CN212455753U - Underground pipeline settlement monitoring point layout device - Google Patents

Underground pipeline settlement monitoring point layout device Download PDF

Info

Publication number
CN212455753U
CN212455753U CN202021425098.2U CN202021425098U CN212455753U CN 212455753 U CN212455753 U CN 212455753U CN 202021425098 U CN202021425098 U CN 202021425098U CN 212455753 U CN212455753 U CN 212455753U
Authority
CN
China
Prior art keywords
monitoring
pipeline
connecting rod
monitoring point
point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021425098.2U
Other languages
Chinese (zh)
Inventor
李支彬
吕金辉
马继山
栗红宇
张磊
韩易
李金宁
杨志军
杨帆
陈泽祺
王守春
刘畅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Geological Foundation Engineering Co
Tianjin Institute Of Geological Engineering Exploration
Original Assignee
Tianjin Geological Foundation Engineering Co
Tianjin Institute Of Geological Engineering Exploration
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Geological Foundation Engineering Co, Tianjin Institute Of Geological Engineering Exploration filed Critical Tianjin Geological Foundation Engineering Co
Priority to CN202021425098.2U priority Critical patent/CN212455753U/en
Application granted granted Critical
Publication of CN212455753U publication Critical patent/CN212455753U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Geophysics And Detection Of Objects (AREA)

Abstract

The utility model relates to a laying device of settlement monitoring points of underground pipelines, which comprises a monitoring point pre-embedding device and a ground surface monitoring connecting rod, wherein the monitoring point pre-embedding device consists of a hoop, a fixing nut and a locking pin shaft; after earth covering and backfilling of the underground pipeline, carrying out measuring point lofting according to the initial coordinates of the embedded device, measuring the elevation of the lofting point, and calculating the embedded depth of the embedded part; drilling holes at the position of the lofting point, finding a monitoring point pre-embedding device, and installing a ground surface monitoring connecting rod on a pre-embedding device fixing nut. The pipeline settlement monitoring device is simple in structure, convenient to manufacture, install and use, free of influence of later-stage construction, not prone to damage of monitoring points and capable of greatly improving the later-stage pipeline settlement monitoring survival rate. The method is suitable for settlement monitoring of underground pipelines, in particular to the arrangement of settlement monitoring measuring points of peripheral moving pipelines in foundation pit monitoring projects.

Description

Underground pipeline settlement monitoring point layout device
Technical Field
The utility model relates to an underground pipeline settlement monitoring, in particular to laying device of underground pipeline settlement monitoring point.
Background
The underground pipeline is influenced by precipitation, construction, underground water level change and the like in the long-term operation process, and the soil body around the pipeline can generate uneven settlement change, so that the underground pipeline can also generate settlement of different degrees, and the safety of the underground pipeline is seriously influenced. Therefore, after the installation and construction of the underground pipeline are finished, the settlement change condition of the underground pipeline needs to be monitored periodically.
The settlement monitoring is needed to be carried out on the underground pipelines close to the periphery in the foundation pit excavation construction, the influence of the foundation pit construction on the pipeline settlement is mastered in time, effective safety measures are taken, and the safety of the peripheral pipelines in the construction is ensured.
There are generally two ways to monitor the settlement of underground pipelines: indirect monitoring points and direct monitoring points. The indirect monitoring point is a pipeline monitoring point which is formed by embedding a steel bar in a drill hole above or on the side of the pipeline and is equal to an earth surface monitoring point, and as the indirect monitoring point is not directly connected with the pipeline, the monitoring data cannot truly reflect the sedimentation state of the pipeline, and misguidance can be caused to later decision; the direct monitoring points are directly connected with the pipeline in a hoop mode, monitoring data can accurately reflect the real settlement state of the pipeline, but the existing arrangement method of the direct monitoring points is often damaged in the later backfilling construction process of the pipeline, and the safety monitoring of the pipeline in the later period is seriously influenced.
Disclosure of Invention
In view of the needs of practice, the utility model provides a laying device of pipeline settlement monitoring point, its simple installation, not influenced by later stage construction, convenient to use is reliable, raises the efficiency when carrying out pipeline settlement monitoring. The concrete technical scheme is, a laying device of pipeline settlement monitoring point, including monitoring point pre-buried device, earth's surface monitoring connecting rod, wherein monitoring point pre-buried device comprises staple bolt, fixation nut, locking pin axle, its characterized in that: a nut is welded and fixed in the middle of each hoop, the nut is matched with the earth surface monitoring connecting rod, the earth surface monitoring connecting rod is screwed in the nut, a locking pin shaft is arranged on the hoop, and the hoop is clamped on the outer surface of the underground pipeline and locked by the locking pin shaft.
The earth's surface monitoring connecting rod be the steel material, one end has the screw thread to with the nut phase-match on the monitoring point pre-buried device, the other end is smooth sphere, is convenient for place the levelling rod.
The beneficial effects of the utility model are that, monitoring point pre-buried device simple structure, preparation, installation and application are convenient, install pre-buried device during pipeline installation construction, do not receive later stage construction influence, subside the monitoring point and be difficult to receive destruction, can promote later stage pipeline settlement monitoring survival rate by a wide margin.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Detailed Description
An embodiment of the present invention will be described below with reference to the accompanying drawings.
As shown in fig. 1, a laying device of pipeline settlement monitoring point, including monitoring point pre-buried device 2, earth's surface monitoring connecting rod 6, wherein monitoring point pre-buried device 2 comprises staple bolt 3, fixation nut 4, lock round pin axle 5, every 3 middle welded fastening of staple bolt have a nut 4, nut 4 matches with earth's surface monitoring connecting rod 6, 6 spiro unions of earth's surface monitoring connecting rod are in nut 4, there is lock round pin axle 5 on the staple bolt 3, staple bolt 3 card package is at pipeline 1 surface underground, with lock round pin axle 5 locking.
The earth's surface monitoring connecting rod 6 is the steel material, and one end has the screw thread to with the nut 4 phase-match on the monitoring point pre-buried device 2, the other end is smooth sphere, is convenient for place the levelling rod.
Examples
Method for laying tap water pipe diameter of 600mm and pipe top buried depth of 2m
During underground construction, the monitoring point pre-embedding device 2 is arranged on an underground pipeline 1 and locked by a locking pin shaft 5, so that a fixing nut 4 is upward, and the size of the fixing nut 4 is 20mm in outer diameter;
measuring the coordinates and the elevation of the center position of the nut 4 on the monitoring point pre-embedding device 2 by adopting a total station coordinate method (300000.000,100000.000, 3.000);
thirdly, after earth covering and backfilling of the underground pipeline, carrying out measuring point lofting according to initial coordinates (300000.000,100000.000) of nuts 4 on the monitoring point pre-embedding device 2, measuring the elevation 5.03 of lofting points, and calculating the embedded part embedding depth h =5.03-3=2.03 m;
fourthly, drilling a hole (the outer diameter of the rhinestone is 12 cm) at the lofting point position (300000.002,100000.003, 5.03) by adopting a rhinestone, wherein the drilling depth is 2.03-0.1=1.93m, and the residual 0.1m is washed by high-pressure water to find the monitoring point embedded device 2;
and (V) mounting a ground surface monitoring connecting rod 6 on a nut 4 on the monitoring point embedding device 2, wherein the length of the ground surface monitoring connecting rod 6 is 1.98m, the diameter of the ground surface monitoring connecting rod is 20mm, placing a PVC protective cylinder with the outer diameter of 12cm in a drilling hole, backfilling fine sand in the protective cylinder to the depth of 1.96m, then matching a protective cover, and finishing the arrangement of direct measuring points of the pipeline, wherein the top space of the ground surface monitoring connecting rod 6 needs to meet the requirement of placing a leveling rod as a standard, and the space is 0.03 m.
The foregoing is a further description of the invention and is not intended to limit the invention to the particular forms disclosed. To the technical field of the utility model belongs to, do not deviate from the utility model discloses the various changes and the modification of going on under the prerequisite of thinking, all should regard as the utility model discloses a protection scope.

Claims (2)

1. The utility model provides a laying device of pipeline settlement monitoring point, includes monitoring point pre-buried device (2), earth's surface monitoring connecting rod (6), wherein monitoring point pre-buried device (2) comprise staple bolt (3), fixation nut (4), lock pin axle (5), its characterized in that: a nut (4) is welded and fixed in the middle of each hoop (3), the nut (4) is matched with the earth surface monitoring connecting rod (6), the earth surface monitoring connecting rod (6) is screwed in the nut (4), a locking pin shaft (5) is arranged on the hoop (3), and the hoop (3) is clamped and wrapped on the outer surface of the underground pipeline (1) and locked by the locking pin shaft (5).
2. The arrangement device of the underground pipeline settlement monitoring points as claimed in claim 1, wherein: the earth's surface monitoring connecting rod (6) be the steel material, one end has the screw thread to with nut (4) phase-match on the pre-buried device of monitoring point (2), the other end is smooth sphere, is convenient for place the levelling rod.
CN202021425098.2U 2020-07-20 2020-07-20 Underground pipeline settlement monitoring point layout device Expired - Fee Related CN212455753U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021425098.2U CN212455753U (en) 2020-07-20 2020-07-20 Underground pipeline settlement monitoring point layout device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021425098.2U CN212455753U (en) 2020-07-20 2020-07-20 Underground pipeline settlement monitoring point layout device

Publications (1)

Publication Number Publication Date
CN212455753U true CN212455753U (en) 2021-02-02

Family

ID=74484700

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021425098.2U Expired - Fee Related CN212455753U (en) 2020-07-20 2020-07-20 Underground pipeline settlement monitoring point layout device

Country Status (1)

Country Link
CN (1) CN212455753U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111795211A (en) * 2020-07-20 2020-10-20 天津市地质工程勘察院 Laying device and method for underground pipeline settlement monitoring points

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111795211A (en) * 2020-07-20 2020-10-20 天津市地质工程勘察院 Laying device and method for underground pipeline settlement monitoring points
CN111795211B (en) * 2020-07-20 2024-04-05 天津市地质工程勘察院 Laying method of underground pipeline settlement monitoring points

Similar Documents

Publication Publication Date Title
CN111795211B (en) Laying method of underground pipeline settlement monitoring points
CN103523411B (en) Horizontal buried oil storage tank and installation and construction method of matched device pipeline thereof
CN201109914Y (en) Apparatus for monitoring sedimentation of soft soil foundation
CN203824876U (en) Experiment device for simulating underground water percolation
CN212455753U (en) Underground pipeline settlement monitoring point layout device
CN110631560A (en) Underground excavation interval monitoring and measuring method for subway station in dense building area
CN103290836A (en) Vacuum decompression compacting and consolidating construction method for soft foundation treatment
CN105822830A (en) In-situ suspension protection construction method of high-pressure gas pipe longitudinally spanning over foundation pit
CN105201000A (en) Wide foundation pit precipitation method capable of remotely monitoring
CN105804041A (en) Large-area ultra-soft foundation settlement monitoring device and method
CN102561293A (en) Water-soil pressure test method for soft-soil deep foundation pits
CN105220719A (en) Deep Thick Soft Ground Area bridge struction pile method for correcting error
CN204214437U (en) Profundal zone surface subsidence monitoring device
CN109443310A (en) A kind of subgrade settlement automated watch-keeping facility and construction technology
CN106353482A (en) Testing system and testing method for disturbance of tunnel construction on side soil body
CN208476230U (en) Shallow deformation monitoring devices of soil landslide
CN104533289B (en) Overhead transmission line grounded screen non-excavating construction method
CN109752763A (en) A kind of fixed device of unpolarizable electrode and its fixed application method
CN114812498A (en) Roadbed filling settlement observation rod height-connection anti-rolling structure and method
CN108489814B (en) Coefficient of static lateral soil pressure K 0 In-situ testing device and testing method
CN103291724A (en) Adjusting nut for roadway surrounding rock convergence and deformation monitoring and using method thereof
CN209055104U (en) A kind of subgrade settlement automated watch-keeping facility
CN208998775U (en) A kind of pipe settlement deformation monitoring device
CN206681045U (en) A variety of monitoring facilities apertures universal protection device
CN203116746U (en) Central standard plate device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210202

Termination date: 20210720

CF01 Termination of patent right due to non-payment of annual fee