CN212264172U - Piercing plug for steel pipe processing - Google Patents

Piercing plug for steel pipe processing Download PDF

Info

Publication number
CN212264172U
CN212264172U CN202020351158.4U CN202020351158U CN212264172U CN 212264172 U CN212264172 U CN 212264172U CN 202020351158 U CN202020351158 U CN 202020351158U CN 212264172 U CN212264172 U CN 212264172U
Authority
CN
China
Prior art keywords
steel pipe
connecting piece
base
top body
lower extreme
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020351158.4U
Other languages
Chinese (zh)
Inventor
吕小军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Jiaye Machinery Manufacturing Co ltd
Original Assignee
Nantong Jiaye Machinery Manufacturing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Jiaye Machinery Manufacturing Co ltd filed Critical Nantong Jiaye Machinery Manufacturing Co ltd
Priority to CN202020351158.4U priority Critical patent/CN212264172U/en
Application granted granted Critical
Publication of CN212264172U publication Critical patent/CN212264172U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a steel pipe machining is with top of perforating relates to steel pipe technical field, for solving current top of perforating because the installation is firm enough and leads to easily walking shape when perforating when using to can not be according to different models and install fixedly, lead to using the problem that receives the limitation. The utility model discloses a top of a body, including a top body, a base lower extreme, it is provided with the iron layer to push up the body upper end, it is provided with the top head portion to push up the body lower extreme, the base lower extreme is provided with the base, the iron layer is inhaled for swing joint with the base to inhale the iron layer, it is provided with the connecting rod to inhale iron layer lower extreme, the connecting rod.

Description

Piercing plug for steel pipe processing
Technical Field
The utility model relates to a steel pipe technical field specifically is a steel pipe processing is with punching top.
Background
The steel pipe is a steel material having a hollow cross section and a length much longer than the diameter or the circumference, and is classified into a circular, square, rectangular and irregular steel pipe according to the cross sectional shape, a carbon structural steel pipe, a low alloy structural steel pipe, an alloy steel pipe and a composite steel pipe according to the material quality, and classified into a steel pipe for a transportation pipe, an engineering structure, a thermal equipment, a petrochemical industry, a machine manufacturing, a geological drilling, a high pressure equipment, and the like according to the use, and classified into a seamless steel pipe and a welded steel pipe according to the production process.
Along with the important function that the steel pipe played in each trade, the kind is also along with more and more, consequently need process into required size or perforate according to the demand when the steel pipe uses, it is more convenient when making the use, especially need utilize special perforation top when perforating, but current perforation top is when using because the installation is not firm enough to walk the shape easily when leading to the perforation, and can not be according to different models and install fixedly, lead to the use to receive the limitation, consequently, need for a steel pipe processing to solve these problems with the perforation top in the market urgently.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a powder metallurgy mould that can closely fix to propose current perforation top in solving above-mentioned background art and walk shape easily when using because the installation is firm enough and lead to perforating, and can not be according to different models and install fixedly, lead to using the problem that receives the limitation.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a steel pipe processing is with perforation top, includes the top body, top body upper end is provided with the top portion, top body lower extreme is provided with the base, the base lower extreme is provided with the iron-absorbing layer, the iron-absorbing layer is swing joint with the base, iron-absorbing layer lower extreme is provided with the connecting rod, the connecting rod outer end is provided with first screw thread, the opening has been seted up in the top body.
Preferably, the opening is internally provided with second threads, a plurality of first grooves distributed at equal intervals are formed in the opening, and a plurality of second grooves distributed at equal intervals are formed in the connecting rod.
Preferably, be provided with the first connecting piece that a plurality of equidistance distributes, a plurality of between opening and the connecting rod be provided with the first plug-in components and the second plug-in components that a plurality of equidistance distributes in the first connecting piece.
Preferably, a sliding groove is formed in the top body and is located at the outer end of the opening.
Preferably, a second connecting piece is arranged in the sliding groove, and a convex block is arranged at the rear end of the second connecting piece.
Preferably, a plurality of mounting holes are formed in the second connecting piece and are distributed at equal intervals.
Compared with the prior art, the beneficial effects of the utility model are that:
1. this steel pipe machining is with perforation top can be convenient for carry on one's body through the first screw thread that sets up and be connected with machine equipment, and the second screw thread that sets up can be convenient for it selects the connected mode according to machine equipment, and the first connecting piece that sets up can be convenient for be connected opening and head rod according to the demand, fixes through first plug-in components and second plug-in components simultaneously, has solved and can't select the problem of installing according to the demand.
2. This steel pipe processing is with punching hole top can be convenient for through the second connecting piece that sets up slide in the spout and select the mounted position, and the second connecting piece is avoided landing from the spout to the lug simultaneously, and the mounting hole of setting can be convenient for the second connecting piece to be fixed on equipment, increases the firm degree of connection simultaneously, and landing or influence trompil shape when avoiding using has solved and has leaded to using the problem that receives the limitation, increases and uses the variety.
Drawings
Fig. 1 is a schematic perspective view of the present invention;
fig. 2 is a schematic sectional view of the present invention;
fig. 3 is a schematic sectional structure diagram of the present invention;
fig. 4 is a schematic view of the bottom structure of the present invention.
In the figure: 1. lifting the body; 2. a head portion; 3. a base; 4. an iron-attracting layer; 5. a connecting rod; 6. a first thread; 7. an opening; 8. a second thread; 9. a first groove; 10. a second groove; 11. a first connecting member; 12. a first plug-in; 13. a second plug-in; 14. a chute; 15. a second connecting member; 16. a bump; 17. and (7) installing holes.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-4, the present invention provides an embodiment: the utility model provides a steel pipe processing is with punching top, includes top body 1, and 1 upper end of top body is provided with top portion 2, and 1 lower extreme of top body is provided with base 3, and 3 lower extremes of base are provided with and inhale iron layer 4, and inhale iron layer 4 and base 3 and be swing joint, inhale iron layer 4 lower extreme and be provided with connecting rod 5, and 5 outer ends of connecting rod are provided with first screw thread 6, have seted up opening 7 in the top body 1.
Further, be provided with second screw thread 8 in the opening 7, seted up the first recess 9 that a plurality of equidistance distributes in the opening 7, seted up the second recess 10 that a plurality of equidistance distributes in the connecting rod 5, can be convenient for push up body 1 through the first screw thread 6 that sets up and be connected with machine equipment, and the second screw thread 8 that sets up can be convenient for it selects the connected mode according to machine equipment.
Further, be provided with the first connecting piece 11 that a plurality of equidistance distributes between opening 7 and connecting rod 5, be provided with the first plug-in components 12 and the second plug-in components 13 that a plurality of equidistance distributes in the first connecting piece 11 of a plurality of, can be convenient for be connected opening 7 and first connecting rod 5 according to the demand through the first connecting piece 11 that sets up, fix through first plug-in components 12 and second plug-in components 13 simultaneously, solved and can't select the problem of installing according to the demand.
Further, a sliding groove 14 is formed in the top body 1, the sliding groove 14 is located at the outer end of the opening 7, and the connecting mode can be conveniently selected through the arranged opening 7 and the sliding groove 14.
Further, a second connecting piece 15 is arranged in the sliding groove 14, a protruding block 16 is arranged at the rear end of the second connecting piece 15, the second connecting piece 15 can be conveniently arranged to slide in the sliding groove 14 to select a mounting position, and meanwhile the protruding block 16 prevents the second connecting piece 15 from sliding off the sliding groove 14.
Further, set up the mounting hole 17 that a plurality of equidistance distributes in the second connecting piece 15, the mounting hole 17 through setting up can be convenient for second connecting piece 15 to fix on equipment, increases the degree of stability of connecting simultaneously, and landing or influence trompil shape when avoiding using has solved the problem that leads to the use to receive the limitation, increases and uses the variety.
The working principle is as follows: when the steel pipe fixing device is used, firstly, a punching machine which is needed to be used for processing a steel pipe is used, then the top body 1 is taken out, the mounting mode of the top body 1 is selected according to the model of machine equipment, the first mode is that the opening 7 which is arranged in the top body 1 can be connected through the second thread 8, the stability can be improved through the connection of the second thread 8, if the connecting rod 5 is needed, the connecting rod 5 can be conveniently connected with the connecting rod 5 according to the requirement through the arranged first connecting piece 11, meanwhile, the first inserting piece 12 and the second inserting piece 13 respectively penetrate through the opening 7 and the connecting rod 5 and the arranged first groove 9 and the second groove 10 to be fixed, the problem that the mounting can not be selected according to the requirement is solved, the third mode is that the second connecting piece 15 can slide out of the sliding groove 14 and can be fixed on the equipment through the mounting hole 17 after sliding to the required position, increase the degree of stability of connection simultaneously, landing or influence the trompil shape when avoiding using, the problem that leads to the use to receive the limitation has been solved, increase and use the variety, and the magnet layer 4 that sets up at 3 lower extremes of base, then can adsorb body 1 and machine equipment mutually on the top, increase the degree of stability, it walks the shape easily when leading to perforating owing to the installation is not firm enough when using to have solved the perforation top from this, and can not be according to different models and install fixedly, lead to using to receive the problem of limitation.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. The utility model provides a steel pipe processing is with perforation top, includes top body (1), its characterized in that: the utility model discloses a top body, including top body (1), base (3), iron layer (4) are inhaled to top body (1) upper end, top body (1) lower extreme is provided with base (3), base (3) lower extreme is provided with inhales iron layer (4), it is swing joint with base (3) to inhale iron layer (4), it is provided with connecting rod (5) to inhale iron layer (4) lower extreme, connecting rod (5) outer end is provided with first screw thread (6), open mouth (7) have been seted up in top body (1).
2. The piercing plug for processing a steel pipe as set forth in claim 1, wherein: be provided with second screw thread (8) in opening (7), first recess (9) that a plurality of equidistance distributes are seted up in opening (7), second recess (10) that a plurality of equidistance distributes are seted up in head rod (5).
3. The piercing plug for processing a steel pipe as set forth in claim 1, wherein: be provided with first connecting piece (11) that a plurality of equidistance distributes, a plurality of between opening (7) and connecting rod (5) be provided with first plug-in components (12) and second plug-in components (13) that a plurality of equidistance distributes in first connecting piece (11).
4. The piercing plug for processing a steel pipe as set forth in claim 1, wherein: a sliding groove (14) is formed in the top body (1), and the sliding groove (14) is located at the outer end of the opening (7).
5. The piercing plug for processing a steel pipe as set forth in claim 4, wherein: a second connecting piece (15) is arranged in the sliding groove (14), and a convex block (16) is arranged at the rear end of the second connecting piece (15).
6. The piercing plug for processing a steel pipe as set forth in claim 5, wherein: a plurality of mounting holes (17) distributed at equal intervals are formed in the second connecting piece (15).
CN202020351158.4U 2020-03-19 2020-03-19 Piercing plug for steel pipe processing Expired - Fee Related CN212264172U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020351158.4U CN212264172U (en) 2020-03-19 2020-03-19 Piercing plug for steel pipe processing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020351158.4U CN212264172U (en) 2020-03-19 2020-03-19 Piercing plug for steel pipe processing

Publications (1)

Publication Number Publication Date
CN212264172U true CN212264172U (en) 2021-01-01

Family

ID=73874244

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020351158.4U Expired - Fee Related CN212264172U (en) 2020-03-19 2020-03-19 Piercing plug for steel pipe processing

Country Status (1)

Country Link
CN (1) CN212264172U (en)

Similar Documents

Publication Publication Date Title
CN212264172U (en) Piercing plug for steel pipe processing
CN203407741U (en) Hollow extruded sheet
CN100448596C (en) Method for production of a component
CN106827594B (en) The lightning-arrest hole forming method and embedded hole processing tool of the web of wind electricity blade
CN210648678U (en) Bearing ring flange inclined hole punching die
CN206865829U (en) A kind of solderless contact pin structure
CN207925297U (en) A kind of shaped core mold
CN205067763U (en) Embedding instrument is used in desert
CN208696051U (en) A kind of hole punching on circular duct mold
CN208214270U (en) A kind of rotor assembly magnetic material die casting equipment
CN205851930U (en) A kind of perforating locator
CN205914788U (en) Rapid indexing perforating device of inclined hole on pipe chute inclined plane for welder
CN202745783U (en) Drilling and milling type spiral external hook for salvaging clustered sucker rod
CN207127073U (en) Small bellows punching sizing mould
CN101813712B (en) Connecting needle for wired fixture
CN206442365U (en) A kind of Kato main body and card cap fasten the metallic mobile phone Kato of assembling
CN2668915Y (en) Rivet
CN213166225U (en) High-efficient drilling equipment is used in pearl processing design
CN213978941U (en) A assembled direction cap for stock
CN214661359U (en) Novel connection structure's dowel sleeve
CN205388072U (en) Metal peg with expansion pipe
CN204200077U (en) A kind of down-the-hole air hammer
CN207297054U (en) The special note anchor device of drill carriage
CN215173057U (en) Novel round-to-square structure
CN217748915U (en) Punching needle

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210101

Termination date: 20210319

CF01 Termination of patent right due to non-payment of annual fee