CN212201302U - Multifunctional construction engineering construction support assembly - Google Patents

Multifunctional construction engineering construction support assembly Download PDF

Info

Publication number
CN212201302U
CN212201302U CN202020760801.9U CN202020760801U CN212201302U CN 212201302 U CN212201302 U CN 212201302U CN 202020760801 U CN202020760801 U CN 202020760801U CN 212201302 U CN212201302 U CN 212201302U
Authority
CN
China
Prior art keywords
fixedly connected
support
pipeline
backup pad
main part
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020760801.9U
Other languages
Chinese (zh)
Inventor
孟凡欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020760801.9U priority Critical patent/CN212201302U/en
Application granted granted Critical
Publication of CN212201302U publication Critical patent/CN212201302U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a multi-functional building engineering construction support subassembly relates to the building engineering field. This multifunctional building engineering construction support subassembly includes support subject and backup pad, and the screw has been seted up in the front of support subject, and the back fixedly connected with and the corresponding second screw rod of screw of backup pad, the front of backup pad are equipped with pipeline clamping mechanism, the back both ends fixedly connected with clamp splice of support subject, and the top threaded connection of clamp splice has first screw rod, and the bottom fixedly connected with of first screw rod supports tight piece. This multifunctional construction engineering construction support subassembly has realized when using the support main part to fix the mould, still can install the backup pad in the support main part simultaneously, fixes interim pipeline and circuit in the front of support main part through pipeline latch mechanism to make interim pipeline and circuit on the building site keep neatly orderly, pipeline latch mechanism's easy operation is convenient, and the user is labour saving and time saving when fixing interim pipeline and circuit.

Description

Multifunctional construction engineering construction support assembly
Technical Field
The utility model relates to a building engineering technical field specifically is a multi-use architecture engineering construction support subassembly.
Background
The building engineering refers to an engineering entity formed by the construction of various building buildings and their auxiliary facilities and the installation of lines, pipes and equipment matched with them, wherein the building buildings refer to the engineering which has top covers, beams, columns, walls, foundations and can form internal spaces and meet the requirements of people for production, living, study and public activities.
In the building engineering construction, need use the construction bracket subassembly convenience to support and fix the template, and current construction bracket subassembly simple structure, the function is single, when the construction, often can arrange a lot of interim pipelines and circuits, interim pipeline is convenient for water, interim circuit is convenient for constructor to carry out some electrical equipment operations, and often chaotic of these interim pipelines and circuits, the construction bracket subassembly is not convenient for arrange in order these interim pipelines and circuits, can not satisfy the demand.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model discloses a multifunctional construction engineering construction bracket component to solve the problem that proposes in the above-mentioned background art.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a multi-functional building engineering construction support subassembly, includes support subject and backup pad, the screw has been seted up in the front of support subject, the back fixedly connected with and the corresponding second screw rod of screw of backup pad, the front of backup pad is equipped with pipeline latch mechanism, the back both ends fixedly connected with clamp splice of support subject, the shape of clamp splice is horizontal "U" shape, the top threaded connection of clamp splice has first screw rod, the top fixedly connected with of first screw rod changes the handle, the bottom fixedly connected with of first screw rod supports tight piece, pipeline latch mechanism includes fixed strip and lower fixed strip, go up the fixed strip and down the activity joint between the fixed strip have the check lock lever.
Preferably, the top of the locking rod is fixedly connected with a swivel, a pin shaft is inserted in the axis of the swivel, a swivel groove corresponding to the locking rod and the swivel is formed in the top of the upper fixing strip, and two ends of the pin shaft penetrate through the side wall of the swivel groove.
Preferably, the bottom fixedly connected with end cap of check lock pole, clamping sleeve and spring have been cup jointed on the check lock pole, the middle part fixedly connected with stopper of check lock pole, clamping sleeve and spring are located between stopper and the end cap, the fluting corresponding with the check lock pole has been seted up to the fixed strip down, the draw-in groove that corresponds with the clamping sleeve has been seted up to the diapire of fixed strip down.
Preferably, the top of the spring is abutted to the clamping sleeve, the bottom of the spring is abutted to the end cap, the spring is in a compression state, and the top of the clamping sleeve is abutted to the limiting block.
Preferably, the number of the support plates is two, and the two support plates are symmetrically distributed around the middle halving part of the bracket main body.
Preferably, a handle is fixedly connected to the side wall of the clamping sleeve.
Preferably, the length of the locking rod is greater than the gap between the upper fixing strip and the lower fixing strip.
The utility model discloses a multifunctional construction engineering construction bracket component, its beneficial effect who possesses as follows:
1. this multifunctional building engineering construction support subassembly, through setting up the support main part, the clamp splice, backup pad and pipeline latch mechanism, realized when using the support main part to fix the mould, the while still can be at the last erection support board of support main part, fix the front in the support main part with interim pipeline and circuit through pipeline latch mechanism, thereby make interim pipeline and circuit on the building site keep neat orderly, pipeline latch mechanism's easy operation is convenient, the user is labour saving and time saving when fixing interim pipeline and circuit, satisfy the user demand.
2. This multifunctional building engineering construction bracket component can carry on spacingly to the chucking cover through setting up the stopper, prevents that chucking cover position from too high influence operation, through setting up the handle person of facilitating the use slip chucking cover, when the user removes the fixed of locking lever, otherwise with the operation of installation locking lever can.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is an enlarged view of a portion A of FIG. 1 according to the present invention;
FIG. 3 is a structural view of the main body of the bracket of the present invention;
fig. 4 is a connection diagram of the support plate and the locking rod of the present invention.
In the figure: 1. a stent body; 101. a screw hole; 2. a clamping block; 3. a first screw; 301. turning a handle; 302. a propping block; 4. a support plate; 401. a second screw; 402. an upper fixing strip; 403. a lower fixing strip; 4031. a card slot; 5. a locking lever; 501. rotating the ring; 502. a pin shaft; 503. a limiting block; 504. an end cap; 6. a clamping sleeve; 601. a handle; 7. a spring.
Detailed Description
The embodiment of the utility model provides a multifunctional construction bracket component, as shown in fig. 1-4, comprising a bracket main body 1 and a supporting plate 4, wherein the front of the bracket main body 1 is provided with a screw hole 101, the back of the supporting plate 4 is fixedly connected with a second screw 401 corresponding to the screw hole 101, the front of the supporting plate 4 is provided with a pipeline clamping mechanism, both ends of the back of the bracket main body 1 are fixedly connected with clamping blocks 2, the clamping blocks 2 are in a horizontal U shape, the top of the clamping blocks 2 is in threaded connection with a first screw 3, the top of the first screw 3 is fixedly connected with a rotating handle 301, the bottom of the first screw 3 is fixedly connected with a resisting block 302, the pipeline clamping mechanism comprises an upper fixing strip 402 and a lower fixing strip 403, a locking rod 5 is movably clamped between the upper fixing strip 402 and the lower fixing strip 403, and through the arrangement of the bracket main body 1, the clamping blocks 2, the supporting plate 4, realized when using support subject 1 to fix the mould, still can install backup pad 4 on support subject 1 simultaneously, fix interim pipeline and circuit in support subject 1's front through pipeline latch mechanism to make interim pipeline and circuit on the building site keep neat orderly, pipeline latch mechanism's easy operation is convenient, and the user is laborsaving in the time-saving of fixing interim pipeline and circuit, satisfies the user demand.
The top fixedly connected with swivel 501 of check lock lever 5, the axle center department of swivel 501 pegs graft there is round pin axle 502, go up the top of fixed strip 402 and offer the turn trough corresponding with check lock lever 5 and swivel 501, the lateral wall in turn trough is passed at the both ends of round pin axle 502, is convenient for check lock lever 5 to rotate on last fixed strip 402 through setting up swivel 501 and round pin axle 502.
Bottom fixedly connected with end cap 504 of check lock lever 5, clamp sleeve 6 and spring 7 have been cup jointed on the check lock lever 5, the middle part fixedly connected with stopper 503 of check lock lever 5, clamp sleeve 6 and spring 7 are located between stopper 503 and the end cap 504, lower fixed strip 403 has seted up the fluting corresponding with check lock lever 5, draw-in groove 4031 corresponding with clamp sleeve 6 has been seted up to the diapire of lower fixed strip 403, be convenient for fix check lock lever 5 on lower fixed strip 403 through setting up clamp sleeve 6 and spring 7.
The top of spring 7 offsets with chucking cover 6, and the bottom of spring 7 offsets with end cap 504, and spring 7 is in compression state, and the top of chucking cover 6 offsets with stopper 503, can carry on spacingly to chucking cover 6 through setting up stopper 503, prevents that chucking cover 6 from putting too high influence operation.
The quantity of backup pad 4 is two sets of, and two sets of backup pads 4 are about the middle halving department symmetric distribution of support main part 1, and the lateral wall fixedly connected with handle 601 of chucking cover 6 through setting up handle 601 person of facilitating the use slip chucking cover 6, when the user removes the fixed of locking lever 5, can vice versa with the operation of installation locking lever 5.
The length of the locking bar 5 is greater than the gap between the upper and lower fixing strips 402 and 403.
The working principle is as follows: when the user used, can use support main part 1 to press from both sides tightly the mould, specifically advance the mould card in "U" shape bayonet socket of clamp splice 2, rotate this moment and change 301, change 301 and drive first screw rod 3 and rotate, first screw rod 3 along screw 101 spiral shell screwing down and promote to support tight piece 302 and press from both sides tightly the mould, use a set of support main part 1 can make both ends fix two sets of moulds.
After fixing the mould, can be at the positive erection bracing board 4 of support main part 1, and then be convenient for fix interim pipeline and interim circuit, concrete operation does, can advance interim pipeline and circuit card between fixed strip 402 and lower fixed strip 403, at this moment, pulling handle 601 drives the motion of chucking cover 6, make chucking cover 6 slide on check lock lever 5 and compression spring 7, and drive check lock lever 5 and rotate, check lock lever 5 drives swivel 501 and rotates along round pin axle 502, make check lock lever 5 card advance in the fluting of fixed strip 403 down, the handle 601 of loosing this moment, spring 7 resets and upwards pushes up chucking cover 6 and moves, chucking cover 6 card advances draw-in groove 4031, realize the fixed to check lock lever 5, and then make interim pipeline and interim circuit card between last fixed strip 402 and lower fixed strip 403.
This device is through setting up support main part 1, clamp splice 2, backup pad 4 and pipeline latch mechanism, realized when using support main part 1 to fix the mould, simultaneously still can install backup pad 4 on support main part 1, fix interim pipeline and circuit in support main part 1's front through pipeline latch mechanism, thereby make interim pipeline and circuit on the building site keep neatly orderly, pipeline latch mechanism's easy operation is convenient, the user is laborsaving in fixed interim pipeline and circuit time saving, satisfy the user demand.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (7)

1. The utility model provides a multi-functional building engineering construction support subassembly, includes support main part (1) and backup pad (4), its characterized in that: screw (101) have been seted up in the front of support main part (1), the back fixedly connected with and the corresponding second screw rod (401) of screw (101) of backup pad (4), the front of backup pad (4) is equipped with pipeline clamping mechanism, the back both ends fixedly connected with clamp splice (2) of support main part (1), the shape of clamp splice (2) is horizontal "U" shape, the top threaded connection of clamp splice (2) has first screw rod (3), the top fixedly connected with of first screw rod (3) changes (301), the bottom fixedly connected with of first screw rod (3) supports tight piece (302), pipeline clamping mechanism includes fixed strip (402) and lower fixed strip (403), it has check lock lever (5) to go up the activity joint between fixed strip (402) and lower fixed strip (403).
2. The multifunctional construction work support assembly according to claim 1, wherein: the top of the locking rod (5) is fixedly connected with a rotating ring (501), a pin shaft (502) is inserted in the axis of the rotating ring (501), a rotating groove corresponding to the locking rod (5) and the rotating ring (501) is formed in the top of the upper fixing strip (402), and two ends of the pin shaft (502) penetrate through the side wall of the rotating groove.
3. The multifunctional construction work support assembly according to claim 1, wherein: the bottom fixedly connected with end cap (504) of check lock lever (5), clamp sleeve (6) and spring (7) have been cup jointed on check lock lever (5), middle part fixedly connected with stopper (503) of check lock lever (5), clamp sleeve (6) and spring (7) are located between stopper (503) and end cap (504), the corresponding fluting with check lock lever (5) has been seted up down in fixed strip (403), draw-in groove (4031) corresponding with clamp sleeve (6) has been seted up to the diapire of fixed strip (403) down.
4. The multifunctional construction work support assembly according to claim 3, wherein: the top of the spring (7) is abutted to the clamping sleeve (6), the bottom of the spring (7) is abutted to the end cap (504), the spring (7) is in a compressed state, and the top of the clamping sleeve (6) is abutted to the limiting block (503).
5. The multifunctional construction work support assembly according to claim 1, wherein: the number of the support plates (4) is two, and the two support plates (4) are symmetrically distributed at the middle bisector of the support main body (1).
6. The multifunctional construction work support assembly according to claim 3, wherein: the side wall of the clamping sleeve (6) is fixedly connected with a handle (601).
7. The multifunctional construction work support assembly according to claim 1, wherein: the length of the locking rod (5) is larger than the gap between the upper fixing strip (402) and the lower fixing strip (403).
CN202020760801.9U 2020-05-11 2020-05-11 Multifunctional construction engineering construction support assembly Expired - Fee Related CN212201302U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020760801.9U CN212201302U (en) 2020-05-11 2020-05-11 Multifunctional construction engineering construction support assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020760801.9U CN212201302U (en) 2020-05-11 2020-05-11 Multifunctional construction engineering construction support assembly

Publications (1)

Publication Number Publication Date
CN212201302U true CN212201302U (en) 2020-12-22

Family

ID=73813949

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020760801.9U Expired - Fee Related CN212201302U (en) 2020-05-11 2020-05-11 Multifunctional construction engineering construction support assembly

Country Status (1)

Country Link
CN (1) CN212201302U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114808681A (en) * 2022-05-17 2022-07-29 中铁三局集团第二工程有限公司 Construction method of bridge buried drain pipe

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114808681A (en) * 2022-05-17 2022-07-29 中铁三局集团第二工程有限公司 Construction method of bridge buried drain pipe

Similar Documents

Publication Publication Date Title
CN211114845U (en) Steel structure support frame for building engineering
CN212201302U (en) Multifunctional construction engineering construction support assembly
CN111043401A (en) Improved water conservancy pipeline supporting and connecting structure for water conservancy project
CN108756073A (en) A kind of reinforcing bar Quick connection sleeve cylinder of angle adjustable
CN212053755U (en) Template anchor clamps of building engineering construction usefulness
CN108756070A (en) A method of it improving building and builds efficiency
CN212802644U (en) Building construction wall strutting arrangement
CN217631741U (en) Protection enclosure that construction used
CN213268934U (en) Be used for interior support of pre-buried electronic box of shear force wall
CN212689400U (en) Roof daylighting panel based on architectural design
CN209942217U (en) Reinforced template for constructional engineering
CN210121829U (en) Novel wall face inslot automatic installation pipe card equipment of building decoration construction
CN210896851U (en) Single-phase transformer with square connecting frame
CN210968536U (en) Fixed clamping structure for municipal building
CN217232745U (en) Connecting and locking device for building template
CN208363603U (en) A kind of column mould clamping device
CN220080113U (en) Waterproof device
CN218242798U (en) Cable erecting device for building construction
CN214739940U (en) Building engineering template fixing device
CN215907427U (en) Connecting and locking device for building template
CN216312659U (en) Porous metal waterproof joint
CN217054349U (en) Concrete forming template convenient to build
CN216921326U (en) Building engineering template fixing device
CN218103049U (en) Light photovoltaic support that stability is strong
CN219138375U (en) Novel K board reinforcement bearing structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201222

Termination date: 20210511

CF01 Termination of patent right due to non-payment of annual fee