CN212105936U - Tunnel construction is with spraying dust fall equipment - Google Patents

Tunnel construction is with spraying dust fall equipment Download PDF

Info

Publication number
CN212105936U
CN212105936U CN202020127010.2U CN202020127010U CN212105936U CN 212105936 U CN212105936 U CN 212105936U CN 202020127010 U CN202020127010 U CN 202020127010U CN 212105936 U CN212105936 U CN 212105936U
Authority
CN
China
Prior art keywords
fixedly connected
water tank
block
tunnel construction
arc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020127010.2U
Other languages
Chinese (zh)
Inventor
唐艳梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Tengyu tunnel machinery Co.,Ltd.
Original Assignee
Quanzhou Lianzheng Information Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Quanzhou Lianzheng Information Technology Co ltd filed Critical Quanzhou Lianzheng Information Technology Co ltd
Priority to CN202020127010.2U priority Critical patent/CN212105936U/en
Application granted granted Critical
Publication of CN212105936U publication Critical patent/CN212105936U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Fire-Extinguishing By Fire Departments, And Fire-Extinguishing Equipment And Control Thereof (AREA)

Abstract

The utility model relates to a tunnel construction technical field just discloses a tunnel construction is with spraying dust fall equipment, including main part, rotary device and fixing device, the top fixedly connected with water tank of main part, the top fixedly connected with rotary device of water tank, the bottom fixedly connected with fixing device of main part, one side fixedly connected with water pump of water tank. This tunnel construction is with spraying dust fall equipment, setting through rotary device, the driving gear rotates and drives drive gear and rotates when the initiative motor of start driving gear one side, the sloping block drives the sliding block and slides in arc hole one side, then the arc piece rotates, then the left circulation storehouse of support column drives the atomising head and rotates, water is taken out from the water tank is inside when starting the water pump, and transmit the inside in circulation storehouse through the water pipe, at last from the atomising head blowout, the atomising head rotates along with the rotation of arc piece, when the convenient dust fall of swing spraying, the spray range has been enlarged, the dust fall is effectual.

Description

Tunnel construction is with spraying dust fall equipment
Technical Field
The utility model relates to a tunnel construction technical field specifically is a tunnel construction is with spraying dust fall equipment.
Background
Tunnel construction is a new engineering construction method which is provided by austrian from the viewpoint of rock mechanics in the long-term tunnel construction practice, is formed by adopting a system formed by a spray anchor technology, monitoring measurement and the like and a rock mechanics theory, and generally causes dust flying in the tunnel construction field during the construction process, thereby causing serious environmental pollution.
Adopt artifical watering at present, waste time and energy, dust suppression effect is poor, intensity of labour is big, sprays the water source and does not pass through the atomizing, directly influences the dust suppression effect, and the scope of spraying is little, and the dust suppression effect is poor, when the whole convenient removal of device, does not have fixed device, easily slides after removing, the influence sprays and the use of dust fall. Therefore, we propose a spraying dust-settling device for tunnel construction to solve the above problems.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art, the utility model provides a tunnel construction is with spraying dust fall equipment possesses the convenience and sprays, sprays that the scope is big, convenient removal and advantage such as fixed, has solved inconvenient spraying, has sprayed that the scope is little, inconvenient fixed problem.
The utility model provides a technical scheme that its technical problem adopted is: the utility model provides a tunnel construction is with spraying dust fall equipment, includes main part, rotary device and fixing device, the top fixedly connected with water tank of main part, the top fixedly connected with rotary device of water tank, the bottom fixedly connected with fixing device of main part, one side fixedly connected with water pump of water tank, one side fixedly connected with water pipe of water tank is kept away from to the water pump.
The rotating device comprises a supporting column, an arc-shaped block is movably connected to the left side of the supporting column, an arc-shaped hole is formed in the arc-shaped block, a ring is fixedly connected to the top of the water tank, a transmission gear is meshed to one side of the ring, a driving gear is meshed to one side of the transmission gear, an inclined block is fixedly connected to the top of the driving gear, a sliding block is fixedly connected to the top of the inclined block, the arc-shaped block is far away from a connecting frame fixedly connected to one side of the supporting column, a flow bin is movably connected to the top of the connecting frame, a spray head is fixedly connected to the left side of the flow bin, and a hydraulic cylinder is fixedly connected.
The fixing device comprises a rotating motor, a threaded rod is movably connected to the left side of the rotating motor, a moving block is connected to the outer surface of the threaded rod in a threaded mode, a moving rod is movably connected to one side of the moving block, a weighting block is movably connected to one side, away from the moving block, of the moving rod, a moving rod is movably connected to one side of the weighting block, and a roller is fixedly connected to the bottom of the main body.
Further, the top of water tank just is located the right side of ring and the bottom fixed connection of support column, one side fixedly connected with isolating pad of main part, the bottom fixed connection of isolating pad and rotating electrical machines is passed through to one side of main part.
Furthermore, the top of pneumatic cylinder and the bottom fixed connection in circulation storehouse, the one side that the water pump was kept away from to the water pipe is with the top fixed connection in circulation storehouse.
Furthermore, the size of sliding block and the size looks adaptation in arc hole, and one side and the arc hole sliding connection of sliding block.
Furthermore, the bottom of the driving gear is movably connected with a driving motor, and the bottom of the driving motor is fixedly connected with the top of the water tank.
Furthermore, a threaded hole matched with the threaded rod is formed in the moving block, one side, far away from the rotating motor, of the threaded rod is movably connected with the main body, and one side, far away from the weighting block, of the moving rod is movably connected with the main body.
The utility model has the advantages that:
1. this tunnel construction is with spraying dust fall equipment, setting through rotary device, the driving gear rotates and drives drive gear and rotate when the initiative motor of start driving gear one side, when the driving gear rotates, the sloping block drives the sliding block and slides in arc hole one side, then the arc piece is driven and is rotated in support column one side, then the left circulation storehouse of support column drives the atomising head and rotates, water is taken out from the water tank is inside when starting the water pump, and transmit the inside in circulation storehouse through the water pipe, at last from the atomising head blowout, the atomising head rotates along with the rotation of arc piece, the convenient dust fall of swing spraying, the circulation storehouse removes when starting the pneumatic cylinder, then the atomising head removes, the spray range has been enlarged, the dust fall effect is better, the practicality of device has been improved.
2. This tunnel construction is with spraying dust fall equipment, through fixing device's setting, after dust fall equipment main part passes through the gyro wheel removal, start rotating electrical machines then the threaded rod rotates thereupon, removes with the movable block thereupon, then the movable rod removes thereupon to the piece removal is aggravated in the drive, and the weight piece can remove thereupon and ground contact, realizes fixing device to equipment main part's fixed, prevents its slip, has guaranteed the holistic stability of dust fall equipment, has the practicality.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below.
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is an enlarged view of the structure A of FIG. 1 according to the present invention;
FIG. 3 is a schematic view of the structure of the rotating device of the present invention;
FIG. 4 is a schematic view of the fixing device of the present invention;
fig. 5 is a side view of the driving gear structure of the present invention.
Description of reference numerals: 1. a main body; 2. a water tank; 3. a rotating device; 301. a support pillar; 302. an arc-shaped block; 303. an arc-shaped hole; 304. a circular ring; 305. a transmission gear; 306. a driving gear; 307. a tapered block; 308. a slider; 309. a connecting frame; 310. circulating the bin; 311. a spray head; 312. a hydraulic cylinder; 4. a fixing device; 401. a rotating electric machine; 402. a threaded rod; 403. a moving block; 404. a travel bar; 405. a weighting block; 406. a movable rod; 407. a roller; 5. a water pump; 6. a water pipe.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
Referring to fig. 1 to 5, a spraying dust-settling device for tunnel construction includes a main body 1, a rotating device 3 and a fixing device 4, a water tank 2 is fixedly connected to the top of the main body 1 for storing a large amount of spraying water, the rotating device 3 is fixedly connected to the top of the water tank 2, the fixing device 4 is fixedly connected to the bottom of the main body 1 for fixing the main body of the device and preventing the main body from sliding, a water pump 5 is fixedly connected to one side of the water tank 2 for pumping out water in the water tank 2, and a water pipe 6 is fixedly connected to one side of the water pump 5 away from the water tank 2 for effectively circulating water in the water tank 2 to an atomizing head 311.
Rotating device 3 includes support column 301, the left side swing joint of support column 301 has arc piece 302, be for the rotation of convenient arc piece 302, arc hole 303 has been seted up to the inside of arc piece 302, be for the slip of convenient sliding block 308, the top fixedly connected with ring 304 of water tank 2, one side meshing of ring 304 has drive gear 305, one side meshing of drive gear 305 has driving gear 306, it conveniently drives oblique piece 307 and rotates when rotating for it, the top fixedly connected with oblique piece 307 of driving gear 306, the top fixedly connected with sliding block 308 of oblique piece 307, one side fixedly connected with connecting frame 309 of support column 301 is kept away from to arc piece 302, the top swing joint of connecting frame 309 has circulation storehouse 310, the left side fixedly connected with atomising head 311 of circulation storehouse 310, the inner wall fixedly connected with pneumatic cylinder 312 of connecting frame 309.
Fixing device 4 includes rotating electrical machines 401, rotating electrical machines 401's left side swing joint has threaded rod 402, be for the rotation of convenient threaded rod 402, threaded rod 402's surface threaded connection has movable block 403, be for the removal of convenient movable block 403, one side swing joint of movable block 403 has carriage release lever 404, one side swing joint that movable block 403 was kept away from to carriage release lever 404 has weight 405, be for the increase stability when conveniently contacting with the ground, prevent to slide, one side swing joint of weight 405 has movable rod 406, the bottom fixedly connected with gyro wheel 407 of main part 1, be for the removal of convenient equipment.
The top of the water tank 2 is fixedly connected with the bottom of the support column 301 at the right side of the circular ring 304, in order to support and fix the support column 301, one side of the main body 1 is fixedly connected with an isolation pad, one side of the main body 1 is fixedly connected with the bottom of the rotating motor 401 through the isolation pad, in order to stably place the rotating motor 401, the top of the hydraulic cylinder 312 is fixedly connected with the bottom of the circulating bin 310, in order to drive the circulating bin 310 and the atomizing head 311 to move when the hydraulic cylinder 312 is started, the atomizing range can be enlarged, one side of the water pipe 6 far away from the water pump 5 is fixedly connected with the top of the circulating bin 310, the size of the sliding block 308 is matched with the size of the arc-shaped hole 303, one side of the sliding block 308 is slidably connected with the arc-shaped hole 303, the bottom of the driving gear 306 is movably connected with a driving motor, the bottom of the driving motor is fixedly connected with the, the side of the threaded rod 402 far away from the rotating motor 401 is movably connected with the main body 1, and the side of the movable rod 406 far away from the weight 405 is movably connected with the main body 1.
When the dust-settling device is used, through the arrangement of the rotating device 3, when a driving motor on one side of the driving gear 306 is started, the driving gear 306 rotates and drives the transmission gear 305 to rotate, when the driving gear 306 rotates, the inclined block 307 drives the sliding block 308 to slide on one side of the arc-shaped hole 303, the arc-shaped block 302 is driven to rotate on one side of the supporting column 301, the circulating bin 310 on the left side of the supporting column 301 drives the spray head 311 to rotate, when the water pump 5 is started, water is pumped out from the inside of the water tank 2 and is transmitted to the inside of the circulating bin 310 through the water pipe 6, and finally the water is sprayed out of the spray head 311, the spray head 311 rotates along with the rotation of the arc-shaped block 302, the swinging spraying is convenient for dust settling, when the hydraulic cylinder 312 is started, the circulating bin 310 moves, the spray head 311 moves, the spraying range is expanded, the dust-settling, starting rotating electrical machines 401 then threaded rod 402 rotates thereupon, moves about with movable block 403 thereupon, and movable rod 404 moves thereupon to drive weight 405 and remove, weight 405 can move thereupon and contact with ground, realize fixing device 4 fixed to the equipment main part, prevent it from sliding, guaranteed the holistic stability of dust fall equipment, have the practicality.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (6)

1. The utility model provides a tunnel construction is with spraying dust fall equipment, includes main part (1), rotary device (3) and fixing device (4), its characterized in that: the water tank (2) is fixedly connected to the top of the main body (1), the rotating device (3) is fixedly connected to the top of the water tank (2), the fixing device (4) is fixedly connected to the bottom of the main body (1), the water pump (5) is fixedly connected to one side of the water tank (2), and the water pipe (6) is fixedly connected to one side, far away from the water tank (2), of the water pump (5);
the rotating device (3) comprises a supporting column (301), the left side of the supporting column (301) is movably connected with an arc-shaped block (302), an arc-shaped hole (303) is formed in the arc-shaped block (302), a circular ring (304) is fixedly connected to the top of the water tank (2), one side of the circular ring (304) is engaged with a transmission gear (305), one side of the transmission gear (305) is engaged with a driving gear (306), the top of the driving gear (306) is fixedly connected with an inclined block (307), the top of the inclined block (307) is fixedly connected with a sliding block (308), one side of the arc-shaped block (302) far away from the supporting column (301) is fixedly connected with a connecting frame (309), the top of the connecting frame (309) is movably connected with a circulation bin (310), the left side of the circulation bin (310) is fixedly connected with a spray head (311), and the inner wall of the connecting frame (309) is fixedly connected with a hydraulic cylinder (312);
the fixing device (4) comprises a rotating motor (401), a threaded rod (402) is movably connected to the left side of the rotating motor (401), a moving block (403) is connected to the outer surface of the threaded rod (402) in a threaded manner, a moving rod (404) is movably connected to one side of the moving block (403), a weighting block (405) is movably connected to one side, away from the moving block (403), of the moving rod (404), a moving rod (406) is movably connected to one side of the weighting block (405), and a roller (407) is fixedly connected to the bottom of the main body (1).
2. The spraying dust-settling equipment for tunnel construction according to claim 1, characterized in that: the top of water tank (2) just is located the right side of ring (304) and the bottom fixed connection of support column (301), one side fixedly connected with isolating pad of main part (1), the bottom fixed connection of isolating pad and rotating electrical machines (401) is passed through to one side of main part (1).
3. The spraying dust-settling equipment for tunnel construction according to claim 1, characterized in that: the top of the hydraulic cylinder (312) is fixedly connected with the bottom of the circulation bin (310), and one side, far away from the water pump (5), of the water pipe (6) is fixedly connected with the top of the circulation bin (310).
4. The spraying dust-settling equipment for tunnel construction according to claim 1, characterized in that: the size of sliding block (308) and the size looks adaptation of arc hole (303), and one side and arc hole (303) sliding connection of sliding block (308).
5. The spraying dust-settling equipment for tunnel construction according to claim 1, characterized in that: the bottom of the driving gear (306) is movably connected with a driving motor, and the bottom of the driving motor is fixedly connected with the top of the water tank (2).
6. The spraying dust-settling equipment for tunnel construction according to claim 1, characterized in that: a threaded hole matched with the threaded rod (402) is formed in the moving block (403), one side, far away from the rotating motor (401), of the threaded rod (402) is movably connected with the main body (1), and one side, far away from the weighting block (405), of the moving rod (406) is movably connected with the main body (1).
CN202020127010.2U 2020-01-20 2020-01-20 Tunnel construction is with spraying dust fall equipment Active CN212105936U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020127010.2U CN212105936U (en) 2020-01-20 2020-01-20 Tunnel construction is with spraying dust fall equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020127010.2U CN212105936U (en) 2020-01-20 2020-01-20 Tunnel construction is with spraying dust fall equipment

Publications (1)

Publication Number Publication Date
CN212105936U true CN212105936U (en) 2020-12-08

Family

ID=73627306

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020127010.2U Active CN212105936U (en) 2020-01-20 2020-01-20 Tunnel construction is with spraying dust fall equipment

Country Status (1)

Country Link
CN (1) CN212105936U (en)

Similar Documents

Publication Publication Date Title
CN107956282B (en) Single-roller-brushing reciprocating type automatic wall surface smearing and painting device
CN204381023U (en) A kind of pipe endoscopic cleaning cart
CN212262725U (en) High-pressure water mist spraying device of dust suppression equipment
CN212105936U (en) Tunnel construction is with spraying dust fall equipment
CN210749044U (en) Building glass top cleaning trolley
CN205113278U (en) Remove automatic washhing and dry integrative car washer
CN211635755U (en) Raise dust cleaning device for construction
CN211707630U (en) Pipeline cleaning device for hydraulic engineering
CN211898112U (en) Solar energy dust fall spraying vehicle for municipal works
CN110681523B (en) Derusting and painting device for naval vessels
CN218077088U (en) Dust fall machine convenient to reciprocal rotation water spray
CN216948626U (en) Self-propelled pumping equipment and self-propelled sprinkling irrigation equipment
CN214552098U (en) Dust collector that foundation construction used
CN210411297U (en) Steel pipe inner and outer wall saponification liquid spraying device
CN108355438A (en) A kind of air deduster
CN210333129U (en) Garden tree whitewashing device
CN113530179A (en) Building interior decoration ground waterproof layer brushing equipment and brushing method thereof
CN215278047U (en) Paint spraying apparatus is used in wind tower preparation
CN205024628U (en) Roadside stone washs equipment
CN214960944U (en) Soil ecological environment prosthetic devices
CN216960789U (en) Vegetation sprinkler is used in mine restoration
CN217774597U (en) Device is applied paint with a brush to afforestation construction with tree trunk
CN220677232U (en) Dust removal spray set
CN219024725U (en) Paint spraying equipment for metal pipe surface machining
CN219587507U (en) Drilling device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210415

Address after: 471000 100 meters east of the intersection of Jianshe Road and Yuzhe Avenue, Zheshang Industrial Park, Matun Town, Mengjin County, Luoyang City, Henan Province

Patentee after: Luoyang Tengyu tunnel machinery Co.,Ltd.

Address before: No. 259, xuanmei village, Shanxia Town, Hui'an County, Quanzhou City, Fujian Province, 362100

Patentee before: QUANZHOU LIANZHENG INFORMATION TECHNOLOGY Co.,Ltd.