Block terminal that electrical engineering used Download PDFInfo
- Publication number
- CN212210169U CN212210169U CN202021034667.0U CN202021034667U CN212210169U CN 212210169 U CN212210169 U CN 212210169U CN 202021034667 U CN202021034667 U CN 202021034667U CN 212210169 U CN212210169 U CN 212210169U
- Authority
- CN
- China
- Prior art keywords
- box
- chamber
- air
- fixedly connected
- air inlet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Cooling Or The Like Of Electrical Apparatus (AREA)
Abstract
本实用新型公开了一种电气工程用的配电箱,包括:主箱、副箱、进气室和出气室,所述主箱两侧外壁通过焊接固定连接有副箱,所述副箱内部通过焊接固定连接有隔板,位于一侧的所述副箱顶部通过隔板分隔有进气室,本实用新型实现了在电气工程用的配电箱使用时,通过散热风扇的转动将外界的空气抽入进气室内部,通过滤芯过滤以后外界的风与循环降温水管接触进行降温,然后降温以后的风通过散热风扇送入主箱内部,对主箱内部的电气元件进行降温,保证降温的同时防止外界灰尘进入主箱内部对电气元件造成污染,通过副箱内部的隔板,便于配电箱内的电气元件进行检修时,便于工具与备配件的存放,便于检修人员拿取。
The utility model discloses a distribution box for electrical engineering, which comprises a main box, an auxiliary box, an air inlet chamber and an air outlet chamber. The outer walls on both sides of the main box are fixedly connected with auxiliary boxes by welding, and the inside of the auxiliary box is A partition plate is fixedly connected by welding, and the top of the auxiliary box located on one side is divided into an air inlet chamber by the partition plate. The air is drawn into the air intake chamber, and after being filtered by the filter element, the outside air contacts with the circulating cooling water pipe to cool down, and then the cooled air is sent to the inside of the main box through the cooling fan to cool the electrical components inside the main box to ensure the cooling effect. At the same time, it prevents external dust from entering the main box and causing pollution to the electrical components. The partition inside the auxiliary box is convenient for the maintenance of the electrical components in the distribution box, which is convenient for the storage of tools and spare parts, and easy for maintenance personnel to take.
Description
技术领域technical field
本实用新型涉及电气工程技术领域,具体为一种电气工程用的配电箱。The utility model relates to the technical field of electrical engineering, in particular to a distribution box for electrical engineering.
背景技术Background technique
配电箱是数据上的海量参数,一般是构成低压林按电气接线,要求将开关设备、测量仪表、保护电器和辅助设备组装在封闭或半封闭金属柜中或屏幅上,构成低压配电箱。正常运行时可借助手动或自动开关接通或分断电路。配电箱具有体积小、安装简便,技术性能特殊、位置固定,配置功能独特、不受场地限制,应用比较普遍,操作稳定可靠,空间利用率高,占地少且具有环保效应的特点。配电箱的用途:合理的分配电能,方便对电路的开合操作。有较高的安全防护等级,能直观的显示电路的导通状态。The distribution box is a mass of parameters on the data, which generally constitutes a low-voltage forest. According to the electrical wiring, switchgear, measuring instruments, protective appliances and auxiliary equipment are required to be assembled in a closed or semi-enclosed metal cabinet or on the screen to form a low-voltage power distribution. box. During normal operation, the circuit can be switched on or off by means of manual or automatic switches. The distribution box has the characteristics of small size, easy installation, special technical performance, fixed location, unique configuration function, no site restrictions, common application, stable and reliable operation, high space utilization, small footprint and environmental protection effects. The purpose of the distribution box: to distribute electric energy reasonably and to facilitate the opening and closing operation of the circuit. It has a high safety protection level and can visually display the conduction state of the circuit.
但是,传统的电气工程用的配电箱在使用过程中存在一些弊端,比如:However, there are some drawbacks in the use of traditional electrical engineering distribution boxes, such as:
1、传统的电气工程用的配电箱在使用时,由于配电箱内部电气元件较多,这些电气元件在运行过程中会产生大量热量,传统的配电箱多采用散热窗被动散热,散热效率较低,同时在散热过程中外界的灰尘容易进入配电箱内部对电气元件造成损伤。1. When the traditional distribution box for electrical engineering is in use, due to the large number of electrical components inside the distribution box, these electrical components will generate a lot of heat during operation. The traditional distribution box mostly uses heat dissipation windows to passively dissipate heat. The efficiency is low, and at the same time, during the heat dissipation process, the external dust easily enters the inside of the distribution box and causes damage to the electrical components.
2、传统的电气工程用的配电箱在使用时,需要定期进行检修维护,但是在检修过程中,检修工具较多,检修过程中无法进行备配件的暂存以及工具的暂存,造成检修人员不断在配电箱与检修装置之间来回切换,影响检修效率。2. When the traditional distribution box for electrical engineering is in use, it needs to be repaired and maintained regularly. However, during the maintenance process, there are many maintenance tools, and the temporary storage of spare parts and tools cannot be carried out during the maintenance process, resulting in maintenance and repair. Personnel constantly switch back and forth between the distribution box and the maintenance device, which affects the maintenance efficiency.
实用新型内容Utility model content
本实用新型的目的在于提供一种电气工程用的配电箱,以解决上述背景技术中提出的问题。The purpose of the present invention is to provide a distribution box for electrical engineering to solve the problems raised in the above background technology.
为实现上述目的,本实用新型提供如下技术方案:一种电气工程用的配电箱,包括:主箱、副箱、进气室和出气室,所述主箱两侧外壁通过焊接固定连接有副箱,所述副箱内部通过焊接固定连接有隔板,位于一侧的所述副箱顶部通过隔板分隔有进气室,位于远离所述进气室一侧的副箱底部通过隔板分隔有出气室,所述副箱位于进气室和出气室外壁处开设有透气格栅,所述副箱内部位于进气室底部以及出气室顶部通过隔板分隔有储物室,所述储物室外侧通过铰链转动连接有储物箱门。In order to achieve the above purpose, the utility model provides the following technical solutions: a power distribution box for electrical engineering, comprising: a main box, an auxiliary box, an air inlet chamber and an air outlet chamber, and the outer walls on both sides of the main box are fixedly connected by welding. Auxiliary box, the interior of the auxiliary box is fixedly connected with a partition by welding, the top of the auxiliary box located on one side is separated by a partition plate, and an intake chamber is separated by a partition plate, and the bottom of the auxiliary box located on the side away from the intake chamber is separated by a partition plate Separated with an air outlet, the auxiliary box is provided with a ventilation grille at the air inlet chamber and the outer wall of the air outlet. A storage box door is pivotally connected to the outside of the storage room through a hinge.
进一步的,所述主箱还包括:防护网和主箱门,所述主箱位于进气室以及出气室中央内壁上通过卡接固定连接有防护网,所述主箱外侧通过铰链转动连接有主箱门。Further, the main box further includes: a protective net and a main box door, the main box is located on the central inner wall of the air inlet chamber and the air outlet chamber, and is fixedly connected with a protective net by clamping, and the outer side of the main box is connected with a hinge through rotation. Main compartment door.
进一步的,所述进气室还包括:散热风机、滤芯、循环降温水管和风机固定板,所述进气室靠近透气格栅一侧内壁通过卡接固定连接有滤芯,所述进气室上下两侧内壁通过卡接固定连接有循环降温水管,所述进气室内壁通过螺钉固定连接有风机固定板,所述风机固定板中央通过支架固定连接有散热风机,所述进气室外侧通过铰链转动连接有进气箱门,使用时,通过散热风扇的转动将外界的空气抽入进气室内部,通过滤芯过滤以后外界的风与循环降温水管接触进行降温,然后降温以后的风通过散热风扇送入主箱内部,对主箱内部的电气元件进行降温,然后从出气室一侧的透气格栅排出,保证降温的同时防止外界灰尘进入主箱内部对电气元件造成污染。Further, the air inlet chamber also includes: a cooling fan, a filter element, a circulating cooling water pipe and a fan fixing plate, the inner wall of the air inlet chamber close to the ventilation grille side is fixedly connected with a filter element by clamping, and the upper and lower parts of the air inlet chamber are connected. The inner walls on both sides are fixedly connected with circulating cooling water pipes by clamping, the air inlet inner wall is fixedly connected with a fan fixing plate by screws, the center of the fan fixing plate is fixedly connected with a cooling fan through a bracket, and the outside of the air inlet is connected by a hinge. The air intake box door is connected by rotation. When in use, the outside air is drawn into the air intake chamber through the rotation of the cooling fan. After filtering through the filter element, the outside air contacts with the circulating cooling water pipe to cool down, and then the cooled air passes through the cooling fan. It is sent into the main box to cool the electrical components inside the main box, and then discharged from the ventilation grille on one side of the air outlet to ensure cooling and prevent external dust from entering the main box and causing pollution to the electrical components.
进一步的,所述出气室还包括:出气箱门,所述出气室外侧通过铰链转动连接有出气箱门,所述出气箱门与出气室接触部位通过卡接固定连接有密封条,用于出气室的密封,防止外界灰尘进入出气室内。Further, the air outlet chamber further comprises: an air outlet box door, an air outlet box door is rotatably connected to the outside of the air outlet chamber through a hinge, and a sealing strip is fixedly connected to the contact part of the air outlet box door and the air outlet chamber by clamping, for air outlet. The sealing of the chamber prevents external dust from entering the outlet chamber.
进一步的,所述循环降温水管进水口一端通过管接头固定连接有循环水泵,所述循环降温水管出水口一端通过管道连接有冷却水箱。Further, one end of the water inlet of the circulating cooling water pipe is fixedly connected with a circulating water pump through a pipe joint, and one end of the water outlet of the circulating cooling water pipe is connected with a cooling water tank through a pipe.
进一步的,所述进气箱门与进气室接触部位通过卡接固定连接有密封条,便于进气室的密封,便于散热风机吹出的风进入到主箱内,与主箱内的热空气进行热交换,加速主箱内的散热。Further, a sealing strip is fixedly connected to the contact part between the air intake box door and the air intake chamber by clamping, which is convenient for the sealing of the air intake chamber, and it is convenient for the wind blown by the cooling fan to enter the main box, and it is convenient for the hot air in the main box. Perform heat exchange to accelerate heat dissipation in the main box.
与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the present utility model are:
1、本实用新型通过设置的主箱、副箱以及进气室,实现了在电气工程用的配电箱使用时,通过散热风扇的转动将外界的空气抽入进气室内部,通过滤芯过滤以后外界的风与循环降温水管接触进行降温,然后降温以后的风通过散热风扇送入主箱内部,对主箱内部的电气元件进行降温,然后从出气室一侧的透气格栅排出,保证降温的同时防止外界灰尘进入主箱内部对电气元件造成污染。1. Through the main box, the auxiliary box and the air intake chamber, the utility model realizes that when the distribution box for electrical engineering is used, the outside air is drawn into the air intake chamber through the rotation of the cooling fan, and filtered through the filter element. After that, the outside air contacts the circulating cooling water pipe to cool down, and then the cooled air is sent into the main box through the cooling fan to cool the electrical components inside the main box, and then discharged from the ventilation grille on the side of the air outlet to ensure cooling. At the same time, it prevents external dust from entering the main box and causing pollution to the electrical components.
2、本实用新型通过设置的主箱、副箱以及进气室,实现了在电气工程用的配电箱使用时,通过副箱内部的隔板,便于配电箱内的电气元件进行检修时,便于工具与备配件的存放,便于检修人员拿取,保证检修工作的顺利进行。2. Through the main box, the auxiliary box and the air intake chamber, the utility model realizes that when the distribution box for electrical engineering is used, the partition inside the auxiliary box is convenient for the maintenance of the electrical components in the distribution box. , easy to store tools and spare parts, easy for maintenance personnel to take, to ensure the smooth progress of maintenance work.
附图说明Description of drawings
图1为本实用新型整体主视结构剖视示意图;1 is a schematic cross-sectional view of the overall front view structure of the present utility model;
图2为本实用新型整体左视结构剖视示意图;Figure 2 is a schematic cross-sectional view of the overall left-view structure of the present utility model;
图3为本实用新型整体主视结构示意图;3 is a schematic diagram of the overall front structure of the utility model;
图4为本实用新型巡皇降温水管主视结构示意图。FIG. 4 is a schematic structural diagram of the main view of the Xunhuang cooling water pipe of the present utility model.
图1-4中:1-主箱;101-防护网;102-主箱门;2-副箱;201-透气格栅;202-隔板;203-储物室;204-储物箱门;3-进气室;301-散热风机;302-滤芯;303-循环降温水管;304-风机固定板;305-进气箱门;4-出气室;401-出气箱门。In Figure 1-4: 1-main box; 101-protective net; 102-main box door; 2-auxiliary box; 201-ventilation grille; 202-partition; 203-storage room; 204-storage box door ; 3- intake chamber; 301- cooling fan; 302- filter element; 303- circulating cooling water pipe; 304- fan fixing plate; 305- intake box door; 4- air outlet chamber; 401- air box door.
具体实施方式Detailed ways
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the implementations. example. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.
请参阅图1-4,本实用新型提供一种技术方案:一种电气工程用的配电箱,包括:主箱1、副箱2、进气室3和出气室4,主箱1两侧外壁通过焊接固定连接有副箱2,副箱2内部通过焊接固定连接有隔板202,位于一侧的副箱2顶部通过隔板202分隔有进气室3,位于远离进气室3一侧的副箱2底部通过隔板202分隔有出气室4,副箱2位于进气室3和出气室4外壁处开设有透气格栅201,副箱2内部位于进气室3底部以及出气室4顶部通过隔板202分隔有储物室203,储物室203外侧通过铰链转动连接有储物箱门204,主箱1还包括:防护网101和主箱门102,主箱1位于进气室3以及出气室4中央内壁上通过卡接固定连接有防护网101,主箱1外侧通过铰链转动连接有主箱门102。1-4, the present utility model provides a technical solution: a power distribution box for electrical engineering, including: a
进气室3还包括:散热风机301、滤芯302、循环降温水管303和风机固定板304,进气室3靠近透气格栅201一侧内壁通过卡接固定连接有滤芯302,进气室3上下两侧内壁通过卡接固定连接有循环降温水管303,进气室3内壁通过螺钉固定连接有风机固定板304,风机固定板304中央通过支架固定连接有散热风机301,进气室3外侧通过铰链转动连接有进气箱门305,使用时,通过散热风扇301的转动将外界的空气抽入进气室3内部,通过滤芯302过滤以后外界的风与循环降温水管303接触进行降温,然后降温以后的风通过散热风扇301送入主箱1内部,对主箱1内部的电气元件进行降温,然后从出气室4一侧的透气格栅201排出,保证降温的同时防止外界灰尘进入主箱1内部对电气元件造成污染。The
出气室4还包括:出气箱门401,出气室4外侧通过铰链转动连接有出气箱门401,出气箱门401与出气室4接触部位通过卡接固定连接有密封条,用于出气室401的密封,防止外界灰尘进入出气室401内,循环降温水管303进水口一端通过管接头固定连接有循环水泵,循环降温水管303出水口一端通过管道连接有冷却水箱,进气箱门305与进气室3接触部位通过卡接固定连接有密封条,便于进气室3的密封,便于散热风机301吹出的风进入到主箱1内,与主箱1内的热空气进行热交换,加速主箱1内的散热。The
工作原理:在电气工程用的配电箱使用时,通过散热风扇301的转动将外界的空气抽入进气室3内部,通过滤芯302过滤以后外界的风与循环降温水管303接触进行降温,然后降温以后的风通过散热风扇301送入主箱1内部,对主箱1内部的电气元件进行降温,然后从出气室4一侧的透气格栅201排出,保证降温的同时防止外界灰尘进入主箱1内部对电气元件造成污染,通过副箱2内部的隔板,便于配电箱内的电气元件进行检修时,便于工具与备配件的存放,便于检修人员拿取,保证检修工作的顺利进行。Working principle: When the power distribution box for electrical engineering is used, the outside air is drawn into the
需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。It should be noted that, in this document, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any relationship between these entities or operations. any such actual relationship or sequence exists. Moreover, the terms "comprising", "comprising" or any other variation thereof are intended to encompass a non-exclusive inclusion such that a process, method, article or device that includes a list of elements includes not only those elements, but also includes not explicitly listed or other elements inherent to such a process, method, article or apparatus.
尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes and modifications can be made to these embodiments without departing from the principles and spirit of the present invention , alternatives and modifications, the scope of the present invention is defined by the appended claims and their equivalents.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202021034667.0U CN212210169U (en) | 2020-06-08 | 2020-06-08 | Block terminal that electrical engineering used |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202021034667.0U CN212210169U (en) | 2020-06-08 | 2020-06-08 | Block terminal that electrical engineering used |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN212210169U true CN212210169U (en) | 2020-12-22 |
Family
ID=73808148
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202021034667.0U Active CN212210169U (en) | 2020-06-08 | 2020-06-08 | Block terminal that electrical engineering used |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN212210169U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116773859A (en) * | 2023-05-29 | 2023-09-19 | 安徽上自仪调节器设备有限公司 | Electric power instrument convenient to maintenance |
-
2020
- 2020-06-08 CN CN202021034667.0U patent/CN212210169U/en active Active
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116773859A (en) * | 2023-05-29 | 2023-09-19 | 安徽上自仪调节器设备有限公司 | Electric power instrument convenient to maintenance |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN211629595U (en) | A ventilation, heat dissipation and dust removal structure for switch cabinets | |
| CN204651719U (en) | One is lowered the temperature power distribution cabinet automatically | |
| CN208142636U (en) | A kind of novel distribution cabinet | |
| CN212210169U (en) | Block terminal that electrical engineering used | |
| CN206059980U (en) | Outdoor power equipment installs room ventilation moisture-proof construction | |
| CN218732638U (en) | Multichannel redundancy power supply control device | |
| CN216355557U (en) | A sealed waterproof distribution cabinet | |
| CN217307049U (en) | A UPS power cabinet with good heat dissipation effect | |
| CN208016233U (en) | A kind of power communication heat-radiating dustproof device | |
| CN212085602U (en) | Heat radiator for high tension switchgear | |
| CN210723740U (en) | Environment-friendly energy-saving low-voltage switch cabinet | |
| CN209088354U (en) | A kind of novel capacitor box | |
| CN211530453U (en) | SF6 gas full-insulation ring main unit | |
| CN209183963U (en) | A transformer distribution cabinet | |
| CN218549122U (en) | Novel power distribution cabinet | |
| CN212968562U (en) | Low-voltage distribution switch cabinet capable of ventilating and radiating | |
| CN221812228U (en) | A transformer electrical cabinet | |
| CN111786285A (en) | An intelligent distribution transformer terminal automatic monitoring cabinet | |
| CN212784443U (en) | High-voltage switch cabinet | |
| CN212085599U (en) | JP cabinet | |
| CN216872577U (en) | Block terminal for electrical engineering | |
| CN213520964U (en) | A distribution box fixing device | |
| CN219513643U (en) | Box-type substation that heat dispersion is good | |
| CN219591971U (en) | Busbar device with stable cooling structure for power distribution room | |
| CN218124138U (en) | 10kV ring net cage with moisture resistance |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP03 | Change of name, title or address | ||
| CP03 | Change of name, title or address |
Address after: 524000 apartment 1126, Jun Zhi No.1 apartment, No.12 Airport Road, Xiashan District, Zhanjiang City, Guangdong Province Patentee after: Guangdong Xingneng Group Co.,Ltd. Address before: Room 1126, 11 / F, jun-1, No.12 Airport Road, Xiashan District, Zhanjiang City, Guangdong Province 524000 Patentee before: Guangdong Xingneng Power Investment Co.,Ltd. |
|
| PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of utility model: A distribution box for electrical engineering Effective date of registration: 20230804 Granted publication date: 20201222 Pledgee: China Everbright Bank Limited by Share Ltd. Zhanjiang branch Pledgor: Guangdong Xingneng Group Co.,Ltd. Registration number: Y2023980051092 |
|
| PC01 | Cancellation of the registration of the contract for pledge of patent right | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Granted publication date: 20201222 Pledgee: China Everbright Bank Limited by Share Ltd. Zhanjiang branch Pledgor: Guangdong Xingneng Group Co.,Ltd. Registration number: Y2023980051092 |
|
| PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of utility model: A distribution box for electrical engineering Granted publication date: 20201222 Pledgee: China Everbright Bank Limited by Share Ltd. Zhanjiang branch Pledgor: Guangdong Xingneng Group Co.,Ltd. Registration number: Y2024980041525 |
|
| PC01 | Cancellation of the registration of the contract for pledge of patent right | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Granted publication date: 20201222 Pledgee: China Everbright Bank Limited by Share Ltd. Zhanjiang branch Pledgor: Guangdong Xingneng Group Co.,Ltd. Registration number: Y2024980041525 |