CN212295587U - Horizontal annular welding construction platform for bin - Google Patents

Horizontal annular welding construction platform for bin Download PDF

Info

Publication number
CN212295587U
CN212295587U CN202021156744.XU CN202021156744U CN212295587U CN 212295587 U CN212295587 U CN 212295587U CN 202021156744 U CN202021156744 U CN 202021156744U CN 212295587 U CN212295587 U CN 212295587U
Authority
CN
China
Prior art keywords
hanging basket
cantilever beam
wheel
bin
walking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021156744.XU
Other languages
Chinese (zh)
Inventor
杜瑞刚
吴博
吴长德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN202021156744.XU priority Critical patent/CN212295587U/en
Application granted granted Critical
Publication of CN212295587U publication Critical patent/CN212295587U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a horizontal annular welding construction platform of a bin cylinder, which comprises a hanging basket and an operation platform arranged in the hanging basket, wherein a rear surrounding frame of the hanging basket is a crawling ladder, lifting lugs are arranged at the top parts of a left surrounding frame and a right surrounding frame of the hanging basket, a left cantilever beam and a right cantilever beam which extend forwards are arranged at the upper part of the hanging basket, and walking wheel assemblies are arranged at the front ends of the left cantilever beam and the right cantilever beam; the walking wheel assembly comprises a connecting frame fixedly connected with the cantilever beam, two walking wheels are mounted in the connecting frame, and the walking wheels are arranged on the upper edge of the bin steel plate; at least one walking wheel assembly is provided with a power assembly, the power assembly comprises a driven gear and a driving gear, wherein the driven gear is fixedly connected to the side surface of the walking wheel, and the driving gear is arranged between the two driven gears and is meshed with the driven gears; the other end of the shaft lever of the driving gear is fixedly connected with a chain wheel, and a chain is arranged on the chain wheel.

Description

Horizontal annular welding construction platform for bin
Technical Field
The utility model belongs to a construction platform, concretely relates to silo annular level welding is with construction platform.
Background
In the industrial building field, a large amount of multi-section bin barrel welding and mounting projects exist, in the field, high-end welding mechanical equipment, namely an annular automatic welding machine appears, but the mechanical equipment is high in price, the maintenance condition often appears, and the overall economic effect is poor, so that most construction units rarely select the annular automatic blasting machine. In actual construction, an automatic circular seam welding machine is mostly used, and the operation is still carried out according to the traditional hanging scaffold or the method of building a circular construction platform and paving a wood springboard. The engineering is high-altitude operation, the traditional hanging scaffold or the construction platform is more in material consumption, the construction cost is high, and the safety of the hanging scaffold in construction is poor. With the progress of the building industry, the existing traditional practice does not meet the requirements of quick construction, safety, stability and movement at any time.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model is that the mode that the bin section of thick bamboo welding adopted the platform sling or set up construction platform consumes financial resources and materials among the prior art, the problem that safety still can not be guaranteed.
In order to solve the technical problem, the utility model provides a technical scheme is:
a horizontal annular welding construction platform for a bin comprises a hanging basket and an operation platform arranged in the hanging basket, wherein a rear surrounding frame of the hanging basket is a crawling ladder, lifting lugs are arranged at the top of a left surrounding frame and the top of a right surrounding frame of the hanging basket, a left cantilever beam and a right cantilever beam which extend forwards are arranged at the upper part of the hanging basket, and walking wheel assemblies are arranged at the front ends of the left cantilever beam and the right cantilever beam; the walking wheel assembly comprises a connecting frame fixedly connected with the cantilever beam, two walking wheels are mounted in the connecting frame, and the walking wheels are arranged on the upper edge of the bin steel plate; at least one walking wheel assembly is provided with a power assembly, the power assembly comprises a driven gear and a driving gear, wherein the driven gear is fixedly connected to the side surface of the walking wheel, and the driving gear is arranged between the two driven gears and is meshed with the driven gears; the other end of the shaft lever of the driving gear is fixedly connected with a chain wheel, and a chain is arranged on the chain wheel.
This device preparation is simpler relatively, and the regional area of platform self is little than conventional construction platform, and the structural frame steel material is few, can be great degree save the use of wood system springboard and support scaffold, make the cost cheaper. The platform moves along with the propulsion of the welding of the cylinder body, has strong operability, safety and reliability, and is very suitable for the installation and welding operation of a multi-section annular cylinder body structure on site.
Preferably, the lower part of the hanging basket is provided with a support rod, the front end of the support rod is provided with a horizontal directional wheel, and the periphery of the horizontal directional wheel is in contact with the outer wall of the bin barrel.
Drawings
FIG. 1 is a general structure diagram of the construction platform;
FIG. 2 is a view of the construction of the walking wheel assembly and power assembly;
FIG. 3 is a schematic diagram of the force applied by the power assembly;
FIG. 4 is a schematic view of a road wheel assembly mounting structure;
fig. 5 is a view showing a structure of a horizontally oriented wheel.
The specification marks the description: a rear enclosure frame-1; a right and a right surrounding frame-2; a lifting lug-3; cantilever beam-4; a traveling wheel assembly-5; a connecting frame-51; a road wheel 52; -a power assembly-6; a driven gear-61; a drive gear-62; a chain-63; a sprocket-64; a strut-7; a horizontally oriented wheel-8; an operating platform-9; a bin steel plate-10; a lead screw-11.
Detailed Description
The technical solution of the present invention will be described clearly and completely with reference to the accompanying drawings, and obviously, the described embodiments are some, but not all embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The following description is combined with the attached drawings 1-5, the horizontal annular welding construction platform for the bin cylinder provided by the utility model comprises a hanging basket and an operation platform 9 arranged in the hanging basket, wherein a rear surrounding frame 1 of the hanging basket is a ladder stand, lifting lugs 3 are arranged at the top parts of a left surrounding frame 2 and a right surrounding frame 2 of the hanging basket, a left cantilever beam and a right cantilever beam (hereinafter collectively referred to as cantilever beams) extending forwards are arranged at the upper part of the hanging basket, and a walking wheel component 5 is arranged at the outer end of each cantilever beam 4; the walking wheel assembly 5 comprises a connecting frame 51 fixedly connected with the cantilever beam 4, two walking wheels 52 are arranged in the connecting frame 51, and the walking wheels 52 are arranged on the upper edge of the bin steel plate 10; at least one walking wheel assembly 5 is provided with a power assembly 6, the power assembly 6 comprises a driven gear 61 and a driving gear 62, wherein the driven gear 61 is fixedly connected to one side of the walking wheel, and the driving gear 62 is arranged between the two driven gears 61 and is meshed with the driven gears 61; the other end of the shaft lever of the driving gear 62 is fixedly connected with a chain wheel 64, and a chain 63 is arranged on the chain wheel 64.
Based on the principle that the larger the moment, the smaller the force, the diameter of the sprocket 64 is equal to or larger than the sum of the diameters of the driven gear 61 and the driving gear 62. The chain wheel 64 is rotated by pulling the chain 63, so as to drive the driven gear 61 and the travelling wheel 52 to rotate, and the operation platform moves on the bin. The chain 63 may be pulled manually or by any known means. For example, the lower end of the chain 63 is mounted on a power sprocket, and the power sprocket is connected with a motor and a speed reducer. And the hanging basket can be moved more conveniently and more laborsavingly by matching the controller.
The lower part of the hanging basket is provided with a supporting rod 7, the outer end of the supporting rod 7 is provided with a horizontal directional wheel 8, and the periphery of the horizontal directional wheel 8 is in contact with the outer wall of the bin barrel. Furthermore, the horizontal orientation wheel 8 is a pulley, a pulley frame of the horizontal orientation wheel 8 is connected with a lead screw 11, and the lead screw 11 is arranged in the support rod 7. The position of the horizontal orientation wheel 8 is adjusted by the rotatable lead screw, and the upright posture of the construction hanging basket can be still kept when the outer side of the welded component inclines. The walking track of the horizontally oriented wheel in the other direction can be used as a reference for judging whether the hanging basket moves horizontally or not.
Two layers of operating platforms 9 can be arranged in the hanging basket and are respectively arranged at the bottom and the middle of the hanging basket. Under the condition of ensuring the stability of the fixing structure of the operating platform, the operating platform 9 can be designed to be detachable and fixed at the bottom of the hanging basket or any height according to construction requirements.
During operation, the construction platform is hoisted by a crane, the walking wheels are aligned with the upper edge of the bin, and the hanging basket is hung on the upper edge of the bin steel plate 10. The mobile construction platform provided by the invention is not limited to welding a circular bin, and is also suitable for linear welding of other vertical steel plates.
The height of the operating platform is fixed in advance according to the height of a welding seam, the chain 63 is pulled to drive the power gear 62 to rotate, the power gear 62 drives the driven gear 61 to rotate, the driven gear 61 is fixedly connected with the walking wheel 52, the walking wheel 52 is installed in the connecting frame 51, and the connecting frame 51 pulls the hanging basket to walk. The hanging basket of the left chain 63 is pulled to move rightwards, and the hanging basket of the right chain is pulled to move leftwards. And pulling the chain to move the hanging basket to the welding point to perform welding. The welding propulsion is matched with the movement of the hanging basket to complete the annular welding of the barrel.
The operating personnel can enter the construction hanging basket from the crawling ladder, and after the operation is finished, the personnel can withdraw on the original way, and the device can be hung on the ground by using a crane.
The invention has the advantages of relatively simple manufacture, smaller area of the platform per se than that of a conventional construction platform, less steel material consumption of the structural frame, capability of saving the use of a wooden gangplank and a supporting scaffold to a greater extent and lower manufacturing cost. The platform moves along with the propulsion of the welding of the cylinder body, has strong operability, safety and reliability, and is very suitable for the installation and welding operation of a multi-section annular cylinder body structure on site.

Claims (2)

1. The utility model provides a horizontal annular welding construction platform in storage cylinder, includes hangs the basket and sets up the operation platform who hangs in the basket, encloses the frame behind the hanging basket and is the cat ladder, and the top that hangs the basket left and right side and enclose the frame is equipped with lug, characterized by: the upper part of the hanging basket is provided with a left cantilever beam and a right cantilever beam which extend forwards, and the front ends of the two cantilever beams (4) are provided with a traveling wheel assembly (5); the walking wheel assembly (5) comprises a connecting frame (51) fixedly connected with the cantilever beam (4), two walking wheels (52) are arranged in the connecting frame (51), and the walking wheels (52) are arranged on the upper edge of the bin steel plate (10); at least one walking wheel assembly (5) is provided with a power assembly (6), the power assembly (6) comprises a driven gear (61) and a driving gear (62), wherein the driven gear (61) is fixedly connected to the side surface of the walking wheel (52), and the driving gear (62) is arranged between the two driven gears (61) and meshed with the driven gears (61); the other end of the shaft lever of the driving gear (62) is fixedly connected with a chain wheel (64), and a chain (63) is arranged on the chain wheel (64).
2. The horizontal annular welding construction platform for the bin according to claim 1, which is characterized in that: the lower part of the hanging basket is provided with a supporting rod (7), the front end of the supporting rod (7) is provided with a horizontal directional wheel (8), and the periphery of the horizontal directional wheel (8) is in contact with the outer wall of the bin barrel.
CN202021156744.XU 2020-06-20 2020-06-20 Horizontal annular welding construction platform for bin Active CN212295587U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021156744.XU CN212295587U (en) 2020-06-20 2020-06-20 Horizontal annular welding construction platform for bin

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021156744.XU CN212295587U (en) 2020-06-20 2020-06-20 Horizontal annular welding construction platform for bin

Publications (1)

Publication Number Publication Date
CN212295587U true CN212295587U (en) 2021-01-05

Family

ID=73942606

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021156744.XU Active CN212295587U (en) 2020-06-20 2020-06-20 Horizontal annular welding construction platform for bin

Country Status (1)

Country Link
CN (1) CN212295587U (en)

Similar Documents

Publication Publication Date Title
CN112938774B (en) Integral hoisting system and hoisting method for assembly type component
CN111017734A (en) Running mechanism of monorail hoisting and transporting equipment
CN204474193U (en) A kind of Pillar-fixing Type Slewing Crane
CN212295587U (en) Horizontal annular welding construction platform for bin
CN210117190U (en) Small material hoister
CN218369642U (en) Wheel type driving rotary warehouse cleaning machine
CN215854729U (en) Gantry crane for high-speed rail
CN111608381A (en) Horizontal annular welding construction platform for bin
CN216476267U (en) Hanging basket frame in ring rail hanging form
CN213171212U (en) A hoisting apparatus for building engineering
CN212866926U (en) Movable supporting beam dismounting device
CN111502294B (en) Automatic installation method of movable precast concrete wallboard
CN111764613A (en) High-altitude equipment installation device in rail traveling area of rail transit engineering and construction method
CN217972282U (en) Trolley for transporting and installing water supply pipeline
CN214298991U (en) Mobilizable building engineering hoist device
CN219279332U (en) Movable rotary long-arm crane
CN219708966U (en) Sports car for hoisting steel plate warehouse roof
CN219786916U (en) Automatic welding device for circular seam of large-sized pressure steel pipe
CN216277007U (en) Construction support with carry material function
CN212478475U (en) Steel construction building scaffold
CN111302188B (en) Construction elevator with prevent rocking structural design
CN211770010U (en) Auxiliary device for moving beam-falling jack
CN213894977U (en) Material lifting device suitable for middle and low-rise building
CN210176333U (en) Labor-saving motor casing lifting appliance with accurate positioning
CN220116071U (en) Travelling car operation platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant