CN212294662U - Gas lift slag return system - Google Patents
Gas lift slag return system Download PDFInfo
- Publication number
- CN212294662U CN212294662U CN202021195422.6U CN202021195422U CN212294662U CN 212294662 U CN212294662 U CN 212294662U CN 202021195422 U CN202021195422 U CN 202021195422U CN 212294662 U CN212294662 U CN 212294662U
- Authority
- CN
- China
- Prior art keywords
- steel
- mud
- pipe
- hole
- drilling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model relates to a slag system is prevented to gas lift, including air feeder, row's sediment pipe, tuber pipe, filter residue device and mud circulation system, the entry end of arranging the sediment pipe stretches into pile foundation hole bottom, and the export of arranging the sediment pipe accesss to the filter residue device, and in the tuber pipe stretched into row's sediment pipe, the air outlet of tuber pipe extended to the entry end of arranging the sediment pipe, and the income wind gap and the air feeder of tuber pipe are connected, and the export and the mud circulation system of filter residue device are connected, and mud circulation system is used for going into the pile foundation downt. The utility model can discharge the rock slag blocks in the hole in time during drilling, the hole bottom is clean, the repeated crushing of drilling cuttings at the hole bottom is less, the hole cleaning efficiency is high, and the pile forming quality is better; the utility model discloses a support frame supports steel mud pit and steel sedimentation tank on water, and mud can manifold cycles use, has increased the use number of times of mud, has reduced the quantity of new preparation mud, but reduction material cost, can avoid the pollution of pile foundation construction to the environment on water moreover.
Description
Technical Field
The utility model relates to a pile foundation construction technical field especially relates to anti-sediment system of gas lift.
Background
The drilling mud is a mixed slurry consisting of water, bentonite (or clay), additives and the like. In the construction process of the drilled pile, when slurry circulates, the pressure difference between the slurry and underground water is utilized to control the water pressure, so that the slurry can form a mud skin on the hole wall to reinforce the hole wall and prevent collapse, and meanwhile, the water level in the hole is stabilized. Meanwhile, the mud also has the functions of carrying out rock-soil fragments, cooling and lubricating the drill bit. Therefore, the pile forming quality is greatly influenced no matter in the hole forming stage or the pouring stage, and the bearing performance of the pile foundation is greatly influenced.
At present, the hole forming of the large-diameter ultra-long pile mainly comprises traditional construction technologies such as rotary drilling, impact drilling, rotary drilling and the like, wherein the rotary drilling comprises forward circulation drilling and reverse circulation drilling, the hole wall is protected and slag is discharged through the circulation of slurry, the rotary drilling and the reverse circulation drilling are the same in the hole forming process, the applicable stratums are basically the same, and the difference is the circulation mode of the slurry.
The existing pore-forming construction method has low efficiency, and the existing slurry circulation system for the construction of the overwater pile foundation can cause pollution to the water environment.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a slag system is turned over in gas lift, can improve pore-forming efficiency and can avoid the pollution of pile foundation construction on water to the environment.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
gas lift anti-sediment system, including air feeder, row's sediment pipe, tuber pipe, filter residue device and mud circulation system, arrange the entry end of sediment pipe and stretch into pile foundation hole bottom, arrange the export of sediment pipe and access to the filter residue device, in the tuber pipe stretched into row's sediment pipe, the air outlet of tuber pipe extended to arrange the entry end of sediment pipe, and the income wind gap and the air feeder of tuber pipe are connected, the export and the mud circulation system of filter residue device are connected, mud circulation system is used for going into the pile foundation downthehole with the mud backward flow.
Preferably, the air duct is coaxial with the slag discharge duct.
Preferably, the air supply device is an air compressor.
Preferably, the residue filtering device is a residue receiving basket.
Further, the gas lift slag returning system further comprises a slurry circulating system, and an outlet of the slag filtering device is connected with the slurry circulating system.
Further, the mud circulating system comprises a steel mud tank, a steel sedimentation tank, a support frame and a plurality of pile foundation steel casing pipes, wherein the pile foundation steel casing pipes are communicated through communicating pipes;
the steel mud pit and the steel sedimentation tank are supported by a support frame, an outlet of the residue filtering device is communicated with the steel sedimentation tank, the steel sedimentation tank is communicated with the steel mud pit, and the mud pit is communicated with one pile foundation steel casing through a mud outlet pipe. Furthermore, the support frame comprises a plurality of foundation steel pipes, a main cross beam, a main longitudinal beam and a bridge deck, the cross beam is erected on the foundation steel pipes, the bottom of the main longitudinal beam is fixedly connected with the cross beam, the top of the main longitudinal beam is connected with the bridge deck, and the steel mud tank and the steel sedimentation tank are installed on the bridge deck.
Preferably, the main longitudinal beam is a bailey piece.
Preferably, the number of the main cross beams is three, and each main cross beam is connected with two foundation steel pipes.
Furthermore, an inclined strut and/or a parallel connection are arranged between two basic steel pipes connected with the same main cross beam.
Preferably, the base steel pipe is a round steel pipe.
Preferably, the main beam is double-spliced I-shaped steel.
Further, a vertical partition plate is arranged in the steel plate box to divide the steel plate box into two compartments, one compartment is used as a steel mud tank, the other compartment is used as a steel sedimentation tank, and an overflow port is formed in the top of the vertical partition plate.
Furthermore, the box opening and the bottom of the steel plate box are reinforced by channel steel, and the periphery of the steel plate box is provided with the scissors back ribs.
Compared with the prior art, the utility model discloses following beneficial effect has:
1, the utility model can discharge the rock slag block in the hole in time during drilling, the hole bottom is clean, the repeated crushing of drilling cuttings at the hole bottom is less, the hole cleaning efficiency is high, and the pile forming quality is better;
2, the utility model discloses a support frame supports steel mud pit and steel sedimentation tank on water, and mud in the bored pile is taken out, reachs the mud pit after the sedimentation of sedimentation tank, and during mud in the mud pit is the pump reflux to the bored pile again, mud can manifold cycles use, has increased the use number of times of mud, has reduced the quantity of new made mud, but reduction material cost, can avoid the pollution of pile foundation construction to the environment on water in addition.
Drawings
Fig. 1 is a schematic structural diagram of the present invention;
FIG. 2 is a schematic structural view of a mud circulation system according to the present invention;
FIG. 3 is a schematic longitudinal section of a steel slurry tank and a settling tank platform;
FIG. 4 is a schematic cross-sectional view of a steel mud pit and settling pond platform;
FIG. 5 is a three-dimensional view of a steel box (reinforcing channels not shown);
FIG. 6 is a schematic view of one side of a steel sheet tank;
FIG. 7 is a construction flow chart for pile foundation pore-forming by using the gas lift slag-removing system of the utility model;
fig. 8 is a pile foundation drilling sequence diagram.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings.
As shown in figure 1, the utility model discloses a slag system is prevented to gas lift, including air feeder 1, work platform 2, row's sediment pipe 3, tuber pipe 4, filter residue device 5 and mud circulation system. The working platform 2 is positioned at the orifice of the pile foundation hole 7, the inlet end of the slag discharge conduit 3 extends into the hole bottom of the pile foundation hole 7, the outlet of the slag discharge conduit 3 is communicated with the slag filtering device 5, the air pipe 4 extends into the slag discharge conduit 3, the air outlet of the air pipe 4 extends to the inlet end of the slag discharge conduit 3, and the air inlet of the air pipe 4 is connected with the air supply device 1.
The outlet of the residue filtering device 5 is connected with the slurry circulating system. Preferably, the air duct 4 is coaxial with the slag discharge duct 3. In the present embodiment, an air compressor is selected as the air supply device 1, and a slag receiving basket is selected as the slag filtering device 5.
The utility model discloses a theory of operation: the air compressor conveys compressed air into the air pipe 4, and the air is discharged from the bottom of the air pipe 4 and forms a gas-liquid mixture with slurry. The sediment at the bottom of the hole is suspended under the impact action of the sprayed gas, and due to the density difference of liquid inside and outside the pipe, three-phase flow of slurry, air and sediment in the hole moves upwards along the slag discharge guide pipe 3 and is discharged out of the hole opening, the slurry enters the slag receiving basket to filter the sediment in the slurry, the filtered slurry enters the hole again through the slurry circulating system, and the circulation is repeated until the thickness of the sediment at the bottom of the hole meets the standard requirement.
In another embodiment, when pile foundation construction is performed on water, environmental pollution caused by the pile foundation construction on water is prevented. As shown in fig. 2, 3 and 4, the mud circulating system comprises a steel mud tank 8, a steel sedimentation tank 9 and a plurality of pile foundation steel casing 6, and the pile foundation steel casing 6 are communicated through a communicating pipe 14.
The quantity of pile foundation steel casing 6 sets up according to drilling quantity, and the drilling has 9 in this embodiment, and 9 drilling are 3 × 3 matrix arrangement, and corresponding pile foundation steel casing 6 has 9, establishes ties through 8 communicating pipes 14 between 9 pile foundation steel casings 6.
The mud pit 8 is communicated with one pile foundation steel casing 6 through a mud outlet pipe 13. The steel sedimentation tank 9 is communicated with the steel mud tank 8, and the steel mud tank 8 and the steel sedimentation tank 9 are supported on the water by a support frame 10.
The support frame 10 comprises a plurality of foundation steel pipes 101, a main cross beam 102, a main longitudinal beam 103 and a bridge deck 104, wherein the cross beam 102 is erected on the foundation steel pipes 101, the bottom of the main longitudinal beam 103 is fixedly connected with the cross beam 102, the top of the main longitudinal beam 103 is connected with the bridge deck 104, and a steel mud tank 8 and a steel sedimentation tank 9 are installed on the bridge deck 104.
There are three main beams 102, and each main beam 102 is connected with two foundation steel pipes 101. An inclined strut 105 and a parallel connection 106 are arranged between two foundation steel pipes 101 connected with the same main beam 102.
As shown in fig. 5, a vertical partition 111 is provided in a steel plate tank 11 to divide the steel plate tank into two compartments, one compartment being a steel slurry tank 8 and the other compartment being a steel sedimentation tank 9, and the opening of the steel plate tank 11 is directed upward. As shown in fig. 6, the opening and bottom of the steel-plate case 11 are reinforced with a No. 8 channel 12, and the scissor back ribs are formed around the steel-plate case with the No. 8 channel 12. The top of the vertical partition 111 is provided with an overflow port 112 to realize the communication between the two compartments.
When in use, new slurry is prepared in the steel slurry pool 8 and is delivered into the pile foundation steel casing 6 through the slurry outlet pipe 13 by a slurry pump. After the drill is started, the air compressor conveys compressed air into the air pipe 4, and the air is discharged from the bottom of the air pipe 4 and forms a gas-liquid mixture with slurry. The sediment at the bottom of the hole is suspended under the impact action of the ejected gas, and due to the density difference of liquid inside and outside the pipe, three-phase flow of slurry, air and sediment in the hole moves upwards along the slag discharge pipe 3 and is discharged out of the hole opening, the slurry enters the slag receiving basket to filter the sediment in the slurry, the filtered slurry flows into the steel sedimentation tank 9 to be sedimentated and then overflows into the steel slurry tank 8, and then flows into the pile foundation steel casing 6 again through the slurry outlet pipe 13 by the slurry pump and flows into each drill hole through the communicating pipe between the pile foundation steel casing 6. A digging machine is specially configured in the drilling process to timely clean the drilling slag in the slurry sleeve box, and the drilling slag is intensively transported to a spoil area by a slag transport vehicle to be abandoned.
The utility model discloses a support frame supports steel mud pit 8 and steel sedimentation tank on water, can avoid the pollution of pile foundation construction to the environment on water. After being discharged, the mud in the drilled pile is precipitated by the sedimentation tank and then reaches the mud tank, the mud in the mud tank is pumped back to the drilled pile, and can be recycled for many times, so that the use times of the mud are increased, the use amount of newly manufactured mud is reduced, and the material cost can be reduced.
Use the utility model discloses a construction method of sediment system is reversed in gas lift is introduced below to take the construction of Shantou Shan north Dai Chenghai section engineering Donglie river main pier pile foundation as an example.
The navigation grade of the east-li river is a III-grade channel of the inland river, so that the overwater drilling platform is erected and the slurry circulation operation is completed on the platform, so that the high requirements on navigation and environmental protection are met. The pile diameter of the main bridge pier pile foundation is 2.5m, the pile enters rock at the depth of about 120m, weathered rock in the pile bottom embedding is not less than 2.5 times of the pile diameter according to design requirements, the sediment thickness is not more than 5cm, the hole forming work efficiency is extremely low by selecting the traditional impact drill under the rock entering requirement of nearly 6.25m, the design requirement on the sediment thickness is difficult to achieve, the combined conversion of reverse circulation hole forming and the impact drill has higher requirements on various indexes such as mud specific gravity and the like, and hole collapse and concrete over-square are easily caused.
Therefore, as shown in fig. 7, the drilling construction of this embodiment adopts a reverse circulation rotary drilling machine and a construction process of cone drilling gas lift reverse slag drilling, which mainly includes mud wall protection, drilling hole formation and hole cleaning.
(1) Drilling sequence
As shown in fig. 8, the pile foundation construction requires hole jumping to reduce the influence of the later pile foundation construction on the previous pile foundation concrete before the design strength is not reached.
(2) Drill model selection
The main piers of the Donglihe super bridge totally comprise 36 cast-in-situ bored piles, the depth from the top surface of the pile casing to the bottom of the hole reaches about 130 meters, and the requirements on the torque of a drilling machine and the quality of a drill rod are high. 6 vehicle-mounted Xinfeng 351 type reverse circulation rotary drilling machines with advanced technical performance and stronger lifting capacity are selected for drilling soft strata, and each drilling machine is provided with 1 cone wheel drill bit for drilling strata. The performance index of the Xinfeng 351 reverse circulation rotary drilling machine is shown in the table 1.
TABLE 1 drill performance index Table
Working principle of Xinfeng 351 type reverse circulation rotary drilling machine: the mud is injected between the drill rod and the drill hole, and soil is cut along with the air injection of the drill rod, and the pipe diameter is much smaller than that of the hole, so that the mud, the cut soil slag and the like are quickly discharged out of the ground from the drill rod and can be recycled after entering a mud sedimentation tank for treatment.
(3) Slurry preparation and performance index
The wall protection slurry is very important in drilling, and is especially important for large-diameter deep holes, mud layers and sand layers with poor slurry making performance, and slurry control. The utility model discloses choose for use not disperse, low solid phase, high viscosity PHP mud.
In order to ensure the smooth operation of the hole forming construction of the bored pile, before formal drilling, calcium bentonite in different producing areas and water, bentonite, caustic soda, PHP and the like in different proportions are selected for trial preparation and verification again, and the mud proportion with the optimal mud indexes is selected. The preparation of the slurry is carried out in the platform slurry preparation area.
Before drilling construction, firstly, a slurry stirrer is adopted to stir bentonite slurry in a slurry preparation area, then a slurry pump is used to pump the bentonite slurry into the steel casing, and when the performance index of the slurry in the steel casing meets the construction requirement, a hole is drilled for drilling.
The utility model discloses the performance index of well mud each construction stage requires to see table 2 in detail.
TABLE 2 slurry Performance index List
(4) Slurry circulation system
In this embodiment, the steel-made slurry tank 8 and the steel-made sedimentation tank 9 are both 6m long, 4m wide, and 3m high. The bridge deck 104 is a 12 cm-thick shaping plate, 1021-type Bailey sheets are selected as the main longitudinal beams 103, the main longitudinal beams 103 are connected through connecting beams, and 8-number channel steel is selected as the connecting beams.
The main beam 102 is 45a double-spliced I-shaped steel, the base steel pipe 101 is a circular steel pipe with the diameter of 630mm and the wall thickness of 10mm, and the inclined strut 105 and the cross joint 106 are 20a channel steel. The steel plate made box 11 has a plate thickness of 1cm, and the overflow port 112 is a rectangular notch of 50cm x 50 cm.
When in use, new slurry is prepared in the steel slurry pool 8 and is delivered into the pile foundation steel casing 6 through the slurry outlet pipe 13 by a slurry pump. After the drill is started, the drill pumps the slurry carrying the drill slag to the steel sedimentation tank 2 for sedimentation, then overflows into the steel slurry tank 1, then is conveyed to the pile foundation steel casing 6 through the slurry pump through the slurry outlet pipe 5, and flows into each drill hole through the communicating pipe between the pile foundation steel casing 6. A digging machine is specially configured in the drilling process to timely clean the drilling slag in the slurry sleeve box, and the drilling slag is intensively transported to a spoil area by a slag transport vehicle to be abandoned.
(5) Positioning and debugging of reverse circulation rotary drilling machine
Before the drilling machine is in place, all preparation works of drilling are comprehensively checked, and the drilling machine is in place after the completion of the check.
The base and the top end of the drilling machine after installation are stable, and displacement is not generated in the drilling process. The drilling machine should keep a good working state, the electric part has no potential safety hazard, and the motor shell should be grounded.
The drilling machine is positioned and leveled on the machine base, and whether the center of the drill bit and the center of the protective cylinder are on the same plumb line and whether the deviation between the drill bit and the center of the hole site is within the standard allowable range is carefully measured and checked. After the drilling tool is confirmed to be correct, whether the verticality of the drill rod meets the requirement, whether the drill rod, the drill bit and other parts are firmly connected, whether the operation is good, and whether the diameter of the drill bit is the same as the designed pile diameter are checked, the length of the drilling tool is checked, all indexes of the slurry are detected, and the drilling can be started after all the indexes are ready.
And detecting the levelness of the pile foundation base once a day in the drilling process, and stopping the drilling machine to pull out the drilling machine to level the base in time if the height difference of the diagonal line of the drilling machine base is more than 10 mm.
(6) Drilling hole by reverse circulation rotary drilling machine
The drilling process is divided into three stages: the drilling stage in the casing, the drilling stage of the weak stratum below the casing and the drilling stage of the rock stratum.
And (3) drilling in the casing: and (2) performing reverse circulation pressurized clear water drilling by adopting a scraper drill bit with the diameter of 2.5m from the bottom opening of the protective cylinder, controlling the footage to be about 2-4 m per hour, supplementing clear water into the hole, precipitating the mixed slurry in a sedimentation tank, then refluxing the slurry into the protective cylinder, and transferring the drilling slag to a slag disposal site.
The drilling stage of the weak stratum with the casing is as follows: when the drilling reaches about 1-2 m close to the bottom opening of the steel casing, a mechanical drill bit with the diameter phi of 2.5m is exchanged, the drill bit is reversely circulated and idled when the drilling is started, a slurry circulating system is started, slurry in the hole is replaced, after the index of the slurry in the hole meets the requirement, high-quality slurry wall protection is reversely circulated and decompressed for drilling, the drilling is slowly carried out near the bottom opening of the steel casing, a stable hole wall is formed, and the footage is controlled to be about 0.3-0.8 m per hour.
And (3) the drill bit resumes normal drilling after exiting the casing by 5-6 m, and according to the characteristics of different stratums, the indexes of the wall protection slurry and the drilling speed are adjusted in time in the drilling process, the drilling footage is 1-3.5 m per hour, and high-quality slurry is supplemented in the hole.
Corresponding drilling process parameters are adopted according to the geological conditions of the stratum, and the details are shown in a table 3.
TABLE 3 different stratum drilling parameter table
Formation of earth | Weight drill (KN) | Number of revolutions (r/min) | Drilling speed (m/h) |
Drilling in casing | ≤4.0 | ||
Fine sand layer (dense) | 100~150 | 10~15 | 1.5~2.0 |
Clay layer of silt and powder | 100~120 | 10~15 | 1~2 |
Middle coarse sand layer (dense) | 150~300 | 5~10 | 2.0~3.0 |
Bottom opening stratum of pile casing | <100 | 5~10 | 0.3~0.8 |
② drilling attention items
a. During the drilling process, the grout is supplemented into the hole at any time, and the water head height in the hole is maintained. The mud surface in the hole is higher than the river surface by more than 3.0m at any time.
b. The lifting drilling tool is stable, and particularly when the drill bit is positioned at the bottom opening of the protective cylinder, the lifting drilling tool must be carefully operated to prevent the drill bit from hooking the protective cylinder and avoiding colliding the steel protective cylinder to disturb the wall of the drilled hole.
c. When a long drill rod is connected, the drilling is stopped, the drilling tool is lifted to 20-30 cm away from the bottom of a hole, the slurry circulation is maintained for more than 10min to remove sediment at the bottom of the hole and carry out and discharge drilling slag in a pipeline, and then the pump is stopped to connect the long drill rod. The drill rod connecting bolt is firmly screwed, and the sealing ring is carefully checked to prevent the drill rod joint from water and gas leakage, so that the reverse circulation cannot work normally.
d. The drilling process should be operated continuously, and should not be stopped for a long time in the middle, so as to shorten the hole-forming period as much as possible.
(7) Confirming the elevation and depth of rock entry
And when the reverse circulation rotary drilling machine drills into a hard rock stratum and cannot drill continuously, confirming the elevation of the pile foundation entering the rock, and giving a specific rock entering depth.
(8) Change roller bit and install gas lift equipment
After confirming the rock-entering depth on site, the reverse circulation rotary drilling machine lifts the drill bit, changes the roller bit and installs the gas lift device.
Type selection and installation of gas lift equipment:
as shown in figure 1, the depth from the bottom of the air pipe 4 to the top surface of the slurry in the hole is h1The height difference from the top surface of the slurry in the hole to the top surface of the slurry in the drill rod is h2The density of three-phase flow in the drill rod is rhonThe density of the liquid outside the drill rod is rhoωThen the pressure difference of the inner liquid column and the outer liquid column acting on the liquid level at the bottom of the air pipe is as follows:
ΔP=ρω*h1-ρn(h1+h2)=(ρω-ρn)*h1-ρn*h2 (1)
the pressure difference drives the three-phase flow above the bottom opening of the air pipe 4 in the drill rod to rise along the drill rod, and various resistances in the circulation process are overcome to form reverse circulation. Considering the pressure loss of the gas supply pipeline, the utility model discloses the air pressure is calculated according to formula (2):
P=ρn*h1/102+Ps (2)
in the formula (2), PsThe pressure loss of the air pipeline is 0.05-0.1 MPa.
From the equation (1), the slurry density ρ outside the pipeωAnd h1、h2Relatively stable, reducing the density ρ of the three-phase currentnThe pressure difference driving the gas lift reverse cycle will increase (by increasing the compressed air volume), so the air flow and pressure to the holes are important parameters affecting the gas lift slag-removing capacity. h is1The larger, h2The smaller h2 is, the greater the pressure difference is, so that reverse circulation can not be formed when slurry is in the hole, and the slurry surface in the hole is kept to reach a proper height so as to increase h1h1 reducing h2h2;ρωRho w is the density of three-phase flow, when the proportion of slurry solid phase in the hole is larger, reverse circulation can not be formed, and only rho w isωWhen ρ w is relatively small, ρ is increasedωρ w and ρnThe difference value of rho n can improve the slag-removing efficiency.
As can be seen from the equation (2), the choice of the air compressor should be determined by P, mainly by h1h1 and ρnAnd ρ n control. The pressure required is greater when the mud weight is greater when the hole is deeper. Therefore, the model of the air compressor is determined by calculating P according to the actual pile length of the project; reducing P as much as possiblesThe air duct should be checked for leakage and tight joints to minimize pressure loss.
(9) When the roller bit drills in, the gas lift equipment is started to form gas lift reverse circulation in the hole.
The drilling working principle of the roller bit is as follows: the drilling machine applies enough axial pressure and rotary torque to the bit through the drill rod, and when the roller bit rotates, each roller rotates around the self axis, and the rolling direction is opposite to the rotation direction of the bit. The teeth of the gear roll rock in the pressurizing and rolling process; because the teeth of the gear contact the rock alternately with single tooth and double tooth, the axis of the gear is high when the single tooth lands, and the axis is low when the double tooth lands, the process is repeated, so that the rock is impacted periodically; and because of the super-top, shaft withdrawing and moving of the cone and the complex cone shape of the cone, the cone still generates certain sliding when working at the bottom of the hole, thereby generating cutting action on rocks. Thus, roller cone drill bits break up rock in effect by a combination of impact, crushing and cutting.
The method for calculating the relevant parameters of the roller bit during drilling comprises the following steps:
a. axial pressure
The reasonable axial pressure can be calculated according to equation (3):
P=(0.06~0.07)f D (3)
in formula (3), f is the firmness factor of the rock, and D is the drill diameter.
If the teeth of the roller cone are blunt, the axial pressure is increased; if the rock has cracks or blocks, the axial pressure is reduced appropriately to reduce the vibration of the drilling machine.
b. Torque of drilling tool
The torque M (N · M) of the drill is calculated according to equation (4):
M=29.6kDP1.5 (4)
in the formula (4), k is a rock characteristic coefficient; d, the diameter of the drill bit is mm; p-axial pressure, kN.
c. Drilling speed
The rate of penetration of the roller cone bit is estimated according to equation (5):
in the formula (5), P is axial pressure, kN; n-the rotation speed of the drilling tool, r/min; d, the diameter of the drill bit is mm; f is the hardness coefficient of the ore rock.
The working principle of the gas lift device is as follows: as shown in fig. 1 and 2, the air compressor delivers compressed air into the air duct, which is discharged through the bottom of the duct to form a gas-liquid mixture with the slurry. The sediment at the bottom of the hole is suspended under the impact action of the sprayed gas, and due to the density difference of liquid inside and outside the pipe, three-phase flow of slurry, air and sediment in the hole moves upwards along the drill pipe and is discharged out of the hole opening to enter the sediment receiving basket. And filtering sediments in the slurry, enabling the filtered slurry to flow into a steel sedimentation tank 9 for sedimentation, then overflowing into a steel slurry tank 8, then enabling the filtered slurry to enter the hole again through a slurry outlet pipe 13 by a slurry pump, and repeatedly circulating until the thickness of the sediments at the bottom of the hole meets the standard requirement.
The reverse circulation system takes gas as a power medium and takes liquid fluid as a delay-lift carrying medium to carry solid particles to return upwards to finally complete gas-liquid-solid three-phase mixed motion, thereby achieving the purposes of quickly forming holes and removing sediments and rock debris in the drill hole.
(10) And after the drilling hole reaches the preset drilling depth, measuring the hole depth and the sediment thickness, and confirming the final hole elevation. The sediment thickness is equal to the difference between the drilling depth and the depth of the hole before pouring.
Collecting drilling slag samples of each stratum in the drilling process, and taking the slag samples (2.5-3 m) once when a drill rod is replaced every time when the reverse circulation rotary drilling is carried out; after entering the rock, the slag sample is extracted once every 0.5m of drilling, the slag sample is fished from a slag hole and washed clean by clear water, the extraction amount is 100g each time, and the serial number is stored.
(11) One-time hole cleaning
And after finishing the hole, cleaning the hole in time. And lifting the drilling tool away from the bottom of the hole by about 30-50 cm during hole cleaning, slowly rotating the drilling tool, supplementing high-quality slurry, performing reverse circulation hole cleaning, and simultaneously keeping a water head in the hole to prevent hole collapse. And when the thickness of the sediment at the bottom of the hole meets the design requirement through detection, stopping to lift the drill in time, moving away the drill and detecting the hole after the index of the slurry in the hole after hole cleaning meets the requirement (the circulation time is controlled to be 2-4 hours, and the circulation meets more than 2 cycles). And detecting the pore diameter and the verticality of the formed hole by using a full-automatic ultrasonic pore-forming detector. And (5) performing pile-forming construction as soon as possible after the pore-forming inspection is qualified.
Of course, the present invention can be embodied in many other forms without departing from the spirit or essential attributes thereof, and it should be understood that various changes and modifications can be made by one skilled in the art without departing from the spirit or essential attributes thereof, and that such changes and modifications are intended to be included within the scope of the appended claims.
Claims (9)
1. The gas lift slag return system is characterized in that: including air feeder, row's sediment pipe, tuber pipe, filter residue device and mud circulation system, arrange the entry end of sediment pipe and stretch into pile foundation hole bottom of the hole, arrange the export of sediment pipe and access to the filter residue device, in the tuber pipe stretched into row sediment pipe, the air outlet of tuber pipe extended to arrange the entry end of sediment pipe, and the income wind gap and the air feeder of tuber pipe are connected, the export and the mud circulation system of filter residue device are connected, the mud circulation system is used for flowing back into the pile foundation downthehole with mud.
2. The gas lift slag removal system of claim 1, wherein: the wind pipe is coaxial with the slag discharge conduit.
3. The gas lift slag removal system of claim 1, wherein: the air supply device is an air compressor.
4. The gas lift slag removal system of claim 1, wherein: the residue filtering device is a residue receiving basket.
5. The gas lift slag removal system of claim 1, wherein: the mud circulating system comprises a steel mud pit, a steel sedimentation tank, a support frame and a plurality of pile foundation steel casing pipes, wherein the pile foundation steel casing pipes are communicated through communicating pipes;
the steel mud pit and the steel sedimentation tank are supported by a support frame, an outlet of the residue filtering device is communicated with the steel sedimentation tank, the steel sedimentation tank is communicated with the steel mud pit, and the steel mud pit is communicated with one pile foundation steel casing through a slurry outlet pipe.
6. The gas lift slag removal system of claim 5, wherein: the support frame includes many foundation steel pipes, main beam, main longitudinal beam and decking, and the crossbeam erects on the foundation steel pipe, main longitudinal beam bottom and crossbeam rigid coupling, and the main longitudinal beam top is connected with the decking, steel mud pit, steel sedimentation tank are installed on the decking.
7. The gas lift slag removal system of claim 6, wherein: the main longitudinal beam is a Bailey sheet.
8. The gas lift slag removal system of claim 6, wherein: the main beam has three, and each main beam is connected with two basic steel pipes.
9. The gas lift slag removal system of claim 8, wherein: and an inclined strut and/or a parallel connection are/is arranged between two basic steel pipes connected with the same main beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021195422.6U CN212294662U (en) | 2020-06-24 | 2020-06-24 | Gas lift slag return system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021195422.6U CN212294662U (en) | 2020-06-24 | 2020-06-24 | Gas lift slag return system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212294662U true CN212294662U (en) | 2021-01-05 |
Family
ID=73941972
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021195422.6U Active CN212294662U (en) | 2020-06-24 | 2020-06-24 | Gas lift slag return system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212294662U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111593731A (en) * | 2020-06-24 | 2020-08-28 | 中建四局土木工程有限公司 | Gas lift slag returning system and construction method adopting same |
CN111677439A (en) * | 2020-06-24 | 2020-09-18 | 中建四局土木工程有限公司 | Drilling hole forming method of reverse circulation rotary drilling machine |
CN111706261A (en) * | 2020-06-24 | 2020-09-25 | 中建四局土木工程有限公司 | Construction method for gas lift slag-return pore-forming of roller drill of large-diameter ultralong rock-socketed pile |
CN114232629A (en) * | 2022-02-25 | 2022-03-25 | 徐州徐工基础工程机械有限公司 | A groove cleaning machine for slotted hole sediment clearance |
CN114541993A (en) * | 2022-03-17 | 2022-05-27 | 中建八局第一建设有限公司 | Totally-enclosed multistage sedimentation underground mud pit device and construction method |
-
2020
- 2020-06-24 CN CN202021195422.6U patent/CN212294662U/en active Active
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111593731A (en) * | 2020-06-24 | 2020-08-28 | 中建四局土木工程有限公司 | Gas lift slag returning system and construction method adopting same |
CN111677439A (en) * | 2020-06-24 | 2020-09-18 | 中建四局土木工程有限公司 | Drilling hole forming method of reverse circulation rotary drilling machine |
CN111706261A (en) * | 2020-06-24 | 2020-09-25 | 中建四局土木工程有限公司 | Construction method for gas lift slag-return pore-forming of roller drill of large-diameter ultralong rock-socketed pile |
CN114232629A (en) * | 2022-02-25 | 2022-03-25 | 徐州徐工基础工程机械有限公司 | A groove cleaning machine for slotted hole sediment clearance |
CN114541993A (en) * | 2022-03-17 | 2022-05-27 | 中建八局第一建设有限公司 | Totally-enclosed multistage sedimentation underground mud pit device and construction method |
CN114541993B (en) * | 2022-03-17 | 2024-02-13 | 中建八局第一建设有限公司 | Totally-enclosed multistage sedimentation underground slurry pond device and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212294662U (en) | Gas lift slag return system | |
CN202337976U (en) | In-hole impact high-pressure jet grouting equipment | |
CN109853571B (en) | Device and method for removing slag at bottom of local gas lift reverse circulation hole before concrete pouring of cast-in-situ bored pile | |
CN112554177B (en) | Construction method of ultra-long small-diameter cast-in-situ bored pile | |
CN104612179B (en) | Through the construction method of the diaphram wall of super thick silty sand ground | |
CN110984221A (en) | Construction method for reinforcing end socket at initial end of air shaft and guide wall structure | |
CN111519679A (en) | Rapid grooving construction method for micro-weathering rock of diaphragm wall | |
WO2022227725A1 (en) | Trench forming construction method | |
CN107338789A (en) | A kind of construction method of down-the-hole percussion triple-pipe high pressure jet grouting stake | |
CN111691409A (en) | Slurry dado construction method | |
CN111706276A (en) | Gas lift slag-returning pore-forming construction method | |
CN111677439A (en) | Drilling hole forming method of reverse circulation rotary drilling machine | |
CN111706261A (en) | Construction method for gas lift slag-return pore-forming of roller drill of large-diameter ultralong rock-socketed pile | |
CN211898541U (en) | Guide wall structure for reinforced structure of air shaft initial end head | |
CN113737780A (en) | Underwater rock-socketed concrete pile and construction method thereof | |
CN111593731A (en) | Gas lift slag returning system and construction method adopting same | |
CN110778322A (en) | Remote large-pipe-diameter multi-terrain mud-water-balance pipe jacking construction method | |
CN104141300A (en) | Foundation pile hole drilling construction process | |
CN102937001A (en) | Well completion process of sandy cobble stratum radial well | |
CN111042820B (en) | Construction method for sand layer with oversized pilot hole by vertical shaft raise-shaft method | |
CN117026948A (en) | Construction method of underwater rotary-digging cast-in-place pile | |
CN213654797U (en) | Compact mud circulating system for reverse circulation drilling machine | |
CN117071611A (en) | Seepage-proofing system of earth-rock dam cofferdam and construction method thereof | |
CN112962579B (en) | Construction method of underground continuous wall of coastal push-filling area | |
CN114482107A (en) | Construction method of impervious wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |