CN212104065U - Air film structure spiral ground pile fixing system - Google Patents

Air film structure spiral ground pile fixing system Download PDF

Info

Publication number
CN212104065U
CN212104065U CN201921353955.XU CN201921353955U CN212104065U CN 212104065 U CN212104065 U CN 212104065U CN 201921353955 U CN201921353955 U CN 201921353955U CN 212104065 U CN212104065 U CN 212104065U
Authority
CN
China
Prior art keywords
film structure
steelframe
shell
gas film
spiral ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921353955.XU
Other languages
Chinese (zh)
Inventor
张一凡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Pharly Fabric Structure Technology Co ltd
Original Assignee
Beijing Pharly Fabric Structure Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Pharly Fabric Structure Technology Co ltd filed Critical Beijing Pharly Fabric Structure Technology Co ltd
Priority to CN201921353955.XU priority Critical patent/CN212104065U/en
Application granted granted Critical
Publication of CN212104065U publication Critical patent/CN212104065U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a gas film structure spiral ground stake fixed system, including steelframe and spiral ground stake, the quantity of spiral ground stake is two and distributes in the left and right sides of steelframe, the fixed ring flange that is equipped with in top of spiral ground stake, two the ring flange all passes through screw and steelframe fixed assembly, the fixed support that is equipped with of left surface of steelframe, both sides are all fixed around the inner wall of support and are equipped with the horizontal pole. The plectane is laminated to splint, extrude the splint, reach fixed effect, cooperation through support and horizontal pole, after accomplishing the gas film structure is fixed, the shell rotates, twine the edge of gas film structure on the shell, cover soil on the steelframe, be applicable to the gas film facility of part interim gas-bearing formula membrane structure and construction in the farmland, the step on concrete placement basis has been removed from, still conveniently demolish the gas film structure of putting up when conveniently putting up at practical application's in-process, can carry out quadratic use.

Description

Air film structure spiral ground pile fixing system
Technical Field
The utility model relates to a gas film structure spiral ground stake technical field, concrete field is a gas film structure spiral ground stake fixed system.
Background
The air film is called as an air-supported film structure, a special building fiber film material is adopted as a shell, the shell is supported by an automatic pressurization and fresh air system to form a building form of a building space, and the air film structure is suitable for developing temporary agricultural production and research facilities, such as an agricultural ecological research simulation space, a vegetable garden and a park greenhouse, temporary facilities easy to move and recombine, such as a large construction site command and meeting center and a temporary gathering place of materials of people in disaster areas, and for partial temporary air-supported film structures and air film facilities built in farmlands, anchoring is not suitable for adopting a mode of pouring concrete anchoring foundations, time and labor are wasted during building, the air film structure can be damaged during dismantling, and secondary use is not facilitated.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a gas film structure spiral ground stake fixing system to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a gas film structure spiral ground pile fixing system comprises a steel frame and spiral ground piles, wherein the number of the spiral ground piles is two, the spiral ground piles are distributed on the left side and the right side of the steel frame, flange plates are fixedly assembled at the top ends of the spiral ground piles, the two flange plates are fixedly assembled with the steel frame through screws, a support is fixedly assembled on the left side face of the steel frame, cross rods are fixedly assembled on the front side and the rear side of the inner wall of the support, a shell is arranged between the two cross rods, sliding grooves are formed in the front side and the rear side of the outer wall of the shell, the cross rods are inserted into the sliding grooves, openings are formed in the upper side face and the lower side face of the shell, clamping plates are hinged to the inner wall of the shell through hinges, a circular ring is fixedly assembled on the right side face of the shell, a connecting rod penetrates through the inner wall of the, the right flank fixed assembly of shell has the lug, the quantity of lug is two, two the lug is located the upper and lower both ends of ring respectively, the lantern ring has all been cup jointed at both ends about the outer wall of connecting rod, two the lantern ring is located the homonymy respectively the lug with between the ring, the spring has all been cup jointed to both sides about the outer wall of connecting rod, the lantern ring is located between lantern ring and the ring respectively.
Preferably, the fixed couple that is equipped with in right flank top of steelframe, the top outer wall of steelframe has cup jointed the pull ring, the right side of pull ring is located the couple below, the articulated clamp plate that is equipped with in top of pull ring, the lower surface of clamp plate closely laminates with the top of steelframe, the left side bottom fixed mounting of clamp plate has the support, the right side end of support rotates and is equipped with the cylinder, cylinder closely laminates with the steelframe.
Preferably, the right sides of the two lantern rings are hinged with pull rods, and the two pull rods are hinged with each other.
Preferably, the left side surface of the clamping plate is fixedly provided with a latch.
Preferably, the right side surface of the housing is fixedly provided with an outer frame, and the outer frame is positioned at the right side of the pull rod.
Preferably, the steel frame is H-shaped steel.
Preferably, the bases are fixedly assembled at the bottom ends of the left side and the right side of the steel frame.
Compared with the prior art, the beneficial effects of the utility model are that: a fixing system for a spiral ground pile of a gas film structure is characterized in that the spiral ground pile is buried in the ground through the matching of a steel frame and the spiral ground pile, the spiral ground pile and the steel frame are connected together through a flange plate and a screw, the edge of the gas film structure is inserted into a shell through the matching of a clamping plate and the shell, the clamping is carried out through the clamping plate, the circular plate is rotated to be attached to the inside of an opening, the circular plate is attached to the clamping plate to extrude the clamping plate to achieve the fixing effect, the shell is rotated after the gas film structure is fixed through the matching of a support and a cross rod, the edge of the gas film structure is wound on the shell to enhance the fixing effect, soil is covered on the steel frame after the fixing is completed, the fixing system is suitable for a part of temporary gas bearing type film structures and gas film facilities built in farmlands, the step of foundation pouring is omitted, the built gas film structure is convenient to dismantle while the actual application process is convenient to build, can be used for two times.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is an enlarged view of the structure at A in FIG. 1;
FIG. 3 is a sectional view of the housing structure of the present invention;
FIG. 4 is a schematic top view of the housing and frame structure of the present invention;
fig. 5 is a schematic view of the pull ring structure of the present invention.
In the figure: 1-steel frame, 2-spiral ground pile, 3-flange plate, 4-support, 5-cross bar, 6-shell, 7-chute, 8-opening, 9-splint, 10-latch, 11-ring, 12-connecting rod, 13-round plate, 14-lug, 15-lantern ring, 16-spring, 17-pull rod, 18-outer frame, 19-pull ring, 20-press plate, 21-support, 22-roller, 23-hook and 24-base.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example one
Referring to fig. 1-4, the present invention provides a technical solution: a gas film structure spiral ground pile fixing system comprises a steel frame 1 and spiral ground piles 2, the number of the spiral ground piles 2 is two, the spiral ground piles are distributed on the left side and the right side of the steel frame 1, flange plates 3 are fixedly assembled at the top ends of the spiral ground piles 2, the two flange plates 3 are fixedly assembled with the steel frame 1 through screws, a support 4 is fixedly assembled on the left side face of the steel frame 1, cross rods 5 are fixedly assembled on the front side and the rear side of the inner wall of the support 4, a shell 6 is arranged between the two cross rods 5, sliding grooves 7 are respectively arranged on the front side and the rear side of the outer wall of the shell 6, the cross rods 5 are inserted in the sliding grooves 7, openings 8 are respectively arranged on the upper side face and the lower side face of the right side face of the shell 6, clamping plates 9 are hinged and assembled on the inner wall of the shell 6 through hinges, a circular ring 11 is fixedly assembled on the right side face, the fixed lug 14 that is equipped with of shell 6's right flank, the quantity of lug 14 is two, and two lugs 14 are located the upper and lower both ends of ring 11 respectively, and lantern ring 15 has all been cup jointed at both ends about the outer wall of connecting rod 12, and two lantern rings 15 are located between homonymy lug 14 and the ring 11 respectively, and spring 16 has all been cup jointed to both sides about the outer wall of connecting rod 12, and lantern ring 16 is located between lantern ring 15 and the ring 11 respectively.
When a temporary air-supported membrane structure and an air film facility built in a farmland are built, firstly digging a soil pit at a designated low point, selecting the required number of steel frames 1 according to the area of the air film facility, placing the steel frames 1 in the dug soil pit, driving spiral ground piles 2 into the soil pit, wherein the spiral ground piles 2 are respectively positioned at the left side and the right side of the steel frames 1, the flange plates 3 at the top ends of the spiral ground piles 2 are contacted with the steel frames 1, fixing the spiral ground piles 2 and the steel frames 1 by using screws, completing pre-embedding of the steel frames 1, extending the air film structure from the right side to the left side of the steel frames 1, extending one end of the left side into the shell 6, pulling the clamping plates 9 at the moment, fixing the clamping plates 9 and the shell 6 together through hinges, clamping the air film structure by the inner walls of the clamping plates 9 and the shell 6, simultaneously pulling the two lantern rings 15 to separate the lantern rings 15 from the convex blocks 14, the lantern ring 15 exerts pressure on the spring 16, elastic deformation takes place for spring 16 because of the elastic property of self, rotate connecting rod 12, connecting rod 12 rotates at the inner wall of ring 11, connecting rod 12 drives plectane 13 at the pivoted in-process and rotates, plectane 13 rotates to the inside of running through opening 8 and pegging graft shell 6, with the inseparable laminating of splint 9 together, stop pulling the lantern ring 15, spring 16 resumes originated elastic state, lantern ring 15 and the inseparable laminating of lug 14, the cross-section of connecting rod 12 is the square, the inner wall of lantern ring 15 also is the assorted square, connecting rod 12 can't rotate at will this moment.
Particularly, the articulated pull rod 17 that is equipped with in the right side of two lantern rings 15, articulated assembly between two pull rods 17 is moving lantern ring 15 in-process, pulls two pull rods 17 to the direction of ring 11 simultaneously, and two pull rings 17 begin to swing, drives two lantern rings 15 at the wobbling in-process and moves, reaches the effect of exerting pressure to spring 16, conveniently dismantles.
Particularly, the fixed latch 10 that is equipped with of left surface of splint 9, latch 10 can increase the contact friction between splint 9 and the air film structure, increases the fixed effect of splint 9, prevents that the air film structure from droing.
Specifically, the outer frame 18 is fixedly assembled on the right side face of the housing 6, the outer frame 18 is located on the right side of the pull rod 17, the outer frame 8 can shield structures such as the circular ring 11, the connecting rod 12, the spring 16 and the circular plate 13, and when the housing 6 is rotated in the using process, the air film structure is wound on the housing 6 and the outer frame 18, so that the air film structure is prevented from being damaged.
Specifically, the steel frame 1 is H-shaped steel.
Particularly, the equal fixed mounting in left and right sides bottom of steelframe 1 has base 24, and base 24's cross-section is triangle-shaped, and triangle-shaped has stability, increases steelframe 1 self stable effect.
The working principle is as follows: when constructing a temporary air-supported membrane structure and an air film facility in a farmland, a plurality of steel frames 1 and spiral ground piles 2 are needed, a soil pit is dug at a designated low point, the required number of the steel frames 1 is selected according to the area of the air film facility, the steel frames 1 are placed in the dug soil pit, the spiral ground piles 2 are driven into the soil pit, the spiral ground piles 2 are respectively positioned at the left side and the right side of the steel frame 1, the flange plates 3 at the top ends of the spiral ground piles 2 are contacted with the steel frames 1, the spiral ground piles 2 and the steel frames 1 are fixed by using screws, the pre-embedding of the steel frames 1 is completed at the moment, the air film structure extends from the right side to the left side of the steel frame 1, one end at the left side extends into the inner part of the shell 6, at the moment, the clamping plate 9 is pulled, the clamping plate 9 is fixed with the shell 6 through hinges, the clamping plate 9 clamps the air film structure with the inner wall of the shell, make lantern ring 15 and lug 14 separation, lantern ring 15 exerts pressure to spring 16, spring 16 takes place elastic deformation because of the elastic property of self, rotating connection rod 12, connecting rod 12 rotates at the inner wall of ring 11, connecting rod 12 drives plectane 13 at the pivoted in-process and rotates, plectane 13 rotates to the inside of running through opening 8 and pegging graft shell 6, with the inseparable laminating of splint 9 together, it is spacing to the position of splint 9, fill into soil in the soil pit, bury steelframe 1 in soil, the operation is fixed a plurality of steelframe 1 to the edge of gas film structure simultaneously, reach the effect of quick fixed setting up.
Example two
Referring to fig. 1 and fig. 5, the technical solution provided by the present embodiment is different from the technical solution in the first embodiment only in that: steelframe 1's right flank top fixed assembly has couple 23, steelframe 1's top outer wall has cup jointed pull ring 19, pull ring 19's right side is located couple 23 below, pull ring 19's top is articulated to be equipped with clamp plate 20, clamp plate 20's lower surface and steelframe 1's top closely laminate, clamp plate 20's left side bottom fixed assembly has support 21, support 21's right side end is rotated and is equipped with cylinder 22, cylinder 22 and steelframe 1 closely laminate.
The shape of the pull ring 19 is as shown in fig. 5, and is n-shaped, before the operation of the technical scheme, the pull ring 19 is sleeved on the steel frame 1, the pull ring 19 is arranged at the bottom end of the hook 23, the pull ring 19 can swing on the side surface of the press plate 20, and the air film structure passes through the space between the press plate 20 and the steel frame 1 for use.
The working principle is as follows: in the in-process of using, cup joint pull ring 19 on steelframe 1 earlier, arrange pull ring 19 in the bottom of couple 23, when carrying out the fixed to the gas film structure, pass the gas film and fix between clamp plate 20 and steelframe 1, accomplish fixed back, it carries out further fixed and spacing to the gas film structure to be located, pull clamp plate 20, laminate clamp plate 20 to steelframe 1's top, support undersetting 21 at clamp plate 20 promotes gyro wheel 22 and laminates together with the gas film structure this moment, gyro wheel 22 laminates the gas film structure, avoid the gas film structure to cause the damage, pull ring 19 laminates together with the below of couple 23 this moment, reach further spacing effect.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (7)

1. The utility model provides a gas film structure spiral ground stake fixed system, includes steelframe (1) and spiral ground stake (2), the quantity of spiral ground stake (2) is two and distributes in the left and right sides of steelframe (1), its characterized in that: the spiral ground pile is characterized in that flange plates (3) are fixedly assembled at the top end of a spiral ground pile (2), the two flange plates (3) are fixedly assembled with a steel frame (1) through screws, a support (4) is fixedly assembled on the left side face of the steel frame (1), cross rods (5) are fixedly assembled on the front side and the rear side of the inner wall of the support (4), a shell (6) is arranged between the cross rods (5), sliding grooves (7) are formed in the front side and the rear side of the outer wall of the shell (6), the cross rods (5) are inserted into the sliding grooves (7), openings (8) are formed in the upper side face and the lower side face of the right side face of the shell (6), clamping plates (9) are hinged to the inner wall of the shell (6) through hinges, circular rings (11) are fixedly assembled on the right side face of the shell (6), connecting rods (12) penetrate through the inner wall of the circular rings (11, plectane (13) run through opening (8) and splint (9) and closely laminate, the right flank fixed assembly of shell (6) has lug (14), the quantity of lug (14) is two, two lug (14) are located the upper and lower both ends of ring (11) respectively, lantern ring (15) have all been cup jointed at both ends about the outer wall of connecting rod (12), two lantern ring (15) are located the homonymy respectively lug (14) with between ring (11), spring (16) have all been cup jointed to both sides about the outer wall of connecting rod (12), spring (16) are located between lantern ring (15) and ring (11) respectively.
2. A gas film structure screw ground pile fixing system as claimed in claim 1, wherein: the right flank top fixed knot of steelframe (1) is equipped with couple (23), pull ring (19) have been cup jointed to the top outer wall of steelframe (1), the right side of pull ring (19) is located couple (23) below, the articulated clamp plate (20) that is equipped with in top of pull ring (19), the lower surface of clamp plate (20) closely laminates with the top of steelframe (1), the left side bottom fixed knot of clamp plate (20) is equipped with support (21), the right side end of support (21) is rotated and is equipped with cylinder (22), cylinder (22) closely laminate with steelframe (1).
3. A gas film structure screw ground pile fixing system as claimed in claim 1, wherein: the right sides of the two lantern rings (15) are hinged with pull rods (17), and the two pull rods (17) are hinged with each other.
4. A gas film structure screw ground pile fixing system as claimed in claim 1, wherein: the left side surface of the clamping plate (9) is fixedly provided with a latch (10).
5. A gas film structure screw ground pile fixing system as claimed in claim 1, wherein: the right side surface of the shell (6) is fixedly provided with an outer frame (18), and the outer frame (18) is positioned on the right side of the pull rod (17).
6. A gas film structure screw ground pile fixing system as claimed in claim 1, wherein: the steel frame (1) is H-shaped steel.
7. A gas film structure screw ground pile fixing system as claimed in claim 1, wherein: the bottom ends of the left side and the right side of the steel frame (1) are fixedly provided with bases (24).
CN201921353955.XU 2019-08-20 2019-08-20 Air film structure spiral ground pile fixing system Expired - Fee Related CN212104065U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921353955.XU CN212104065U (en) 2019-08-20 2019-08-20 Air film structure spiral ground pile fixing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921353955.XU CN212104065U (en) 2019-08-20 2019-08-20 Air film structure spiral ground pile fixing system

Publications (1)

Publication Number Publication Date
CN212104065U true CN212104065U (en) 2020-12-08

Family

ID=73621381

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921353955.XU Expired - Fee Related CN212104065U (en) 2019-08-20 2019-08-20 Air film structure spiral ground pile fixing system

Country Status (1)

Country Link
CN (1) CN212104065U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112878496A (en) * 2021-01-08 2021-06-01 福州外语外贸学院 Detachable assembly type building structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112878496A (en) * 2021-01-08 2021-06-01 福州外语外贸学院 Detachable assembly type building structure

Similar Documents

Publication Publication Date Title
CN212104065U (en) Air film structure spiral ground pile fixing system
CN110552513A (en) Foundation trench earth and stone square operation dustproof shed and erection method
CN210529713U (en) Deep foundation pit supporting structure
CN209388578U (en) A kind of civil engineering class colleges and universities sponge city teaching mode and architectural teaching model
CN210917388U (en) Easy dismouting formula underground structure
CN114482594A (en) Construction method for retaining support of historical landscape civil-improvement commercial building structure
CN206728729U (en) A kind of removable thermal insulation membrane structure heliogreenhouse
JPH0460019A (en) Master pile horizontal sheet-pile method
CN206942208U (en) A kind of Liftable type migratory bird people place
CN216041207U (en) Soil supporting construction between assembled foundation ditch stake
CN211898494U (en) Building foundation pile
CN220978104U (en) Assembled retaining wall
CN214246523U (en) Civil engineering safety scaffold
JPS63151726A (en) Underground structure consisting of continuous underground wall
CN212508383U (en) Foundation pile strutting arrangement that underground space undercut adds layer construction usefulness
CN211510040U (en) Novel afforestation plant fixed knot constructs
CN213571998U (en) Double round timber pile cofferdam structure
CN212614091U (en) Building construction foundation encloses fender
CN216218978U (en) A pin-connected panel greening structure for propping up fender structure
RU2382851C1 (en) Truss-strip foundation
CN210641621U (en) Root inserting fixing device for agricultural greenhouse
CN217204082U (en) Civil engineering pile foundation construction structures
CN216752880U (en) Movable tree box device
CN218195953U (en) Multi-fulcrum continuous beam bridge type prefabricated pedestal
CN212026127U (en) Check net for bank protection and slope protection

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201208

Termination date: 20210820

CF01 Termination of patent right due to non-payment of annual fee