CN212527593U - Installation tool for locking nut of high-speed shafting of wind power gear box - Google Patents

Installation tool for locking nut of high-speed shafting of wind power gear box Download PDF

Info

Publication number
CN212527593U
CN212527593U CN202020810754.4U CN202020810754U CN212527593U CN 212527593 U CN212527593 U CN 212527593U CN 202020810754 U CN202020810754 U CN 202020810754U CN 212527593 U CN212527593 U CN 212527593U
Authority
CN
China
Prior art keywords
tool
circular plate
sleeve
shafting
locking nut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020810754.4U
Other languages
Chinese (zh)
Inventor
黄正廷
王健
傅旸
吴伟强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Avis Transmission Technology Co ltd
Original Assignee
Nanjing Avis Transmission Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Avis Transmission Technology Co ltd filed Critical Nanjing Avis Transmission Technology Co ltd
Priority to CN202020810754.4U priority Critical patent/CN212527593U/en
Application granted granted Critical
Publication of CN212527593U publication Critical patent/CN212527593U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Wind Motors (AREA)

Abstract

The utility model provides a wind-powered electricity generation gear box high speed shafting lock nut's installation frock, its characterized in that: the high-speed shafting is vertically arranged and fixedly arranged on the ground track; the end surface of the blade end of the high-speed shafting faces the lower shafting part and is arranged below the locking nut; the tightening tool main body is a sleeve, a plurality of downward extending sheet-shaped bulges are uniformly distributed on the circumference of the lower end surface of the sleeve and used as clamping jaws, a tool circular plate is welded on the upper end surface of the sleeve, and a screw hole is formed in the end surface of the tool circular plate; one side of a clamping jaw of the tightening tool is sleeved into a clamping groove in the excircle of the locking nut, a tool bolt is screwed into a screw hole formed in the end face of the tool circular plate and is fixedly arranged on the tool circular plate, and a torque wrench and a bolt sleeve are arranged on the tool bolt. The utility model relates to a simple structure, the assembly is reliable, the easy operation and safe wind-powered electricity generation gear box high speed shafting lock nut's installation frock.

Description

Installation tool for locking nut of high-speed shafting of wind power gear box
Technical Field
The utility model relates to a wind-powered electricity generation gear box is with installation frock, specifically speaking are an installation frock that is used for high-speed shafting lock nut of wind-powered electricity generation gear box.
Background
A high-speed shaft system of a wind power gearbox is locked with shaft system parts by using locking nuts, in the prior art, in the installation process, the nuts are manually screwed, and then locking nuts excircle are firmly hammered by using tools such as nylon bar or copper bar, and the nuts are hammered until threads are screwed tightly, so that the shaft system parts are locked.
The prior art has the following disadvantages:
1. the self structure of the locking nut is limited, and the torque cannot be controlled directly by using a torque wrench;
2. the tightening force is also dependent on manpower;
3. the force applied by each person is inconsistent, and the magnitude of the applied tightening force cannot be controlled;
4. the operation process is dangerous due to hard smashing by manpower.
SUMMERY OF THE UTILITY MODEL
The utility model provides an installation frock of high-speed shafting lock nut of wind-powered electricity generation gear box, its purpose is solved prior art's shortcoming, provides a simple structure, and the assembly is reliable, easy operation and safe installation frock.
The utility model provides a technical scheme that its technical problem adopted is:
the utility model provides an installation frock of wind-powered electricity generation gear box high speed shafting lock nut which characterized in that:
the high-speed shafting is vertically arranged and fixedly arranged on the ground track; the end surface of the blade end of the high-speed shafting faces the lower shafting part and is arranged below the locking nut;
the tightening tool main body is a sleeve, a plurality of downward extending sheet-shaped bulges are uniformly distributed on the circumference of the lower end surface of the sleeve and used as clamping jaws, a tool circular plate is welded on the upper end surface of the sleeve, and a screw hole is formed in the end surface of the tool circular plate;
one side of a clamping jaw of the tightening tool is sleeved into a clamping groove in the excircle of the locking nut, a tool bolt is screwed into a screw hole formed in the end face of the tool circular plate and is fixedly arranged on the tool circular plate, and a torque wrench and a bolt sleeve are arranged on the tool bolt.
The fixing tool is provided with a through hole, and a bolt penetrates through the through hole and is then screwed with the ground track; the fixing tool is provided with a through hole and a groove which are coaxial, the high-speed shaft system is vertically arranged, the end face of the blade end of the high-speed shaft system is arranged on the upper surface of the groove, a bolt penetrates through the through hole and then is screwed in a screw hole formed in the end face of the blade end of the high-speed shaft system, and a bearing at the blade end of the high-speed shaft system is embedded in the groove.
The fixing tool is composed of a circular plate and a plurality of fixed connecting blocks uniformly welded around the circular plate, and the bolts penetrate through holes which are screwed and connected with the ground track and are arranged on the fixed connecting blocks; the through hole and the groove of the coaxial line are arranged on the circular plate.
The excircle of the sleeve is welded with a U-shaped handle.
The utility model discloses an useful part lies in:
1. the tool is simple, the structure is simple, and the processing and the manufacturing are easy;
2. the existing conditions can be fully utilized, and the operation is convenient;
3. the pre-tightening force can be effectively controlled, and the reliability of assembly is ensured;
4. the risk brought by manual hard smashing installation is reduced, and the safety factor of field work is improved.
Drawings
The present invention will be further explained with reference to the drawings and examples.
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a top view of the fixing tool of the present invention;
fig. 3 is the utility model discloses turn round tight frock structure chart.
Detailed Description
In order to more clearly illustrate the technical solution of the present invention, the drawings used in the description will be briefly introduced, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other embodiments can be obtained according to the drawings without inventive labor.
The utility model provides an installation frock of wind-powered electricity generation gear box high speed shafting lock nut especially is applicable to 1660KW wind-powered electricity generation gear box high speed shafting lock nut's installation.
As shown in fig. 1 and 2:
the fixed tooling 1 is a welding part, the circular plate 12 and four fixed connecting blocks 11 uniformly welded around the circular plate 12 are formed, through holes 15 are formed in the fixed connecting blocks 11, and bolts 17 are used for being screwed with the ground rail 100 after penetrating through the through holes 15 so as to fix the fixed tooling 1 on the ground rail 100; the center of the circular plate 12 is provided with a through hole 13 and a groove 14 which are coaxial, the high-speed shaft system 3 is vertically arranged, the end surface of the blade end of the high-speed shaft system 3 is arranged on the upper surface of the groove 14, a bolt 16 penetrates through the through hole 13 and then is screwed in a screw hole arranged on the end surface of the blade end of the high-speed shaft system 3, and a blade end bearing 31 of the high-speed shaft system 3 is embedded in the groove 14, so that the high-speed shaft system 3 can be vertically arranged and fixedly arranged on the fixing tool 1.
As shown in fig. 1 and 3:
the tight frock 2 of turning round is for taking jaw formula sleeve, and also the main part is sleeve 20, and sleeve 20's lower terminal surface circumference equipartition has 6 downward flaky archs as jack catch 21 to at sleeve 20's up end welding frock plectane 22, the terminal surface of frock plectane 22 is opened has screw 23, and sleeve 20's excircle welding has two U type handles 24 so that carry and take.
As shown in fig. 1:
the fixing tool 1 is installed on the ground track 100, the high-speed shafting 3 is vertically placed and fixedly installed on the fixing tool 1, the locking nut 4 is upward in side, namely, the shafting part is arranged below the locking nut 4.
One side of a clamping jaw 21 of the tightening tool 2 is sleeved into a clamping groove in the outer circle of the locking nut 4, the tool bolt 5 is screwed into a screw hole 23 and is fixedly arranged on a tool circular plate 22, the torque wrench 6 and the bolt sleeve 7 are arranged on the tool bolt 5, an appropriate torque is selected, the applied pretightening force is controlled by the torque wrench 6, the tightening tool 2 is transmitted through the tool bolt 5, the clamping jaw 21 of the tightening tool 2 transmits the tightening force to the locking nut 4 through the clamping groove in the outer circle of the locking nut 4, and therefore the tightening of the locking nut 4 is achieved.
The utility model provides a frock adopts enough light spare parts to make up and assembles, utilizes the structural feature of wind-powered electricity generation gear box shafting itself, realizes lock nut 4's pretension and the size of effective control pretightning force. The high-speed shaft system 3 is fixed by utilizing the characteristics of the high-speed shaft system 3 and the actual conditions of a factory so as to prevent the locking nut 4 from being pre-tightened in the later period; according to lock nut 4 structure itself, 2 sizes of frock are screwed up in supporting design, realize torsion's switching through screwing up frock 2, and effective control pretightning force size reduces the risk that manual operation, pound etc. produced hard, improves the reliability of assembly.
The embodiments in the present description are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other. The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (4)

1. The utility model provides an installation frock of wind-powered electricity generation gear box high speed shafting lock nut which characterized in that:
the high-speed shaft system is vertically arranged and fixedly installed on the fixed tool; the end surface of the blade end of the high-speed shafting faces the lower shafting part and is arranged below the locking nut; the tightening tool main body is a sleeve, a plurality of downward extending sheet-shaped bulges are uniformly distributed on the circumference of the lower end surface of the sleeve and used as clamping jaws, a tool circular plate is welded on the upper end surface of the sleeve, and a screw hole is formed in the end surface of the tool circular plate; one side of a clamping jaw of the tightening tool is sleeved into a clamping groove in the excircle of the locking nut, a tool bolt is screwed into a screw hole formed in the end face of the tool circular plate and is fixedly arranged on the tool circular plate, and a torque wrench and a bolt sleeve are arranged on the tool bolt.
2. The mounting tool for the locking nut of the high-speed shafting of the wind power gear box, according to claim 1, is characterized in that: the fixing tool is provided with a through hole, and a bolt penetrates through the through hole and is then screwed with the ground track; the fixing tool is provided with a through hole and a groove which are coaxial, the high-speed shaft system is vertically arranged, the end face of the blade end of the high-speed shaft system is arranged on the upper surface of the groove, a bolt penetrates through the through hole and then is screwed in a screw hole formed in the end face of the blade end of the high-speed shaft system, and a bearing at the blade end of the high-speed shaft system is embedded in the groove.
3. The mounting tool for the locking nut of the high-speed shafting of the wind power gear box, according to claim 2, is characterized in that: the fixed tool is composed of a circular plate and a plurality of fixed connecting blocks uniformly welded around the circular plate, and through holes for connecting ground rails are arranged on the fixed connecting blocks in a screwed mode; the through hole and the groove of the coaxial line are arranged on the circular plate.
4. The mounting tool for the locking nut of the high-speed shafting of the wind power gear box, according to claim 1, is characterized in that: the excircle of the sleeve is welded with a U-shaped handle.
CN202020810754.4U 2020-05-15 2020-05-15 Installation tool for locking nut of high-speed shafting of wind power gear box Active CN212527593U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020810754.4U CN212527593U (en) 2020-05-15 2020-05-15 Installation tool for locking nut of high-speed shafting of wind power gear box

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020810754.4U CN212527593U (en) 2020-05-15 2020-05-15 Installation tool for locking nut of high-speed shafting of wind power gear box

Publications (1)

Publication Number Publication Date
CN212527593U true CN212527593U (en) 2021-02-12

Family

ID=74542340

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020810754.4U Active CN212527593U (en) 2020-05-15 2020-05-15 Installation tool for locking nut of high-speed shafting of wind power gear box

Country Status (1)

Country Link
CN (1) CN212527593U (en)

Similar Documents

Publication Publication Date Title
CN212527593U (en) Installation tool for locking nut of high-speed shafting of wind power gear box
CN112975814A (en) Electric tightening device for remote back bolt of power transmission line
CN208843560U (en) A kind of dedicated gripper of coal mine
CN111390803A (en) Electric installation device for nuts on foundation bolts of section steel columns
CN201405309Y (en) Synchronous screwing device for connecting main shaft tightening ring with screw bolt
CN101898299A (en) Synchronous screwing device of connecting bolt of expanded ring of spindle and installation method thereof
CN211992708U (en) Electric installation device for nuts on foundation bolts of section steel columns
CN216328068U (en) Auxiliary tool for preventing following rotation of single bolt tightening nut
CN210178852U (en) Gear labor-saving lead screw
CN211579400U (en) High-voltage transmission pole tower line feeding device
CN211145074U (en) Roughening device suitable for foundation bolt
CN212044421U (en) Steel rail fastener bolt spanner
CN203056124U (en) Multifunctional one-way cable clamp
CN220869970U (en) Flower basket bolt
CN2448911Y (en) Back-off device for sucker rod
CN201874927U (en) Fixing clamp for electrical power engineering
CN203266564U (en) Tower crane bolt tightening tool
CN217842328U (en) Locking device of wind generating set main bearing locking nut
CN221186307U (en) Large-torque electric wrench
CN210693260U (en) Heavy-load single-sheet insulator replacement tool
CN220218359U (en) Pumping unit balance weight nut loosening and unloading device
CN218556908U (en) Chain belt type electric wrench
CN210163010U (en) Power battery module stone tongs
CN214979546U (en) Efficient turnover tool for connecting plate sub-assembly in gearbox
CN219599341U (en) Ground potential fastening tension-resistant tower drainage bolt combination tool for high-voltage transmission line

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant