CN212507112U - Roof parapet waterproof construction - Google Patents

Roof parapet waterproof construction Download PDF

Info

Publication number
CN212507112U
CN212507112U CN202020945828.5U CN202020945828U CN212507112U CN 212507112 U CN212507112 U CN 212507112U CN 202020945828 U CN202020945828 U CN 202020945828U CN 212507112 U CN212507112 U CN 212507112U
Authority
CN
China
Prior art keywords
parapet
cast
roof
roofing
waterproof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020945828.5U
Other languages
Chinese (zh)
Inventor
彭振峰
何强龙
郑成梁
陈业伟
栗运飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
China Construction Fourth Engineering Bureau Construction and Development Co Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
China Construction Fourth Engineering Bureau Construction and Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd, China Construction Fourth Engineering Bureau Construction and Development Co Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN202020945828.5U priority Critical patent/CN212507112U/en
Application granted granted Critical
Publication of CN212507112U publication Critical patent/CN212507112U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to the technical field of building, in particular to a roof parapet waterproof structure, which comprises a cast-in-place coping arranged on the parapet, wherein the cast-in-place coping protrudes out of the parapet towards a roof side, a prefabricated concrete fillet is arranged at the joint of the parapet and the roof, a reentrant corner part formed by the parapet and the roof is provided with a waterproof coiled material, the waterproof coiled material is upturned to the lower edge of the cast-in-place coping and is fixed on the parapet through a cement nail and a galvanized gasket, and the upper end of the waterproof coiled material is caulked by asphalt cement paste; the utility model provides a roofing parapet waterproof construction is convenient, practices thrift the cost, and it can effectively prevent the parapet seepage, strengthens parapet reentrant corner impervious ability, avoids waterproof layer infiltration and roofing waterproof layer to overflow, suitable further popularization and application.

Description

Roof parapet waterproof construction
Technical Field
The utility model relates to a building technical field specifically is a roofing parapet waterproof construction.
Background
Parapet (also known as granddaughter wall) is a low wall around the roof of a building, and has the main functions of maintenance safety. According to the national building code, the height of the parapet wall on the roof of the upper part of the house is generally not less than 1.1m and not more than 1.5m at most.
In the current building construction process, due to the self construction characteristics of a building, water is easy to accumulate at a right-angle structure formed by a roof and a parapet, and then the phenomena of water seepage and water leakage at the top end of the building are easy to occur, so that the normal use of the building is influenced.
SUMMERY OF THE UTILITY MODEL
In order to solve the above mentioned problems, the utility model provides a waterproof structure of roofing parapet.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a roofing parapet waterproof construction, is including setting up the cast-in-place coping on the parapet, cast-in-place coping is towards roofing side protrusion parapet, the handing-over department of parapet and roofing sets up a prefabricated concrete radius angle, the reentrant corner position that parapet and roofing formed is equipped with a waterproofing membrane, waterproofing membrane turns over on to the lower edge of cast-in-place coping and is fixed in the parapet through cement nail and galvanized gasket, the asphalt cement caulking is used to the waterproofing membrane upper end.
Preferably, the height from the cast-in-place coping to the roof is 500mm, and the cast-in-place coping protrudes out of the parapet wall by 40 mm.
Preferably, the waterproof coiled material is turned up by 500 mm.
Preferably, the cement nails are horizontally nailed at the tail end of the waterproof coiled material, and the distance between the adjacent cement nails is 500 mm.
Preferably, the lower edge of the cast-in-place coping facing the roof side is provided with an inclined notch.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model provides a roofing parapet waterproof construction is convenient, practices thrift the cost, and it can effectively prevent the parapet seepage, strengthens parapet reentrant corner impervious ability, avoids waterproof layer infiltration and roofing waterproof layer to overflow, suitable further popularization and application.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is an enlarged view of the a portion of the present invention.
In the drawings, the reference numerals denote the following components:
parapet-1; carrying out cast-in-place coping-2; concrete fillet-3; waterproof coiled material-4; galvanized gasket-5; cement nail-6; notch-7; and 8, a roof.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.
Referring to fig. 1-2, a roof parapet waterproof structure includes a cast-in-place press top 2 disposed on a parapet 1, wherein the cast-in-place press top 2 has a thickness of 100mm, the height from the cast-in-place press top 2 to a roof 8 is 500mm, the cast-in-place press top 2 protrudes out of the parapet 40mm toward the roof 8, a 100 x 100mm prefabricated concrete fillet 3 is disposed at a junction of the parapet 1 and the roof 8, and the 100 x 100mm prefabricated concrete fillet 3 is disposed to prevent water accumulation at the junction of the parapet 1 and the roof 8; a waterproof roll 4 is arranged at an internal corner part formed by the parapet wall 1 and the roof 8 and used for further preventing rainwater from seeping downwards, the waterproof roll 4 is turned upwards by 500mm to the lower edge of the cast-in-place coping 2 and is fixed on the parapet wall 1 through a cement nail 6 and a galvanized gasket 5, the waterproof roll 4 is turned upwards by 500mm to the lower edge of the cast-in-place coping 2, the cast-in-place coping 2 can shield the upper end of the waterproof roll 4, and rainwater is prevented from flowing into the waterproof roll 4 from the upper end to cause water seepage of the waterproof layer and overflow of the waterproof layer of the roof; and the upper end of the waterproof coiled material 4 is caulked by asphalt ointment, so that the sealing property of the waterproof coiled material 4 is further improved.
Further, the cement nails 6 are horizontally nailed to the tail end of the waterproof roll 4, and the distance between the adjacent cement nails 6 is 500 mm.
Further, the lower edge of the cast-in-place coping 2 facing the roof 8 side is provided with an inclined notch 7; the upper end of the waterproof coiled material 4 extends into the gap 7, and asphalt factice is filled into the gap 7 to caulk the upper port of the waterproof coiled material 4; this kind of setting makes 4 upper ends of waterproofing membrane can stretch into to breach 7 in, can effectively prevent the condition that 4 upper ends of waterproofing membrane intake after filling into the asphalt factice, and the caulking of the asphalt factice of being convenient for of setting up of breach 7 simultaneously only needs with the asphalt factice directly squeeze into in breach 7 can.
In the description herein, references to the description of "one embodiment," "an example," "a specific example," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The preferred embodiments of the present invention disclosed above are intended only to help illustrate the present invention. The preferred embodiments are not intended to be exhaustive or to limit the invention to the precise embodiments disclosed. Obviously, many modifications and variations are possible in light of the above teaching. The embodiments were chosen and described in order to best explain the principles of the invention and its practical applications, to thereby enable others skilled in the art to best understand the invention for and utilize the invention. The present invention is limited only by the claims and their full scope and equivalents.

Claims (5)

1. The utility model provides a roofing parapet waterproof construction, its characterized in that, is including setting up cast-in-place overhead (2) on parapet (1), cast-in-place overhead (2) is towards roofing (8) side protrusion parapet (1), the handing-over department of parapet (1) and roofing (8) sets up a prefabricated concrete radius angle (3), the reentrant corner position that parapet (1) and roofing (8) formed is equipped with one waterproofing membrane (4), waterproofing membrane (4) upturn is fixed in parapet (1) to the lower edge of cast-in-place overhead (2) and through cement nail (6) and zinc-plated gasket (5), asphalt cement caulking is used to waterproofing membrane (4) upper end.
2. A water-proof construction for parapet roofing as claimed in claim 1, characterised in that the height of the cast-in-place coping (2) to the roof (8) is 500mm and the cast-in-place coping (2) protrudes the parapet wall by 40 mm.
3. A roofing parapet waterproofing construction according to claim 2, characterized in that the waterproofing membrane (4) is turned up 500 mm.
4. A waterproof structure for parapet of roof as claimed in claim 1, wherein said cement nails (6) are horizontally nailed to the end of the waterproof roll (4), and the interval between the adjacent cement nails (6) is 500 mm.
5. A water-proof structure for parapet roof as claimed in any one of claims 1 to 4, characterised in that the lower edge of the cast-in-place coping (2) facing the roof (8) is provided with a slanting notch (7).
CN202020945828.5U 2020-05-29 2020-05-29 Roof parapet waterproof construction Active CN212507112U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020945828.5U CN212507112U (en) 2020-05-29 2020-05-29 Roof parapet waterproof construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020945828.5U CN212507112U (en) 2020-05-29 2020-05-29 Roof parapet waterproof construction

Publications (1)

Publication Number Publication Date
CN212507112U true CN212507112U (en) 2021-02-09

Family

ID=74391808

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020945828.5U Active CN212507112U (en) 2020-05-29 2020-05-29 Roof parapet waterproof construction

Country Status (1)

Country Link
CN (1) CN212507112U (en)

Similar Documents

Publication Publication Date Title
CN208280470U (en) A kind of parapet of roofing waterproof construction
CN209413154U (en) Pitched roof assembled eave structure
CN102677832A (en) Roof deformation joint cornice structure for water resistance and construction method for roof deformation joint cornice structure
CN113653242B (en) Stepped deformation joint engagement structure for high-low roof
CN212507112U (en) Roof parapet waterproof construction
CN211850449U (en) Parapet binding off waterproof construction
CN210508097U (en) Novel roof deformation joint structure
CN215858659U (en) Waterproof parapet inner gutter structure
CN212562113U (en) Steel construction roof daylighting node structure
CN212562218U (en) Roof deformation joint leakage-proof structure
CN203613698U (en) Roof for mobile house
CN218643693U (en) High-efficient waterproof construction of roofing parapet
CN207160433U (en) Roof structure applied to sponge urban construction
CN214941766U (en) Waterproof double-T-plate roof
CN212561944U (en) Leakage-proof structure for junction of roof and outer wall
CN217204967U (en) Building roof parapet outsourcing waterproof construction and building
CN208280332U (en) Steel structural roof and block wall intersection waterproof construction system
CN218541213U (en) Roof deformation joint waterproof construction
CN211597410U (en) Roof subsiding crack parapet waterproof construction
CN216276511U (en) Roofing equipment foundation and waterproof structure thereof
CN215054662U (en) Gutter flashing connection node structure used in parapet wall
CN216429171U (en) Coal conveying trestle roof board and coal conveying gallery roof connection structure of thermal power plant
CN217537605U (en) Waterproof roofing connected node structure of building is worn to pipeline
CN216007576U (en) Block tile roof gable eave structure
CN217711415U (en) Prefabricated drainage system of prefabricated building roof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant