CN212406263U - Side inspection modular machine room - Google Patents

Side inspection modular machine room Download PDF

Info

Publication number
CN212406263U
CN212406263U CN202020906068.7U CN202020906068U CN212406263U CN 212406263 U CN212406263 U CN 212406263U CN 202020906068 U CN202020906068 U CN 202020906068U CN 212406263 U CN212406263 U CN 212406263U
Authority
CN
China
Prior art keywords
machine room
data
power
computer lab
cabinet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020906068.7U
Other languages
Chinese (zh)
Inventor
郭俊辉
刘凯
李国华
何燊达
张鸿
林超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen General Station Of Exit And Entry Frontier Inspection Of PRC
Original Assignee
Shenzhen General Station Of Exit And Entry Frontier Inspection Of PRC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen General Station Of Exit And Entry Frontier Inspection Of PRC filed Critical Shenzhen General Station Of Exit And Entry Frontier Inspection Of PRC
Priority to CN202020906068.7U priority Critical patent/CN212406263U/en
Application granted granted Critical
Publication of CN212406263U publication Critical patent/CN212406263U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Air Conditioning Control Device (AREA)

Abstract

The utility model discloses a side inspection modular machine room, wherein a machine room power system, a plurality of IT cabinets, a refrigerating system and a machine room power environment monitoring system are arranged in the machine room; the IT cabinet, the power distribution cabinet and the air conditioner are arranged side by side at two sides of the machine room, and a cold air channel is formed in the middle of the machine room; the machine room power environment monitoring system is used for collecting and analyzing environmental data, machine room power system data, video monitoring data and refrigeration system data in the machine room and displaying the environmental data, the machine room power system data, the video monitoring data and the refrigeration system data on a user platform. The utility model discloses assemble into a complete computer lab module with different functional unit, collect distribution, refrigeration, control, management and system in an organic whole such as maintenance, safety, realized the seamless integration of power supply, refrigeration and management subassembly to make its intelligence, efficient operation. The utility model discloses a modularization computer lab has the advantage of high dense low consumption, quick deployment, nimble extension, has improved the equipment operating efficiency of limit inspection computer lab effectively to construction cycle and cost have been controlled.

Description

Side inspection modular machine room
Technical Field
The utility model relates to an equipment technical field is built to the computer lab, concretely relates to modularization computer lab is examined on limit.
Background
With the more and more mature information technology, the more and more information technology is applied in the frontier defense inspection system, the frontier inspection station generally constructs an independent machine room to store servers, provides IT service for passengers and staff, generally places dozens of small machine cabinets in dozens of square meters, places hundreds of large machine cabinets in dozens of square meters, and places various servers and small-sized machines in the machine room. The temperature and humidity of the machine room and antistatic measures have strict requirements, and non-professional project personnel can not enter the machine room generally.
The existing machine room is long in construction time and cannot be built and used quickly, and time cost and labor cost for building the machine room are high.
SUMMERY OF THE UTILITY MODEL
To the defect among the prior art, the utility model provides a modularization computer lab is examined on limit to improve the computer lab and build speed, effectively reduce construction cycle and human cost.
The utility model discloses an above-mentioned technical problem is solved to following technical means:
the system comprises a side inspection modular machine room, wherein a machine room power system, a plurality of IT cabinets, a refrigeration system and a machine room power environment system are arranged in the machine room; the machine room power system comprises a power distribution cabinet, and the refrigeration system comprises an air conditioner; the IT cabinet, the power distribution cabinet and the air conditioner are arranged side by side at two sides of the machine room, and a cold air channel is formed in the middle of the machine room;
the machine room power environment monitoring system is used for collecting and analyzing environmental data, machine room power system data, video monitoring data and refrigeration system data in the machine room and displaying the environmental data, the machine room power system data, the video monitoring data and the refrigeration system data on a user platform.
Further, the IT cabinet comprises a cabinet body, and a server, a collector, an optical fiber box and a distribution frame which are arranged in the cabinet body;
the server is in optical signal communication with servers in other IT cabinets through the optical fiber box and in network signal communication with the servers in the other IT cabinets through the distribution frame;
the collector is used for collecting temperature information of the server.
Further, computer lab power environment monitored control system includes communication connection's temperature and humidity sensor, communication connection's camera, network digital video recorder, switch board, UPS, precision air conditioner, PDU, collector and switch, the switch is connected with the control room signal, temperature and humidity sensor sets up in the computer lab, the camera sets up the computer lab top.
Further, the wiring is carried out in the machine room through a wiring groove, and the wiring groove is hung on a ceiling of the machine room.
Further, the wiring groove is a groove type grid bridge, and the wiring groove is hung on the ceiling of the machine room through a pull rod.
The beneficial effects of the utility model are embodied in:
the utility model discloses assemble into a complete computer lab module with different functional unit, collect distribution, refrigeration, control, management and system in an organic whole such as maintenance, safety, realized the seamless integration of power supply, refrigeration and management subassembly to make its intelligence, efficient operation. The equipment cabinet is used as a unit for flexible expansion, and dynamic and rapid growth of services is supported.
And simultaneously, the utility model discloses a modularization computer lab has the advantage of high dense low consumption, quick deployment, nimble extension, has improved the equipment operating efficiency of limit inspection computer lab effectively to construction cycle and cost have been controlled.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the embodiments or the technical solutions in the prior art will be briefly described below. Throughout the drawings, like elements or portions are generally identified by like reference numerals. In the drawings, elements or portions are not necessarily drawn to scale.
Fig. 1 is a top view of a side inspection modular machine room according to an embodiment of the present invention;
fig. 2 is a schematic structural diagram of an IT cabinet of a side inspection modular machine room according to an embodiment of the present invention;
fig. 3 is a schematic structural diagram of a wiring groove in the edge inspection modular machine room provided by the embodiment of the present invention.
Detailed Description
Embodiments of the present invention will be described in detail below with reference to the accompanying drawings. The following examples are only for illustrating the technical solutions of the present invention more clearly, and therefore are only examples, and the protection scope of the present invention is not limited thereby.
It is to be noted that unless otherwise specified, technical or scientific terms used herein shall have the ordinary meaning as understood by those skilled in the art to which the present invention belongs.
As shown in fig. 1-3, the side inspection modular machine room of the present invention has a machine room power system, a plurality of IT cabinets 2, a refrigeration system and a machine room power environment monitoring system; the machine room power system comprises a power distribution cabinet 1, and the refrigerating system comprises an air conditioner 3; the IT cabinet 2, the power distribution cabinet 1 and the air conditioner 3 are arranged side by side at two sides of the machine room, and a cold air channel is formed in the middle of the machine room; the machine room power environment monitoring system collects and analyzes environmental data, machine room power system data, video monitoring data and refrigeration system data in the machine room and displays the data on a user platform; in this embodiment, the collector is a HUAWEI EIM 03C.
Specifically, the IT cabinet 2 includes a cabinet 21, and a server 22, a collector 23, an optical fiber box 24 and a distribution frame 25 which are arranged in the cabinet 21; the server 22 performs optical signal communication with the servers 22 in other IT cabinets 2 through the optical fiber box 24, that is, optical signal communication can be performed between the two IT cabinets by connecting the two IT cabinets to the optical fiber box 24 through optical fibers, and network signal communication is performed with the servers 22 in other IT cabinets 2 through the distribution frame 25. The installation interface standards are unified, and the delivery installation deployment period is reduced to 8-12 weeks.
The collector 23 is used for collecting temperature data of the server 22. When the computer room is constructed, the collector on one of the IT cabinets is selected as a computer room center collector, the collectors on other IT cabinets are in signal connection with the computer room center collector, and the computer room center collector is in signal connection with the switch, so that collected data are uploaded to the control room through the switch, and a controller can timely master the operation condition of each IT cabinet.
Computer lab power environment monitored control system includes communication connection's temperature and humidity sensor 6, communication connection's camera 7, network digital video recorder, switch board, UPS, precision air conditioner, PDU, collector and switch, and the switch is connected with the control room signal, and temperature and humidity sensor 6 sets up in the computer lab, and temperature and humidity sensor 6 is used for gathering the temperature and humidity data in the computer lab, and camera 7 is in order to be used for acquireing the video information in the computer lab. The collector in the machine room power environment monitoring system is a machine room center collector, and data transmission is carried out through the machine room center collector, so that the number of devices is reduced, the cost is saved, and meanwhile, the maintenance is convenient.
Specifically, the wiring is carried out in the machine room through the wiring groove 4, and the wiring groove 4 is hung on the ceiling of the machine room. The wiring groove 4 is a groove type grid bridge, and the wiring groove 4 is hung on the ceiling of the machine room through a pull rod 5. Wiring through wiring groove 4, can avoid the line body winding confusion for the subassembly speed, the later maintenance of also being convenient for overhauls.
To sum up, the utility model discloses assemble into a complete computer lab module with different functional unit, collect distribution, refrigeration, control, management and system in an organic whole such as maintenance, safety, realized power supply, refrigeration and management subassembly's seamless integration to make its intelligence, efficient operation. The equipment cabinet is used as a unit for flexible expansion, and dynamic and rapid growth of services is supported.
And simultaneously, the utility model discloses a modularization computer lab has the advantage of high dense low consumption, quick deployment, nimble extension, has improved the equipment operating efficiency of limit inspection computer lab effectively to construction cycle and cost have been controlled.
Finally, it should be noted that: the above embodiments are only used to illustrate the technical solution of the present invention, and not to limit the same; although the present invention has been described in detail with reference to the foregoing embodiments, it should be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; such modifications and substitutions do not substantially depart from the scope of the embodiments of the present invention, and are intended to be covered by the claims and the specification.

Claims (5)

1. Side inspection modularization computer lab, its characterized in that: a machine room power system, a plurality of IT cabinets (2), a refrigerating system and a machine room power environment monitoring system are arranged in the machine room; the machine room power system comprises a power distribution cabinet (1), and the refrigeration system comprises an air conditioner (3); the IT cabinet (2), the power distribution cabinet (1) and the air conditioner (3) are arranged side by side on two sides of the machine room, and a cold air channel is formed in the middle of the machine room;
the machine room power environment monitoring system is used for collecting and analyzing environmental data, machine room power system data, video monitoring data and refrigeration system data in the machine room and displaying the environmental data, the machine room power system data, the video monitoring data and the refrigeration system data on a user platform.
2. The edge inspection modular machine room of claim 1, wherein: the IT cabinet (2) comprises a cabinet body (21), and a server (22), a collector (23), an optical fiber box (24) and a distribution frame (25) which are arranged in the cabinet body (21);
the server (22) is in optical signal communication with servers (22) in other IT cabinets (2) through an optical fiber box (24), and is in network signal communication with the servers (22) in other IT cabinets (2) through a distribution frame (25);
the collector (23) is used for collecting temperature information of the server (22).
3. The edge inspection modular machine room of claim 1, wherein: computer lab power environment monitored control system includes communication connection's temperature and humidity sensor (6), communication connection's camera (7), network digital video recorder, switch board, UPS, precision air conditioner, PDU, collector and switch, the switch is connected with control room signal, temperature and humidity sensor sets up in the computer lab, the camera sets up the computer lab top.
4. The edge inspection modular machine room of claim 1, wherein: the machine room is internally wired through a wiring groove (4), and the wiring groove (4) is hung on the ceiling of the machine room.
5. The edge inspection modular machine room of claim 4, wherein: the wiring groove (4) is a groove type grid bridge, and the wiring groove (4) is hung on the ceiling of the machine room through a pull rod (5).
CN202020906068.7U 2020-05-26 2020-05-26 Side inspection modular machine room Active CN212406263U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020906068.7U CN212406263U (en) 2020-05-26 2020-05-26 Side inspection modular machine room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020906068.7U CN212406263U (en) 2020-05-26 2020-05-26 Side inspection modular machine room

Publications (1)

Publication Number Publication Date
CN212406263U true CN212406263U (en) 2021-01-26

Family

ID=74403078

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020906068.7U Active CN212406263U (en) 2020-05-26 2020-05-26 Side inspection modular machine room

Country Status (1)

Country Link
CN (1) CN212406263U (en)

Similar Documents

Publication Publication Date Title
CN102287330A (en) Wind farm remote real-time monitoring and intelligent video remote viewing system adopting 3rd generation (3G) network
EA002992B1 (en) Structured system for monitoring and controlling the engineering equipment of an installation
CN110096035A (en) High-precision high-speed sports platform Synchronous motion control system and method based on Open VPX
CN103632524A (en) Multi-platform energy consumption monitoring system with various access ways
CN114559846B (en) Energy storage power station management device and management method
CN202282841U (en) Monitoring system for crossing circuit operation and environment
CN209627057U (en) Intelligent Mobile Robot control system
CN212406263U (en) Side inspection modular machine room
CN203773327U (en) Remote monitoring system of power distribution rooms
CN110108366A (en) A kind of infrared cable vault's temp measuring system of dot matrix based on dispatch network
CN209979068U (en) Dot matrix infrared cable chamber temperature measuring device based on scheduling network
CN207612365U (en) Unattended field overhead line video monitoring apparatus
CN206115680U (en) Use electric information collection device
CN207817501U (en) A kind of IT-room environment monitoring system based on big data
CN206135540U (en) Photovoltaic power station monitoring system
US20240146036A1 (en) New-type bus power distribution micromodule
CN113810797B (en) Intelligent ODN management system and method based on optical port state monitoring
CN114336960A (en) Digital new energy power station intelligent equipment supervisory systems
CN210297754U (en) Data link for circulation of patrol information of service substation equipment
CN209118116U (en) Heat exchange station electromechanical equipment Internet of Things multi-path monitoring device
CN112701696A (en) Novel intelligent distribution box
CN208227085U (en) A kind of concentrating type CDC data monitoring device
CN217441912U (en) Energy management and monitoring system applied to refrigerant air conditioner
CN110365107A (en) A kind of distributed terminator monitoring system
CN110163383A (en) A kind of construction method in the substation information library based on AR technology