CN212154306U CN202020489780.1U CN202020489780U CN212154306U CN 212154306 U CN212154306 U CN 212154306U CN 202020489780 U CN202020489780 U CN 202020489780U CN 212154306 U CN212154306 U CN 212154306U
Authority
CN
China
Prior art keywords
factory building
workshop
groove
fixedly connected
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020489780.1U
Other languages
Chinese (zh)
Inventor
侯显波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhaotong Asia Pacific Advertising Co ltd
Original Assignee
Zhaotong Asia Pacific Advertising Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhaotong Asia Pacific Advertising Co ltd filed Critical Zhaotong Asia Pacific Advertising Co ltd
Priority to CN202020489780.1U priority Critical patent/CN212154306U/en
Application granted granted Critical
Publication of CN212154306U publication Critical patent/CN212154306U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a mobilizable steel construction factory building, including first factory building and second factory building, second factory building one end is in first factory building inboardly, first factory building all is provided with the slider with second factory building bottom both sides, the equal fixedly connected with stopper in first factory building and second factory building bottom both sides, stopper bottom fixedly connected with stop collar, the spacing groove has been seted up on stop collar bottom surface, the spacing inslot side is provided with the gyro wheel, gyro wheel one end is in stop collar outside bottom, first draw-in groove has been seted up on gyro wheel outside surface, the gyro wheel bottom is in the slider top, just the slider top is in first draw-in groove inboard, and its technical scheme main points are: through having designed this device, build simple to operate, the manipulation is nimble, and is safe in utilization, can in time follow-up, makes things convenient for the extension in machining space, and the material resources of using manpower sparingly for the progress, reduce cost improves production efficiency.

Description

Mobilizable steel construction factory building
Technical Field
The utility model belongs to steel construction factory building field, concretely relates to mobilizable steel construction factory building.
Background
The steel structure factory building mainly means that main bearing components are made of steel. Including the steel post, the girder steel, steel construction basis, steel roof truss (certainly the span of factory building is bigger, all is steel construction roof truss basically now), the steel roof, the wall of noticing the steel construction also can adopt the brick wall to maintain. As the steel yield of China is increased, steel structure plants are mostly adopted, and particularly, the steel structure plants can be divided into light steel structure plants and heavy steel structure plants. Industrial and civil building facilities built by steel are called steel structures, the existing steel structure factory building is fixedly installed on the ground and cannot be moved, when the machining space needs to be enlarged, only near outdoor machining can be performed sometimes, the working condition is not good, and the machining quality of workpieces is influenced.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a mobilizable steel construction factory building to it is subaerial that fixed mounting is fixed mounting to propose current steel construction factory building in solving above-mentioned background art, can not remove, when needs enlarge the processing space, can only be near open-air processing sometimes, and the operating mode is not good, influences work piece processingquality.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a mobilizable steel construction factory building, includes first factory building and second factory building, second factory building one end is in first factory building inboard, first factory building and second factory building bottom both sides all are provided with the slider, the equal fixedly connected with stopper in first factory building and second factory building bottom both sides, stopper bottom fixedly connected with stop collar, the spacing groove has been seted up on stop collar bottom surface, the spacing inslot side is provided with the gyro wheel, gyro wheel one end is in stop collar outside bottom, first draw-in groove has been seted up on gyro wheel outside surface, the gyro wheel bottom is in the slider top, just the slider top is in first draw-in groove inboard.
Preferably, the outside both ends of first factory building and the inboard both ends of second factory building all are provided with the bull stick, the fixed block has all been cup jointed at the bull stick both ends, the fixed block is fixed connection with first factory building, second factory building, the bull stick outside is provided with the canvas, canvas one end is provided with the fixture block, the second draw-in groove has been seted up to fixture block top surface one side, fixture block bottom fixedly connected with stay cord.
Preferably, the outside both ends of first factory building and the equal fixedly connected with connecting block in the inboard both ends of second factory building, the spread groove has been seted up on connecting block one end surface, the connecting block top is provided with the bolt, bolt one end through connection inner wall play trip spread groove is inboard, the spout has been seted up in the outside that the bolt is in connecting block inner wall.
Preferably, a rotating shaft is arranged at the joint of the roller and the limiting groove, and the roller is rotatably connected with the limiting sleeve through the rotating shaft.
Preferably, the surfaces of two ends of the rotating rod are provided with hairsprings, one end of each hairspring is fixedly connected with the rotating rod, and the other end of each hairspring is fixedly connected with the fixed block.
Preferably, the length of the first factory building is two thirds of the length of the second factory building, and the first factory building is in sliding connection with the second factory building.
Preferably, the bolt is of a cylindrical structure, and the bolt is in sliding connection with the sliding groove.
Compared with the prior art, the beneficial effects of the utility model are that:
(1) through having designed this device, build simple to operate, the manipulation is nimble, and is safe in utilization, can in time follow-up, makes things convenient for the extension in machining space, and the material resources of using manpower sparingly for the progress, reduce cost improves production efficiency.
(2) Through having designed the canvas, when raining or sun are too big, can expand and shelter from, can withdraw when not needing, through having designed the hairspring, the canvas can be withdrawed easy operation automatically.
Drawings
Fig. 1 is one of the schematic structural diagrams of the present invention;
FIG. 2 is the front view structure diagram of the plant
FIG. 3 is a schematic view of the pulley structure of the present invention;
fig. 4 is an enlarged schematic view of a portion a of fig. 2 according to the present invention;
fig. 5 is an enlarged schematic view of the structure at B in fig. 2 according to the present invention.
Description of the reference numerals
1. A first plant; 2. a second plant; 3. a limiting block; 4. a slider; 5. pulling a rope; 6. a limiting sleeve; 7. a limiting groove; 8. a roller; 9. a first card slot; 10. a fixed block; 11. a rotating rod; 12. canvas; 13. a clamping block; 14. a second card slot; 15. connecting blocks; 16. connecting grooves; 17. a bolt; 18. a chute.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-5, the present invention provides a technical solution, wherein the technical solution is as follows:
the utility model provides a mobilizable steel construction factory building, including first factory building 1 and second factory building 2, 2 one ends of second factory building are in 1 inboards of first factory building, 1 and 2 bottom both sides of second factory building all are provided with slider 4 of first factory building, 1 and 2 bottom both sides of second factory building equal fixedly connected with stopper 3 of first factory building, 3 bottom fixedly connected with stop collar 6 of stopper, spacing groove 7 has been seted up on 6 bottom surfaces of stop collar, 7 inboards of spacing groove are provided with gyro wheel 8, 8 one ends of gyro wheel are in 6 outside bottoms of stop collar, first draw-in groove 9 has been seted up on 8 outside surfaces of gyro wheel, 8 bottoms of gyro wheel are in 4 tops of slider, and 4 tops of slider are in first draw-in.
In order to facilitate the installation of canvas 12, in this embodiment, it is preferred, the outside both ends of first factory building 1 all are provided with bull stick 11 with the inboard both ends of second factory building 2, fixed block 10 has all been cup jointed at bull stick 11 both ends, fixed block 10 is fixed connection with first factory building 1, second factory building 2, the 11 outsides of bull stick are provided with canvas 12, canvas 12 one end is provided with fixture block 13, second draw-in groove 14 has been seted up to fixture block 13 top surface one side, fixture block 13 bottom fixedly connected with stay cord 5.
In order to fix the canvas 12 that will expand for the convenience, in this embodiment, preferably, the equal fixedly connected with connecting block 15 in the outside both ends of first factory building 1 and the inboard both ends of second factory building 2, connecting block 15 one end surface has seted up spread groove 16, and connecting block 15 top is provided with bolt 17, and bolt 17 one end runs through connecting block 15 inner wall and goes out the trip spread groove 16 inboard, and bolt 17 is in the outside of connecting block 15 inner wall and has seted up spout 18.
In order to facilitate the rotation of the roller 8, in this embodiment, preferably, a rotating shaft is disposed at a joint of the roller 8 and the limiting groove 7, and the roller 8 is rotatably connected with the limiting sleeve 6 through the rotating shaft.
In order to facilitate the automatic retraction of the canvas 12, in this embodiment, preferably, both end surfaces of the rotating rod 11 are provided with a hairspring, one end of the hairspring is fixedly connected with the rotating rod 11, and the other end of the hairspring is fixedly connected with the fixed block 10.
In order to facilitate the first factory building 1 and the second factory building 2 to slide synchronously, in this embodiment, preferably, the length of the first factory building 1 is two thirds of the length of the second factory building 2, and the first factory building 1 and the second factory building 2 are connected in a sliding manner.
In order to facilitate the installation of the latch 17, in this embodiment, it is preferable that the latch 17 has a cylindrical structure, and the latch 17 is slidably connected to the sliding groove 18.
The utility model discloses a theory of operation and use flow:
after the device is installed, the first factory building 1 and the second factory building 2 are made of materials according to the width and the height of the first factory building 1 and the second factory building 2, if the span is very large, the requirement is very high, H steel and I steel are used as an upright post and a steel beam, and a square tube combined steel upright post or a welded tube upright post can be combined with a steel tube frame beam. If the small color steel shed with the span of less than twelve meters can be directly made of round pipes and square pipes, the sliding block 4 is needed to be made into an embedded foundation according to the actual conditions of a construction site, most of roofs are made of square pipe sandalwood strips or C-shaped steel purlins and color steel tiles, the first factory building 1 or the second factory building 2 is moved only by pushing the first factory building 1 and the second factory building 2 to move along the direction of the sliding block 4 through the roller 8, the sliding block 4 needs to be embedded in advance, concrete is poured, when raining or needing sun shading, the pull rope 5 is pulled to drive the clamping block 13 to move downwards, the canvas 12 wound on the surface of the rotating rod 11 is unfolded until the clamping block 13 is positioned at one side of the connecting groove 16, the clamping block 13 is inserted into the inner side of the connecting groove 16, the second clamping groove 14 is positioned at the bottom end of the sliding groove 18, the bolt 17 is inserted into the inner side of the, safe in utilization can in time follow-up, makes things convenient for the extension of processing space, and the material resources of using manpower sparingly for the progress, reduce cost improves production efficiency. Through having designed canvas 12, when raining or sun are too big, can expand and shelter from, can withdraw when not needing, through having designed the hairspring, canvas 12 can withdraw easy operation automatically.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. A movable steel structure factory building comprises a first factory building (1) and a second factory building (2), it is characterized in that one end of the second workshop (2) is positioned at the inner side of the first workshop (1), the two sides of the bottom ends of the first workshop (1) and the second workshop (2) are respectively provided with a sliding block (4), the two sides of the bottom ends of the first workshop (1) and the second workshop (2) are fixedly connected with limit blocks (3), the bottom end of the limiting block (3) is fixedly connected with a limiting sleeve (6), the surface of the bottom end of the limiting sleeve (6) is provided with a limiting groove (7), the inner side of the limiting groove (7) is provided with a roller (8), one end of the roller (8) is positioned at the bottom end of the outer side of the limiting sleeve (6), first draw-in groove (9) have been seted up to gyro wheel (8) outside surface, gyro wheel (8) bottom is in slider (4) top, just slider (4) top is in first draw-in groove (9) inboard.
2. The movable steel structure workshop according to claim 1, wherein rotating rods (11) are arranged at two ends of the outer side of the first workshop (1) and two ends of the inner side of the second workshop (2), fixed blocks (10) are sleeved at two ends of each rotating rod (11), the fixed blocks (10) are fixedly connected with the first workshop (1) and the second workshop (2), canvas (12) are arranged on the outer side of each rotating rod (11), a clamping block (13) is arranged at one end of each canvas (12), a second clamping groove (14) is formed in one side of the top end surface of each clamping block (13), and a pull rope (5) is fixedly connected to the bottom end of each clamping block (13).
3. The movable steel structure workshop according to claim 2, wherein the outer two ends of the first workshop (1) and the inner two ends of the second workshop (2) are fixedly connected with connecting blocks (15), a connecting groove (16) is formed in the surface of one end of each connecting block (15), a bolt (17) is arranged at the top end of each connecting block (15), one end of each bolt (17) penetrates through the inner wall of each connecting block (15) to move out of the connecting groove (16) and is located at the outer side of the inner wall of each connecting block (15) to form a sliding groove (18).
4. The movable steel structure factory building according to claim 1, wherein a rotating shaft is arranged at the joint of the roller (8) and the limiting groove (7), and the roller (8) is rotatably connected with the limiting sleeve (6) through the rotating shaft.
5. The movable steel structure factory building according to claim 2, wherein the surfaces of two ends of the rotating rod (11) are provided with hairsprings, one end of each hairspring is fixedly connected with the rotating rod (11), and the other end of each hairspring is fixedly connected with the fixed block (10).
6. The movable steel structure factory building according to claim 1, wherein the length of the first factory building (1) is two thirds of the length of the second factory building (2), and the first factory building (1) is connected with the second factory building (2) in a sliding manner.
7. The movable steel structure factory building according to claim 3, wherein the plug (17) is of a cylindrical structure, and the plug (17) is in sliding connection with the sliding groove (18).
CN202020489780.1U 2020-04-07 2020-04-07 Mobilizable steel construction factory building Expired - Fee Related CN212154306U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020489780.1U CN212154306U (en) 2020-04-07 2020-04-07 Mobilizable steel construction factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020489780.1U CN212154306U (en) 2020-04-07 2020-04-07 Mobilizable steel construction factory building

Publications (1)

Publication Number Publication Date
CN212154306U true CN212154306U (en) 2020-12-15

Family

ID=73725188

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020489780.1U Expired - Fee Related CN212154306U (en) 2020-04-07 2020-04-07 Mobilizable steel construction factory building

Country Status (1)

Country Link
CN (1) CN212154306U (en)

Similar Documents

Publication Publication Date Title
CN210500761U (en) Remove telescopic precast beam and spray health preserving big-arch shelter
CN212154306U (en) Mobilizable steel construction factory building
CN109736569B (en) Truss type template support frame and template support structure
CN205755991U (en) The double string beam framework of glasshouse big shack of assembled
CN205935580U (en) Novel large tracts of land mechanical float
CN201850711U (en) Rainproof sun shelter
CN218881810U (en) Dust curtain net bearing device around construction foundation pit
CN111648473A (en) High-strength steel structure
CN217759861U (en) Adjustable platform for pipeline construction under platform beam
CN211200009U (en) Adjustable road side form accurate supporting device
CN213142727U (en) Adjustable bracing structure for building engineering design
CN104060813A (en) Construction device and method for large-span steel girder frame connection platform
CN105993705A (en) Assembled double-chord beam greenhouse skeleton
CN207761194U (en) Rain collector on garden layout bamboo pavilion
CN206205452U (en) A kind of telescopic bulk concrete pours regularization operating platform
CN220954763U (en) Telescopic steel bar machining shed
CN211547415U (en) Simple semi-automatic folding construction hanging basket
CN204266663U (en) A kind of area of heavy rainfull building uses Multifunctional rain-proof canopy
CN208918345U (en) A kind of mobile awning of beam making field construction
CN218581181U (en) Movable formwork for large-channel construction
CN211229662U (en) Weather enclosure is used in cement concrete road surface construction
CN217270248U (en) Safe stoping supporting mechanism for mine working face
CN221346764U (en) Sunshade system of glass daylighting roof
CN220979018U (en) Room type tent convenient to build and good in stability
CN216446492U (en) Electric telescopic sunshade and rainproof shed for hanging basket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201215