CN212358313U - Inside concrete curing equipment of piping lane - Google Patents

Inside concrete curing equipment of piping lane Download PDF

Info

Publication number
CN212358313U
CN212358313U CN202020899169.6U CN202020899169U CN212358313U CN 212358313 U CN212358313 U CN 212358313U CN 202020899169 U CN202020899169 U CN 202020899169U CN 212358313 U CN212358313 U CN 212358313U
Authority
CN
China
Prior art keywords
pipeline
water
maintenance
piping lane
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020899169.6U
Other languages
Chinese (zh)
Inventor
哈建波
梁云生
董书滨
刘兴波
董志伟
洪开荣
李志军
马新磊
黄圣
吴相斌
张文军
王秋林
师赛燚
毕海柱
刘伟
贾吉春
付彬彬
郭立亚
李晓辉
李社伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
China Railway Tunnel Group Erchu Co Ltd
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
China Railway Tunnel Group Erchu Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG, China Railway Tunnel Group Erchu Co Ltd filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN202020899169.6U priority Critical patent/CN212358313U/en
Application granted granted Critical
Publication of CN212358313U publication Critical patent/CN212358313U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a concrete curing equipment in pipe gallery, including the support frame, be used for the running gear that moves inside the pipe gallery and be used for the water route system of water storage and spraying maintenance water, the support frame includes first stand, second stand, floorbar and platform, and the floorbar is installed between first stand and second stand, and the platform sets up at the top of first stand and second stand; the travelling mechanism comprises travelling wheels, and the travelling wheels are arranged at the bottoms of the first upright post and the second upright post; the waterway system comprises a water storage tank, a water treatment device, a water pump and a maintenance pipeline, the maintenance pipeline comprises a first pipeline, a second pipeline and a third pipeline, and the first pipeline, the second pipeline and the third pipeline are respectively arranged corresponding to the side wall and the top wall inside the pipe gallery. The utility model discloses a curing equipment is at the inside reciprocating motion of piping lane, and the maintenance pipeline passes through the position that pipeline adjusting part adjusted the maintenance pipeline, and the atomizer that sets up on the maintenance pipeline evenly sprays maintenance water to piping lane inside, improves the maintenance effect of concrete.

Description

Inside concrete curing equipment of piping lane
Technical Field
The utility model belongs to the technical field of piping lane construction equipment, especially, relate to an inside concrete curing equipment of piping lane.
Background
The utility tunnel is city underground piping's utility corridor, is the tunnel form, according to the use needs, can design for single cabin piping lane, also can design for many cabins piping lane, various engineering pipelines such as city electric power, communication, gas, heat supply, plumbing all can set up in the piping lane to convenient management and maintenance. Along with the rapid development of economy, municipal utility tunnel ization development has become city construction and the mainstream trend of transformation, and at present, the inside concrete maintenance operation of piping lane is because construction space is narrow, and mechanical maintenance operation difficulty adopts artifical watering maintenance mostly, and the operation randomness is great, and the homogeneity is relatively poor, and the maintenance effect is unsatisfactory to artifical watering causes the water waste, and the maintenance cost is high.
Therefore, in order to solve the above technical problems, it is necessary to design a concrete curing apparatus suitable for the inside of a multi-cabin pipe gallery.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a simple structure, easy operation, maintenance are effectual, the maintenance is with low costs the inside concrete curing equipment of piping lane.
The technical scheme of the utility model as follows:
a concrete curing device in a pipe gallery comprises a support frame, a travelling mechanism used for moving in the pipe gallery and a waterway system used for storing water and spraying curing water;
the supporting frame comprises a first upright post, a second upright post and a bottom beam, the bottom beam is arranged between the first upright post and the second upright post, and a platform is arranged at the top of the supporting frame;
the travelling mechanism comprises travelling wheels, and the travelling wheels are arranged at the bottoms of the first upright post and the second upright post;
the water path system comprises a water storage tank, a water treatment device, a water pump and a maintenance pipeline, wherein the water storage tank is communicated with a water inlet of the water treatment device, a water outlet of the water storage tank is connected with the water pump through a water pipe, the water pump is connected with the maintenance pipeline through a water pipe, the maintenance pipeline comprises a first pipeline, a second pipeline and a third pipeline which are communicated with the water pipe, the first pipeline and the second pipeline are symmetrically installed on two sides of the support frame through pipeline adjusting components, the third pipeline is installed on the support frame through pipeline adjusting components, the third pipeline is located above the platform, and the first pipeline, the second pipeline and the third pipeline respectively correspond to side walls and top walls inside the pipe gallery to be used for spraying maintenance water into the pipe gallery respectively.
In the above technical scheme, the pipeline adjusting assembly comprises a telescopic sleeve and an adjusting core, the telescopic sleeve is connected with the support frame, one end of the adjusting core is installed in the telescopic sleeve, and the other end of the adjusting core is connected with the maintenance pipeline so as to adjust the position of the maintenance pipeline.
In the above technical scheme, the first pipeline and the second pipeline are in an inverted L shape, the third pipeline is a horizontally arranged straight pipe, and the first pipeline, the second pipeline and the third pipeline are provided with atomizing nozzles.
In the technical scheme, one side of the first pipeline and one side of the second pipeline are connected with the support frame through the horizontally arranged pipeline adjusting assembly, and the bottom of the third pipeline is connected with the support frame through the vertically arranged pipeline adjusting assembly.
In the above technical scheme, the waterway system further comprises a pressure regulating device, and the pressure regulating device is connected with the water pump through a water pipe so as to be used for regulating the water pressure of the maintenance water conveyed to the maintenance pipeline.
In the above technical scheme, the number of the first upright columns is two, the number of the second upright columns is two, the first upright columns are arranged on the front side of the maintenance equipment, and the second upright columns are arranged on the rear side of the maintenance equipment.
In the technical scheme, the walking wheels comprise two groups of walking wheels, each group of walking wheels comprises a driving wheel and a driven wheel, and the driving wheels of the two groups of walking wheels are arranged diagonally.
In the technical scheme, be equipped with detecting system on the curing equipment, detecting system includes environment humidity detection device, concrete temperature detection device, water level detection device, temperature detection device and walking switching-over trigger device, environment humidity detection device, concrete temperature detection device install on the platform of support frame, water level detection device installs the lower part of storage water tank, temperature detection device installs the delivery port of storage water tank, walking switching-over trigger device installs on the support body of walking wheel.
In the above technical scheme, the maintenance equipment is provided with a control system, and the control system is electrically connected with the detection system and the waterway system to control the operation of the maintenance equipment.
In the technical scheme, the maintenance equipment is provided with a guardrail, a ladder stand and a cable reel, the ladder stand is installed on one side of the support frame, the cable reel is installed on the support frame, and the guardrail is installed on the platform.
The utility model has the advantages and positive effects that:
1. the utility model discloses a maintenance of equipment passes through running gear at the inside reciprocating motion of piping lane, and the maintenance pipeline passes through the pipeline adjusting part and is connected with the support frame and can adjust the position of maintenance pipeline according to the construction requirement of piping lane, and the atomizer that sets up on the maintenance pipeline evenly sprays maintenance water to piping lane inside, sprays the maintenance with traditional manual work and compares, and the watering maintenance sputtering mode is little to concrete surface damage degree, improves the maintenance effect of concrete.
2. The utility model discloses a curing equipment is at inside reciprocal walking and the maintenance of piping lane, has guaranteed the promptness and the validity of maintenance, has avoided the influence of human factor to the construction effect.
3. Support frame, running gear, check out test set, waterway system's fast assembly, the narrow construction environment of adaptation many cabins piping lane inner space that can be better improves the level of mechanical maintenance operation, and it is convenient to be under construction.
4. The utility model discloses a maintenance equipment can adopt the control panel of switch board or remote controller control device's operation, and the bimodulus control mechanism can be controlled equipment in the equipment operation region or outside, and the operating position is convenient and safe.
Drawings
FIG. 1 is a front view of the concrete curing equipment inside the pipe gallery of the present invention;
FIG. 2 is a left side view of the concrete curing equipment inside the pipe gallery of the present invention;
figure 3 is the utility model discloses a top view of inside concrete curing equipment of piping lane.
In the figure:
1. track row 2, walking wheels 3 and first upright post
4. Control system 5, platform 6, pipeline adjusting part
7. First pipeline 8, guardrail 9, water treatment facilities
10. Support column 11, water storage tank 12 and water pump
13. Cable reel 14, bottom beam 15, third pipeline
16. Second pipeline 17, ladder 18, pipe gallery
19. Maintenance pipeline 20 and second upright post
Detailed Description
The present invention will be described in further detail with reference to specific examples. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the present disclosure, as defined by the following claims.
Example 1
As shown in the figures, the concrete curing equipment in the pipe rack of the utility model comprises a support frame, a traveling mechanism used for moving in the pipe rack 18, a waterway system used for storing water and spraying curing water, and a detection system used for detecting the internal environment of the pipe rack 18 and the state of the waterway system;
the support frame comprises a first upright post 3, a second upright post 20 and a bottom beam 14, wherein the bottom beam 14 is arranged between the first upright post 3 and the second upright post 20, and the top of the support frame is provided with a platform 5;
the travelling mechanism comprises a travelling wheel 2, and the travelling wheel 2 is arranged at the bottoms of the first upright post 3 and the second upright post 20;
the waterway system comprises a water storage tank 11, a water treatment device 9, a water pump 12 and a maintenance pipeline 19, the water storage tank 11 is communicated with the water inlet of the water treatment device 9, the water outlet of the water storage tank 11 is connected with the water pump 12 through a water delivery pipe, the water pump 12 is connected with a maintenance pipeline 19 through a water conveying pipe, the maintenance pipeline 19 comprises a first pipeline 7, a second pipeline 16 and a third pipeline 15 which are communicated through the water conveying pipe, the first pipeline 7 and the second pipeline 16 are symmetrically arranged at two sides of the supporting frame through the pipeline adjusting component 6, the third pipeline 15 is arranged on the supporting frame through the pipeline adjusting component 6, the third pipeline 15 is positioned above the platform 5, and the first pipeline 7, the second pipeline 16 and the third pipeline 15 are respectively arranged corresponding to the side wall and the top wall of the interior of the pipe gallery 18 and are used for respectively spraying maintenance water to the interior of the pipe gallery 18;
the detection system comprises an environment humidity detection device, a concrete temperature detection device, a water level detection device, a water temperature detection device and a walking reversing trigger device, wherein the environment humidity detection device and the concrete temperature detection device are installed on a platform 5 of the support frame, the water level detection device is installed on the lower portion of the water storage tank 11, the water temperature detection device is installed at a water outlet of the water storage tank 11, and the walking reversing trigger device is installed on a frame body of a walking wheel 2.
Further, the number of the first columns 3 is two, the number of the second columns 20 is two, the first columns 3 are arranged on the front side of the maintenance equipment, and the second columns 20 are arranged on the rear side of the maintenance equipment.
Further, the pipeline adjusting assembly 6 comprises a telescopic sleeve and an adjusting core, the telescopic sleeve is connected with the support frame, one end of the adjusting core is installed in the telescopic sleeve, the other end of the adjusting core is connected with the maintenance pipeline 19, and the extending length can be adjusted in an inner-outer telescopic mode so as to adjust the position of the maintenance pipeline 19.
Further, first pipeline 7 and second pipeline 16 are "shape of falling L", third pipeline 15 is the straight tube that the level set up, be equipped with atomizer on first pipeline 7, second pipeline 16 and the third pipeline 15, the pipeline adjusting part 6 that the level set up is passed through to one side of first pipeline 7 and second pipeline 16 installs the rear side at the support frame (installs on second stand 20), the pipeline adjusting part 6 that the bottom of third pipeline 15 was passed through vertical setting is installed on the support frame.
Furthermore, each group of the walking wheels 2 are connected with the first upright post 3 and the second upright post 20 through bolts, and a driven wheel in each group of the walking wheels 2 is driven by a driving wheel to move.
Furthermore, the environment humidity detection device (adopting a humidity sensor), the concrete temperature detection device (adopting a temperature sensor), the water level detection device (adopting a liquid level sensor), the water temperature detection device (adopting a temperature sensor) and the walking reversing trigger device (adopting a limit switch), the environment humidity detection device and the concrete temperature detection device are arranged on the platform 5 of the support frame and are used for detecting the environment humidity inside the pipe gallery 18 and the temperature of concrete, the water level detection device is installed at the lower part of the water storage tank 11 for detecting the water level condition in the water storage tank 11, the water temperature detection device is arranged at the water outlet of the water storage tank 11 and is used for detecting the temperature of the maintenance water output by the water storage tank 11, the walking reversing trigger device is installed on the frame body of the walking wheel 2 and used for triggering reversing after the maintenance equipment runs to a preset position.
Furthermore, a control system 4 is arranged on the maintenance equipment, the control system 4 is electrically connected with the detection system and the waterway system to control the operation of the maintenance equipment, the control system 4 receives the information collected by the detection system and controls the maintenance equipment to perform maintenance operation in a preset interval according to the program setting of the control system 4, the control system 4 comprises a control cabinet arranged on the support frame and a remote controller used for remotely controlling the operation of the maintenance equipment, and an operation panel is arranged outside the control cabinet.
Lay prefabricated track row 1 on the bottom plate of piping lane 18, walking wheel 2 removes on track row 1, and maintenance equipment can move in the inside constrictive construction space of piping lane 18, need not the manual work and sprays maintenance water and carry out the maintenance, and the degree of consistency of spraying is good, effectively improves the maintenance effect of concrete.
Example 2
On the basis of embodiment 1, the waterway system further comprises a pressure regulating device, and the pressure regulating device is connected with the water pump 12 through a water pipe and is used for regulating the water pressure of the curing water conveyed to the curing pipeline 19.
Further, a support column 10 is arranged in the middle of the bottom beam 14, and the top of the support column 10 is connected with the bottom surface of the platform 5.
Furthermore, the water treatment device 9 comprises a filtering water tank filled with activated carbon or filtering sand and a clean water tank, and the water pump 12 is communicated with the clean water tank and used for pumping the purified maintenance water pump 12 into the maintenance pipeline 19, so that the maintenance water is sprayed to the concrete inside the pipe gallery 18 for maintenance work.
The maintenance water in the water storage tank 11 is treated by the water treatment device 9 to remove substances such as impurity particles in the water, the cleanliness of the maintenance water is protected, the blockage of a water delivery pipe and an atomizing spray head is reduced, meanwhile, according to the regulation of technical regulations on railway engineering construction safety, the temperature difference between the maintenance water temperature and the concrete surface temperature does not exceed 15 ℃, the temperature is monitored by a detection system, the temperature difference between the maintenance water temperature and the concrete surface temperature is strictly controlled not to exceed 15 ℃, and the maintenance effect of the concrete is improved.
Example 3
On the basis of embodiment 1, be equipped with guardrail 8, cat ladder 17 and cable reel 13 on the maintenance equipment, cat ladder 17 is installed in the rear side of support frame, cable reel 13 is installed the front side of support frame, guardrail 8 is installed on platform 5.
Spatially relative terms, such as "upper," "lower," "left," "right," and the like, may be used in the embodiments for ease of description to describe one element or feature's relationship to another element or feature as illustrated in the figures. It will be understood that the spatial terms are intended to encompass different orientations of the device in use or operation in addition to the orientation depicted in the figures. For example, if the device in the figures is turned over, elements described as "below" other elements or features would then be oriented "above" the other elements or features. Thus, the exemplary term "lower" can encompass both an upper and a lower orientation. The device may be otherwise oriented (rotated 90 degrees or at other orientations) and the spatially relative descriptors used herein interpreted accordingly.
Moreover, relational terms such as "first" and "second," and the like, may be used solely to distinguish one element from another element having the same name, without necessarily requiring or implying any actual such relationship or order between such elements.
While one embodiment of the present invention has been described in detail, the description is only a preferred embodiment of the present invention, and should not be considered as limiting the scope of the present invention. All equivalent changes, modifications and the like made in accordance with the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims (10)

1. The utility model provides an inside concrete curing equipment of piping lane which characterized in that: comprises a supporting frame, a travelling mechanism used for moving in the pipe gallery and a waterway system used for storing and spraying curing water;
the supporting frame comprises a first upright post, a second upright post and a bottom beam, the bottom beam is arranged between the first upright post and the second upright post, and a platform is arranged at the top of the supporting frame;
the travelling mechanism comprises travelling wheels, and the travelling wheels are arranged at the bottoms of the first upright post and the second upright post;
the water path system comprises a water storage tank, a water treatment device, a water pump and a maintenance pipeline, wherein the water storage tank is communicated with a water inlet of the water treatment device, a water outlet of the water storage tank is connected with the water pump through a water pipe, the water pump is connected with the maintenance pipeline through a water pipe, the maintenance pipeline comprises a first pipeline, a second pipeline and a third pipeline which are communicated with the water pipe, the first pipeline and the second pipeline are symmetrically installed on two sides of the support frame through pipeline adjusting components, the third pipeline is installed on the support frame through pipeline adjusting components, the third pipeline is located above the platform, and the first pipeline, the second pipeline and the third pipeline respectively correspond to side walls and top walls inside the pipe gallery to be used for spraying maintenance water into the pipe gallery respectively.
2. The inside concrete curing equipment of piping lane of claim 1, characterized in that: the pipeline adjusting assembly comprises a telescopic sleeve and an adjusting core, the telescopic sleeve is connected with the support frame, one end of the adjusting core is installed in the telescopic sleeve, and the other end of the adjusting core is connected with the maintenance pipeline to adjust the position of the maintenance pipeline.
3. The inside concrete curing equipment of piping lane of claim 2, characterized in that: the first pipeline and the second pipeline are in an inverted L shape, the third pipeline is a straight pipe arranged horizontally, and the first pipeline, the second pipeline and the third pipeline are provided with atomizing nozzles.
4. The inside concrete curing equipment of piping lane of claim 3, characterized in that: one side of the first pipeline and one side of the second pipeline are connected with the support frame through the horizontally arranged pipeline adjusting assemblies, and the bottom of the third pipeline is connected with the support frame through the vertically arranged pipeline adjusting assemblies.
5. The inside concrete curing equipment of piping lane of claim 4, characterized in that: the waterway system further comprises a pressure regulating device, and the pressure regulating device is connected with the water pump through a water pipe and is used for regulating the water pressure of the maintenance water conveyed to the maintenance pipeline.
6. The inside concrete curing equipment of piping lane of claim 1, characterized in that: the number of the first stand columns is two, the number of the second stand columns is two, the first stand columns are arranged on the front side of the maintenance equipment, and the second stand columns are arranged on the rear side of the maintenance equipment.
7. The inside concrete curing equipment of piping lane of claim 1, characterized in that: the walking wheels comprise two groups of walking wheels, each group of walking wheels comprises a driving wheel and a driven wheel, and the driving wheels of the two groups of walking wheels are arranged diagonally.
8. The inside concrete curing equipment of piping lane of claim 1, characterized in that: be equipped with detecting system on the curing equipment, detecting system includes ambient humidity detection device, concrete temperature-detecting device, water level detection device, temperature detection device and walking switching-over trigger device, ambient humidity detection device, concrete temperature detection device install on the platform of support frame, water level detection device installs the lower part of storage water tank, water temperature detection device installs the delivery port of storage water tank, walking switching-over trigger device installs on the support body of walking wheel.
9. The inside concrete curing equipment of piping lane of claim 8, characterized in that: and the maintenance equipment is provided with a control system, and the control system is electrically connected with the detection system and the waterway system and is used for controlling the operation of the maintenance equipment.
10. The inside concrete curing equipment of piping lane of claim 1, characterized in that: the maintenance equipment is provided with a guardrail, a ladder stand and a cable reel, the ladder stand is installed on one side of the supporting frame, the cable reel is installed on the supporting frame, and the guardrail is installed on the platform.
CN202020899169.6U 2020-05-25 2020-05-25 Inside concrete curing equipment of piping lane Active CN212358313U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020899169.6U CN212358313U (en) 2020-05-25 2020-05-25 Inside concrete curing equipment of piping lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020899169.6U CN212358313U (en) 2020-05-25 2020-05-25 Inside concrete curing equipment of piping lane

Publications (1)

Publication Number Publication Date
CN212358313U true CN212358313U (en) 2021-01-15

Family

ID=74155003

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020899169.6U Active CN212358313U (en) 2020-05-25 2020-05-25 Inside concrete curing equipment of piping lane

Country Status (1)

Country Link
CN (1) CN212358313U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636429A (en) * 2020-05-25 2020-09-08 中铁隧道集团二处有限公司 Concrete curing equipment in piping lane

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636429A (en) * 2020-05-25 2020-09-08 中铁隧道集团二处有限公司 Concrete curing equipment in piping lane

Similar Documents

Publication Publication Date Title
CN107053444A (en) A kind of box beam automatic spraying device
CN208778004U (en) A kind of tunnel automatic spray maintenance trolley
CN109236326B (en) Intelligent tunnel two-lining spraying maintenance trolley
CN207177922U (en) Electronic walking type tunnel form concrete health chassis
CN212358313U (en) Inside concrete curing equipment of piping lane
CN108678800A (en) A kind of tunnel health dust-extraction unit and dust removal method
CN110637800B (en) Automatic medicine spraying system
CN203523467U (en) Automatic sprinkling device
CN203024300U (en) Mobile mist curtain type spray cooling equipment
CN113211617B (en) Energy-saving prefabricated Liang Yanghu spraying system
CN111636429A (en) Concrete curing equipment in piping lane
CN111809458A (en) Self-flowing type ballast bed sprinkling system
CN208660681U (en) A kind of building site slag-soil truck Dust Improvement device
CN112814727A (en) Tunnel construction dust monitoring and automatic water spraying system
CN103392563A (en) Automatic sprinkling irrigation equipment
WO2006000026A1 (en) Irrigation of race tracks
CN108043143B (en) Air purification system for treating road surface haze
CN208230161U (en) Automatic spraying device and box beam curing system
CN111058871A (en) Two lining concrete self-propelled spray curing means in tunnel
CN206242237U (en) A kind of box beam automatic spraying device
CN211513889U (en) Vehicle-mounted air purification device
CN111720141A (en) Maintenance method based on four-cabin pipe gallery internal concrete maintenance equipment
CN209809103U (en) Vehicle disinfection channel
CN203140388U (en) Automatic cleaning device for chemical reaction kettle
CN219990103U (en) Traditional Chinese medicine curing greenhouse

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant