CN212224619U CN202020465907.6U CN202020465907U CN212224619U CN 212224619 U CN212224619 U CN 212224619U CN 202020465907 U CN202020465907 U CN 202020465907U CN 212224619 U CN212224619 U CN 212224619U
Authority
CN
China
Prior art keywords
template
connecting plate
threaded rod
building engineering
engineering construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020465907.6U
Other languages
Chinese (zh)
Inventor
赵恬
王堇轩
代忠华
周虹
鱼宝丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Fourth Construction Group Co ltd
Original Assignee
Gansu Fourth Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Fourth Construction Group Co ltd filed Critical Gansu Fourth Construction Group Co ltd
Priority to CN202020465907.6U priority Critical patent/CN212224619U/en
Application granted granted Critical
Publication of CN212224619U publication Critical patent/CN212224619U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Moulds, Cores, Or Mandrels (AREA)

Abstract

The utility model discloses a building engineering construction is with hanging mould device, including first template and second template, the first connecting plate of first template both ends lateral wall fixedly connected with, be equipped with the draw-in groove on the first connecting plate, the draw-in groove both sides communicate respectively has first spout and second spout, one side intercommunication that the draw-in groove was kept away from to first spout has the through-hole, the through-hole both ends are rotated and are connected with the threaded rod, be connected with two on the threaded rod about draw-in groove horizontal center line symmetry set up and with second spout sliding connection's dead lever, the equal fixedly connected with second connecting plate of second template both ends lateral wall, the one end that the second template was kept away from to the second connecting plate is equipped with integrated into one piece's first stopper. The utility model completes the fixation between the templates through the matching between the two connecting plates, thereby saving time and labor; the fixing and the dismounting between the two templates can be simply and effectively realized by arranging the threaded rod with reverse textures.

Description

Building engineering construction is with hanging mould device
Technical Field
The utility model belongs to the technical field of building engineering, especially, building engineering construction is with hanging mould device.
Background
The hanging mould can be also called a hanging mould, which refers to a mould plate which is not supported and is hung on other fixed objects, and the most obvious difference from other construction mould plates is that no support is arranged below the hanging mould plate, and loads are generally applied to the side direction of the hanging mould plate to keep the structure of the hanging mould plate stable.
The fixing of hanging mould is an important link in hanging mould use, and the fixed concrete component levelness, the straightness that hangs down that has influenced of hanging mould, however fixed the mode that often uses the iron wire ligature to hanging mould at present, and not only the installation is wasted time and energy, and dismantles equally and wastes time and energy.
Therefore, the formwork hanging device for building engineering construction is provided to solve the problems.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the problem that the fixed mode of hanging mould is complicated among the prior art, and the mould device that hangs is used in building engineering construction that provides.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a building engineering construction is with hanging mould device, includes first template and second template, the first connecting plate of first template both ends lateral wall fixedly connected with, be equipped with the draw-in groove on the first connecting plate, the draw-in groove both sides communicate respectively has first spout and second spout, one side intercommunication that the draw-in groove was kept away from to first spout has the through-hole, the through-hole both ends are rotated and are connected with the threaded rod, be connected with two on the threaded rod about draw-in groove horizontal center line symmetry set up and with second spout sliding connection's dead lever, the equal fixedly connected with second connecting plate of second template both ends lateral wall, the one end that the second template was kept away from to the second connecting plate is equipped with integrated into one piece.
Preferably, fixedly connected with and threaded rod threaded connection's nut on the dead lever, fixedly connected with second stopper on the threaded rod, just the texture at second stopper both ends sets up in reverse.
Preferably, a handle is fixedly connected to the top of the threaded rod.
Preferably, the threaded rod is rotatably connected with two ends of the through hole through bearings.
Preferably, the horizontal and vertical sizes of the clamping groove are larger than those of the second connecting plate and the first limiting block.
Preferably, the first connecting plate and the second connecting plate are respectively fixed on the first template and the second template through three screws distributed in a triangular manner.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the first connecting plate is arranged on the first template, the second connecting plate is arranged on the second template, and the templates are fixed by matching the two connecting plates, so that the effect of saving time and labor is achieved;
2. the threaded rod with reverse thread textures can enable the two fixing rods to be close to or far away from each other by rotating the handle, so that the two templates can be fixed and detached conveniently and quickly;
3. first connecting plate and second connecting plate are fixed with first template and second template respectively through three screws that are triangular distribution, can furthest's assurance first connecting plate, second connecting plate and the steadiness between first template and the second template.
Drawings
Fig. 1 is a schematic perspective view of a formwork hanging device for construction of building engineering according to the present invention;
FIG. 2 is an enlarged view of the structure at A in FIG. 1;
fig. 3 is a schematic structural view of a first template in the form hoisting device for building engineering construction provided by the utility model;
fig. 4 is a schematic cross-sectional structure view of a first template in the form hoisting device for building engineering construction provided by the utility model;
FIG. 5 is an enlarged view of the structure at B in FIG. 4;
fig. 6 is the utility model provides a second template's among building engineering construction hoisting formwork device structure schematic diagram.
In the figure: the first template, the second template, the first connecting plate, the clamping groove, the through hole, the first sliding groove, the second sliding groove, the clamping groove, the through hole, the first sliding groove, the second sliding groove, the threaded rod, the nut, the fixing rod, the second connecting plate, the first limiting block, the second limiting block, the handle and the handle are all 1.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-6, a formwork hanging device for building engineering construction, including first template 1 and second template 2, first connecting plate 3 of 1 both ends lateral wall fixedly connected with of first template, be equipped with draw-in groove 4 on first connecting plate 3, draw-in groove 4 both sides communicate respectively has first spout 6 and second spout 7, one side intercommunication that draw-in groove 4 was kept away from to first spout 6 has through-hole 5, the through-hole 5 both ends are rotated and are connected with threaded rod 8, be connected with two on the threaded rod 8 about draw-in groove 4 horizontal center line symmetry set up and with second spout 7 sliding connection's dead lever 10, the equal fixedly connected with second connecting plate 11 of 2 both ends lateral wall of second template, the one end that second template 2 was kept away from to second connecting plate 11 is equipped with integrated into one piece's first stopper 12.
It is worth mentioning that, fixedly connected with and threaded rod 8 threaded connection's nut 9 on the dead lever 10, dead lever 10 passes through nut 9 and threaded rod 8 threaded connection, fixedly connected with second stopper 13 on the threaded rod 8, and the reverse setting of texture at second stopper 13 both ends, two nuts 9 can keep away from each other simultaneously or be close to each other when this kind of setting can realize threaded rod 8 rotates, two nuts 9 drive two dead levers 10 and keep away from each other or be close to each other, thereby more convenient completion dead lever 10 is to the chucking of first stopper 12 with relax.
Specifically, the top of the threaded rod 8 is fixedly connected with a handle 14, and the threaded rod 8 can be rotated more conveniently and more laborsavingly through the handle 14.
It is worth mentioning that the threaded rod 8 is rotatably connected with the two ends of the through hole 5 through bearings, and the bearings can enable the threaded rod 8 to rotate more conveniently and do not move in other directions.
It should be noted that the horizontal and vertical dimensions of the clamping groove 4 are greater than those of the second connecting plate 11 and the first limiting block 12, and the clamping groove 4 can be easily passed through by the second connecting plate 11 and the first limiting block 12 due to the arrangement, so that the initial installation between the first template 1 and the second template 2 is facilitated.
It is worth mentioning that the first connecting plate 3 and the second connecting plate 11 are respectively fixed on the first template 1 and the second template 2 through three screws distributed in a triangular manner, and the fixing mode can be the simplest and most effective to fix the first connecting plate 3 and the second connecting plate 11 on the first template 1 and the second template 2 respectively.
When the utility model is installed and fixed, the second connecting plate 11 and the first limiting block 12 firstly pass through the clamping groove 4, the first template 1 is connected with the first connecting block 1, one side of the second template 2 connected with the second connecting block 1 faces outwards, then the handle 14 is rotated, the handle 14 is rotated to drive the threaded rod 8 to rotate, the threaded rod 8 rotates to enable the two nuts 9 to move towards the mutually approaching direction, the two nuts 9 can drive the two fixing rods 10 to mutually approach until the two fixing rods 10 are contacted with the second connecting plate 11, the fixing rods 10 are clamped between the first limiting block 12 and the second connecting plate 11, the structure is shown in figure 1, then the other end of the template is fixed according to the method, after the template is fixed, pouring forming can be carried out in the frame formed by the template, the acting force of the clamping groove 4, the second connecting plate 11 and the first limiting block 12 is mutually connected between the templates, the structure of the device is ensured to have enough stability, and the device is not required to be reinforced from the outside and is convenient to disassemble.
The utility model discloses during the dismantlement, earlier with 14 antiport of handle, handle 14 makes two nuts 9 keep away from each other through threaded rod 8, and two nuts 9 can drive two dead levers 10 and keep away from each other, and the position of dead lever 10 is removed and is stopped rotating handle 14 after first stopper 12 can freely pass draw-in groove 4, separates second connecting block 1 and first stopper 12 and draw-in groove 4 again.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. A formwork hanging device for building engineering construction comprises a first formwork (1) and a second formwork (2), it is characterized in that the side walls of the two ends of the first template (1) are fixedly connected with first connecting plates (3), a clamping groove (4) is arranged on the first connecting plate (3), a first sliding groove (6) and a second sliding groove (7) are respectively communicated with two sides of the clamping groove (4), one side of the first sliding chute (6) far away from the clamping groove (4) is communicated with a through hole (5), two ends of the through hole (5) are rotatably connected with threaded rods (8), the threaded rods (8) are connected with two fixed rods (10) which are symmetrically arranged around the horizontal central line of the clamping groove (4) and are in sliding connection with the second sliding groove (7), the side walls of two ends of the second template (2) are fixedly connected with second connecting plates (11), and one end of the second connecting plate (11) far away from the second template (2) is provided with a first limiting block (12) which is integrally formed.
2. The formwork hanging device for building engineering construction according to claim 1, wherein the fixing rod (10) is fixedly connected with a nut (9) in threaded connection with a threaded rod (8), the threaded rod (8) is fixedly connected with a second limiting block (13), and textures at two ends of the second limiting block (13) are arranged in an opposite direction.
3. The form hanging device for building engineering construction according to claim 1, characterized in that a handle (14) is fixedly connected to the top of the threaded rod (8).
4. The form hanging device for building engineering construction according to claim 1, wherein the threaded rod (8) is rotatably connected with two ends of the through hole (5) through bearings.
5. The formwork hanging device for building engineering construction according to claim 1, wherein the horizontal and vertical dimensions of the clamping groove (4) are larger than those of the second connecting plate (11) and the first limiting block (12).
6. The formwork hanging device for building engineering construction according to claim 1, wherein the first connecting plate (3) and the second connecting plate (11) are respectively fixed on the first formwork (1) and the second formwork (2) through three screws distributed in a triangular shape.
CN202020465907.6U 2020-04-02 2020-04-02 Building engineering construction is with hanging mould device Expired - Fee Related CN212224619U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020465907.6U CN212224619U (en) 2020-04-02 2020-04-02 Building engineering construction is with hanging mould device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020465907.6U CN212224619U (en) 2020-04-02 2020-04-02 Building engineering construction is with hanging mould device

Publications (1)

Publication Number Publication Date
CN212224619U true CN212224619U (en) 2020-12-25

Family

ID=73904301

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020465907.6U Expired - Fee Related CN212224619U (en) 2020-04-02 2020-04-02 Building engineering construction is with hanging mould device

Country Status (1)

Country Link
CN (1) CN212224619U (en)

Similar Documents

Publication Publication Date Title
CN212224619U (en) Building engineering construction is with hanging mould device
CN113183310A (en) Be used for prefabricated building PC wall conversion layer to reserve joint bar positioner
CN206844643U (en) Post-cast strip independence braced wing support combination unit
CN215407370U (en) Construction structures is pour in step to two walls of building movement joint concrete
CN206655478U (en) Adjustable window hole molding board support meanss
CN210917962U (en) Steel bar truss floor support plate framework
CN212535093U (en) Connecting device of building templates
CN208844919U (en) A kind of construction form and shoring early-dismantling device
CN211523432U (en) Municipal works production is with pouring template
CN106884533A (en) Adjustable window hole molding board support meanss
CN213509585U (en) Deviation preventing device for hanging under beam
CN207227970U (en) A kind of drawing and pulling type box girder inner formwork
CN207245154U (en) A kind of aluminium frame covers plastic building mould
CN217924874U (en) A high formwork angle brace mechanism for construction
CN220147873U (en) Multifunctional special transportation frame for improving safety of PC (polycarbonate) component
CN221298606U (en) Fixed bolster for construction template
CN217734840U (en) Aluminum alloy suspended formwork template
CN212026865U (en) Fixing device of beam column reinforcing bar for building
CN210976606U (en) Template fixing device that construction used
CN212562498U (en) Special buckle connecting piece for building formwork support
CN214925589U (en) Be used for prefabricated building PC wall conversion layer to reserve joint bar positioner
CN213418477U (en) Adjustable caisson type toilet construction formwork lifting device
CN214144685U (en) Modular building wall pours template
CN109025263A (en) A kind of construction form and shoring early-dismantling device
CN216474414U (en) Auxiliary material machine of highway engineering construction usefulness

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201225