CN212356802U - Stabilizer workshop circulating cooling water system - Google Patents

Stabilizer workshop circulating cooling water system Download PDF

Info

Publication number
CN212356802U
CN212356802U CN202020175856.3U CN202020175856U CN212356802U CN 212356802 U CN212356802 U CN 212356802U CN 202020175856 U CN202020175856 U CN 202020175856U CN 212356802 U CN212356802 U CN 212356802U
Authority
CN
China
Prior art keywords
water
workshop
stabilizer
water system
circulating cooling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020175856.3U
Other languages
Chinese (zh)
Inventor
谭学政
蒋建林
潘学良
冯国良
魏先刚
张佃群
庞松强
魏坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Sanyi Group Co ltd
Original Assignee
Shandong Sanyi Industrial Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Sanyi Industrial Co ltd filed Critical Shandong Sanyi Industrial Co ltd
Priority to CN202020175856.3U priority Critical patent/CN212356802U/en
Application granted granted Critical
Publication of CN212356802U publication Critical patent/CN212356802U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a stabilizer workshop circulation cooling water system relates to water circulating system technical field, including the cistern, stabilizer workshop water system and chlorinated polyethylene workshop water system, install the immersible pump in the cistern, the immersible pump is held through the end of intaking of first water piping connection to stabilizer workshop water system, stabilizer workshop water system's play water end is connected to the cistern through first drain pipe, be connected with the second inlet tube on the first drain pipe, the second advances water piping connection to chlorinated polyethylene workshop water system's the end of intaking, first inlet tube, all install the valve on first drain pipe and the second inlet tube. The utility model provides a thermal technical problem after stabilizer workshop water-cooling is handled among the prior art, the utility model discloses with the effectual utilization of heat after the stabilizer workshop water-cooling is handled in the washing technology of chlorinated polyethylene, improved the washing quality promptly, realized energy-conserving production again.

Description

Stabilizer workshop circulating cooling water system
Technical Field
The utility model relates to a hydrologic cycle technical field, in particular to stabilizer workshop circulation cooling water system.
Background
Stabilizer workshop needs water-cooling to handle, need follow the cistern and introduce cold water, and cold water absorbs the heat after the heat exchange and flows back in the cistern for this part of heat can not got up by effectual utilization, leads to the waste of energy.
SUMMERY OF THE UTILITY MODEL
To above defect, the utility model aims at providing a stabilizer workshop circulation cooling water system aims at solving among the prior art technical problem that the heat after the water-cooling of stabilizer workshop is handled can not effectively be utilized.
In order to solve the technical problem, the technical scheme of the utility model is that:
the utility model provides a stabilizer workshop circulation cooling water system, including the cistern, stabilizer workshop water system and chlorinated polyethylene workshop water system, install the immersible pump in the cistern, the immersible pump is held through the end of intaking of first water piping connection to stabilizer workshop water system, the play water end of stabilizer workshop water system is connected to the cistern through first drain pipe, be connected with the second inlet tube on the first drain pipe, the second advances water piping connection to chlorinated polyethylene workshop water system's the end of intaking, first inlet tube, all install the valve on first drain pipe and the second inlet tube.
Wherein, chlorinated polyethylene workshop water system's play water end is connected to the wastewater disposal basin through the second drain pipe, and the wastewater disposal basin top is connected to the cistern through the third drain pipe, and the wastewater disposal basin has the neutralizer storage tank through feed liquor union coupling, and the water pump is all installed with the feed liquor pipe to the third drain pipe.
Wherein, the bottom of the wastewater disposal basin is provided with a drain outlet provided with a valve.
Wherein, the third drain pipe is connected with a filter device in series.
The top of the reservoir is connected with a water supply source through a third water inlet pipe, the third water inlet pipe is provided with an electromagnetic valve, an electronic liquid level meter is arranged in the reservoir, and the electronic liquid level meter and the electromagnetic valve are electrically connected to the same control system.
Wherein, the second water inlet pipe is provided with a speed regulating valve.
Wherein, install manometer and thermocouple thermometer on the first inlet tube.
After the technical scheme is adopted, the beneficial effects of the utility model are that:
because the utility model discloses stabilizer workshop circulation cooling water system includes the cistern, stabilizer workshop water system and chlorinated polyethylene workshop water system, install the immersible pump in the cistern, the immersible pump is held through the end of intaking of first advance water piping connection to stabilizer workshop water system, stabilizer workshop water system's play water end is connected to the cistern through first drain pipe, be connected with the second inlet tube on the first drain pipe, the second advances water piping connection to chlorinated polyethylene workshop water system's the end of intaking, first inlet tube, all install the valve on first drain pipe and the second inlet tube. After the water conveyed by the reservoir absorbs heat in the production of the stabilizer, one part of water flows back to the reservoir, and the other part of water enters a water system for chlorinated polyethylene workshop and is used for washing the chlorinated polyethylene, so that the excessive heat in the stabilizer workshop is used for washing the chlorinated polyethylene, the washing effect is effectively improved, and the energy waste is reduced.
Because chlorinated polyethylene workshop water system's play water end is connected to the wastewater disposal basin through the second drain pipe, the wastewater disposal basin top is connected to the cistern through the third drain pipe, the wastewater disposal basin has the neutralizer storage tank through the feed liquor union coupling, the water pump is all installed with the feed liquor pipe to the third drain pipe, because the waste liquid is acidity, waste water discharges back in the wastewater disposal basin, the water pump on the feed liquor pipe carries out neutralization reaction with the alkali lye suction in the neutralizer storage tank to the wastewater disposal basin in, and the sediment of stewing, upper water after the sediment is pumped back to the cistern through the water pump of third drain pipe, realize the recycle of water.
Because the bottom of the wastewater pool is provided with the drain outlet provided with the valve, the lower-layer sediments in the wastewater pool can be effectively emptied, and the wastewater pool is convenient to clean.
Because the third drain pipe is connected with the filtering device in series, impurities of water flowing back to the reservoir are filtered, the water recycling performance is improved, and the pollution of the backflow water to the reservoir is reduced.
To sum up, the utility model provides a thermal technical problem after stabilizer workshop water-cooling is handled among the prior art, the utility model discloses with the effectual utilization of heat after the stabilizer workshop water-cooling is handled in the washing technology of chlorinated polyethylene, improved the washing quality promptly, realized energy-conserving production again.
Drawings
FIG. 1 is a schematic structural diagram of a first embodiment of a circulating cooling water system in a stabilizer workshop according to the present invention;
FIG. 2 is a schematic structural diagram of a second embodiment of the circulating cooling water system in the stabilizer workshop according to the present invention;
in the figure, a water storage tank 1, a submersible pump 10, an electronic liquid level meter 11, a stabilizer workshop water system 2, a chlorinated polyethylene workshop water system 3, a wastewater pond 4, a neutralizer storage tank 40, a sewage discharge port 41, a filtering device 42, a pressure gauge 50, a thermocouple thermometer 51, a speed regulating valve 52 and an electromagnetic valve 53.
Detailed Description
The present invention will be further explained with reference to the accompanying drawings.
The position that the direction that involves in this specification all takes the position of the utility model discloses a stabilizer workshop circulating cooling water system during normal operating as the standard, does not restrict the position when its storage and transportation, only represents relative position relation, does not represent absolute position relation.
The first embodiment is as follows:
as shown in fig. 1, the stabilizer workshop circulating cooling water system comprises a water storage tank 1, a stabilizer workshop water system 2 and a chlorinated polyethylene workshop water system 3, water with the temperature lower than 15 ℃ is stored in the water storage tank 1, the stabilizer workshop water system 2 and the chlorinated polyethylene workshop water system 3 both comprise a water inlet end and a water outlet end, a submersible pump 10 is installed in the water storage tank 1, the water outlet end of the submersible pump 10 is connected with one end of a first water inlet pipe, the other end of the first water inlet pipe is connected to the water inlet end of the stabilizer workshop water system 2, the water outlet end of the stabilizer workshop water system 2 flows back to the water storage tank 1 through a first water drainage pipe, the first water drainage pipe is connected with one end of a second water inlet pipe through a tap, the other end of the second water inlet pipe is connected to the water inlet end of the chlorinated polyethylene workshop water system 3, valves are installed on the first water inlet pipe, the first water drainage, the valve is preferably a ball valve. When the device is used, the submersible pump 10 pumps water in the water storage tank 1 into the stabilizer workshop water consumption system 2, heat in stabilizer production is absorbed through a heat exchange principle, the temperature of the stabilizer production system is reduced, the temperature of the heated water reaches 40-60 ℃, part of the water flows back into the water storage tank 1, the other part of the water flows into the chlorinated polyethylene workshop water consumption system 3 and is used for washing chlorinated polyethylene, waste water after washing is discharged after sewage treatment, and the waste water can also flow back into the water storage tank 1 after sewage treatment, so that more heat in the stabilizer workshop is used for washing the chlorinated polyethylene, the washing effect is effectively improved, and energy waste is reduced.
Further, the top of the reservoir 1 is connected with a water supply source through a third water inlet pipe, a solenoid valve 53 is installed on the third water inlet pipe, an electronic liquid level meter 11 is installed in the reservoir 1, the electronic liquid level meter 11 is electrically connected with the solenoid valve 53 to the same control system, when the water level in the reservoir 1 is lower than a preset low water level, the electronic liquid level meter 11 sends a detection signal to the control system, the control system controls the solenoid valve 53 to be opened, a water pump assembly of the water supply source pumps water into the reservoir 1, until the electronic liquid level meter 11 detects that the water level in the reservoir 1 reaches a preset high water level, water supply is stopped, and the solenoid valve 53 is closed.
Further, a speed regulating valve 52 is installed on the second water inlet pipe and used for accurately controlling the water inflow of the second water inlet pipe.
Further, install manometer 50 and thermocouple thermometer 51 on the first inlet tube, manometer 50 is used for detecting water supply system's pressure value, and thermocouple thermometer 51 is used for detecting water supply temperature, synthesizes and forms the protection to immersible pump 10.
Example 2:
the difference between this embodiment and the first embodiment is that, as shown in fig. 2, the water outlet end of the chlorinated polyethylene workshop water system 3 is connected with one end of the second drain pipe, the other end of the second drain pipe is connected with the middle part of the wastewater pond 4, the top of the wastewater pond 4 is connected with one end of the third drain pipe, the other end of the third drain pipe is connected with the top of the reservoir 1, the wastewater pond 4 is connected with the neutralizer storage tank 40 through the liquid inlet pipe, and the water pumps are installed on the third drain pipe and the liquid inlet pipe. Because the waste liquid is acidic, after the waste water is discharged into the waste water tank 4, the alkali liquor in the neutralizer storage tank 40 is pumped into the waste water tank 4 by the water pump on the liquid inlet pipe for neutralization reaction, and the waste water is stood for precipitation, and the precipitated upper-layer water is pumped back into the reservoir 1 by the water pump of the third drain pipe, so that the water is recycled.
Further, the bottom of the wastewater tank 4 is provided with a drain outlet 41 provided with a valve for emptying the lower sediment in the wastewater tank 4.
Furthermore, a filter device 42 is connected in series to the third drain pipe for filtering impurities from the water returning to the water reservoir 1.
The present invention is not limited to the above specific embodiments, and those skilled in the art can make various changes without creative labor from the above conception, and all the changes fall within the protection scope of the present invention.

Claims (7)

1. The utility model provides a stabilizer workshop circulation cooling water system, includes cistern, stabilizer workshop water system and chlorinated polyethylene workshop water system, install the immersible pump in the cistern, the immersible pump is connected to through first inlet tube the end of intaking of stabilizer workshop water system, the play water end of stabilizer workshop water system is connected to through first drain pipe the cistern, its characterized in that, be connected with the second inlet tube on the first drain pipe, the second advances water piping connection to chlorinated polyethylene workshop water system's the end of intaking, first inlet tube first drain pipe and all install the valve on the second inlet tube.
2. The stabilizer plant circulating cooling water system as claimed in claim 1, wherein the water outlet end of the chlorinated polyethylene plant water system is connected to a wastewater pool through a second water discharge pipe, the top of the wastewater pool is connected to the water reservoir through a third water discharge pipe, the wastewater pool is connected to a neutralizer storage tank through a liquid inlet pipe, and a water pump is installed on each of the third water discharge pipe and the liquid inlet pipe.
3. The stabilizer workshop circulating cooling water system as claimed in claim 2, wherein a drain outlet provided with a valve is arranged at the bottom of the wastewater tank.
4. The stabilizer workshop circulating cooling water system as claimed in claim 2, wherein the third water discharge pipe is connected with a filtering device in series.
5. The stabilizer workshop circulating cooling water system as claimed in claim 1, wherein the top of the reservoir is connected with a water supply source through a third water inlet pipe, a solenoid valve is installed on the third water inlet pipe, an electronic liquid level meter is installed in the reservoir, and the electronic liquid level meter and the solenoid valve are electrically connected with the same control system.
6. The stabilizer workshop circulating cooling water system as claimed in claim 1, wherein the second water inlet pipe is provided with a speed regulating valve.
7. The stabilizer workshop circulating cooling water system as claimed in any one of claims 1 to 6, wherein the first water inlet pipe is provided with a pressure gauge and a thermocouple thermometer.
CN202020175856.3U 2020-02-17 2020-02-17 Stabilizer workshop circulating cooling water system Active CN212356802U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020175856.3U CN212356802U (en) 2020-02-17 2020-02-17 Stabilizer workshop circulating cooling water system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020175856.3U CN212356802U (en) 2020-02-17 2020-02-17 Stabilizer workshop circulating cooling water system

Publications (1)

Publication Number Publication Date
CN212356802U true CN212356802U (en) 2021-01-15

Family

ID=74144938

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020175856.3U Active CN212356802U (en) 2020-02-17 2020-02-17 Stabilizer workshop circulating cooling water system

Country Status (1)

Country Link
CN (1) CN212356802U (en)

Similar Documents

Publication Publication Date Title
CN102287861B (en) Heating afterheat automatically reclaiming system
CN1916510A (en) Wash apparatus of heat pump of recovering residual heat from bathhouse
CN205580291U (en) Plate heat exchanger from belt cleaning device
CN109578974A (en) A kind of boiler waste heat recovery system and energy-saving boiler system
CN107060002A (en) Water purifier waste water recycling system and the method that moisturizing is carried out to electric heater
CN212356802U (en) Stabilizer workshop circulating cooling water system
CN204611732U (en) A kind of blowdown system
CN206486921U (en) A kind of intelligent environmental protection type house water system
CN216255232U (en) Heat recovery system of konjak cooking pond
CN202757258U (en) Heat-pump water heater
CN206989753U (en) Cheese dyeing waste water residual heat utilizes device
CN206768931U (en) Water purifier waste water recycling system for intelligent domestic
CN201322557Y (en) Bath waste water residual heat reclaiming energy saver
CN207294469U (en) Water purifier wastewater recycling system
CN218379919U (en) Water source heat pump hot water system for recovering waste water and waste heat by utilizing fire pool
CN212362496U (en) Waste heat recovery automation device
CN206339005U (en) A kind of cooling water circulation reutilization system
CN214090162U (en) Novel water resource energy-saving equipment
CN107339896A (en) Cheese dyeing waste water residual heat utilizes device
CN215295919U (en) Heat exchange device for landfill leachate treatment
CN216008826U (en) Plunger pump hydraulic oil-water cooling device
CN209516836U (en) A kind of generator cooling-water water charging system
CN205102248U (en) Sanitary wastewater waste heat recovery heating system of family
CN216172214U (en) High-efficient hybrid hot water circulation module
CN217873220U (en) Machine seals water closed circulation device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: No.135, Huilongshan Road, Longshan hi tech Industrial Park, Linqu County, Weifang City, Shandong Province 262600

Patentee after: Shandong Sanyi Group Co.,Ltd.

Address before: No.135, Huilongshan Road, Longshan hi tech Industrial Park, Linqu County, Weifang City, Shandong Province 262600

Patentee before: SHANDONG SANYI INDUSTRIAL CO.,LTD.

CP01 Change in the name or title of a patent holder