CN212317403U - Waterproof laying equipment for building construction - Google Patents

Waterproof laying equipment for building construction Download PDF

Info

Publication number
CN212317403U
CN212317403U CN202020540435.6U CN202020540435U CN212317403U CN 212317403 U CN212317403 U CN 212317403U CN 202020540435 U CN202020540435 U CN 202020540435U CN 212317403 U CN212317403 U CN 212317403U
Authority
CN
China
Prior art keywords
fixedly connected
waterproof
base plate
pipe
chamber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020540435.6U
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Underground Application Technology Research Institute Co ltd
Original Assignee
Chongqing Underground Application Technology Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Underground Application Technology Research Institute Co ltd filed Critical Chongqing Underground Application Technology Research Institute Co ltd
Priority to CN202020540435.6U priority Critical patent/CN212317403U/en
Application granted granted Critical
Publication of CN212317403U publication Critical patent/CN212317403U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Cleaning By Liquid Or Steam (AREA)

Abstract

The utility model discloses a waterproof laying equipment for building construction, include base plate, pushing away material structure, scrape the material structure and wash the structure, the equal fixedly connected with gyro wheel of four corners of base plate bottom, one side fixedly connected with push rod on base plate top, the opposite side fixedly connected with material chamber on base plate top. The utility model discloses a be provided with and scrape the material structure and realize carrying out the function that the waste material struck off to material intracavity wall, the material can begin waterproof material's the process of laying after the inlet pipe enters into the inside in material chamber, waterproof material lays through the discharging pipe ejection of compact of material chamber one side bottom, thereby use waterproof material probably adheres to in a large number in the inner wall in material chamber and causes the waste, consequently, can start agitator motor, agitator motor drives both sides stirring leaf through the bottom (mixing) shaft and rotates the inner wall of scraping the wall board and scraping the material chamber that can utilize stirring leaf both sides when stirring waterproof material, thereby accomplish the cleanness to the inner wall in material chamber, reduce the waste of material.

Description

Waterproof laying equipment for building construction
Technical Field
The utility model relates to a building construction technical field specifically is a waterproof laying equipment for building construction.
Background
In building construction, often need carry out waterproof the laying in the process of laying, mainly utilize waterproof material to lay to the building through laying equipment to realize waterproof efficiency, there are the waterproof laying equipment that multiple building construction used on the market at present, though this kind of equipment use of current also can be enough to satisfy daily demand, nevertheless also generally can have some defects.
In the process of implementing the present invention, the inventor finds that at least the following problems exist in the prior art and are not solved:
(1) the traditional waterproof laying equipment has no internal wall scraping stirring structure, so that coating can be accumulated on the inner wall of a material cavity in the using process or the coating is unevenly stirred and accumulated in a block shape, thereby causing waste;
(2) the traditional waterproof laying equipment has no cleaning structure, so that the interior is easy to dirty after long-term use, and the quality of the coating is influenced;
(3) traditional waterproof laying equipment does not have pushing equipment to the coating accumulates to expect that the intracavity portion may be inconvenient ejection of compact.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a waterproof laying equipment for building construction to propose in solving above-mentioned background art not scraping the wall structure, not having the problem of clean structure and inconvenient ejection of compact.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a waterproof laying equipment for building construction, includes base plate, pushing equipment, scrapes the material structure and washs the structure, the equal fixedly connected with gyro wheel of four corners of base plate bottom, one side fixedly connected with push rod on base plate top, the opposite side fixedly connected with material chamber on base plate top, and the inside and the top fixedly connected with in material chamber scrape the material structure, the bottom fixedly connected with discharging pipe of material chamber one side, and be provided with the control valve on the discharging pipe, the top fixedly connected with inlet pipe of material chamber surface one side, the outside one side fixedly connected with in material chamber washs the structure, the bottom fixedly connected with who washs the structure pushes equipment, and one side that pushes equipment runs through to the inside in material chamber and extends to the inside one side in material chamber.
Preferably, material pushing block, belt, material pushing motor, the cover body, a thread cylinder and a threaded rod are installed in proper order inside the material pushing structure, the horizontal fixedly connected with thread cylinder in the cover body pushes the material pushing motor to be fixed on one side of the top end of the cover body, and the belt is fixedly connected with one side of the material pushing motor, the material pushing motor is connected and driven between the belt and the thread cylinder.
Preferably, the inside swing joint of screw thread section of thick bamboo has the threaded rod, and one side of threaded rod transversely runs through the material chamber and extends to the inside one side of material chamber, and the threaded rod extends to one side fixedly connected with ejector pad in material chamber, is provided with the external screw thread on the lateral wall of threaded rod, is provided with the internal thread on the inside wall of screw thread section of thick bamboo, is threaded connection between screw thread section of thick bamboo and the threaded rod.
Preferably, scrape the inside of material structure and install stirring leaf, (mixing) shaft, agitator motor in proper order and scrape the wallboard, agitator motor is fixed in the intermediate position department on material chamber top, and agitator motor's the bottom is vertical to run through and extends to the inside in material chamber, agitator motor's bottom fixedly connected with (mixing) shaft, the equal fixedly connected with stirring leaf in both ends of (mixing) shaft, the equal fixedly connected with in both sides of stirring leaf scrape the wallboard.
Preferably, wash the inside of structure and install branch pipe, outlet pipe, water pump, drinking-water pipe, water tank, shower and atomizer in proper order, the water tank is fixed in one side of material chamber, one side fixedly connected with water pump on water tank top, the bottom fixedly connected with drinking-water pipe of water pump, and the vertical bottom that runs through to the water tank and extend to the water tank inside of drinking-water pipe, one side fixedly connected with outlet pipe of water pump, and the top fixedly connected with branch pipe on one side of the outlet pipe.
Preferably, the spray pipes are respectively fixed at two sides of the top end of the material cavity, the bottom ends of the spray pipes are uniformly and fixedly connected with atomizing nozzles, and the atomizing nozzles are arranged at equal intervals.
Compared with the prior art, the beneficial effects of the utility model are that: the waterproof laying equipment for building construction realizes scraping of the inner wall of the material cavity, cleaning of the inner part of the material cavity and convenient discharging;
(1) the scraping structure is arranged to realize the function of scraping waste materials on the inner wall of the material cavity, the material enters the material cavity through the feeding pipe and then can start the laying process of the waterproof material, the waterproof material is laid through discharging of the discharging pipe at the bottom end of one side of the material cavity, and the waterproof material can be attached to the inner wall of the material cavity in a large amount in the using process, so that the stirring motor can be started;
(2) the cleaning structure is arranged to clean the interior of the material cavity, a small amount of residues still exist even if the waterproof material is scraped by the wall scraping plate after the waterproof material is used, at the moment, the water pump can be started, and the water pump pumps water through the water pumping pipe at the bottom and is discharged from the atomizing nozzle at the bottom of the spraying pipe after passing through the water outlet pipe and the branch pipe, so that the interior of the material cavity is cleaned and is cleaner;
(3) the material pushing structure is arranged to realize convenient pushing of materials, the waterproof coating is likely to be thick after the interior of the material filling cavity, and the phenomenon that the coating cannot be discharged occurs, the material pushing motor can be started at the moment and drives the thread cylinder in the cover body to rotate through the belt, and then the threaded rod in threaded connection with the thread cylinder rotates, so that the threaded rod drives the material pushing block to move at the bottom end of the material cavity, and the coating accumulated on the side edge starts to be pushed, and the coating is discharged from the discharging pipe.
Drawings
Fig. 1 is a schematic front view of a cross-sectional structure of the present invention;
FIG. 2 is a schematic view of the front cross-sectional structure of the pushing structure of the present invention;
FIG. 3 is a front view of the scraping structure of the present invention showing a partially enlarged structure;
fig. 4 is an enlarged partial cross-sectional view of the point a in fig. 1 according to the present invention.
In the figure: 1. a push rod; 2. a roller; 3. a substrate; 4. a material pushing structure; 401. a material pushing block; 402. a belt; 403. a material pushing motor; 404. a cover body; 405. a threaded barrel; 406. a threaded rod; 5. a material cavity; 6. a discharge pipe; 7. a control valve; 8. a scraping structure; 801. stirring blades; 802. a stirring shaft; 803. a stirring motor; 804. scraping a wall plate; 9. a feed pipe; 10. cleaning the structure; 1001. a branch pipe; 1002. a water outlet pipe; 1003. a water pump; 1004. a water pumping pipe; 1005. a water tank; 1006. a shower pipe; 1007. an atomizing spray head.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides an embodiment: a waterproof laying device for building construction comprises a base plate 3, a material pushing structure 4, a material scraping structure 8 and a cleaning structure 10, wherein four corners of the bottom end of the base plate 3 are fixedly connected with idler wheels 2, one side of the top end of the base plate 3 is fixedly connected with a push rod 1, the other side of the top end of the base plate 3 is fixedly connected with a material cavity 5, the inner part and the top end of the material cavity 5 are fixedly connected with the material scraping structure 8, the bottom end of one side of the material cavity 5 is fixedly connected with a material discharging pipe 6, a control valve 7 is arranged on the material discharging pipe 6, the top end of one side of the outer surface of the material cavity 5 is fixedly connected with a material feeding pipe 9, one side of the outer part of the material cavity 5 is fixedly connected with the cleaning structure 10, the bottom end of the cleaning structure 10 is fixedly connected;
a pushing block 401, a belt 402, a pushing motor 403, a cover body 404, a threaded cylinder 405 and a threaded rod 406 are sequentially installed inside the pushing structure 4, the threaded cylinder 405 is transversely and fixedly connected inside the cover body 404, the pushing motor 403 is fixed on one side of the top end of the cover body 404, the type of the pushing motor 403 can be Y90S-2, the belt 402 is fixedly connected on one side of the pushing motor 403, the pushing motor 403 is connected and driven with the threaded cylinder 405 through the belt 402, the threaded rod 406 is movably connected inside the threaded cylinder 405, one side of the threaded rod 406 transversely penetrates through the material cavity 5 and extends to one side inside the material cavity 5, the pushing block 401 is fixedly connected on one side of the threaded rod 406 extending to the material cavity 5, external threads are arranged on the outer side wall of the threaded rod 406, internal threads are arranged on the inner side wall of the threaded cylinder 405, and the;
specifically, as shown in fig. 1 and fig. 2, when the mechanism is used, firstly, after the waterproof paint is poured into the material cavity 5, the paint may not be discharged due to the thick paint, at this time, the material pushing motor 403 may be started, the material pushing motor 403 drives the threaded cylinder 405 in the cover 404 to rotate through the belt 402, and then the threaded rod 406 in threaded connection with the threaded cylinder 405 rotates, so that the threaded rod 406 drives the material pushing block 401 to move at the bottom end of the material cavity 5, and the paint accumulated on the side edge starts to be pushed and discharged from the material discharging pipe 6;
the stirring blade 801, the stirring shaft 802, the stirring motor 803 and the wall scraping plate 804 are sequentially arranged in the scraping structure 8, the stirring motor 803 is fixed at the middle position of the top end of the material cavity 5, the model of the stirring motor 803 can be Y90L-2, the bottom end of the stirring motor 803 vertically penetrates through and extends into the material cavity 5, the stirring shaft 802 is fixedly connected to the bottom end of the stirring motor 803, the stirring blades 801 are fixedly connected to both ends of the stirring shaft 802, and the wall scraping plates 804 are fixedly connected to both sides of the stirring blades 801;
specifically, as shown in fig. 1 and 3, when the mechanism is used, firstly, after a material enters the material cavity 5 through the feeding pipe 9, a waterproof material laying process can be started, the waterproof material is laid by discharging through the discharging pipe 6 at the bottom end of one side of the material cavity 5, and during the use process, the waterproof material may be attached to the inner wall of the material cavity 5 in a large amount to cause waste, so that the stirring motor 803 can be started, the stirring motor 803 can drive the stirring blades 801 at two sides to rotate through the bottom stirring shaft 802 to stir the waterproof material, and can scrape the inner wall of the material cavity 5 by using the wall scraping plates 804 at two sides of the stirring blades 801, thereby completing the cleaning of the inner wall of the material cavity 5 and reducing the waste of the material;
a branch pipe 1001, a water outlet pipe 1002, a water pump 1003, a water pumping pipe 1004, a water tank 1005, a spray pipe 1006 and atomizing nozzles 1007 are sequentially installed inside the cleaning structure 10, the water tank 1005 is fixed on one side of the material cavity 5, the water pump 1003 is fixedly connected to one side of the top end of the water tank 1005, the water pump 1003 can be ISGD in type, the water pumping pipe 1004 is fixedly connected to the bottom end of the water pump 1003, the water pumping pipe 1004 vertically penetrates through the water tank 1005 and extends to the bottom end inside the water tank 1005, the water outlet pipe 1002 is fixedly connected to one side of the water pump 1003, the branch pipe 1001 is fixedly connected to the top end of one side of the water outlet pipe 1002, the spray pipes 1006 are respectively fixed to two sides of the top end inside the material cavity 5, the atomizing nozzles 1007;
specifically, as shown in fig. 1 and 4, when the mechanism is used, firstly, a small amount of waterproof material remains even if the waterproof material is scraped by the scraping plate 804 after the waterproof material is used, at this time, the water pump 1003 can be started, and the water pump 1003 pumps water through the bottom water pumping pipe 1004 and then is discharged from the atomizing nozzle 1007 at the bottom of the spraying pipe 1006 after passing through the water outlet pipe 1002 and the branch pipe 1001, so that the interior of the material cavity 5 is cleaned and is cleaner.
The working principle is as follows: the utility model discloses when using, at first, the material can begin waterproof material's the process of laying after entering into the inside of material chamber 5 through inlet pipe 9, waterproof material lays through the 6 ejection of compact of discharging pipe of material chamber 5 one side bottom, thereby use waterproof material probably a large amount of inner walls that adhere to material chamber 5 cause the waste, consequently, agitator motor 803 can be started, agitator motor 803 drives both sides stirring leaf 801 through bottom (mixing) shaft 802 and rotates and can utilize the wallboard 804 of scraping that stirs leaf 801 both sides to scrape the inner wall of material chamber 5 when stirring waterproof material, thereby accomplish the cleanness to the inner wall of material chamber 5, reduce the waste of material.
Then, after the waterproof paint is poured into the material cavity 5, the paint may not be discharged due to the thick paint, at this time, the material pushing motor 403 may be started, the material pushing motor 403 drives the threaded cylinder 405 in the cover 404 to rotate through the belt 402, and then the threaded rod 406 in threaded connection with the threaded cylinder 405 further rotates, so that the threaded rod 406 drives the material pushing block 401 to move at the bottom end of the material cavity 5, and the paint accumulated on the side edge starts to be pushed, and is discharged from the discharging pipe 6.
Finally, even if the waterproof material is scraped through the scraping plate 804 after the use and still has a small amount of residue, the water pump 1003 can be started at the moment, the water pump 1003 pumps water through the bottom water pumping pipe 1004 and is discharged from the atomizing nozzle 1007 at the bottom of the spraying pipe 1006 after passing through the water outlet pipe 1002 and the branch pipe 1001, and therefore the interior of the material cavity 5 is cleaned and is made to be cleaner.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. The utility model provides a waterproof laying equipment for building construction, includes base plate (3), pushes away material structure (4), scrapes material structure (8) and washs structure (10), its characterized in that: the utility model discloses a material cleaning device, including base plate (3), one side fixedly connected with push rod (1) on base plate (3) top, the equal fixedly connected with gyro wheel (2) of four corners of base plate (3) bottom, one side fixedly connected with push rod (1) on base plate (3) top, opposite side fixedly connected with material chamber (5) on base plate (3) top, and the inside and the top fixedly connected with of material chamber (5) scrape material structure (8), the bottom fixedly connected with discharging pipe (6) of material chamber (5) one side, and be provided with control valve (7) on discharging pipe (6), the top fixedly connected with inlet pipe (9) of material chamber (5) surface one side, the outside one side fixedly connected with of material chamber (5) washs structure (10), the bottom fixedly connected with who washs structure (10) pushes away material structure (4), and pushes away one side of material structure (4) and runs through.
2. The waterproof laying apparatus for building construction according to claim 1, characterized in that: the inside of pushing away material structure (4) is installed in proper order and is pushed away material piece (401), belt (402), material motor (403), the cover body (404), a screw thread section of thick bamboo (405) and threaded rod (406), the horizontal fixedly connected with screw thread section of thick bamboo (405) in inside of the cover body (404), pushes away material motor (403) and is fixed in one side on cover body (404) top, and pushes away one side fixedly connected with belt (402) of material motor (403), it is connected the transmission to push away between material motor (403) through belt (402) and screw thread section of thick bamboo (405).
3. The waterproof laying apparatus for building construction according to claim 2, characterized in that: the material cavity feeding device is characterized in that a threaded rod (406) is movably connected inside the threaded barrel (405), one side of the threaded rod (406) transversely penetrates through the material cavity (5) and extends to one side inside the material cavity (5), the threaded rod (406) extends to one side of the material cavity (5) and is fixedly connected with a material pushing block (401), an external thread is arranged on the outer side wall of the threaded rod (406), an internal thread is arranged on the inner side wall of the threaded barrel (405), and the threaded barrel (405) is in threaded connection with the threaded rod (406).
4. The waterproof laying apparatus for building construction according to claim 1, characterized in that: scrape the inside of material structure (8) and install stirring leaf (801) in proper order, (mixing) shaft (802), agitator motor (803) and scrape wallboard (804), agitator motor (803) are fixed in the intermediate position department on material chamber (5) top, the vertical inside that runs through and extend to material chamber (5) in bottom of agitator motor (803), the bottom fixedly connected with (mixing) shaft (802) of agitator motor (803), the equal fixedly connected with stirring leaf (801) in both ends of (mixing) shaft (802), the equal fixedly connected with in both sides of stirring leaf (801) scrapes wallboard (804).
5. The waterproof laying apparatus for building construction according to claim 1, characterized in that: wash the inside of structure (10) and install branch pipe (1001) in proper order, outlet pipe (1002), water pump (1003), drinking-water pipe (1004), water tank (1005), shower (1006) and atomizer (1007), water tank (1005) are fixed in one side of material chamber (5), one side fixedly connected with water pump (1003) on water tank (1005) top, bottom fixedly connected with drinking-water pipe (1004) of water pump (1003), and drinking-water pipe (1004) vertically run through to water tank (1005) and extend to the inside bottom of water tank (1005), one side fixedly connected with outlet pipe (1002) of water pump (1003), and the top fixedly connected with branch pipe (1001) of outlet pipe (1002) one side.
6. The waterproof laying apparatus for building construction according to claim 5, characterized in that: the spray pipes (1006) are respectively fixed on two sides of the top end inside the material cavity (5), the bottom ends of the spray pipes (1006) are uniformly and fixedly connected with atomizing nozzles (1007), and the atomizing nozzles (1007) are arranged at equal intervals.
CN202020540435.6U 2020-04-14 2020-04-14 Waterproof laying equipment for building construction Active CN212317403U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020540435.6U CN212317403U (en) 2020-04-14 2020-04-14 Waterproof laying equipment for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020540435.6U CN212317403U (en) 2020-04-14 2020-04-14 Waterproof laying equipment for building construction

Publications (1)

Publication Number Publication Date
CN212317403U true CN212317403U (en) 2021-01-08

Family

ID=74019911

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020540435.6U Active CN212317403U (en) 2020-04-14 2020-04-14 Waterproof laying equipment for building construction

Country Status (1)

Country Link
CN (1) CN212317403U (en)

Similar Documents

Publication Publication Date Title
CN213005886U (en) Mortar agitating unit for construction convenient to use
CN216023318U (en) Scraping device of effluent water sump silt of being convenient for clear away
CN211221260U (en) Glazing slurry supply device
CN212370743U (en) Building water supply and drainage pipeline cleaning device
CN207509524U (en) For the beating apparatus of rubber strip production
CN212317403U (en) Waterproof laying equipment for building construction
CN213883091U (en) Self-cleaning type sewage tank for floor washing equipment
CN214233646U (en) Vertical stirring equipment for aquaculture innocent treatment
CN211517985U (en) Interlocking piece production is with mixing raw materials blanking machine
CN220352700U (en) Road construction decontamination equipment
CN220247489U (en) Energy-saving spraying device for green building
CN213101669U (en) Multistage agitating unit that production real mineral varnish resin emulsion was used
CN212663269U (en) Handheld agitated vessel of building that possesses clearance effect
CN211802859U (en) Little water all-in-one of steam
CN213761408U (en) Stirring device for paint production
CN211221391U (en) Agitating lorry tank structure convenient for cleaning concrete
CN217887840U (en) Three-shaft type dust humidifier
CN214716368U (en) Dispersion tank for producing coating
CN220559604U (en) Mortar spraying device for anti-corrosion engineering
CN215859142U (en) Dry-mixed mortar spraying device
CN219261651U (en) Uniform painting device
CN220329524U (en) Wall adhesive scraping device
CN220026758U (en) Paint stirring equipment
CN219445533U (en) Concrete mixing device for bridge construction
CN218255916U (en) Shield constructs mortar mixing stirring device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant