CN212427427U - Along unsettled installing support of river course barricade steel pipe - Google Patents
Along unsettled installing support of river course barricade steel pipe Download PDFInfo
- Publication number
- CN212427427U CN212427427U CN202020938484.5U CN202020938484U CN212427427U CN 212427427 U CN212427427 U CN 212427427U CN 202020938484 U CN202020938484 U CN 202020938484U CN 212427427 U CN212427427 U CN 212427427U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- triangle
- river course
- shaped support
- horizontal direction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model relates to a sewage treatment technical field specifically discloses along unsettled installing support of river course barricade steel pipe, including the triangle-shaped support, stop device and expansion bolts, a right-angle side of triangle-shaped support passes through expansion bolts to be fixed on the river course barricade, and another right angle border horizontal direction of triangle-shaped support arranges and perpendicular to river course barricade, and the steel pipe is placed on the right angle edge that the edge horizontal direction arranged of triangle-shaped support, and stop device welds and is spacing with the steel pipe on the right angle edge that the edge horizontal direction arranged of triangle-shaped support. The aim at of this patent is solved sewage pipe (steel pipe) and is adopted in the river course to build the buttress along the traditional technology of river course installation, then the steel pipe encapsulates the construction cycle length, problem with high costs that fixed mounting leads to on the buttress along the buttress.
Description
Technical Field
The utility model relates to a sewage treatment technical field, in particular to unsettled installing support of border river way barricade steel pipe.
Background
The traditional process for installing the sewage pipeline (steel pipe) along the river channel generally adopts the steps of building the buttress in the river channel, and then fixedly installing the steel pipe along the buttress in a sealing mode.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art, the utility model provides a technical problem provides the unsettled installing support of following river course barricade steel pipe, solves sewage pipe (steel pipe) and adopts in the traditional technology of river course installation to build the buttress in the river course, then the steel pipe seals the construction cycle length that fixed mounting leads to, problem with high costs on following the buttress.
In order to solve the above problem, the utility model discloses the technical scheme who adopts is: along unsettled installing support of river course barricade steel pipe, including triangle-shaped support, stop device and expansion bolts, a right angle limit of triangle-shaped support passes through expansion bolts to be fixed on the river course barricade, another right angle of triangle-shaped support is arranged and perpendicular to river course barricade along the horizontal direction, and the steel pipe is placed on the right angle edge that the edge horizontal direction arranged of triangle-shaped support, stop device welds and is spacing with the steel pipe on the right angle edge that the edge horizontal direction arranged of triangle-shaped support.
The technical principle of the technical scheme is as follows: after one right-angle side of the triangular support is fixed on the river channel retaining wall through the expansion bolts, the other right-angle side of the triangular support is arranged along the horizontal direction and is perpendicular to the river channel retaining wall, a plurality of triangular supports are arranged at intervals uniformly in sequence, the steel pipe is placed on the right-angle side of the triangular support arranged along the horizontal direction, and then the limiting device is welded on the right-angle side of the support arranged along the horizontal direction and is limited by the steel pipe.
The beneficial effect that this scheme produced is:
1. the installation of the steel pipe along the river channel adopts the support installation, the material is simple and convenient, the operation is simple, the installation is quick, the cost is low, and the construction period is greatly shortened.
2. The support mounting steel pipe occupies that river course space is little, does not influence river course rivers, and river course geology, flood season etc. do not influence the construction progress, all can normally be under construction, and the support mounting pipeline is firm and not receive the river disturbance, and pipeline, support are maintained and are changed portably.
Furthermore, the triangular bracket and the limiting device are respectively formed by welding galvanized angle steel with the thickness of 50 x 6mm, and the galvanized angle steel is firm and durable.
Furthermore, the lower end of the vertical downward right-angle side of the support extends downwards 10-30cm than the lower end of the oblique side, so that the firmness of the triangular support is enhanced.
Furthermore, the distance between two adjacent triangular supports is 1-1.5m, the distance is proper, and the cost is saved on the premise of ensuring the support of the steel pipe.
Furthermore, the distance between two adjacent limiting devices is 4-6m, the distance is proper, and the cost is saved on the premise of ensuring that the support of the steel pipe is met.
Furthermore, stop device's cross section is "n" style of calligraphy, and stop device is spacing at stop device's inside with the steel pipe.
Drawings
Fig. 1 is a side view of the overall structure of the bracket.
Fig. 2 is a front view of the overall structure of the bracket.
Detailed Description
The following is further detailed by way of specific embodiments:
reference numerals in the drawings of the specification include: triangle-shaped support 1, expansion bolts 2, steel pipe 3, stop device 4, river course barricade 5.
The embodiment is basically as shown in the attached figures 1-2: along unsettled installing support of river course barricade steel pipe, including triangle-shaped support 1, stop device 4 and expansion bolts 2, as shown in fig. 1, a right-angle side of triangle-shaped support 1 is fixed on river course barricade 5 through expansion bolts 2(M14 x 200), another right-angle side of triangle-shaped support 1 is arranged and perpendicular to river course barricade 5 along the horizontal direction, steel pipe 3 is placed on the right-angle side that arranges along the horizontal direction of triangle-shaped support 1, steel pipe 3 is parallel with river course barricade 5, the lower extreme of the vertical decurrent right-angle side of triangle-shaped support 1 is than the lower extreme downwardly extending 15cm of hypotenuse, strengthen triangle-shaped support 1's fastness, stop device 4 welds the right-angle side that arranges along the horizontal direction of triangle-shaped support 1 on, stop device 4's cross section is "n" style of calligraphy, stop device.
The diameter of the steel pipe 3 in the embodiment is 300mm, and according to the dead weight of the steel pipe 3 and the maximum sewage flow weight, the triangular bracket 1 and the limiting device 4 in the embodiment are formed by welding galvanized angle steel with the thickness of 50 x 6mm, and the galvanized angle steel is firm and durable. The distance between two adjacent triangular supports 1 is 1m, and the distance is suitable, so that the cost is saved on the premise of ensuring that the support of the steel pipe 3 is met. The distance between two adjacent limiting devices 4 is 5m, the distance is appropriate, and the cost is saved on the premise of ensuring that the support of the steel pipe 3 is met. As shown in fig. 2, 5 triangular supports 1 are taken as a unit, only the triangular supports 1 at two ends are provided with fixing devices, and the three triangular supports 1 in the middle are not required to be provided with limiting devices 4 and are circulated continuously.
The specific implementation process is as follows: pass through expansion bolts 2 with a right-angle side of triangle-shaped support 1 and fix back on river course barricade 5, another right angle border horizontal direction of triangle-shaped support 1 arranges and perpendicular to river course barricade 5, set up 5 triangle-shaped supports 1 back at interval 1m in proper order, place steel pipe 3 on the right-angle side that the edge horizontal direction arranged of triangle-shaped support 1, weld stop device 4 again on the right-angle side that the edge horizontal direction arranged of triangle-shaped support 1 at both ends and spacing steel pipe 3, analogize until installing steel pipe 3 is whole with this.
The above description is only an example of the present invention, and the common general knowledge of the known specific structures and characteristics of the embodiments is not described herein. It should be noted that, for those skilled in the art, without departing from the structure of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicability of the patent. The scope of the claims of the present application shall be determined by the contents of the claims, and the description of the embodiments and the like in the specification shall be used to explain the contents of the claims.
Claims (6)
1. Along the unsettled installing support of river course barricade steel pipe, its characterized in that: including triangle-shaped support, stop device and expansion bolts, a right angle side of triangle-shaped support passes through expansion bolts to be fixed on the river course retaining wall, another right angle border horizontal direction of triangle-shaped support arranges and perpendicular to river course retaining wall, and the right angle side that the steel pipe was arranged along the horizontal direction at the triangle-shaped support is placed to the steel pipe, stop device welds on the right angle side that the horizontal direction of edge arranged of triangle-shaped support and with the steel pipe spacing.
2. The riverway retaining wall steel pipe suspension mounting bracket as claimed in claim 1, wherein: the triangular bracket and the limiting device are formed by welding galvanized angle steel with the thickness of 50 x 6 mm.
3. The riverway retaining wall steel pipe suspension mounting bracket as claimed in claim 1, wherein: the lower end of the vertical downward right-angle side of the support extends downwards 10-30cm than the lower end of the inclined side.
4. The riverway retaining wall steel pipe suspension mounting bracket as claimed in claim 1, wherein: the distance between two adjacent triangular brackets is 1-1.5 m.
5. The riverway retaining wall steel pipe suspension mounting bracket as claimed in claim 1, wherein: the distance between two adjacent limiting devices is 4-6 m.
6. The riverway retaining wall steel pipe suspension mounting bracket as claimed in claim 1, wherein: the cross section of the limiting device is n-shaped.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020938484.5U CN212427427U (en) | 2020-05-28 | 2020-05-28 | Along unsettled installing support of river course barricade steel pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020938484.5U CN212427427U (en) | 2020-05-28 | 2020-05-28 | Along unsettled installing support of river course barricade steel pipe |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212427427U true CN212427427U (en) | 2021-01-29 |
Family
ID=74269748
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020938484.5U Active CN212427427U (en) | 2020-05-28 | 2020-05-28 | Along unsettled installing support of river course barricade steel pipe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212427427U (en) |
-
2020
- 2020-05-28 CN CN202020938484.5U patent/CN212427427U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204589927U (en) | Combined fast-assembled glass fiber reinforced plastic retaining dam for water body restoration | |
CN204164500U (en) | A kind of tunnel pipeline fixing bracket | |
CN102828473A (en) | Sound barrier and mounting method | |
CN212427427U (en) | Along unsettled installing support of river course barricade steel pipe | |
CN202899051U (en) | Acoustic barrier | |
CN107634706A (en) | A kind of photovoltaic plant array bracket | |
CN103967021A (en) | Prestress support system for strip rectangular foundation ditch | |
KR101626357B1 (en) | Solar generating system | |
CN219776815U (en) | Flowmeter installation device | |
CN104563064B (en) | Combined fast-assembled glass fiber reinforced plastic retaining dam for water body restoration | |
CN216904738U (en) | Horizontal damping dovetail type balance plate device of flexible photovoltaic support | |
CN110308264B (en) | Open-air heating test device suitable for morning and evening tides salt marsh wetland | |
CN105507210B (en) | The domatic steel facing assembled steel-structure dam of low-angle length | |
CN205957134U (en) | A novel suspended structure for boiler cigarette wind channel | |
CN204401904U (en) | Siphon rainwater suspension pipe fixing device | |
CN204716629U (en) | The fixed rack structure that a kind of submerged pump automatic coupling is installed | |
CN105703289A (en) | Cable protection tube bridge crossing structure | |
CN202749386U (en) | Column pile-type photovoltaic support system | |
CN219041677U (en) | Desert soil photovoltaic support | |
CN205242503U (en) | Water intake device under complex geological environment | |
CN211973988U (en) | Stone material water curtain waterproof construction | |
CN206337582U (en) | A kind of support meanss of steel pipe gallery | |
CN214271657U (en) | Flexible steel frame supporting structure for river-crossing cable | |
CN213417717U (en) | Double-row type river channel cutoff retaining dam | |
CN217026645U (en) | Prevent throwing device on steel temporary bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |