CN212336832U - GIS removes installation factory building arrangement structure - Google Patents

GIS removes installation factory building arrangement structure Download PDF

Info

Publication number
CN212336832U
CN212336832U CN202022215424.3U CN202022215424U CN212336832U CN 212336832 U CN212336832 U CN 212336832U CN 202022215424 U CN202022215424 U CN 202022215424U CN 212336832 U CN212336832 U CN 212336832U
Authority
CN
China
Prior art keywords
gis
factory building
installation
track
vertical direction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022215424.3U
Other languages
Chinese (zh)
Inventor
韩志萍
周春雨
王兴谦
康鹏
张海明
刘小刚
马占国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northwest Electric Power Design Institute of China Power Engineering Consulting Group
State Grid Qinghai Electric Power Co Ltd
Original Assignee
Northwest Electric Power Design Institute of China Power Engineering Consulting Group
State Grid Qinghai Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northwest Electric Power Design Institute of China Power Engineering Consulting Group, State Grid Qinghai Electric Power Co Ltd filed Critical Northwest Electric Power Design Institute of China Power Engineering Consulting Group
Priority to CN202022215424.3U priority Critical patent/CN212336832U/en
Application granted granted Critical
Publication of CN212336832U publication Critical patent/CN212336832U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a GIS removes installation factory building arrangement structure, including the horizontal direction removal track and the vertical direction removal track that are L type cross arrangement, the horizontal direction and the vertical direction of installation factory building are provided with the walking crane respectively, and the factory building running gear that the installation factory building passes through the bottom sprag can follow horizontal direction removal track and vertical direction removal track and remove, and horizontal direction removal track and vertical direction removal orbital cross position are provided with and are used for installing the factory building elevating gear that the factory building rises, provide the rotatory 90 operating space of factory building running gear. The utility model discloses a GIS equipment need not dismantle and reassemble the factory building and can turn to when "L" type is arranged, has improved the quality and the installation rate of GIS installation.

Description

GIS removes installation factory building arrangement structure
Technical Field
The utility model belongs to super high voltage power transmission and transformation field, concretely relates to GIS removes installation factory building arrangement structure.
Background
Along with the high-speed development of power grid construction, the scale of an ultrahigh voltage transformer substation project is larger and larger, and the problem that the occupied area is large when conventional power distribution devices are adopted for arrangement is more and more prominent. In the design of a part of 750kV transformer substations, in order to meet the requirements of smooth outgoing lines, land occupation saving, reduction of field excavation and filling engineering quantity and the like, 800kV GIS equipment is generally arranged in an L shape.
In order to ensure the installation quality of the GIS, the GIS needs to be installed in a dust-free, impurity-free, dry and clean GIS mobile factory environment, so that the installation environment of the GIS is improved, the construction period is shortened, and all-weather installation conditions are realized.
The 800kV GIS equipment of the conventional transformer substation is arranged in a straight line shape, and an 800kV GIS mobile workshop is pushed forward along with the GIS arranged in the straight line shape. When the GIS equipment needs to be arranged in an L shape, the GIS mobile plant is firstly detached and then installed on the plant rail after turning again before the L-shaped turning, so that the construction can be continued. In the dismantling process, the GIS equipment and the bus at the L-shaped corner are exposed in the air, so that the mobile workshop parts are difficult to avoid falling off during dismantling, and the damage to the GIS equipment is possibly caused; and the construction period is long, hidden dangers are brought to the installation quality of GIS equipment, and influences are brought to the construction of the whole transformer substation.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a turn to and remove the problem when arranging to above-mentioned among the prior art 800kV GIS equipment adoption "L" type, provide a GIS and remove installation factory building arrangement structure, when realizing that GIS equipment "L" type is arranged, need not dismantle and reassemble the function that the factory building can turn to again, improve the quality of GIS installation, shorten construction period.
In order to achieve the above object, the utility model provides a GIS removes installation factory building arrangement structure has following technical scheme: including the horizontal direction removal track and the vertical direction removal track that are L type cross arrangement, the horizontal direction and the vertical direction of installation factory building set up the walking crane respectively, the installation factory building can remove along horizontal direction removal track and vertical direction removal track through factory building running gear, horizontal direction removal track and vertical direction removal orbital cross position are provided with and are used for installing the factory building rising device that the factory building risees, provide the rotatory 90 operating space of factory building running gear.
Preferably, horizontal direction remove the track and the vertical direction remove the track all including two tracks of parallel arrangement, two track intervals that horizontal direction removed the track and the vertical direction removes the track are equal, the installation factory building be square factory building.
Preferably, 800kV three-phase GIS equipment, 800kV three-phase GIS I bus and 800kV three-phase GIS II bus in the horizontal direction are arranged between two tracks of the horizontal direction moving track, 800kV three-phase GIS equipment, 800kV three-phase GIS I bus and 800kV three-phase GIS II bus in the vertical direction are arranged between two tracks of the vertical direction moving track, and the horizontal direction intersects with the 800kV three-phase GIS equipment, 800kV three-phase GIS I bus and 800kV three-phase GIS II bus in the vertical direction.
Preferably, a plant lifting device is arranged at the intersection position of the two rails of the horizontal direction moving rail and the vertical direction moving rail.
Preferably, the factory building lifting device adopts a jack, and the jack is pre-embedded at a set position.
Preferably, the bottom of the installation workshop is provided with a clamping groove, and the workshop travelling mechanism rotates and then falls into the clamping groove again.
Preferably, a frame is arranged on the periphery of the installation workshop, and a color steel plate is laid on the frame to realize sealing and heat insulation.
The utility model discloses GIS removes mobile method of installing factory building arrangement structure, including following step:
on L type cross arrangement's horizontal direction removal track and vertical direction removal track, support the installation factory building through factory building running gear and remove along horizontal direction removal track or vertical direction removal track, when removing to horizontal direction removal track and vertical direction removal orbital cross position, rise the installation factory building through factory building rising device, accomplish orbital switching with factory building running gear rotation 90 again, then fall down the installation factory building and combine with factory building running gear again, realize that the L type turns to.
Compared with the prior art, the utility model discloses following beneficial effect has: the mobile installation workshop does not need to be disassembled and reassembled, and the fine installation of the L-shaped arrangement of the 800kV outdoor GIS equipment can be realized, so that the quality of GIS installation is improved, and the construction period is shortened. The utility model discloses a factory building layout structure installation flexibility is high, can adapt to the arbitrary direction installation of GIS equipment that "L" type was arranged. The utility model discloses can ensure "L" type GIS equipment fixing environment, improve GIS installation work efficiency, realize whole batch production installation, because the track all sets up and follows outside GIS equipment foundation, the butt joint is accomplished on GIS installation place completely, does not occupy the peripheral place. The utility model discloses a GIS equipment fixing finishes the back, and the factory building track can be backfilled or dismantled, does not influence GIS equipment foundation. The utility model discloses a remove the installation factory building and can used repeatedly in a plurality of projects, expect that economic benefits is good.
Drawings
The local schematic diagram of 1800 kV outdoor GIS L-shaped arrangement is shown;
FIG. 2 is a schematic diagram of an arrangement structure of an 800kV outdoor GIS movable installation workshop;
in the drawings: 1-moving the rail in a horizontal direction; 2-moving the rail in the vertical direction; 3-a plant walking mechanism in the horizontal direction; 4-a plant walking mechanism in the vertical direction; 5-a plant lifting device; 6-running a crane in parallel with water in the plant; 7-vertically walking the crane in the factory building.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
The utility model is suitable for an installation factory building arrangement structure is arranged to 800kV GIS equipment "L" type, realizes not dismantling and reassembles 800kV GIS factory building, can accomplish 800kV GIS equipment "L" type promptly and arrange fast assembly.
Referring to fig. 1-2, the utility model discloses a GIS removes installation factory building arrangement structure, including the horizontal direction that is L type cross arrangement removal track 1 and the vertical direction removal track 2, the horizontal direction and the vertical direction of installation factory building are provided with the interior water parallel of factory building and walk capable crane 6 and the interior vertical direction of factory building respectively and walk capable crane 7, the installation factory building can remove track 1 and vertical direction removal track 2 along the horizontal direction through the factory building running gear of bottom sprag, horizontal direction removal track 1 and vertical direction removal track 2 all include two tracks of parallel arrangement, two track intervals that horizontal direction removal track 1 and vertical direction removed track 2 equal, the installation factory building is the square factory building. The horizontal direction removes 800kV three-phase GIS equipment, 800kV three-phase GIS I generating line and 800kV three-phase GIS II generating line of arranging the horizontal direction between two tracks of track 1, and the vertical direction removes 800kV three-phase GIS equipment, 800kV three-phase GIS I generating line and 800kV three-phase GIS II generating line of arranging the vertical direction between two tracks of track 2, and the horizontal direction is crossing with the vertical direction's 800kV three-phase GIS equipment, 800kV three-phase GIS I generating line and 800kV three-phase GIS II generating line. The crossing positions of the two rails of the horizontal moving rail 1 and the vertical moving rail 2 are provided with a plant lifting device 5, and the plant lifting device 5 is used for lifting an installation plant, so that an operation space for rotating the plant travelling mechanism by 90 degrees is provided. The factory building lifting device 5 adopts a jack which is pre-embedded at a set position. The bottom of installation factory building is equipped with the draw-in groove of cooperation factory building running gear, can fall into the draw-in groove again after the rotatory 90 of factory building running gear. The periphery of the installation workshop is provided with a frame, and a color steel plate is laid on the frame to realize sealing and heat insulation.
The utility model discloses GIS removes mobile method of installing factory building arrangement structure, including following step:
on L type cross arrangement's horizontal direction removal track 1 and vertical direction removal track 2, support the installation factory building and remove along horizontal direction removal track 1 or vertical direction removal track 2 through factory building running gear and remove, when removing to the crossing position of horizontal direction removal track 1 and vertical direction removal track 2, rise the installation factory building through factory building rising device 5, again with the rotation of factory building running gear 90, will install the factory building again and fall and combine with factory building running gear.
The following exemplary is given the utility model discloses the working process that removes factory building L type and turn to:
1. a is an equipment to-be-installed area, B is a mobile workshop, before GIS installation is carried out, B is controlled to move on a track along the equipment direction, the area A is emptied, then a travelling crane is used for hoisting a GIS unit to be installed and butted into the area A, an assembly workshop B is moved to the area A, sealing, dust removal, dehumidification and other work are carried out, the assembly workshop B can be butted and installed after the installation environment meets the requirements, for the units with heavier specific weight such as a breaker, the travelling crane is directly used for accurately positioning, other units are hoisted to the area to be installed by the crane, and hoisting and butting are carried out by a travelling crane in the mobile workshop;
2. after the equipment at the position A is installed, a jack is used for jacking the whole movable workshop to meet the rotating operation space of the travelling mechanism at the bottom of the workshop to a height, the travelling mechanism is installed again after rotating for 90 degrees, the jack is removed, and the workshop falls into the vertical direction track again;
3. and the installation workshop is moved into the area C to perform installation work. And finally, dismantling the mobile workshop after the GIS is installed.
The utility model has the advantages of it is following:
1. the movable installation workshop is not disassembled and reassembled, and the L-shaped arrangement fine installation of the 800kV outdoor GIS equipment is realized;
2. the installation flexibility is high, and the installation of GIS equipment in an L-shaped arrangement in any direction can be adapted;
3. the installation environment of the L-shaped GIS equipment is ensured, the work efficiency of GIS installation is improved, and the whole-process industrialized installation is realized;
4. the rails are arranged on the outer edge of the GIS equipment foundation, and the butt joint is completely completed on a GIS installation site without occupying a peripheral site;
5. after the GIS equipment is installed, the plant rails can be backfilled or disassembled, and the foundation of the GIS equipment is not affected;
6. the movable installation workshop can be repeatedly used in a plurality of projects, and the expected economic benefit is good.
The above-described preferred embodiments of the present invention are not intended to limit the present invention, and it should be understood by those skilled in the art that the present invention can be modified and replaced by other simple modifications and replacements without departing from the spirit and principle of the present invention, and these modifications and replacements also fall within the protection scope of the appended claims.

Claims (7)

1. The utility model provides a GIS removes installation factory building arrangement structure which characterized in that: including horizontal direction removal track (1) and the vertical direction removal track (2) that are L type cross arrangement, the horizontal direction and the vertical direction of installation factory building are provided with the walking crane respectively, the factory building running gear of installation factory building through the bottom sprag can remove along horizontal direction removal track (1) and vertical direction removal track (2), the cross position of horizontal direction removal track (1) and vertical direction removal track (2) is provided with and is used for rising factory building rising device (5) of installation factory building, provide the rotatory 90 operating space of factory building running gear.
2. The GIS mobile installation plant arrangement of claim 1, wherein: horizontal direction remove track (1) and vertical direction and remove track (2) and all include two tracks of parallel arrangement, two track intervals that horizontal direction removed track (1) and vertical direction removed track (2) are equal, the installation factory building be square factory building.
3. The GIS mobile installation plant arrangement of claim 2, wherein: the horizontal direction removes 800kV three-phase GIS equipment, 800kV three-phase GIS I generating line and 800kV three-phase GIS II generating line of arranging the horizontal direction between two tracks of track (1) horizontal direction, and the vertical direction removes 800kV three-phase GIS equipment, 800kV three-phase GIS I generating line and 800kV three-phase GIS II generating line of arranging the vertical direction between two tracks of track (2) vertical direction, and the horizontal direction is crossing with the vertical direction's 800kV three-phase GIS equipment, 800kV three-phase GIS I generating line and 800kV three-phase GIS II generating line.
4. The GIS mobile installation plant arrangement of claim 2, wherein: the crossing positions of the two rails of the horizontal moving rail (1) and the vertical moving rail (2) are provided with a plant lifting device (5).
5. The GIS mobile installation plant arrangement of claim 1 or 4, wherein: the factory building lifting device (5) adopts a jack which is pre-buried at a set position.
6. The GIS mobile installation plant arrangement of claim 1, wherein: the bottom of the installation workshop is provided with a clamping groove matched with the workshop travelling mechanism, and the workshop travelling mechanism rotates and then falls into the clamping groove again.
7. The GIS mobile installation plant arrangement of claim 1, wherein: the periphery of the installation workshop is provided with a frame, and a color steel plate is laid on the frame to realize sealing and heat insulation.
CN202022215424.3U 2020-09-30 2020-09-30 GIS removes installation factory building arrangement structure Active CN212336832U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022215424.3U CN212336832U (en) 2020-09-30 2020-09-30 GIS removes installation factory building arrangement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022215424.3U CN212336832U (en) 2020-09-30 2020-09-30 GIS removes installation factory building arrangement structure

Publications (1)

Publication Number Publication Date
CN212336832U true CN212336832U (en) 2021-01-12

Family

ID=74072043

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022215424.3U Active CN212336832U (en) 2020-09-30 2020-09-30 GIS removes installation factory building arrangement structure

Country Status (1)

Country Link
CN (1) CN212336832U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638500A (en) * 2021-09-23 2021-11-12 山东建筑大学 Rotatable and translational U-shaped building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638500A (en) * 2021-09-23 2021-11-12 山东建筑大学 Rotatable and translational U-shaped building

Similar Documents

Publication Publication Date Title
CN212336832U (en) GIS removes installation factory building arrangement structure
CN112031491A (en) 800kV outdoor GIS mobile installation workshop layout structure and mobile method
CN206395349U (en) A kind of Semi-automatic aerating cabinet produces transfer device
CN103400668B (en) A kind of composite insulator rotates staining device
CN203905597U (en) Combined type high-low cross arm with drilling and crossing functions
CN115625462A (en) Marine wind power tower cylinder tube section outer wall longitudinal joint rail mounted automatic weld equips
CN204873491U (en) Self -supporting does not have crossbeam hoist system
CN210857941U (en) Lifting device for housing construction
CN218345112U (en) Construction lifting device for single well power distribution
CN203433920U (en) Rotation pollution device for composite insulator
CN213460958U (en) Auxiliary fixing support for cable assembly
CN213325075U (en) Movable chute structure of sand making building
CN113699296B (en) Method and device for in-situ dry dedusting rapid reconstruction of blast furnace wet dedusting
KR100785517B1 (en) A movable maintenance car
CN219611302U (en) Power transmission and transformation engineering cable fixing support
CN203415877U (en) Hoisting tool for replacing isolation switch
CN203607801U (en) Power distribution structure for pipe bus crossing road
Li et al. Transmission line electrification spanning construction technology
CN215378408U (en) Power cable concrete packaging structure that crosses way in transformer substation
CN113585340B (en) Piping lane building construction system and construction method thereof
CN220954502U (en) A travelling bogie device for subway open cut station
CN214674252U (en) Arrangement structure above main cable trench of indoor GIS (geographic information System) control cubicle
CN212527652U (en) Fixing device is used in CT machine trouble maintenance
CN218620245U (en) A overhaul platform for operating device of high voltage circuit breaker
CN213093687U (en) 10kv movable box-type substation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant