CN212103693U - Bridge floor anticollision barrier construction platform - Google Patents
Bridge floor anticollision barrier construction platform Download PDFInfo
- Publication number
- CN212103693U CN212103693U CN202020476164.2U CN202020476164U CN212103693U CN 212103693 U CN212103693 U CN 212103693U CN 202020476164 U CN202020476164 U CN 202020476164U CN 212103693 U CN212103693 U CN 212103693U
- Authority
- CN
- China
- Prior art keywords
- construction
- platform
- frame
- hanging basket
- crash barrier
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The application discloses bridge floor anticollision barrier construction platform compares with prior art, includes: constructing a frame; the construction channel is communicated with the construction rack; the traveling mechanism is arranged at the bottom of the construction rack; the movable hanging basket is arranged on the construction channel and used for supporting the operation of constructors; the movable hanging basket has a working state of unfolding to provide a construction space for constructors and a storage state of folding in the construction channel. The application provides a bridge floor anticollision barrier construction platform compares in prior art, and its construction accident incidence that can reduce the construction platform operation improves the construction operation environment in the bridge floor anticollision barrier outside, has ensured constructor's safety to a very big degree.
Description
Technical Field
The application relates to the technical field of bridge construction, more specifically says, especially relates to a bridge floor anticollision barrier construction platform.
Background
At present, when the bridge deck crash barrier works outside the bridge construction site or the bridge deck crash barrier is maintained outside the bridge deck crash barrier, especially a viaduct needs to be placed in the operation outside the bridge deck crash barrier for an operator, an operation area belongs to a suspension state, great inconvenience is brought to construction, and potential safety hazards exist.
In the prior art, a mode of combining a simple iron support and a safety rope is basically adopted, the mode has a plurality of uncertain factors, and the simple iron support is arranged on a bridge floor anti-collision guardrail, so that the simple iron support is easy to slide, and an operator is in an unsafe shaking state; working under the environment, the labor intensity of operators is high, the operators need to keep track of the safety state of the operators all the time, and the working efficiency is low.
Therefore, how to provide a bridge floor crash barrier construction platform, it can reduce the construction accident incidence of construction platform operation, improves the construction operation environment in the bridge floor crash barrier outside, has become the technical problem that technical staff in the field had a urgent need to solve.
SUMMERY OF THE UTILITY MODEL
For solving above-mentioned technical problem, this application provides a bridge floor crash barrier construction platform, and its construction accident incidence that can reduce the construction platform operation improves the construction operation environment in the bridge floor crash barrier outside.
The technical scheme provided by the application is as follows:
the application provides a bridge floor anticollision barrier construction platform, include: constructing a frame; the construction channel is communicated with the construction rack; the traveling mechanism is arranged at the bottom of the construction rack; the movable hanging basket is arranged on the construction channel and used for supporting the operation of constructors; the movable hanging basket has a working state of unfolding to provide a construction space for constructors and a storage state of folding in the construction channel.
Further, in an preferred mode of the present invention, a counterweight structure is provided on the construction rack, the counterweight structure is located the construction rack is kept away from one side of the movable hanging basket.
Further, the utility model relates to an among the preferred mode, bridge floor anticollision barrier construction platform still includes: a guide mechanism, the guide mechanism comprising: the guide bracket is fixed on the construction rack; and the guide wheel is arranged on the guide bracket and used for abutting against the side surface of the bridge deck anti-collision guardrail.
Further, in a preferred mode of the present invention, the guide bracket is a telescopic guide bracket.
Further, in a preferred mode of the present invention, the movable hanging basket includes: the hanging basket frame is hinged with the bottom end of the construction channel and has a vertically upward folding state and a working state which is horizontal to the side of the bridge; and the guardrail bracket is arranged on the hanging basket frame.
Further, in a preferred mode of the present invention, the guardrail support is perpendicular to the basket frame.
Further, in a preferred embodiment of the present invention, the movable hanging basket further comprises: the limiting plate is arranged below the hanging basket frame and used for limiting the rotation angle of the hanging basket frame.
Further, in the preferred mode of the present invention, the anti-collision guardrail construction platform further comprises: with hang the basket frame and can dismantle the support of inserting soon of connecting, it can dismantle the setting and be in to insert soon the basket frame is in one side of keeping away from the construction passageway under the operating condition for protect constructor to avoid the bridge side to fall.
Further, in a preferred mode of the present invention, the construction machine frame includes: a stent body; the walking platform is arranged on the bracket body; and the side surface protection structure is arranged on the walking platform.
Further, the utility model relates to an among the preferred mode, bridge floor anticollision barrier construction platform still includes: and the traffic stair is connected with the construction rack.
The utility model provides a pair of bridge floor anticollision barrier construction platform compares with prior art, include: constructing a frame; the construction channel is communicated with the construction rack; the traveling mechanism is arranged at the bottom of the construction rack; the movable hanging basket is arranged on the construction channel and used for supporting the operation of constructors; the activity is hung the basket and is had the expansion and provide the operating condition in construction space for the constructor to and draw in the accepting state in the construction passageway, wherein, the construction frame, the moment of tumbling that the steady moment that construction passageway self weight produced is far greater than the weight production of constructor and construction material, ensure construction safe and reliable, the setting of activity is hung the basket and can be effectively avoided the barrier in the work progress, makes things convenient for the exhibition of deployment of construction platform when work begins simultaneously, and the transfer of construction platform behind the work completion, the technical scheme of the utility model compared in prior art, its construction accident incidence that can reduce the construction platform operation improves the construction operation environment in the bridge floor anticollision guardrail outside, has ensured constructor's safety in the very big degree.
Drawings
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present application, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a front view of a bridge floor crash barrier construction platform provided in an embodiment of the present invention;
FIG. 2 is a top view of a bridge floor crash barrier construction platform provided in an embodiment of the present invention;
FIG. 3 is a side view of a bridge deck crash barrier construction platform provided in an embodiment of the present invention;
FIG. 4 is a schematic view of a three-dimensional structure of a bridge floor crash barrier construction platform provided in an embodiment of the present invention;
fig. 5 is a schematic view of the movable hanging basket according to the embodiment of the present invention in a folded state;
fig. 6 is a schematic view of the movable hanging basket according to the embodiment of the present invention in an expanded working state.
Detailed Description
In order to make those skilled in the art better understand the technical solutions in the present application, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only a part of the embodiments of the present application, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
It will be understood that when an element is referred to as being "fixed" or "disposed" on another element, it can be directly on the other element or be indirectly disposed on the other element; when an element is referred to as being "connected to" another element, it can be directly connected to the other element or be indirectly connected to the other element.
It will be understood that the terms "length," "width," "upper," "lower," "front," "rear," "first," "second," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like, as used herein, refer to an orientation or positional relationship indicated in the drawings that is solely for the purpose of facilitating the description and simplifying the description, and do not indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and thus should not be considered as limiting the present application.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present application, "plurality" or "a plurality" means two or more unless specifically limited otherwise.
It should be understood that the structures, ratios, sizes, and the like shown in the drawings are only used for matching the disclosure of the specification, so as to be understood and read by those skilled in the art, and are not used to limit the practical limit conditions of the present application, so that the modifications of the structures, the changes of the ratio relationships, or the adjustment of the sizes, do not have the technical essence, and the modifications, the changes of the ratio relationships, or the adjustment of the sizes, are all within the scope of the technical contents disclosed in the present application without affecting the efficacy and the achievable purpose of the present application.
Please refer to fig. 1 to 6, an embodiment of the present application provides a bridge deck crash barrier construction platform, which includes: constructing a frame 1; a construction channel 2 communicated with the construction rack 1; the traveling mechanism 3 is arranged at the bottom of the construction rack 1; a movable hanging basket 4 which is arranged on the construction channel 2 and is used for supporting the operation of constructors; the movable hanging basket 4 has a working state of unfolding to provide a construction space for constructors and a storage state of folding in the construction channel 2.
The embodiment of the utility model provides a bridge floor anticollision barrier construction platform specifically includes: constructing a frame 1; a construction channel 2 communicated with the construction rack 1; the traveling mechanism 3 is arranged at the bottom of the construction rack 1; a movable hanging basket 4 which is arranged on the construction channel 2 and is used for supporting the operation of constructors; the activity is hung basket 4 and is had the expansion and provide the operating condition in construction space for the constructor, and draw in the state of accomodating in construction passageway 2, wherein, construction frame 1, the steady moment that construction passageway 2 self weight produced is far more than the moment of tumbling that the weight of constructor and construction material produced, ensures construction safe and reliable, and the activity is hung basket 4's setting can effectively avoid the barrier in the work progress, makes things convenient for the exhibition of construction platform when work begins simultaneously, and the transfer of construction platform after the work is ended, the technical scheme of the utility model relates to a, compare in prior art, its construction accident incidence that can reduce the construction platform operation improves the construction operation environment in the bridge floor anticollision guardrail outside, has ensured constructor's safety in the very big degree.
Specifically, in the embodiment of the utility model provides an in, be equipped with counter weight structure 5 on the construction frame 1, counter weight structure 5 is located construction frame 1 is kept away from one side of basket 4 is hung in the activity.
Wherein, running gear 3 installs in the bottom of construction frame 1, and running gear 3 includes: the walking base plate 301 is arranged at the bottom of the construction rack 1, and the walking wheels 302 are arranged on the walking base plate 301.
Specifically, in the embodiment of the utility model provides an in, bridge floor anticollision barrier construction platform still includes: a guide mechanism 6, the guide mechanism 6 comprising: a guide bracket 601 fixed to the construction machine frame 1; and the guide wheel 602 is arranged on the guide bracket 601 and is used for abutting against the side surface of the bridge deck crash barrier.
Specifically, in the embodiment of the present invention, the guiding bracket 601 is specifically a telescopic guiding bracket 601.
The guide mechanism 6 is composed of a guide support 601, a guide wheel 602 and a bolt assembly, and can adopt two structures of a telescopic guide support or a fixed guide support, one end of the guide mechanism 6 is fixed on the construction rack 1, and the guide wheel 602 at the other end abuts against the side face of the anti-collision guardrail of the bridge floor, so that the moving position of the construction platform is ensured to be correct, and safety accidents are avoided.
Specifically, in the embodiment of the present invention, the movable hanging basket 4 includes: the hanging basket frame is hinged with the bottom end of the construction channel 2 and has a vertically upward folding state and a working state which is horizontal to the side of the bridge; and the guardrail bracket is arranged on the hanging basket frame.
Specifically, in the embodiment of the utility model provides an in, the guardrail support with hang the perpendicular setting of basket frame.
Specifically, in the embodiment of the present invention, the movable hanging basket 4 further includes: the limiting plate is arranged below the hanging basket frame and used for limiting the rotation angle of the hanging basket frame.
The movable hanging basket can effectively solve the problem that the movable hanging basket meets obstacles in the construction process to a greater extent, and meanwhile, the movable hanging basket is convenient for the arrangement and the exhibition of the construction platform when the work is started and the transfer of the construction platform after the work is finished.
Specifically, in the embodiment of the utility model provides an in, the flat still includes of anticollision barrier construction: with hang basket frame and can dismantle the quick support 7 of inserting of connection, it can dismantle the setting and be in to insert support 7 soon hang basket frame and be in one side of keeping away from construction passageway 2 under the operating condition for protect constructor to avoid the bridge side to fall.
Wherein, the activity is hung basket 4 and is connected with construction passageway 2 through round pin axle subassembly 9, the activity is hung basket 4 and is in the open mode when the during operation, for constructor provides construction work platform space, non-during operation activity is hung basket 4 and is drawn in to construction passageway 2, during operating condition, earlier with positioning bolt 10 revolve to non-operating space state, hang basket 4 with the activity again and open, insert fast inserting support 7, get into operating condition, during non-operating condition, earlier take off fast inserting support 7, the activity is hung basket 4 and is drawn in and place in construction passageway 2, revolve out positioning bolt 10 again, it is fixed to borrow the shank of bolt messenger, the setting of inserting support 7 soon can be hung basket 4 in the activity and draw in the state and make things convenient for constructor current under.
Specifically, in the embodiment of the present invention, the construction machine frame 1 includes: a stent body; the walking platform is arranged on the bracket body; and the side surface protection structure is arranged on the walking platform.
Specifically, in the embodiment of the utility model provides an in, bridge floor anticollision barrier construction platform still includes: and the traffic stair 8 is connected with the construction rack 1.
Explaining more specifically, when maintenance is maintained in work or the bridge floor crash barrier outside in bridge construction site bridge floor crash barrier at present, especially overpass need place operating personnel in the operation of bridge floor crash barrier outside, and the operation region belongs to unsettled state, brings very big inconvenience for the construction, and has the potential safety hazard, and present field processing scheme adopts the mode that simple and easy iron stand and safety rope combined together basically, and this mode operation has a great deal of uncertain factor, and the accident rate is high, and the concrete analysis is as follows:
the simple iron support is arranged on the bridge floor anti-collision guardrail, so that the simple iron support is easy to slide, and an operator is in an unsafe shaking state;
the simple bracket is manufactured by welding local materials on site, the manufacturing process quality standard is not uniform, the structure has no strength safety check calculation, the integral rigidity is weak and easy to deform, the operation requirement cannot be met, and the potential safety hazard exists.
Working under the environment, the labor intensity of operators is high, and the operators need to keep track of the safety state of the operators all the time, so that the working efficiency is low and the quality is general.
The embodiment of the utility model provides a bridge floor anticollision barrier construction platform, it uses or the operating procedure specifically as follows:
with bridge floor anticollision barrier construction platform on-the-spot reasonable placement: adjusting the position, and then abutting guide wheels of the guide part against the side surface of the bridge floor crash barrier; constructors carry construction materials to enter the bottom of the right side rack from the channel; rotating the positioning bolt, opening the movable hanging basket, and inserting the quick insertion bracket; in the operation state, a bridge deck operator drives the platform to move in the process, and the guide wheel of the guide mechanism is propped against the anti-collision side face of the bridge; after the operation is finished, the quick-inserting support is taken down, the movable hanging basket is folded, the positioning bolt is rotated again for positioning, and finally constructors return to the bridge floor from the channel. The stable moment that construction frame, construction passageway self weight produced is far greater than the moment of tumbling that constructor and construction material's weight produced, ensures construction safe and reliable, and the barrier can effectively be avoided in the work progress in the setting of activity string basket, and the cloth exhibition of construction platform when simultaneously making things convenient for the work to and the transfer of construction platform after the work is finished.
From top to the utility model provides a bridge floor anticollision barrier construction platform, its stability moment that utilizes equipment self weight to produce is far more than the moment principle of tumbling that the weight of operating personnel and construction materials produced, it is steady to ensure the equipment operation, the operation is steady on the platform does not have and rocks, constructor's operation environment comfort level promotes by a wide margin, promote construction work efficiency and quality improvement, usable bridge floor personnel drive platform removes, but constructor continuity of operation in the basket is hung in the activity, the lifting efficiency, and the rigidity is good, can realize reuse, compare in prior art, it can reduce the construction accident incidence of construction platform operation, improve the construction work environment in the bridge floor anticollision barrier outside, constructor's safety has been ensured to a great extent.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.
Claims (10)
1. The utility model provides a bridge floor crash barrier construction platform which characterized in that includes:
constructing a frame;
the construction channel is communicated with the construction rack;
the traveling mechanism is arranged at the bottom of the construction rack;
the movable hanging basket is arranged on the construction channel and used for supporting the operation of constructors;
the movable hanging basket has a working state of unfolding to provide a construction space for constructors and a storage state of folding in the construction channel.
2. The bridge deck crash barrier construction platform of claim 1, wherein a counterweight structure is provided on the construction frame, the counterweight structure being located on a side of the construction frame remote from the removable hanging basket.
3. The bridge deck crash barrier construction platform of claim 2, further comprising: a guide mechanism, the guide mechanism comprising: the guide bracket is fixed on the construction rack; and the guide wheel is arranged on the guide bracket and used for abutting against the side surface of the bridge deck anti-collision guardrail.
4. The bridge deck crash barrier construction platform of claim 3, wherein said guide support is in particular a telescopic guide support.
5. The bridge deck crash barrier construction platform of claim 3, wherein said movable baskets comprise: the hanging basket frame is hinged with the bottom end of the construction channel and has a vertically upward folding state and a working state which is horizontal to the side of the bridge; and the guardrail bracket is arranged on the hanging basket frame.
6. The bridge deck crash barrier construction platform of claim 5, wherein said barrier supports are disposed perpendicular to said cradle frame.
7. The bridge deck crash barrier construction platform of claim 5, wherein said movable baskets further comprise: the limiting plate is arranged below the hanging basket frame and used for limiting the rotation angle of the hanging basket frame.
8. The bridge deck crash barrier construction platform of claim 5, further comprising: with hang the basket frame and can dismantle the support of inserting soon of connecting, it can dismantle the setting and be in to insert soon the basket frame is in one side of keeping away from the construction passageway under the operating condition for protect constructor to avoid the bridge side to fall.
9. The bridge deck crash barrier construction platform of claim 1, wherein said construction frame comprises: a stent body; the walking platform is arranged on the bracket body; and the side surface protection structure is arranged on the walking platform.
10. The bridge deck crash barrier construction platform of claim 9, further comprising: and the traffic stair is connected with the construction rack.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020476164.2U CN212103693U (en) | 2020-04-03 | 2020-04-03 | Bridge floor anticollision barrier construction platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020476164.2U CN212103693U (en) | 2020-04-03 | 2020-04-03 | Bridge floor anticollision barrier construction platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212103693U true CN212103693U (en) | 2020-12-08 |
Family
ID=73636567
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020476164.2U Expired - Fee Related CN212103693U (en) | 2020-04-03 | 2020-04-03 | Bridge floor anticollision barrier construction platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212103693U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113718646A (en) * | 2021-10-13 | 2021-11-30 | 中建八局第二建设有限公司 | Municipal administration overhead is with hanging basket device |
-
2020
- 2020-04-03 CN CN202020476164.2U patent/CN212103693U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113718646A (en) * | 2021-10-13 | 2021-11-30 | 中建八局第二建设有限公司 | Municipal administration overhead is with hanging basket device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2202121A1 (en) | Support device for walking machines | |
CN212103693U (en) | Bridge floor anticollision barrier construction platform | |
US4555890A (en) | Process for the installation of curtain walls and apparatus for the execution of the process | |
CN214245364U (en) | Roll-over stand of bridge inspection vehicle | |
CN109019461A (en) | A kind of articulated arm lift small with working area | |
CN108657949B (en) | Pneumatic monorail crane installation device and method | |
KR102038526B1 (en) | High place working vehicles having tiltable and raollerable basket | |
CN208168314U (en) | Folding type hanging hanger operation platform | |
CN217175594U (en) | Construction frame | |
CN107487723B (en) | A kind of substation equipment maintenance and repair hoisting apparatus | |
CN206126733U (en) | Light lift | |
CN106629470B (en) | Lift level-sensing device apparatus for examination and repair | |
CN213060114U (en) | Lifting operation platform for decoration design | |
CN213326443U (en) | Quick unloading platform | |
CN211257754U (en) | Steel construction removes scaffold | |
CN213509525U (en) | High-altitude operation platform with high safety | |
CN207841283U (en) | A kind of traction electric machine stator rolling disk storage rack | |
CN114382012A (en) | Bridge construction lifts by crane better hanging flower basket of wind-resistance for equipment | |
CN210049214U (en) | Overhauling trolley | |
CN208632041U (en) | A kind of power engineering installation vehicle | |
CN220011944U (en) | Vehicle-mounted folding crane | |
CN213171108U (en) | Anti-swing device for hoisting steel structure connecting piece | |
CN219931553U (en) | Telescopic folding scaffold | |
CN215291324U (en) | High altitude construction is with slowly falling equipment | |
CN218714909U (en) | Scaffold convenient to installation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201208 |
|
CF01 | Termination of patent right due to non-payment of annual fee |