CN212359193U - High altitude construction worker protector - Google Patents

High altitude construction worker protector Download PDF

Info

Publication number
CN212359193U
CN212359193U CN202020613829.XU CN202020613829U CN212359193U CN 212359193 U CN212359193 U CN 212359193U CN 202020613829 U CN202020613829 U CN 202020613829U CN 212359193 U CN212359193 U CN 212359193U
Authority
CN
China
Prior art keywords
upright post
stand
rail
bottom plate
high altitude
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020613829.XU
Other languages
Chinese (zh)
Inventor
刘妹方
王钢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020613829.XU priority Critical patent/CN212359193U/en
Application granted granted Critical
Publication of CN212359193U publication Critical patent/CN212359193U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The utility model discloses a high-altitude construction worker protection device, which comprises a bottom plate, a protection rod and a hinge, wherein a first upright post is welded at the upper end corner of the bottom plate, a second rail is welded at the upper part of the first upright post, the second rail penetrates through the second upright post to a third upright post, a slider is arranged inside the second rail, the protection rod is fixedly arranged between the first upright post and the second upright post, a bolt is fixed at the crossed part of the protection rod, a door frame is arranged between the third upright post and the sixth upright post, a protective net is welded around the bottom plate, a fifth upright post is welded in the middle of the other side edge of the bottom plate, a fourth upright post and a sixth upright post are respectively welded at the two sides of the fifth upright post, a first rail is fixedly arranged between the fourth upright post and the fifth upright post, a third rail is fixedly arranged between the fifth upright post and the sixth upright post, the utility model discloses in using high altitude building, can be comprehensive protect the workman.

Description

High altitude construction worker protector
Technical Field
The utility model relates to a building protection field specifically is a high altitude construction worker protector.
Background
Along with the vigorous development of the real estate building industry in China, a large amount of overhead work is needed for building workers, the working danger is very high, high-altitude falling accidents which occur every year are continuous, the existing high-altitude protective guard part works by adopting a top lifting rope, but the stability is poor, the phenomenon of shaking along with wind can occur, the distance between the protective guards is large, the falling of instruments placed at the bottom is easy to occur, accidents occur, the height of the protective guards is fixed, the operation is inconvenient due to height difference, if the weather temperature is too high, dizziness can occur and fall over the protective guards, safety belts can be fixed at the waist of some people, and the operation range is influenced to a certain extent.
Therefore, there is a need for an overhead construction worker protection device that solves the above problems.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a high altitude construction workman protector to it is not comprehensive to provide safety protection in solving above-mentioned background art, the inconvenient problem of operation.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a high altitude construction worker protector, includes bottom plate, fender rod and hinge, the upper end corner welding of bottom plate has first stand, the second horizontal bar has been welded to the upper portion of first stand, the second horizontal bar runs through second stand to third stand, the internally mounted of second horizontal bar has the slider, fender rod fixed mounting is between first stand and second stand, the cross section of fender rod is fixed with the bolt, be provided with the door frame between third stand and the sixth stand, the welding has the protection network around the bottom plate, the welding has the fifth stand in the middle of the opposite side edge of bottom plate, fourth stand and sixth stand have been welded respectively to the both sides of fifth stand, fixed mounting has first horizontal bar between fourth stand and the fifth stand, fixed mounting has the third horizontal bar between fifth stand and the sixth stand.
Preferably, a sliding groove is formed in the second rail, a sliding block is movably mounted in the sliding groove and is I-shaped, and a circular ring is arranged at the bottom of the sliding block.
Preferably, the bottom plate is of a solid structure, and the upper surface of the bottom plate is provided with anti-skid grains.
Preferably, the hinge is installed through the cross screw in the surface of third stand, the other half of hinge passes through the cross screw connection on the door frame.
Preferably, the height of the protective net is 25 cm, the protective net is wrapped and fixed on the peripheries of the first upright post and the third upright post, and the protective net is in a dense net shape.
Preferably, the third rail is located above the fifth upright and the sixth upright, the third rail and the second rail are located on the same horizontal plane, the height of the first rail is lower than that of the third rail, and the difference in height ranges from 15 cm to 30 cm.
Compared with the prior art, the beneficial effects of the utility model are that:
1. this rail of high altitude construction workman's rail guard adopts cross welding to fix, has reduced the great gap that the guardrail appears, and the top guardrail of working position adopts high low two parts to constitute, has made things convenient for the personnel of height difference to work, and has surrounded the protection network in the bottom, when operating personnel has equipment, puts and can not appear unexpected the bumping in the inside of rail guard to lead to the equipment accident to fall, cause the damage of equipment.
2. The slide rail is arranged in the guardrail at the top of one side of the guardrail, so that a safety belt can be fixed at the waist during working, one end of the safety belt is fixed on the slide block of the slide rail, the slide rail faces the ground in the direction, dust is prevented from entering the slide rail, operation residues are prevented from falling into the slide rail, the normal movement of the slide rail is influenced, the moving range is enlarged due to the flexible movement of the slide rail, the operation of an operator is not influenced, and the secondary protection effect can be achieved.
Drawings
Fig. 1 is a schematic front view of the present invention;
fig. 2 is a schematic front view of the cross-sectional structure of the present invention;
fig. 3 is a schematic diagram of the right-side view structure of the present invention;
fig. 4 is a schematic partial sectional view of the slide rail of the present invention.
In the figure: 1. a base plate; 2. a first upright post; 3. a first rail; 4. a second rail; 5. a second upright post; 6. a slider; 7. a bolt; 8. a third column; 9. a guard bar; 10. a protective net; 11. a fourth column; 12. a fifth column; 13. a third rail; 14. a sixth upright post; 15. a door frame; 16. a hinge; 17. a cross screw; 18. a circular ring; 19. a chute.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides an embodiment:
a high-altitude construction worker protection device comprises a bottom plate 1, a protection rod 9 and a hinge 16, wherein a first upright post 2 is welded at the upper end corner of the bottom plate 1, the bottom plate 1 is of a solid structure, anti-slip lines are arranged on the upper surface of the bottom plate 1 and can effectively prevent a person from sliding, the floor is made of stainless steel, the floor can easily slip when encountering water, objects can possibly slide when being placed, the friction force of the floor is increased due to the design of the anti-slip lines at the bottom, the sliding phenomenon cannot occur, a second cross bar 4 is welded on the upper portion of the first upright post 2, the second cross bar 4 penetrates through a second upright post 5 to a third upright post 8, a sliding block 6 is arranged inside the second cross bar 4, a sliding groove 19 is formed inside the second cross bar 4, a sliding block 6 is movably arranged in the sliding groove 19, the sliding block 6 is I-shaped, a circular ring 18 is arranged at the bottom of the sliding block 6, the second cross bar 4, the sliding, if an accident occurs, the forces applied to the three parts are suddenly increased, and if the material is poor, the three parts are difficult to protect, and the three parts are broken.
The protective rod 9 is fixedly installed between the first upright post 2 and the second upright post 5, a bolt 7 is fixed at the intersection part of the protective rod 9, the adjacent upright posts are separated by the protective rod 9, the structure is the same, a door frame 15 is arranged between the third upright post 8 and the sixth upright post 14, the interior of the door frame 15 is also blocked by the protective rod 9, the door frame 15 is arranged on the protective net 10, when an operator enters the device, the operator needs to cross the protective net 10 to enter the device, a hinge 16 is installed on the surface of the third upright post 8 through a cross screw 17, the other half of the hinge 16 is connected to the door frame 15 through the cross screw 17, the protective net 10 is welded around the bottom plate 1, the height of the protective net 10 is 25 cm, the protective net 10 is wrapped and fixed on the peripheries of the first upright post 2 and the third upright post 8, the protective net 10 is dense-mesh-shaped, the net can effectively protect objects, if the net does not need to be made of metal materials, the net can also be made of common nylon ropes, the net can also play the same protection role when being tightly tied on the upright posts, but the net has a shorter service life and needs to be replaced regularly, a fifth upright post 12 is welded in the middle of the other side edge of the bottom plate 1, a fourth upright post 11 and a sixth upright post 14 are respectively welded on two sides of the fifth upright post 12, a first rail 3 is fixedly arranged between the fourth upright post 11 and the fifth upright post 12, a third rail 13 is fixedly arranged between the fifth upright post 12 and the sixth upright post 14, the third rail 13 is positioned above the fifth upright post 12 and the sixth upright post 14, the third rail 13 and the second rail 4 are positioned on the same horizontal plane, the height of the first rail 3 is lower than that of the third rail 13, the height difference range of the heights is 15-30 cm, the height difference between the first rail 3 and the third rail 13 is determined according to actual conditions, if necessary, it can be changed into a lifting structure, so that the lifting height range can be greatly increased.
The working principle is as follows: the device needs to be installed on a lifting platform to work, the height of the device is determined by the lifting platform, firstly, a worker opens a door frame 15 to enter the device, required equipment can be taken together and placed at the corner of a bottom plate 1, the device is placed by upright columns such as a third upright column 8, the dense net structure of a protective net 10 can effectively protect objects and the like placed at the bottom to prevent the objects from falling, then the door frame 15 is closed and fixed, the device can be taken out to prevent the anti-falling safety belt from being buckled on a circular ring 18 in the rising process, the moving effect of a sliding block 6 is checked by the way, if certain resistance exists during moving, a proper amount of lubricant can be dripped into the sliding groove 19, the sliding block 6 slides back and forth, so that the lubricating oil fully contacts the whole sliding groove 19 until the safety belt moves smoothly, the safety belt is just positioned at the back and cannot influence the movement of the worker, and when the, can not walk about because of operating personnel need make a round trip to influence its normal work activity, according to staff's use high custom, possess two sections not co-altitude protection fences and can supply the staff to select, the lower first banister of selectable 3 parts of height, otherwise then select third banister 13 parts, thereby make operating personnel can possess comfortable operating height, can not cause personnel's excessive consumption because of the inconvenience of operating height, indirect influence operating personnel's work efficiency.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. The utility model provides a high altitude construction workman protector, includes bottom plate (1), fender rod (9) and hinge (16), its characterized in that: the corner welding of the upper end of bottom plate (1) has first stand (2), the upper portion welding of first stand (2) has second banister (4), second banister (4) runs through second stand (5) to third stand (8), the internally mounted of second banister (4) has slider (6), fender rod (9) fixed mounting is between first stand (2) and second stand (5), the intersection position of fender rod (9) is fixed with bolt (7), be provided with door frame (15) between third stand (8) and sixth stand (14), the welding has protection network (10) around bottom plate (1), the welding has fifth stand (12) in the middle of the opposite side edge of bottom plate (1), the welding has fourth stand (11) and sixth stand (14) respectively to the both sides of fifth stand (12), fixed mounting has first banister (3) between fourth stand (11) and fifth stand (12), and a third rail (13) is fixedly arranged between the fifth upright post (12) and the sixth upright post (14).
2. A high altitude construction worker protection device as claimed in claim 1, wherein: a sliding groove (19) is formed in the second rail (4), a sliding block (6) is movably mounted in the sliding groove (19), the sliding block (6) is I-shaped, and a circular ring (18) is arranged at the bottom of the sliding block (6).
3. A high altitude construction worker protection device according to claim 1, characterized in that the bottom plate (1) is a solid structure, and the upper surface of the bottom plate (1) is provided with anti-skid lines.
4. A high altitude construction worker protection device as claimed in claim 1, wherein: hinge (16) are installed through cross screw (17) in the surface of third stand (8), hinge (16) are half to be connected on door frame (15) through cross screw (17).
5. A high altitude construction worker protection device as claimed in claim 1, wherein: the height of the protective net (10) is 25 cm, the protective net (10) is wrapped and fixed on the peripheries of the first upright post (2) and the third upright post (8), and the protective net (10) is in a dense net shape.
6. A high altitude construction worker protection device as claimed in claim 1, wherein: the third rail (13) is positioned above the fifth upright post (12) and the sixth upright post (14), the third rail (13) and the second rail (4) are positioned on the same horizontal plane, the height of the first rail (3) is lower than that of the third rail (13), and the difference height range is 15-30 cm.
CN202020613829.XU 2020-04-22 2020-04-22 High altitude construction worker protector Expired - Fee Related CN212359193U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020613829.XU CN212359193U (en) 2020-04-22 2020-04-22 High altitude construction worker protector

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020613829.XU CN212359193U (en) 2020-04-22 2020-04-22 High altitude construction worker protector

Publications (1)

Publication Number Publication Date
CN212359193U true CN212359193U (en) 2021-01-15

Family

ID=74133476

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020613829.XU Expired - Fee Related CN212359193U (en) 2020-04-22 2020-04-22 High altitude construction worker protector

Country Status (1)

Country Link
CN (1) CN212359193U (en)

Similar Documents

Publication Publication Date Title
CN202831589U (en) Movable type security operating platform
CN212359193U (en) High altitude construction worker protector
CN212024619U (en) Tower machine climbs climbing safety belt cable suspension device
CN211470608U (en) A protector for tower crane driver climbing
CN203264090U (en) Tower fall prevention safety device for work high above ground
CN219100889U (en) Anti-falling angle steel tower
CN201303221Y (en) Distribution transformer overhauling platform device on 10KV column
CN210738199U (en) Communication tower for electronic information engineering
CN114050500A (en) Power transmission line is along preventing weighing down track tower climbing manned chair
CN217872612U (en) Device for hanging safety belt on outdoor vertical ladder
CN219826052U (en) Building construction support
CN218597695U (en) Auxiliary installation mechanism of rail transit elevated section outer side guardrail
CN217838316U (en) Climbing device for rural power grid consolidation and lifting engineering
CN214399703U (en) Movable workbench capable of preventing high-altitude falling
CN213006593U (en) Bridging-preventing structure of adjustable hot melting machine
CN216276829U (en) Automatic protection scaffold
CN210460720U (en) Protection device for colliery hydraulic support
CN207364633U (en) A kind of safety slip cable system
CN209704623U (en) It is a kind of to be laid in the road of inclined gallery for protecting the flexible climbing net of flight attendant
CN211037940U (en) Safety device for building electrical construction
CN217867799U (en) Light safety protection device for crane walking channel
CN117823015A (en) Gravity type automatic closing anti-falling door for platform
CN220645802U (en) Safety platform for building external climbing ladder
CN208561510U (en) A kind of anti-climbing safety device of tower crane
Zhiyong et al. Design and Test of Self-Rescue Safety Belt for Power Line Operation at Heights

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210115