CN212383259U - Recovery unit of water economy resource for building construction site - Google Patents

Recovery unit of water economy resource for building construction site Download PDF

Info

Publication number
CN212383259U
CN212383259U CN202020338779.9U CN202020338779U CN212383259U CN 212383259 U CN212383259 U CN 212383259U CN 202020338779 U CN202020338779 U CN 202020338779U CN 212383259 U CN212383259 U CN 212383259U
Authority
CN
China
Prior art keywords
water
pipe
device main
main body
suction pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020338779.9U
Other languages
Chinese (zh)
Inventor
郑莉娇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cscec Guangsha Fujian Construction Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020338779.9U priority Critical patent/CN212383259U/en
Application granted granted Critical
Publication of CN212383259U publication Critical patent/CN212383259U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Filtration Of Liquid (AREA)

Abstract

The utility model provides a water-saving resource recovery device for construction sites, which comprises a device main body, a fixed pipe is fixedly arranged at the lower end of the left side of the device main body, a water inlet pipe is fixedly arranged in the fixed pipe, a water suction pipe is movably arranged at the lower end of the fixed pipe, connecting rods are fixedly connected with the two sides of the water suction pipe, the upper end of the water inlet pipe is communicated with the inside of the water storage cavity, so that when the water pump is electrically connected with an external power supply, suction can be generated at the lower end of the water inlet pipe, thereby sucking accumulated water at the hollow part of the construction site upwards, guiding the accumulated water into the water storage cavity for collection, improving the treatment efficiency of the accumulated water of the construction site, meanwhile, the upper end of the water suction pipe is in a joint arrangement sleeved outside the water inlet pipe, so that the connecting rod can be driven by the spring in the chute at the lower end of the fixed pipe, the water suction pipe is driven to move towards the lower end to be jointed with the ground, thereby can stretch into the building site pothole bottom with the suction pipe lower extreme to further improve the collection efficiency of ponding.

Description

Recovery unit of water economy resource for building construction site
Technical Field
The utility model relates to a construction water resource recovery technical field specifically is a recovery unit of water economy resource for building construction site.
Background
After the building site excavation, the air pollution such as raise dust must be caused in a large number of business turn over of dregs car, and the dregs car also further causes the pollution to the urban road easily simultaneously, consequently according to building site civilized construction standard, must wash the dregs car that comes out from the building site to the public road of pollution-free outside also reduces the raise dust that the dregs car brought up simultaneously.
At present, the dregs car washes and needs to consume a large amount of building site water, and if set up unreasonablely, or wash the improper etc. of mode, cause the waste of water resource easily, cause the sump in building site pothole department simultaneously, cause building site ponding, lead to the unable recovery of water resource to and influence safety in production, but present building site ponding is handled mostly artifical manual going on, when inefficiency, can't filter sewage reuse.
SUMMERY OF THE UTILITY MODEL
The utility model provides a recovery unit of water economy resource for building site to solve ordinary building site ponding treatment inefficiency and can't filter the problem of retrieving.
In order to realize the purpose, the utility model provides a water-saving resource recovery device for construction sites, which comprises a device main body, wherein a fixed pipe is fixedly arranged at the lower end of the left side of the device main body, a water inlet pipe is fixedly arranged in the fixed pipe, a water suction pipe is movably arranged at the lower end of the fixed pipe, connecting rods are fixedly connected with the two sides of the water suction pipe, a chute is arranged at the inner side of the lower end of the fixed pipe, a water pump is fixedly arranged at the lower end of the left side of the inner part of the device main body, a storage battery is fixedly arranged at the lower end of the right side of the inner part of the device main body, a water storage cavity is fixedly arranged at the upper end of the inner part of the device main body, a sealing door is fixedly arranged at the lower end of the front, the device main part right side lower extreme fixed mounting has the footboard, device main part right side middle-end fixed mounting has the outlet pipe.
Further, the water pump is electrically connected with the storage battery, the water pump is arranged at the middle end of the water inlet pipe, and the upper end of the water inlet pipe is communicated to the interior of the water storage cavity.
Further, the upper end of the water suction pipe is sleeved outside the water inlet pipe and is arranged in a laminating mode, the outer end of the connecting rod is arranged in the sliding groove, and a spring is fixedly arranged in the sliding groove.
Furthermore, the pedal is horizontally arranged on the left side, and is obliquely arranged on the right side.
Furthermore, the fixing frame is obliquely arranged with the lower end facing right.
Further, motor and battery electric connection, the retaining chamber is worn out to fixed frame upper end and is contacted with the bull stick, the bull stick middle-end is one side arc evagination setting, the spring is equipped with to the fixed frame's of the relative position of retaining chamber lower extreme solid installation.
The utility model provides a recovery unit of water economy resource for building site has following beneficial effect:
(1) the device is through managing the upper end through absorbing water and set up for cup jointing the laminating in the inlet tube outside for can order about the connecting rod through the spring in the fixed pipe lower extreme spout, so that drive absorb water tub to the lower extreme remove with the ground laminating, thereby can stretch into building site pothole bottom with the tub lower extreme that absorbs water, set up for the left side level through the footboard simultaneously, the right side slope sets up, then can step on the footboard through the user foot, with the device main part left side perk that makes progress, carries out the processing of another ponding hole.
(2) The device sets up for the slope of lower extreme rightwards through fixed frame, utilizes the inclined plane to move down with the impurity of filtering down, improves what the filter screen prevents stifled efficiency and life, and the water storage chamber is worn out to the fixed frame upper end of rethread and is contacted with the bull stick, then after motor and external power source intercommunication start-up, can drive the bull stick rotation that the middle-end set up for one side arc evagination to the effort that the spring in water storage chamber bottom was overcome to the fixed frame of intermittent type drive moves down, thereby further improves the efficiency of cleaing away of impurity on the filter screen.
Drawings
Fig. 1 is a perspective view of the device body of the present invention;
fig. 2 is a perspective view of the inside of the device body of the present invention;
FIG. 3 is a perspective view of the interior of the reservoir chamber of the present invention;
fig. 4 is a left side view of the fixing frame of the present invention.
In FIGS. 1-4: 1-device body, 2-fixed tube, 3-water suction tube, 4-storage battery, 5-pedal, 6-water outlet tube, 7-water inlet tube, 8-water pump, 9-connecting rod, 10-chute, 11-water storage cavity, 12-motor, 13-rotating rod, 14-sealing door, 15-fixed frame and 16-filter screen.
Detailed Description
Referring to fig. 1 to 4, an exploded schematic view and a plan schematic view of a water saving recycling apparatus for construction sites are shown.
The embodiment provides a water-saving resource recovery device for a building construction site, which comprises a device main body 1, wherein a fixed pipe 2 is fixedly arranged at the lower end of the left side of the device main body 1, a water inlet pipe 7 is fixedly arranged inside the fixed pipe 2, a water suction pipe 3 is movably arranged at the lower end of the fixed pipe 2, connecting rods 9 are fixedly connected with two sides of the water suction pipe 3, a chute 10 is arranged at the inner side of the lower end of the fixed pipe 2, a water pump 8 is fixedly arranged at the lower end of the left side inside the device main body 1, a storage battery 4 is fixedly arranged at the lower end of the right side inside the device main body 1, a water storage cavity 11 is fixedly arranged at the upper end inside the device main body 1, a sealing door 14 is fixedly arranged at the lower end of the front side of the water storage cavity 11, a motor 12, the lower end of the right side of the device main body 1 is fixedly provided with a pedal 5, and the middle end of the right side of the device main body 1 is fixedly provided with a water outlet pipe 6.
When concrete implementation, water pump 8 and battery 4 electric connection, water pump 8 set up the middle-end at inlet tube 7, and the inlet tube 7 upper end communicates to inside the retaining chamber 11 to upwards attract the ponding of building site hollow department, collect in the leading-in retaining chamber 11, improve the treatment effeciency of building site ponding.
When concrete implementation, the 3 upper ends of the water suction pipes are sleeved outside the water inlet pipe 7, and are arranged for laminating, the outer ends of the connecting rods 9 are arranged in the sliding grooves 10, springs are fixedly arranged in the sliding grooves 10, the connecting rods 9 can be driven by the springs in the sliding grooves 10 at the lower ends of the fixed pipes 2, the water suction pipes 3 are driven to move towards the lower ends and be laminated with the ground, the lower ends of the water suction pipes 3 can stretch into the bottom of the hollow building site, and therefore the collection efficiency of accumulated water is further improved.
When the device is specifically implemented, the pedal 5 is horizontally arranged on the left side, and the right side is obliquely arranged, so that the pedal can be stepped by a user, the left side of the device main body 1 is tilted upwards, the lower end of the water suction pipe 3 is conveniently lifted out of a hollow place of a construction site, and the treatment of another water accumulation pit is carried out.
When concrete implementation, fixed frame 15 is the slope setting of lower extreme rightward to let water pipe 6 outwards flow recycle's clean water, reach water resource recycle's effect, utilize the inclined plane to move down the impurity under filtering simultaneously, improve the stifled efficiency of preventing of filter screen 16, with life.
When concrete implementation, motor 12 and battery 4 electric connection, the retaining chamber 11 is worn out to fixed frame 15 upper end and is contacted with bull stick 13, bull stick 13 middle-end is one side arc evagination setting, the spring is equipped with to the position of 11 lower extremes fixed frame 15 admittedly of retaining chamber, then after motor 12 and external power source intercommunication start-up, can drive the bull stick rotation that the middle-end set up for one side arc evagination, thereby the effort that 11 bottom springs in retaining chamber were overcome to the fixed frame 15 of intermittent drive moves down, thereby further improve the efficiency of cleaing away of impurity on the filter screen 16, can pass through the positive sealing door 14 in retaining chamber 11 at last, make and conveniently open retaining intracavity 11 inside, carry out the concentrated clearance of impurity.
The utility model relates to a recovery unit operating principle of water economy resource for building construction site as follows:
firstly, the handle on the right side of the device main body 1 can be passed through, the device main body 1 is moved to a place where accumulated water needs to be treated, the upper end of the water inlet pipe 7 is communicated to the inside of the water storage cavity 11, and then suction force can be generated at the lower end of the water inlet pipe 7 after the water pump 8 is electrically connected with an external power supply, so that the accumulated water in the pit of a construction site is upwards sucked and guided into the water storage cavity 11 for collection, the treatment efficiency of the accumulated water in the construction site is improved, meanwhile, the upper end of the water suction pipe 3 is in a joint arrangement outside the water inlet pipe 7, so that the connecting rod 9 can be driven by a spring in the chute 10 at the lower end of the fixed pipe 2, so that the water suction pipe 3 is driven to move towards the lower end and be jointed with the ground, so that the lower end of the water suction pipe 3 can stretch into the bottom of the pit of, the left side of the device main body 1 is tilted upwards, so that the lower end of the water suction pipe 3 is conveniently lifted out of a hollow part of a construction site, another water accumulation pit is processed, then the fixing frame 15 is obliquely arranged with the lower end facing right, impurities in accumulated water entering the water storage cavity 11 can be blocked and filtered through the inner side filter screen 16, so that recyclable clean water flows out of the water outlet pipe 6, the effect of recycling water resources is achieved, meanwhile, the filtered impurities move downwards through the inclined plane, the anti-blocking efficiency and the service life of the filter screen 16 are improved, the upper end of the fixing frame 15 penetrates out of the water storage cavity 11 to be contacted with the rotating rod 13, after the motor 12 is communicated and started with an external power supply, the rotating rod with the middle end in an arc shape protruding outwards is driven to rotate, the fixing frame 15 is driven to overcome the acting force of a spring at the bottom end of the water storage cavity 11 to move downwards, and the removing efficiency of the impurities on, finally, the inside of the water storage cavity 11 can be conveniently opened through the sealing door 14 on the front surface of the water storage cavity 11, and the impurities are intensively cleaned.

Claims (6)

1. The utility model provides a recovery unit of water economy resource for building construction site, includes device main part (1), its characterized in that: the device is characterized in that a fixed pipe (2) is fixedly installed at the lower end of the left side of a device main body (1), a water inlet pipe (7) is fixedly installed inside the fixed pipe (2), a water suction pipe (3) is movably installed at the lower end of the fixed pipe (2), connecting rods (9) are fixedly connected to the two sides of the water suction pipe (3), a chute (10) is formed in the inner side of the lower end of the fixed pipe (2), a water pump (8) is fixedly installed at the lower end of the left side inside the device main body (1), a storage battery (4) is fixedly installed at the lower end of the right side inside the device main body (1), a water storage cavity (11) is fixedly installed at the upper end inside the device main body (1), a sealing door (14) is fixedly installed at the lower end of the front side of the water storage cavity (11, the water storage device is characterized in that a fixing frame (15) is movably mounted inside the water storage cavity (11), a filter screen (16) is fixedly mounted on the inner side of the fixing frame (15), a pedal (5) is fixedly mounted at the lower end of the right side of the device body (1), and a water outlet pipe (6) is fixedly mounted at the middle end of the right side of the device body (1).
2. The water resource saving recovery device for construction sites according to claim 1, wherein: the water pump (8) is electrically connected with the storage battery (4), the water pump (8) is arranged at the middle end of the water inlet pipe (7), and the upper end of the water inlet pipe (7) is communicated to the interior of the water storage cavity (11).
3. The water resource saving recovery device for construction sites according to claim 1, wherein: the water suction pipe is characterized in that the upper end of the water suction pipe (3) is sleeved outside the water inlet pipe (7) and is arranged in a laminating manner, the outer end of the connecting rod (9) is arranged in the sliding groove (10), and a spring is fixedly arranged in the sliding groove (10).
4. The water resource saving recovery device for construction sites according to claim 1, wherein: the pedal (5) is horizontally arranged on the left side and obliquely arranged on the right side.
5. The water resource saving recovery device for construction sites according to claim 1, wherein: the fixing frame (15) is obliquely arranged with the lower end facing right.
6. The water resource saving recovery device for construction sites according to claim 1, wherein: motor (12) and battery (4) electric connection, retaining chamber (11) and bull stick (13) contact are worn out to fixed frame (15) upper end, bull stick (13) middle-end is one side arc evagination setting, the fixed position of retaining chamber (11) lower extreme relatively fixed frame (15) installs the spring.
CN202020338779.9U 2020-03-17 2020-03-17 Recovery unit of water economy resource for building construction site Active CN212383259U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020338779.9U CN212383259U (en) 2020-03-17 2020-03-17 Recovery unit of water economy resource for building construction site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020338779.9U CN212383259U (en) 2020-03-17 2020-03-17 Recovery unit of water economy resource for building construction site

Publications (1)

Publication Number Publication Date
CN212383259U true CN212383259U (en) 2021-01-22

Family

ID=74248161

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020338779.9U Active CN212383259U (en) 2020-03-17 2020-03-17 Recovery unit of water economy resource for building construction site

Country Status (1)

Country Link
CN (1) CN212383259U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113756420A (en) * 2021-10-25 2021-12-07 武传辉 Building construction hole topography ponding remove device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113756420A (en) * 2021-10-25 2021-12-07 武传辉 Building construction hole topography ponding remove device

Similar Documents

Publication Publication Date Title
CN103479305B (en) A kind of water circulation ground washing vehicle
CN212383259U (en) Recovery unit of water economy resource for building construction site
CN114804448B (en) Small movable solar sewage treatment device
CN214022182U (en) Energy-saving external cleaning device for air conditioner
CN113521845A (en) Sponge urban rainwater treatment and recycling integrated equipment and treatment method thereof
CN215993851U (en) Surface cleaning machine
CN216628429U (en) Water-saving floor cleaning machine
CN214294017U (en) Plastic mold dust collector
CN213129346U (en) Dust collector dust collection box capable of preventing dust from flowing backwards
CN214073171U (en) Intelligent floor washing machine with dirty water recovery function
CN210104653U (en) Portable permeable pavement cleaning vehicle
CN108791218B (en) Vehicle cleaning machine for building site
CN108002203B (en) A kind of application method of handrail cleaning device
CN213328855U (en) Belt cleaning device for bridge
CN207073306U (en) Assembled moves toilet
CN203294073U (en) Wheel cleaning system located on entrance to basement parking
CN212651532U (en) Diatom mud water paint processing dry powder workshop dust collector
CN217781854U (en) Ground surface yin-moisture accumulated water treatment device
CN217285649U (en) Cleaning equipment with dry-wet separation function
CN210646835U (en) Electrostatic precipitator self-cleaning system
CN214597526U (en) High-efficient oil removal slagging-off all-in-one
CN214916994U (en) Water circulating device of sand washer
CN220013926U (en) Promote and reform transform engineering with high strength escape canal
CN217325184U (en) Road dust removal cleaning device
CN216418575U (en) Reservoir for secondary water supply

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220727

Address after: 351100 room 2705, building B, Jiulong community office building, No. 999, lihuadong Avenue, Xialin street, Chengxiang District, Putian City, Fujian Province

Patentee after: CSCEC Guangsha (Fujian) Construction Co.,Ltd.

Address before: 243000 No.13 Kangfu Road, Yushan District, Ma'anshan City, Anhui Province

Patentee before: Zheng Lijiao