the connection strength between the extension 11 and the first portion 100 or the second portion 101, a connection portion 12 is provided between the first portion 100 or the second portion 101 and the extension 11. That is, the connection portion 12 may be disposed between the first portion 100 and the extension portion 11, between the second portion 101 and the extension portion 11, or between the first portion 100 and the extension portion 11 and between the second portion 101 and the extension portion 11, so as to enhance the connection strength between each two and improve the strength of the whole front girder 10.
Specifically, in this embodiment, the connection portion 12 may be disposed between the first portion 100 and the extension portion 11, the connection portion 12 includes a support pillar 120, a first pull rod 121, and a second pull rod 122, the support pillar 120 is disposed at one end of the first portion 100 close to the extension portion 11, one end of the first pull rod 121 is connected to the first portion 100, the other end is connected to the upper end of the support pillar 120, one end of the second pull rod 122 is connected to the upper end of the support pillar 120, and the other end is connected to the extension portion 11.
That is, the first portion, the first tie rod 121, the second tie rod 122 and the extension portion 11 together form a triangle, so that a triangular support is realized, the support pillar 120 is arranged along the height direction of the front girder (as shown in the Z direction in fig. 1, 3 and 4), the first tie rod 121 and the second tie rod 122 can be well supported to support the first portion 100 and the extension portion 11 of the front girder 10, and the connection strength between the first portion 100 and the extension portion 11 is increased.
Specifically, in the present embodiment, the connecting ear plates 13 are disposed between the first pull rod 121 and the first portion 100, between the second pull rod 122 and the extending portion 11, and between the first pull rod 121 and the supporting upright 120, and between the second pull rod 122 and the supporting upright 120. By providing the connecting ear plate 13, the two ends of the first pull rod 121 can be conveniently connected and disassembled with the first portion 100 and the supporting upright 120 through the pin shafts, and the two ends of the second pull rod 122 can be conveniently connected and disassembled with the supporting upright 120 and the extending portion through the pin shafts.
Specifically, in this embodiment, the upper portion of the support pillar 120 is provided with a first double-ear plate 123 and a second double-ear plate 124, the first double-ear plate 123 is connected to the first rod 121, and the second double-ear plate 124 is connected to the second rod 122. First binaural board 123 and second binaural board 124 are symmetrically disposed on upper portion of support column 120, and are respectively connected to first pull rod 121 and second pull rod 122, so that not only can the stress transmitted by first pull rod 121 and second pull rod 122 be uniformly borne, but also the first pull rod 121, second pull rod 122 and support column 120 can be conveniently disassembled.
Further, in order to avoid the first and second double lug plates 123 and 124 from being affected by stress and causing cracks or fissures, in the present embodiment, stress release hole sealing plates 127 are disposed at the junctions of the first and second double lug plates 123 and 124 and the support columns 120. Through setting up stress release hole shrouding 127, can make the stress of first binaural board 123 and second binaural board 124 obtain fine release, promote the service strength of first binaural board 123 and second binaural board 124, avoid appearing fracture or crackle, ensure the performance and the joint strength of connecting portion 12.
Specifically, in this embodiment, a cover plate 125 is disposed at the upper end of the support pillar 120, and a lifting ear plate 126 is disposed on the cover plate 125. Through set up apron 125 in the upper end of support post 120, can avoid in objects such as rainwater get into the support post, cause the corruption to the support post, simultaneously, set up hoist and mount otic placode 126 on the apron, be convenient for support post's installation and transportation.
Specifically, in the present embodiment, the lower end of the support column 120 is provided with a support plate 15, and the support plate 15 is used for fixedly arranging the support column 120 on the first portion 100. That is, the support post 120 is disposed on the first portion 100 through the support plate 15, a slit is formed at the lower end of the support post 120, so that the support plate 15 is inserted into the support post 120 through the slit, and the support post 120 and the support plate 15 are welded together to achieve a fixed connection therebetween. Support plate 15 may be fixedly welded to first portion 100 prior to mounting support column 120 to support plate 15, and support column 120 may be connected to support plate 15 to facilitate mounting support column 120.
In addition, in order to increase the mounting strength of the support columns on the first portion, as shown in fig. 3-4, in the present embodiment, the first portion 100 is provided with the cross beam 14, and the support plate 15 is provided on the cross beam 14. The cross beam 14 is arranged along the width direction (as shown in the Y direction in fig. 4) of the front girder 10, the support plates 15 are arranged at both ends of the cross beam 14, that is, the support columns 120 are arranged at both ends of the cross beam 14, and the connecting portions 12 are arranged at both ends of the cross beam 14 in the width direction of the front girder 10, so that the connection strength between the extension portion 11 and the first portion 100 or the second portion 101 can be well enhanced.
That is, by providing the support plate 15 on the cross member 14, the mounting strength of the support plate 15 can be enhanced well, and further, the mounting strength of the support columns 120 is improved, and the mounting of the support plate 15 and the support columns 120 is facilitated. Meanwhile, the lower end of the support column 120 is provided with a cylindrical sealing plate 128 for sealing the opening between the lower end of the support column 120 and the support plate 15.
As above, be applied to the technical scheme of the utility model, the utility model provides a pair of bank bridge has set up the extension through in the front between the first portion of girder and the second portion and has made the length of preceding girder to increase. The first part or the second part is connected with the extension part through the connecting part, a stable triangular supporting structure is formed together, the connecting strength between the first part and the second part is enhanced, the structural strength of the whole front girder is improved, and the extension part can well meet the use safety requirement of the front girder.
To sum up, the above embodiments provided by the present invention are merely illustrative of the principles and effects of the present invention, and are not intended to limit the present invention. Modifications and variations can be made to the above-described embodiments by those skilled in the art without departing from the spirit and scope of the present invention. Accordingly, it is intended that all equivalent modifications or changes which may be made by those skilled in the art without departing from the spirit and technical spirit of the present invention be covered by the claims of the present invention.

Claims (10)

1. The utility model provides a shore bridge, includes preceding girder, its characterized in that, preceding girder includes first portion, second portion and locates extension between first portion and the second portion, the both ends of extension respectively with first portion and second portion fixed connection, first portion, and/or, the second portion with be equipped with connecting portion between the extension, connecting portion are used for strengthening first portion, and/or, the second portion with joint strength between the extension.
2. The shore bridge of claim 1 wherein said first connection of said extension to said first portion is at the end of an original reach and the distance between said first connection and said second connection of said extension to said second portion is an extended reach.
3. The shore bridge of claim 1 or 2, wherein said connection portion comprises a support post, a first tie bar and a second tie bar, said support post being disposed at an end of said first portion adjacent to said extension portion, said first tie bar having one end connected to said first portion and the other end connected to an upper end of said support post, said second tie bar having one end connected to an upper end of said support post and the other end connected to said extension portion.
4. The shore bridge of claim 3 wherein connecting lugs are provided between said first tie bar and said first portion, between said second tie bar and said extension, and between said first tie bar and said second tie bar and said support columns.
5. The shore bridge of claim 3 wherein said support column has a first double ear plate and a second double ear plate disposed on an upper portion thereof, said first double ear plate being connected to said first tie bar and said second double ear plate being connected to said second tie bar.
6. The shore bridge of claim 5 wherein a stress relief aperture closure is provided at the junction of said first and second binaural panels and said support columns.
7. The shore bridge of claim 5 wherein said support columns have cover plates at their upper ends, said cover plates having lifting lugs.
8. The shore bridge of claim 5 wherein said support columns have support plates at their lower ends for fixedly positioning said support columns on said first portion.
9. The shore bridge of claim 8 wherein said first portion has a cross member and said support plate is disposed on said cross member.
10. The shore bridge of claim 8 wherein said support columns have cylindrical closure plates at their lower ends for closing the openings between the lower ends of said support columns and said support plates.
CN202021503974.9U 2020-07-27 2020-07-27 Shore bridge Active CN212559145U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021503974.9U CN212559145U (en) 2020-07-27 2020-07-27 Shore bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021503974.9U CN212559145U (en) 2020-07-27 2020-07-27 Shore bridge

Publications (1)

Publication Number Publication Date
CN212559145U true CN212559145U (en) 2021-02-19

Family

ID=74632234

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021503974.9U Active CN212559145U (en) 2020-07-27 2020-07-27 Shore bridge

Country Status (1)

Country Link
CN (1) CN212559145U (en)

Similar Documents

Publication Publication Date Title
CN104947850B (en) Roof system spindle-shaped truss and construction method thereof
CN103643812B (en) Prefabricated cabin cabin push up splicing construction and using the structure and cabin formula prefabricated cabin
CN105780989B (en) A kind of twin beams building cover structure
CN201092281Y (en) Concrete stirring transportation tank vehicle
CN101723237B (en) Novel soft rope strut type hanger for box girder
CN212559145U (en) Shore bridge
CN103466472A (en) Auxiliary arm system and crawler crane
CN105060142A (en) Integrally mounted and transported luffing fly jib of crawler crane
CN217810564U (en) Asymmetric splicing system of prefabricated box girder multi-section cantilever
CN111717793A (en) Shore bridge and method for prolonging front girder of same
CN105421251A (en) Plate-girder jacking support mechanism and plate-girder jacking support tool
CN215592333U (en) Multi-adaptability double-guide-beam bridge crane lifting appliance device with adjustable hole pitch
CN202499652U (en) Rotary table seat body for crane and crane
CN205295915U (en) Wave form steel web nose girder
US20200307969A1 (en) Telescopic boom and mobile crane
CN204661179U (en) Jib structure, boom system and hoisting crane
CN217555620U (en) Girder structure reinforcing back bow before bridge crane
CN220432085U (en) Main beam head structure of metallurgical crane
CN217102826U (en) Boom head, boom and working machine
CN105088962A (en) Integrated hoisting method for corrugated steel web part
CN203212248U (en) Double-box type telescopic arm structure
CN218174436U (en) Novel auxiliary beam of lorry-mounted crane truck
CN216839022U (en) Bridge construction operation platform
CN212198225U (en) Gantry crane
CN212426680U (en) Sectional type stride steel case roof beam greatly