CN212257105U - Quick installation base of transformer for construction - Google Patents

Quick installation base of transformer for construction Download PDF

Info

Publication number
CN212257105U
CN212257105U CN202021326935.6U CN202021326935U CN212257105U CN 212257105 U CN212257105 U CN 212257105U CN 202021326935 U CN202021326935 U CN 202021326935U CN 212257105 U CN212257105 U CN 212257105U
Authority
CN
China
Prior art keywords
transformer
base
fixed
mounting bar
recess
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021326935.6U
Other languages
Chinese (zh)
Inventor
林养希
周晓晖
陈达
黄花
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Panpan Construction Co ltd
Original Assignee
Fujian Panpan Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Panpan Construction Co ltd filed Critical Fujian Panpan Construction Co ltd
Priority to CN202021326935.6U priority Critical patent/CN212257105U/en
Application granted granted Critical
Publication of CN212257105U publication Critical patent/CN212257105U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Housings And Mounting Of Transformers (AREA)

Abstract

The utility model discloses a quick installation base of transformer for construction, which comprises a base, the upper end of base is seted up flutedly, the inside joint of recess has the transformer, the lower extreme welding of transformer has two mounting bars, two the lower extreme of the position correspondence recess of mounting bar is fixed and has been seted up two joint grooves, two the front and back lateral wall of base is all run through to the front and back end in joint groove, two the both ends of mounting bar all extend to the outside of base, the fixed plate that is provided with in front side of recess. Through setting up base, recess, transformer, mounting bar, joint groove, fixed plate, butt joint groove and butt joint piece's cooperation use, solved current transformer for construction, it is fixed comparatively complicated, current transformer is fixed mostly adopts at transformer lower extreme welding mounting bar, carries out many thread tightening with the mounting bar to the mount after, and fixed unstability also often appears in fixed back transformer, takes place the problem that the slope rocked.

Description

Quick installation base of transformer for construction
Technical Field
The utility model belongs to the technical field of the building, especially, relate to a base is installed fast to transformer for construction.
Background
The building construction refers to production activities in the engineering construction implementation stage, is a construction process of various buildings, and can also be a process of changing various lines on a design drawing into a real object at a specified place, and comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like, and the place of the construction operation is called a building construction site or a construction site.
Need use the transformer to satisfy the power consumption demand of some large-scale apparatus in the building work progress, the most unable convenient installation of current transformer adopts at transformer lower extreme welding mounting bar more, then fixes mounting bar and support frame through the multiunit bolt, neither can install fast, also unable better fixed transformer, and the installation level has the deviation slightly and will leads to the transformer to take place the skew to rock.
SUMMERY OF THE UTILITY MODEL
Problem to prior art exists, the utility model provides a quick installation base of transformer for construction can realize quick installation, and the installation back position is comparatively fixed, can also guarantee the level setting of transformer, at the ground installation of unevenness, also can carry out the leveling with the base, realizes the steady work of transformer. .
The utility model discloses a realize like this, which comprises a base, the upper end of base is seted up flutedly, the inside joint of recess has the transformer, the lower extreme welding of transformer has two mounting bars, two the lower extreme of the position correspondence recess of mounting bar is fixed and has been seted up two joint grooves, two the front and back end in joint groove all runs through the lateral wall around the base, two the both ends of mounting bar all extend to the outside of base, the fixed plate that is provided with in front side of recess, the both ends of fixed plate are all fixed and are provided with butt joint piece, two the position correspondence base lateral wall of butt joint piece has all seted up the butt joint groove.
As the utility model discloses it is preferred, the first screw hole has all been fixed to have seted up, two to the upper end of the butt joint piece at fixed plate both ends the upper end wall of butt joint groove all runs through the position that the base corresponds first screw hole and has seted up the second screw hole, corresponds first screw hole and the inside equal threaded connection of second screw hole have the threaded rod.
As the utility model discloses it is preferred, the inside wall of recess and the inside wall of fixed plate are all fixed and are provided with the rubber pad.
As the utility model discloses it is preferred, the lower extreme four corners department of base all fixedly is provided with hydraulic pressure post.
As the utility model discloses preferred, four the lower extreme of hydraulic pressure post is all fixed and is provided with the bottom plate.
As the utility model discloses it is preferred, the cross sectional dimension of mounting bar is the same with the cross sectional dimension in joint groove, the cross sectional dimension of transformer is less than the cross sectional dimension of recess.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. the utility model discloses a set up base, recess, transformer, mounting bar, joint groove, fixed plate, butt joint groove and butt joint piece's cooperation and use, solved current transformer for the construction, it is fixed comparatively complicated, current transformer is fixed to adopt mostly at transformer lower extreme welding mounting bar, carries out the multiple thread tightening with the mounting bar to the mount after, and fixed unstable also often appears in fixed back transformer, takes place the problem that the slope rocked.
2. The utility model discloses a set up first screw hole, second screw hole and threaded rod, can be so that after recess and joint groove at transformer and mounting bar joint, pass through butt joint piece and butt joint groove joint with the fixed plate, and then make fixed plate joint recess front side mounting bar for the mounting bar is fixed, then through first screw hole and the inside threaded connection threaded rod of second screw hole, make fixed plate and base fixed, and then guaranteed the fixed of mounting bar and transformer.
3. The utility model discloses a set up the rubber pad, can be so that reduce the collision between transformer and the recess lateral wall, avoid vibrations to arouse transformer and recess lateral wall contact to lead to the transformer to damage, the rubber pad can also increase frictional force simultaneously, avoids the transformer to take place the displacement.
4. The utility model discloses a set up the hydraulic pressure post, can be so that four landing legs of base lower extreme all can be adjusted by the hydraulic pressure post, realize four landing legs and can adjust the height alone, both can guarantee that the transformer can nimble height-adjusting, can also realize the co-altitude through four landing legs of independent control on the ground of unevenness for the transformer keeps the level.
5. The utility model discloses a set up the bottom plate, can be so that four landing leg lower extremes all have great holding surface, avoid leading to the landing leg to sink because of the soil texture is soft, and then the problem of the transformer slope that arouses.
6. The utility model discloses a cross sectional dimension that sets up the mounting bar is the same with the cross sectional dimension in joint groove, can guarantee whole device joint fixed mounting bar back, and the mounting bar does not have the free gap, and then plays fixed transformer's effect.
Drawings
Fig. 1 is a schematic view of an overall structure provided by an embodiment of the present invention;
fig. 2 is a schematic structural view of a base and a fixing plate provided in an embodiment of the present invention;
fig. 3 is a schematic view of a base structure provided by an embodiment of the present invention;
fig. 4 is a schematic structural view of a fixing plate according to an embodiment of the present invention;
in the figure: 1. a base; 2. a groove; 201. a clamping groove; 202. a rubber pad; 3. a transformer; 301. mounting a bar; 4. a fixing plate; 401. a butt joint block; 402. a first threaded hole; 5. a butt joint groove; 501. a second threaded hole; 6. a threaded rod; 7. a hydraulic column; 8. a base plate.
Detailed Description
In order to further understand the contents, features and effects of the present invention, the following embodiments are illustrated and described in detail with reference to the accompanying drawings.
The structure of the present invention will be described in detail with reference to the accompanying drawings.
As shown in fig. 1 to 4, the embodiment of the utility model provides a pair of base is installed fast to transformer for construction, including base 1, base 1's upper end is seted up flutedly 2, the inside joint of recess 2 has transformer 3, transformer 3's lower extreme welding has two mounting bars 301, two joint grooves 201 have been seted up to the lower extreme that two mounting bars 301's position corresponds recess 2 is fixed, the front and back lateral wall of base 1 is all run through to the front and back end in two joint grooves 201, the both ends of two mounting bars 301 all extend to the outside of base 1, the fixed plate 4 that is provided with in recess 2's front side, fixed plate 4's both ends are all fixed and are provided with butt joint piece 401, butt joint groove 5 has all been seted up to two butt joint piece 401's position correspondence.
Referring to fig. 1, 2, 3 and 4, the upper ends of the abutting blocks 401 at the two ends of the fixing plate 4 are both fixedly provided with first threaded holes 402, the upper end walls of the two abutting grooves 5 are both penetrated through the positions of the base 1 corresponding to the first threaded holes 402 and provided with second threaded holes 501, and threaded rods 6 are respectively connected to the inner parts of the first threaded holes 402 and the second threaded holes 501 in a threaded manner.
Adopt above-mentioned scheme: through setting up first screw hole 402, second screw hole 501 and threaded rod 6, can be so that after transformer 3 and mounting bar 301 joint are at recess 2 and joint groove 201, with fixed plate 4 through butt joint piece 401 and butt joint groove 5 joint, and then make fixed plate 4 joint recess 2 front side mounting bar 301, make mounting bar 301 fixed, then through first screw hole 402 and second screw hole 501 internal thread connection threaded rod 6, make fixed plate 4 fixed with base 1, and then guaranteed mounting bar 301 and transformer 3's fixed.
Referring to fig. 2 and 3, a rubber pad 202 is fixedly disposed on both inner sidewalls of the groove 2 and the fixing plate 4.
Adopt above-mentioned scheme: through setting up rubber pad 202, can be so that reduce the collision between transformer 3 and the recess 2 lateral wall, avoid vibrations to arouse transformer 3 and recess 2 lateral wall contact to lead to transformer 3 to damage, rubber pad 202 can also increase frictional force simultaneously, avoids transformer 3 to take place the displacement.
Referring to fig. 1, hydraulic columns 7 are fixedly arranged at four corners of the lower end of the base 1.
Adopt above-mentioned scheme: through setting up hydraulic column 7, can be so that four landing legs of base 1 lower extreme all can be adjusted by hydraulic column 7, realize that four landing legs can adjust the height alone, both can guarantee that transformer 3 can nimble height-adjusting, can also realize through the not co-altitude of four landing legs of independent control on the ground of unevenness for transformer 3 keeps the level.
Referring to fig. 1, bottom plates 8 are fixedly provided at the lower ends of four hydraulic cylinders 7.
Adopt above-mentioned scheme: through setting up bottom plate 8, can be so that four landing leg lower extremes all have great holding surface, avoid leading to the landing leg to sink because of the soil property is soft, and then the problem of the transformer 3 slope that arouses.
Referring to fig. 1, 2 and 3, the sectional size of the mounting bar 301 is the same as that of the catching groove 201, and the sectional size of the transformer 3 is smaller than that of the groove 2.
Adopt above-mentioned scheme: the cross sectional dimension through setting up mounting bar 301 is the same with the cross sectional dimension in joint groove 201, can guarantee that whole device joint fixed mounting bar 301 back, mounting bar 301 does not have the free gap, and then plays fixed transformer 3's effect.
The utility model discloses a theory of operation:
when the installation structure is used, firstly, a base is placed at a position to be installed, then the base 1 is adjusted to be horizontal by adjusting the heights of four hydraulic columns 7, the bottom plate 8 arranged at the lower ends of the hydraulic columns 7 can effectively avoid the problem of sinking of supporting legs caused by loose and soft soil, then, two threaded rods 6 are taken down, a fixing plate 4 is taken out, then a transformer 3 and a mounting bar 301 at the lower end of the transformer 3 are placed at the upper end of the base 1 from the front side of a groove 2, the mounting bar 301 is clamped in a clamping groove 201, then the transformer 3 and the mounting bar 301 are pushed into the groove 2 until the transformer 3 is pushed to the side wall of the rear end of the groove 2, at the moment, the end part of the mounting bar 301 at the rear end extends out of the outer side of the base 1 along the clamping groove 201, finally, the fixing plate 4 is horizontally pushed in from the front side, a butt joint block 401 is butted in a butt joint groove 5, the fixing plate 4 is, and then whole transformer 3 is installed fixedly fast, levels base 1 once more at last, guarantees that transformer 3 horizontal work.
In summary, the following steps: this base is installed fast to transformer for construction, through setting up base 1, recess 2, joint groove 201, rubber pad 202, transformer 3, mounting bar 301, fixed plate 4, butt joint piece 401, first screw hole 402, butt joint groove 5, second screw hole 501, threaded rod 6, hydraulic pressure post 7 and bottom plate 8's cooperation is used, the current transformer for construction has been solved, it is fixed comparatively complicated, current transformer is fixed to adopt mostly at transformer lower extreme welded mounting bar, carry out the mounting bar with the mounting bar after to the mount multi-thread fixed, fixed unstability also often appears in fixed back transformer, take place the problem that the slope rocked.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a base is installed fast to transformer for construction, includes base (1), its characterized in that: the upper end of base (1) is seted up flutedly (2), recess (2) inside joint has transformer (3), the lower extreme welding of transformer (3) has two mounting bars (301), two the lower extreme of the position correspondence recess (2) of mounting bar (301) is fixed has seted up two joint grooves (201), two the front and back lateral wall of base (1) is all run through to the front and back end in joint groove (201), two the both ends of mounting bar (301) all extend to the outside of base (1), the front side of recess (2) is fixed and is provided with fixed plate (4), the both ends of fixed plate (4) are all fixed and are provided with butt joint piece (401), two butt joint groove (5) have all been seted up to the position correspondence base (1) lateral wall of butt joint piece (401).
2. The transformer quick installation base for building construction according to claim 1, characterized in that: the upper end of the butt joint blocks (401) at the two ends of the fixing plate (4) is fixedly provided with first threaded holes (402), the upper end wall of the butt joint groove (5) penetrates through the position, corresponding to the first threaded holes (402), of the base (1) and is provided with second threaded holes (501), and threaded rods (6) are connected with the first threaded holes (402) and the second threaded holes (501) in an internal uniform threaded mode.
3. The transformer quick installation base for building construction according to claim 1, characterized in that: and rubber pads (202) are fixedly arranged on the inner side walls of the grooves (2) and the inner side walls of the fixing plates (4).
4. The transformer quick installation base for building construction according to claim 1, characterized in that: the four corners of the lower end of the base (1) are fixedly provided with hydraulic columns (7).
5. The transformer quick installation base for building construction according to claim 4, characterized in that: the lower ends of the four hydraulic columns (7) are fixedly provided with bottom plates (8).
6. The transformer quick installation base for building construction according to claim 1, characterized in that: the cross sectional dimension of mounting bar (301) is the same with the cross sectional dimension of joint groove (201), the cross sectional dimension of transformer (3) is less than the cross sectional dimension of recess (2).
CN202021326935.6U 2020-07-08 2020-07-08 Quick installation base of transformer for construction Expired - Fee Related CN212257105U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021326935.6U CN212257105U (en) 2020-07-08 2020-07-08 Quick installation base of transformer for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021326935.6U CN212257105U (en) 2020-07-08 2020-07-08 Quick installation base of transformer for construction

Publications (1)

Publication Number Publication Date
CN212257105U true CN212257105U (en) 2020-12-29

Family

ID=73979639

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021326935.6U Expired - Fee Related CN212257105U (en) 2020-07-08 2020-07-08 Quick installation base of transformer for construction

Country Status (1)

Country Link
CN (1) CN212257105U (en)

Similar Documents

Publication Publication Date Title
CN102661040B (en) Combined early-disassembly template device
CN209344644U (en) A kind of cable auxiliary arrangement tooling with elevating function
CN212257105U (en) Quick installation base of transformer for construction
CN201152024Y (en) Oblique wall ledger beam strutting piece
CN204624885U (en) A kind of standard knot support chassis of elevator
CN209817099U (en) Large-span steel house room bearing structure
CN219196719U (en) Cantilever support template for water inlet tower construction
CN206784605U (en) A kind of wall extends embedded iron parts installation structure
CN216076366U (en) Concrete spreader split heads for building
CN211646412U (en) Foundation pit supporting device for construction engineering construction
CN210768079U (en) Base for transmission tower
CN209323529U (en) A kind of frame-type double-row pile cement soil wall foundation pit enclosure structure
CN209703318U (en) A kind of regularization bridge type cast-in-situ floor support construction
CN206646830U (en) Large span can turnover type concrete pump pipe type steel support system
CN209535822U (en) Suspension device is used in a kind of transhipment of cement backplate
CN220284835U (en) Deep foundation pit supporting structure
CN212450308U (en) Crane base for building construction
CN211736501U (en) Novel supporting device for constructional engineering
CN220746896U (en) Anti-floating anchor rod fixing device
CN218912351U (en) Stable connection structure is consolidated to building
CN212391191U (en) Installation fine adjustment device for embedded part of vibrating table actuator
CN220622434U (en) Anti-drop structure is used in hydraulic engineering equipment installation
CN216157254U (en) Support frame for construction
CN214739603U (en) Super thick terrace dividing strip installation adjusting device
CN211114964U (en) Assembled securing device for construction steel frame

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201229

Termination date: 20210708