CN212026740U - Assembled curtain wall - Google Patents

Assembled curtain wall Download PDF

Info

Publication number
CN212026740U
CN212026740U CN201922420183.3U CN201922420183U CN212026740U CN 212026740 U CN212026740 U CN 212026740U CN 201922420183 U CN201922420183 U CN 201922420183U CN 212026740 U CN212026740 U CN 212026740U
Authority
CN
China
Prior art keywords
plate
curtain wall
transverse plate
bracket
side plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922420183.3U
Other languages
Chinese (zh)
Inventor
史建文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiamen Sihe Technology Co ltd
Original Assignee
Xiamen Sihe Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiamen Sihe Technology Co ltd filed Critical Xiamen Sihe Technology Co ltd
Priority to CN201922420183.3U priority Critical patent/CN212026740U/en
Application granted granted Critical
Publication of CN212026740U publication Critical patent/CN212026740U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model provides an assembled curtain, include: positioning pieces are fixedly arranged at intervals; the connecting piece is connected to the positioning piece through a bolt; the vertical rod is connected to the connecting piece through a bolt; a cross bar vertically fixed on the vertical bar through a corner piece; the hanging pieces are arranged on the cross rod at intervals; and the curtain wall plate is fixed on the hanging piece. The utility model discloses structural design is ingenious, and lifting surface area is big, and can allow concrete surface certain limit's construction error, and the practicality is strong.

Description

一种装配式幕墙An assembled curtain wall

技术领域technical field

本实用新型涉及幕墙安装领域,更具体的说是,涉及一种装配式幕墙。The utility model relates to the field of curtain wall installation, in particular to an assembled curtain wall.

背景技术Background technique

幕墙是建筑的外墙围护,不承重,像幕布一样挂上去,故又称为“帷幕墙”,是现代大型和高层建筑常用的带有装饰效果的轻质墙体。由面板和支承结构体系组成的,可相对主体结构有一定位移能力或自身有一定变形能力、不承担主体结构所作用的建筑外围护结构或装饰性结构(外墙框架式支撑体系也是幕墙体系的一种)。The curtain wall is the outer wall of the building. It is not load-bearing and hangs like a curtain, so it is also called "curtain wall". It is a lightweight wall with decorative effects commonly used in modern large and high-rise buildings. It is composed of panels and supporting structure systems, which can have a certain displacement ability relative to the main structure or have a certain deformation ability itself, and do not undertake the role of the main structure. a kind).

目前,现有市场上的幕墙挂件大多安装在幕墙板的上下边缘,不仅容易对幕墙板的边缘产生破坏,而且容易在安装槽内积水,降低幕墙板的安全牢固性,且挂件的位移能力差,实用性较低。At present, most of the curtain wall pendants on the market are installed on the upper and lower edges of the curtain wall panels, which not only easily damages the edges of the curtain wall panels, but also easily accumulates water in the installation grooves, which reduces the safety and firmness of the curtain wall panels and the displacement ability of the pendants. Poor, low practicality.

实用新型内容Utility model content

本实用新型提供了一种装配式幕墙,可以有效解决上述问题。The utility model provides an assembled curtain wall, which can effectively solve the above problems.

本实用新型是这样实现的:The utility model is realized in this way:

一种装配式幕墙,包括:A prefabricated curtain wall, comprising:

间隔固定设置的定位件;Positioning pieces with fixed intervals;

通过螺栓连接于所述定位件上的连接件;A connecting piece connected to the positioning piece by bolts;

通过螺栓连接于所述连接件上的竖杆;a vertical rod connected to the connecting piece by bolts;

通过角件垂直固定于所述竖杆上的横杆;a cross bar vertically fixed on the vertical bar through a corner piece;

间隔设置于所述横杆上的挂件;以及pendants arranged at intervals on the crossbar; and

固定于所述挂件上的幕墙板。The curtain wall panel fixed on the pendant.

作为进一步改进的,所述定位件包括:As a further improvement, the positioning member includes:

螺栓安装板,其上间隔设置有第一条孔;The bolt mounting plate is provided with a first hole at intervals;

分别垂直连接于所述螺栓安装板两端的侧板;respectively vertically connected to the side plates at both ends of the bolt mounting plate;

分别垂直连接于所述侧板远离所述螺栓安装板一端的底板。The bottom plates are respectively vertically connected to the bottom plates at one end of the side plate away from the bolt mounting plate.

作为进一步改进的,所述连接件包括:第一连接板,其上间隔设置有通过螺栓与所述第一条孔配合的第二条孔;垂直连接于所述第一连接件远离所述定位件一端的第二连接板,其上间隔设置有第三条孔。As a further improvement, the connecting piece includes: a first connecting plate, on which second holes are arranged at intervals and matched with the first holes through bolts; vertically connected to the first connecting piece away from the positioning The second connecting plate at one end of the component is provided with third holes at intervals.

作为进一步改进的,所述挂件包括:As a further improvement, the pendant includes:

第一支架;the first bracket;

通过螺栓连接于所述第一支架上的第二支架;a second bracket connected to the first bracket by bolts;

分别套设于所述第一支架和所述第二支架上的幕墙支架,其用于固定在所述幕墙板上。The curtain wall brackets respectively sleeved on the first bracket and the second bracket are used to be fixed on the curtain wall board.

作为进一步改进的,所述第一支架包括:As a further improvement, the first bracket includes:

第一横板,其上设置有通孔;The first horizontal plate is provided with through holes;

垂直连接于所述第一横板一端的第一侧板;a first side plate vertically connected to one end of the first horizontal plate;

平行设置于所述第一横板下方且连接于所述第一侧板靠近所述第一横板一侧的第二横板,其上设置有第四条孔;a second horizontal plate arranged in parallel below the first horizontal plate and connected to the side of the first side plate close to the first horizontal plate, and a fourth hole is arranged on the second horizontal plate;

垂直设置于所述第一侧板远离所述第二横板一端的第三横板;以及a third transverse plate vertically disposed at one end of the first side plate away from the second transverse plate; and

垂直连接于所述第三横板靠近所述第二横板一侧的第二侧板。The second side plate is vertically connected to the side of the third horizontal plate close to the second horizontal plate.

作为进一步改进的,所述第二支架包括:As a further improvement, the second bracket includes:

设置于所述第一横板上的第四横板,其上设置有通过螺栓与所述通孔配合的第五条孔;The fourth horizontal plate arranged on the first horizontal plate is provided with a fifth hole which is matched with the through hole through a bolt;

垂直连接于所述第四横板远离所述第一支架一侧的第三侧板。The third side plate is vertically connected to the side of the fourth horizontal plate away from the first bracket.

作为进一步改进的,所述幕墙支架包括:As a further improvement, the curtain wall bracket includes:

第四侧板;the fourth side panel;

垂直连接于所述第四侧板远离所述第一支架一端的第五横板,其上设置有第一螺纹孔;a fifth transverse plate vertically connected to one end of the fourth side plate away from the first bracket, and a first threaded hole is provided on it;

垂直连接于所述第五横板靠近所述第四侧板一侧且与所述第四侧板平行的第五侧板;a fifth side plate vertically connected to the side of the fifth horizontal plate close to the fourth side plate and parallel to the fourth side plate;

末端向上斜置连接于所述第五侧板远离所述第四侧板一侧的卡接板,其与竖直面成一定锐角;以及The end is obliquely connected to the clamping plate on the side of the fifth side plate away from the fourth side plate, which forms a certain acute angle with the vertical plane; and

螺接于所述第一螺纹孔的调整螺栓。an adjustment bolt screwed to the first threaded hole.

作为进一步改进的,所述挂件进一步包括用于限制幕墙支架移动的保险件,其包括:As a further improvement, the pendant further includes a safety piece for restricting the movement of the curtain wall bracket, which includes:

设置于所述第五横板上方的第六横板,其上设置有与所述调整螺栓配合的第二螺纹孔;a sixth horizontal plate arranged above the fifth horizontal plate, and a second threaded hole matched with the adjustment bolt is arranged on the sixth horizontal plate;

垂直连接于所述第六横板靠近所述第一支架一侧的第六侧板;以及a sixth side plate vertically connected to a side of the sixth transverse plate close to the first bracket; and

垂直连接于所述第六侧板靠近所述第六横板一侧且平行于所述第六横板的第七横板,其设置于所述第三侧板下方。A seventh horizontal plate vertically connected to a side of the sixth side plate close to the sixth horizontal plate and parallel to the sixth horizontal plate is disposed below the third side plate.

本实用新型的有益效果是:采用定位件固定在混凝土表面上,连接件与定位件的结合,使得竖杆可以实现上下、左右和前后位置上的调节;在挂件和横杆、竖杆上设置有个方向的条孔,提升了本实用新型的可位移范围,提升了对不同施工环境的适应能力。采用在幕墙板的直立面上开孔,解决了安装槽上积水的问题,提升了幕墙板的安全牢固性。本实用新型结构设计巧妙,受力面积大,且能允许混凝土表面一定范围的施工误差,实用性强。The beneficial effects of the utility model are as follows: the positioning piece is fixed on the concrete surface, and the combination of the connecting piece and the positioning piece enables the vertical rod to realize the adjustment of the up and down, left and right and front and rear positions; The strip hole in one direction improves the displacement range of the utility model and the adaptability to different construction environments. Holes are opened on the vertical surface of the curtain wall panel, which solves the problem of water accumulation on the installation groove and improves the safety and firmness of the curtain wall panel. The utility model has the advantages of ingenious structural design, large force bearing area, and a certain range of construction errors on the concrete surface, and high practicability.

附图说明Description of drawings

为了更清楚地说明本实用新型实施方式的技术方案,下面将对实施方式中所需要使用的附图作简单地介绍,应当理解,以下附图仅示出了本实用新型的某些实施例,因此不应被看作是对范围的限定,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他相关的附图。In order to illustrate the technical solutions of the embodiments of the present invention more clearly, the accompanying drawings required in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of the present invention. Therefore, it should not be regarded as a limitation of the scope. For those of ordinary skill in the art, other related drawings can also be obtained from these drawings without any creative effort.

图1是本实用新型实施例一提供的整体结构示意图。FIG. 1 is a schematic diagram of the overall structure provided by Embodiment 1 of the present invention.

图2是本实用新型实施例一提供的部分结构示意图。FIG. 2 is a partial structural schematic diagram provided by Embodiment 1 of the present invention.

图3是本实用新型实施例一提供的挂件与幕墙装配结构剖视图。3 is a cross-sectional view of the assembly structure of the pendant and the curtain wall provided by the first embodiment of the present invention.

图4是本实用新型实施例一提供的挂件、横杆和竖杆的装配结构示意图。FIG. 4 is a schematic diagram of the assembly structure of the pendant, the horizontal bar and the vertical bar provided in the first embodiment of the present invention.

图5是本实用新型实施例一提供的第一支架和第二支架的结构示意图。FIG. 5 is a schematic structural diagram of a first bracket and a second bracket provided in Embodiment 1 of the present invention.

图6是本实用新型实施例一提供的第一支架结构示意图。FIG. 6 is a schematic structural diagram of a first support provided in Embodiment 1 of the present invention.

图7是本实用新型实施例一提供的第二支架结构示意图。FIG. 7 is a schematic structural diagram of a second support provided in Embodiment 1 of the present invention.

图8是本实用新型实施例一提供的幕墙支架结构示意图。FIG. 8 is a schematic structural diagram of a curtain wall support provided in Embodiment 1 of the present invention.

图9是本实用新型实施例一提供的定位件与连接件的装配结构示意图。FIG. 9 is a schematic diagram of the assembly structure of the positioning member and the connecting member according to the first embodiment of the present invention.

图10是本实用新型实施例一提供的连接件结构示意图。FIG. 10 is a schematic structural diagram of a connector provided in Embodiment 1 of the present invention.

图11是本实用新型实施例一提供的定位件正面结构示意图。11 is a schematic diagram of the front structure of the positioning member provided in the first embodiment of the present invention.

图12是本实用新型实施例二提供的定位件结构示意图。12 is a schematic structural diagram of a positioning member provided in Embodiment 2 of the present invention.

图13是本实用新型实施例三提供的带有保险件的局部结构示意图。FIG. 13 is a partial structural schematic diagram with a safety piece provided by the third embodiment of the present invention.

图14是本实用新型实施例三提供的保险件结构示意图。FIG. 14 is a schematic structural diagram of a safety piece provided in Embodiment 3 of the present invention.

图15是本实用新型实施例提供的幕墙板结构示意图。15 is a schematic structural diagram of a curtain wall panel provided by an embodiment of the present invention.

图16是本实用新型实施例一提供的定位件背面结构示意图。FIG. 16 is a schematic diagram of the rear structure of the positioning member provided in the first embodiment of the present invention.

图中:1.定位件 11.螺栓安装板 111.第一条孔 1111.条孔主体In the picture: 1. Positioning part 11. Bolt mounting plate 111. The first hole 1111. The main body of the hole

1112.螺栓进入孔 12.侧板 13.底板 131.长腰孔1112. Bolt entry hole 12. Side plate 13. Bottom plate 131. Long waist hole

14.第一加强板 15.第二加强板 16.定位柱 2.连接件14. The first reinforcing plate 15. The second reinforcing plate 16. The positioning column 2. The connecting piece

21.第一连接板 211.第二条孔 22.第二连接板21. The first connecting plate 211. The second hole 22. The second connecting plate

221.第三条孔 3.竖杆 4.横杆 5.角件 6.挂件221. Third hole 3. Vertical bar 4. Cross bar 5. Corner piece 6. Pendant

61.第一支架 611.第一横板 6111.通孔 612.第一侧板61. The first bracket 611. The first horizontal plate 6111. The through hole 612. The first side plate

613.第二横板 6131.第四条孔 614.第三横板 615.第二侧板613. Second horizontal plate 6131. Fourth hole 614. Third horizontal plate 615. Second side plate

62.第二支架 621.第四横板 6211.第五条孔 622.第三侧板62. Second bracket 621. Fourth horizontal plate 6211. Fifth hole 622. Third side plate

63.幕墙支架 631.第四侧板 632.第五横板 6321.第一螺纹孔63. Curtain wall bracket 631. Fourth side plate 632. Fifth cross plate 6321. First threaded hole

633.第五侧板 634.卡接板 635.调整螺栓 64.保险件633. Fifth side plate 634. Snap plate 635. Adjusting bolt 64. Safety part

641.第六横板 6411.第二螺纹孔 642.第六侧板641. Sixth cross plate 6411. Second threaded hole 642. Sixth side plate

643.第七横板 7.幕墙板 71.安装槽643. Seventh horizontal plate 7. Curtain wall plate 71. Installation groove

具体实施方式Detailed ways

为使本实用新型实施方式的目的、技术方案和优点更加清楚,下面将结合本实用新型实施方式中的附图,对本实用新型实施方式中的技术方案进行清楚、完整地描述,显然,所描述的实施方式是本实用新型一部分实施方式,而不是全部的实施方式。基于本实用新型中的实施方式,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施方式,都属于本实用新型保护的范围。因此,以下对在附图中提供的本实用新型的实施方式的详细描述并非旨在限制要求保护的本实用新型的范围,而是仅仅表示本实用新型的选定实施方式。基于本实用新型中的实施方式,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施方式,都属于本实用新型保护的范围。In order to make the purposes, technical solutions and advantages of the embodiments of the present invention more clear, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described The embodiments of the present invention are a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention. Accordingly, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the invention as claimed, but is merely representative of selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.

在本实用新型的描述中,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本实用新型的描述中,“多个”的含义是两个或两个以上,除非另有明确具体的限定。In the description of the present invention, the terms "first" and "second" are only used for the purpose of description, and cannot be understood as indicating or implying relative importance or implying the number of indicated technical features. Thus, a feature defined as "first" or "second" may expressly or implicitly include one or more of that feature. In the description of the present invention, "plurality" means two or more, unless otherwise expressly and specifically defined.

实施例一Example 1

参照图1至图11所示,一种装配式幕墙,包括:间隔固定设置的定位件1;通过螺栓连接于所述定位件1上的连接件2;通过螺栓连接于所述连接件2上的竖杆3;通过角件5垂直固定于所述竖杆3上的横杆4;间隔设置于所述横杆4上的挂件6;以及固定于所述挂件6上的幕墙板7。采用定位件1固定在混凝土表面上,连接件2与定位件1的结合,使得竖杆3可以实现上下、左右和前后位置上的调节;在挂件6和横杆4、竖杆3上设置有个方向的条孔,提升了本实用新型的可位移范围,提升了对不同施工环境的适应能力。采用在幕墙板7的直立面上开孔,解决了安装槽上积水的问题,提升了幕墙板7的安全牢固性。本实用新型结构设计巧妙,受力面积大,且能允许混凝土表面一定范围的施工误差,实用性强。Referring to FIGS. 1 to 11 , a prefabricated curtain wall includes: a positioning member 1 that is fixed at intervals; a connecting member 2 connected to the positioning member 1 by bolts; connected to the connecting member 2 by bolts The vertical bar 3; the horizontal bar 4 vertically fixed on the vertical bar 3 through the corner piece 5; the pendant 6 arranged on the horizontal bar 4 at intervals; The positioning member 1 is used to fix on the concrete surface, and the combination of the connecting member 2 and the positioning member 1 enables the vertical rod 3 to realize the adjustment of the up and down, left and right and front and rear positions; The strip holes in each direction improve the movable range of the utility model and the adaptability to different construction environments. By opening holes on the vertical surface of the curtain wall panel 7 , the problem of water accumulation on the installation groove is solved, and the safety and firmness of the curtain wall panel 7 is improved. The utility model has the advantages of ingenious structural design, large force bearing area, and a certain range of construction errors on the concrete surface, and high practicability.

参照图11所示,所述定位件1包括:螺栓安装板11,其上间隔设置有第一条孔111;分别垂直连接于所述螺栓安装板11两端的侧板12;分别垂直连接于所述侧板12远离所述螺栓安装板11一端的底板13。所述第一条孔111包括:条孔主体1111和设置于所述条孔主体1111一端的螺栓进入孔1112,使得螺栓进入第一条孔111时,先将螺栓头部从螺栓进入孔1112 中放入,然后在条孔主体1111中平移,且条孔主体1111起到了对螺栓限位的作用。所述定位件1进一步包括:垂直连接于所述螺栓安装板11靠近所述侧板12一端且与所述侧板12平行的第一加强板14;分别连接于所述侧板12和所述第一加强板14一端且与所述螺栓安装板11垂直的第二加强板15。所述底板13上间隔设置有长腰孔131,螺栓通过长腰孔131将定位件1锁附在混凝土墙面上,底板13贴合在混凝土墙面上,完成定位件1的安装。Referring to FIG. 11 , the positioning member 1 includes: a bolt mounting plate 11 on which a first hole 111 is arranged at intervals; side plates 12 vertically connected to both ends of the bolt mounting plate 11 ; The side plate 12 is away from the bottom plate 13 at one end of the bolt mounting plate 11 . The first strip hole 111 includes: a strip hole main body 1111 and a bolt entry hole 1112 provided at one end of the strip hole main body 1111, so that when the bolt enters the first strip hole 111, the bolt head is first inserted from the bolt into the hole 1112 Put in, and then translate in the main body 1111 of the strip hole, and the main body 1111 of the strip hole plays the role of limiting the position of the bolt. The positioning member 1 further includes: a first reinforcing plate 14 vertically connected to one end of the bolt mounting plate 11 close to the side plate 12 and parallel to the side plate 12; respectively connected to the side plate 12 and the side plate 12. One end of the first reinforcing plate 14 is a second reinforcing plate 15 which is perpendicular to the bolt mounting plate 11 . The bottom plate 13 is provided with long waist holes 131 at intervals. The bolts lock the positioning member 1 on the concrete wall through the long waist holes 131 . The bottom plate 13 is attached to the concrete wall to complete the installation of the positioning member 1 .

参照图9至图10所示,所述连接件2包括:第一连接板21,其上间隔设置有通过螺栓与所述第一条孔111配合的第二条孔211;垂直连接于所述第一连接件2远离所述定位件1一端的第二连接板22,其上间隔设置有第三条孔221。第一条孔111与第二条孔211垂直,第二条孔211与第三条孔 221在空间上垂直,使得连接件2与定位件1配合时,锁附在连接件2上的竖杆3可以进行相对于定位件1的上下、前后、左右的位置调节,进而允许一定范围内的施工误差,同时也极大地提升了本实用新型的实用性。Referring to FIG. 9 to FIG. 10 , the connecting member 2 includes: a first connecting plate 21 , on which second holes 211 are arranged at intervals to cooperate with the first holes 111 through bolts; The second connecting plate 22 at one end of the first connecting member 2 away from the positioning member 1 is provided with third holes 221 at intervals thereon. The first hole 111 is perpendicular to the second hole 211 , and the second hole 211 and the third hole 221 are perpendicular in space, so that when the connecting piece 2 is matched with the positioning piece 1 , the vertical rods attached to the connecting piece 2 are locked. 3. The position adjustment of up and down, front and rear, and left and right relative to the positioning member 1 can be performed, thereby allowing construction errors within a certain range, and also greatly improving the practicability of the present utility model.

参照图4至图5所示,所述挂件6包括:第一支架61;通过螺栓连接于所述第一支架61上的第二支架62;分别套设于所述第一支架61和所述第二支架62上的幕墙支架63,其用于固定在所述幕墙板7上。所述横杆4 上设置有条孔,使得安装在所述横杆4上的挂件6可以在横杆4上平移,进而允许幕墙板7安装槽71一定程度的加工误差,同时也提升了本实用新型对不同尺寸的幕墙板7的适用范围。4 to 5 , the hanger 6 includes: a first bracket 61 ; a second bracket 62 connected to the first bracket 61 by bolts; sleeved on the first bracket 61 and the first bracket 61 respectively The curtain wall bracket 63 on the second bracket 62 is used to be fixed on the curtain wall panel 7 . The cross bar 4 is provided with a strip hole, so that the pendant 6 installed on the cross bar 4 can translate on the cross bar 4, thereby allowing a certain degree of machining error of the installation groove 71 of the curtain wall panel 7, and at the same time improving the cost. The scope of application of the utility model to curtain wall panels 7 of different sizes.

参照图5至图6所示,所述第一支架61包括:第一横板611,其上设置有通孔6111;垂直连接于所述第一横板611一端的第一侧板612;平行设置于所述第一横板611下方且连接于所述第一侧板612靠近所述第一横板611一侧的第二横板613,其上设置有第四条孔6131;垂直设置于所述第一侧板612远离所述第二横板613一端的第三横板614;以及垂直连接于所述第三横板614靠近所述第二横板613一侧的第二侧板615。所述第四条孔6131的设置,使得第一支架61可以与横杆4相对移动,进而调整安装在第一支架61上的幕墙支架63的前后位置。5 to 6 , the first bracket 61 includes: a first horizontal plate 611 with a through hole 6111 disposed thereon; a first side plate 612 vertically connected to one end of the first horizontal plate 611; parallel A fourth hole 6131 is provided on the second transverse plate 613 disposed below the first transverse plate 611 and connected to the side of the first side plate 612 close to the first transverse plate 611 ; A third horizontal plate 614 at one end of the first side plate 612 away from the second horizontal plate 613 ; and a second side plate 615 vertically connected to the side of the third horizontal plate 614 close to the second horizontal plate 613 . The setting of the fourth hole 6131 enables the first bracket 61 to move relative to the cross bar 4 , thereby adjusting the front and rear positions of the curtain wall bracket 63 installed on the first bracket 61 .

参照图5至图7所示,所述第二支架62包括:设置于所述第一横板611 上的第四横板621,其上设置有通过螺栓与所述通孔6111配合的第五条孔 6211;垂直连接于所述第四横板621远离所述第一支架61一侧的第三侧板 622。所述第五条孔6211的设置使得第二支架62可以与所述第一支架61 相对移动,在第一支架61位置的基础上,进一步的调整安装在第二支架62 上的幕墙支架63的前后位置。Referring to FIGS. 5 to 7 , the second bracket 62 includes: a fourth horizontal plate 621 disposed on the first horizontal plate 611 , and a fifth horizontal plate 621 , which is fitted with the through hole 6111 through bolts, is disposed on the fourth horizontal plate 621 . Bar hole 6211 ; vertically connected to the third side plate 622 on the side of the fourth horizontal plate 621 away from the first bracket 61 . The setting of the fifth hole 6211 enables the second bracket 62 to move relative to the first bracket 61. Based on the position of the first bracket 61, the curtain wall bracket 63 installed on the second bracket 62 can be further adjusted. front and rear position.

参照图8所示,所述幕墙支架63包括:第四侧板631;垂直连接于所述第四侧板631远离所述第一支架61一端的第五横板632,其上设置有第一螺纹孔6321;垂直连接于所述第五横板632靠近所述第四侧板631一侧且与所述第四侧板631平行的第五侧板633;末端向上斜置连接于所述第五侧板633远离所述第四侧板631一侧的卡接板634,其与竖直面成一定锐角;以及螺接于所述第一螺纹孔6321的调整螺栓635。所述幕墙板7上下边沿开设有斜置的安装槽71,其与所述卡接板634卡接配合,当安装槽71与卡接板634配合之后,通过强力粘合剂将幕墙挂件6固定在幕墙板7上。调整螺栓635抵接于所述第二侧板615或所述第三侧板622上,通过调节调整螺栓635,使得幕墙支架63与挂件6的相对高度发生变化,从而使得幕墙板7的安装高度发生变化。Referring to FIG. 8 , the curtain wall bracket 63 includes: a fourth side plate 631; Threaded hole 6321; vertically connected to the fifth lateral plate 632 close to the fourth side plate 631 and parallel to the fifth side plate 633; The clamping plate 634 on the side of the fifth side plate 633 away from the fourth side plate 631 forms a certain acute angle with the vertical plane; and the adjusting bolt 635 screwed to the first threaded hole 6321 . The upper and lower edges of the curtain wall panel 7 are provided with oblique installation grooves 71, which are engaged with the clamping plate 634. After the installation groove 71 is matched with the clamping plate 634, the curtain wall pendant 6 is fixed by a strong adhesive. on the curtain wall panel 7. The adjustment bolts 635 are in contact with the second side plate 615 or the third side plate 622. By adjusting the adjustment bolts 635, the relative height of the curtain wall bracket 63 and the pendant 6 changes, so that the installation height of the curtain wall plate 7 is changed. change.

其中,需要说明的是,所述第一支架61上的幕墙板7和所述第二支架 62上的幕墙板7不是同一块幕墙板7,所述第一支架61上的幕墙板7拼接在所述第二支架62上的幕墙板7的下方。Wherein, it should be noted that the curtain wall panel 7 on the first bracket 61 and the curtain wall panel 7 on the second bracket 62 are not the same curtain wall panel 7, and the curtain wall panel 7 on the first bracket 61 is spliced in Below the curtain wall panel 7 on the second bracket 62 .

所述卡接板634与竖直面形成的角度为10°~80°。本实施例中,所述卡接板634与竖直面形成的角度为35°。The angle formed by the clamping plate 634 and the vertical plane is 10°˜80°. In this embodiment, the angle formed between the snap plate 634 and the vertical plane is 35°.

本实施例提供的一种装配式幕墙的工作原理为:通过螺栓穿过定位件1 底板13的长腰孔131,先将定位件1定位在混凝土的表面上,所述定位件1的底面贴合在混凝土表面上。将两个对向设置的连接件2装配在所述定位件1的第一条孔111上,将竖杆3锁附在两侧的连接板上。通过角件5将若干个横杆4间隔固定在相邻的竖杆3上。由于横杆4上设置有条孔,使得安装在横杆4上的挂件6可以在横杆4上平移,进而调整第一支架61和第二支架62的整体位置,从而适配幕墙板7上的幕墙支架63的位置。随后将幕墙支架63安装在调整好位置的第一支架61和第二支架62上。通过调节调整螺栓635,实现幕墙板7的幕墙支架63完全与第一支架61和第二支架62接触,也可调节调整螺栓635,从而调整幕墙板7的装配位置。The working principle of a prefabricated curtain wall provided by this embodiment is as follows: the positioning member 1 is first positioned on the surface of the concrete through the long waist hole 131 of the bottom plate 13 of the positioning member 1 through bolts, and the bottom surface of the positioning member 1 is attached to the surface of the concrete. on the concrete surface. Assemble the two opposite connecting pieces 2 on the first hole 111 of the positioning piece 1 , and lock the vertical rods 3 on the connecting plates on both sides. Several horizontal bars 4 are fixed on the adjacent vertical bars 3 at intervals through the corner pieces 5 . Since the cross bar 4 is provided with a hole, the pendant 6 installed on the cross bar 4 can be translated on the cross bar 4, thereby adjusting the overall position of the first bracket 61 and the second bracket 62, so as to fit the curtain wall panel 7. the position of the curtain wall bracket 63. Then, the curtain wall brackets 63 are installed on the first brackets 61 and the second brackets 62 in the adjusted positions. By adjusting the adjusting bolts 635 , the curtain wall brackets 63 of the curtain wall panel 7 are completely in contact with the first bracket 61 and the second bracket 62 , and the adjusting bolts 635 can also be adjusted to adjust the assembly position of the curtain wall panel 7 .

实施例二Embodiment 2

参照图12所示,本实施例与实施例一的不同之处在于,所述定位件1 进一步包括间隔垂直连接于所述底板13远离所述侧板12一侧的定位柱16;所述底板13设置于所述侧板12下方。在建筑外墙的混凝土浇筑时,将定位件1预埋进混凝土墙面中,使得螺栓安装板11与混凝土表面平齐,所述定位柱16起到了固定的作用。Referring to FIG. 12 , the difference between this embodiment and the first embodiment is that the positioning member 1 further includes a positioning column 16 vertically connected to the side of the bottom plate 13 away from the side plate 12 at intervals; the bottom plate 13 is arranged below the side plate 12 . When the concrete of the building exterior wall is poured, the positioning member 1 is pre-buried in the concrete wall surface, so that the bolt mounting plate 11 is flush with the concrete surface, and the positioning column 16 plays a fixed role.

实施例三Embodiment 3

参照图13至图15所示,本实施例与实施例一的不同之处在于,所述挂件6进一步包括用于限制幕墙支架63移动的保险件64,其包括:设置于所述第五横板632上方的第六横板641,其上设置有与所述调整螺栓635配合的第二螺纹孔6411;垂直连接于所述第六横板641靠近所述第一支架61 一侧的第六侧板642;以及垂直连接于所述第六侧板642靠近所述第六横板 641一侧且平行于所述第六横板641的第七横板643,其设置于所述第三侧板622下方。所述保险件64固定在所述幕墙支架63上,随着幕墙支架63 的移动而移动,所述保险件64的设置使得幕墙支架63在套设进所述第一支架61和所述第二支架62的过程中,起到了限位保护的作用,且防止使用过程中的幕墙板7由于楼体晃动而发生脱落。Referring to FIGS. 13 to 15 , the difference between this embodiment and the first embodiment is that the pendant 6 further includes a safety member 64 for restricting the movement of the curtain wall bracket 63 , which includes: The sixth horizontal plate 641 above the plate 632 is provided with a second threaded hole 6411 which is matched with the adjusting bolt 635; side plate 642; and a seventh transverse plate 643 vertically connected to the sixth side plate 642 near the sixth transverse plate 641 and parallel to the sixth transverse plate 641, and disposed on the third side below plate 622. The safety piece 64 is fixed on the curtain wall bracket 63 and moves with the movement of the curtain wall bracket 63. The arrangement of the safety piece 64 makes the curtain wall bracket 63 sleeved into the first bracket 61 and the second During the process of the bracket 62, it plays a role of limit protection, and prevents the curtain wall panel 7 from falling off due to the shaking of the building during use.

以上所述仅为本实用新型的优选实施方式而已,并不用于限制本实用新型,对于本领域的技术人员来说,本实用新型可以有各种更改和变化。凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims (8)

1. An assembled curtain wall, comprising: positioning pieces are fixedly arranged at intervals;
the connecting piece is connected to the positioning piece through a bolt;
the vertical rod is connected to the connecting piece through a bolt;
a cross bar vertically fixed on the vertical bar through a corner piece; the hanging pieces are arranged on the cross rod at intervals and comprise third side plates; and the curtain wall plate is fixed on the hanging piece.
2. The fabricated curtain wall of claim 1 wherein the positioning member comprises:
the bolt mounting plate is provided with first holes at intervals; the side plates are respectively and vertically connected to two ends of the bolt mounting plate; and the bottom plates are respectively and vertically connected to one ends of the side plates, which are far away from the bolt mounting plate.
3. An assembled curtain wall as claimed in claim 2 wherein the connector comprises: the first connecting plate is provided with second holes matched with the first holes through bolts at intervals; and the second connecting plate is vertically connected to one end of the connecting piece, which is far away from the positioning piece, and third holes are formed in the second connecting plate at intervals.
4. The fabricated curtain wall of claim 1 wherein the hanging member comprises:
a first bracket; a second bracket connected to the first bracket by a bolt;
the curtain wall brackets are respectively sleeved on the first bracket and the second bracket and used for being fixed on the curtain wall plate.
5. The fabricated curtain wall of claim 4 wherein the first bracket comprises:
the first transverse plate is provided with a through hole;
the first side plate is vertically connected to one end of the first transverse plate; the second transverse plate is arranged below the first transverse plate in parallel and connected to one side of the first side plate close to the first transverse plate, and a fourth hole is formed in the second transverse plate;
the third transverse plate is vertically arranged at one end of the first side plate, which is far away from the second transverse plate; and the second side plate is vertically connected to one side of the third transverse plate close to the second transverse plate.
6. The fabricated curtain wall of claim 5 wherein the second bracket comprises:
the fourth transverse plate is arranged on the first transverse plate, and a fifth hole matched with the through hole through a bolt is formed in the fourth transverse plate;
and the third side plate is vertically connected to one side of the fourth transverse plate, which is far away from the first support.
7. The fabricated curtain wall of claim 4 wherein the curtain wall brackets comprise:
a fourth side plate;
a fifth transverse plate which is vertically connected with one end of the fourth side plate far away from the first bracket and is provided with a first threaded hole;
the fifth side plate is vertically connected to one side, close to the fourth side plate, of the fifth transverse plate and is parallel to the fourth side plate;
the tail end of the clamping plate is connected to one side of the fifth side plate, which is far away from the fourth side plate, in an upward inclined mode, and an acute angle is formed between the clamping plate and a vertical plane; and
and the adjusting bolt is screwed in the first threaded hole.
8. The curtain wall assembly of claim 7, wherein the hanger further comprises a safety for limiting movement of the curtain wall bracket, comprising:
the sixth transverse plate is arranged above the fifth transverse plate, and a second threaded hole matched with the adjusting bolt is formed in the sixth transverse plate;
the sixth side plate is vertically connected to one side, close to the first support, of the sixth transverse plate; and
and the seventh transverse plate is vertically connected to one side of the sixth side plate, close to the sixth transverse plate, is parallel to the sixth transverse plate and is arranged below the third side plate.
CN201922420183.3U 2019-12-28 2019-12-28 Assembled curtain wall Expired - Fee Related CN212026740U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922420183.3U CN212026740U (en) 2019-12-28 2019-12-28 Assembled curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922420183.3U CN212026740U (en) 2019-12-28 2019-12-28 Assembled curtain wall

Publications (1)

Publication Number Publication Date
CN212026740U true CN212026740U (en) 2020-11-27

Family

ID=73482670

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922420183.3U Expired - Fee Related CN212026740U (en) 2019-12-28 2019-12-28 Assembled curtain wall

Country Status (1)

Country Link
CN (1) CN212026740U (en)

Similar Documents

Publication Publication Date Title
KR101341438B1 (en) Curtainwall system
KR20130045711A (en) Indoor decorative curtain wall construction unit
CN108086571A (en) Receive side drop level furred ceiling
CN211523646U (en) Panel connector and hanging type partition wall applied to same
CN210459726U (en) Aluminum plate furred ceiling structure of preventing falling
CN211714329U (en) Light gauge steel gypsum board suspended ceiling structure
CN201762935U (en) Plate wall material dry-hanging device and its column
KR20070009265A (en) Interior wall panel installation structure using bracket fitting
CN212026740U (en) Assembled curtain wall
CN211774933U (en) A curtain wall installation pendant
CN211666039U (en) A curtain wall installation pendant
CN211499354U (en) A curtain wall installation pendant
CN115787896B (en) A connection structure for curtain wall units and its usage method
CN211666033U (en) Locating component for mounting curtain wall
US20240035277A1 (en) Connector bracket for non-rectangular grid
CN213062597U (en) Indoor furred ceiling is with convenient to detach's aluminium veneer mechanism
CN209891633U (en) An angle splicing profile
CN205476606U (en) Multi -functional scalable wallboard open -type cloakroom system
CN112832477B (en) An exterior wall concrete hanging board
CN109296119B (en) Unit type curtain wall connecting mechanism
CN211447412U (en) Connecting structure of cross beam and vertical beam of glass curtain wall
CN210459881U (en) Aluminum alloy decorative line system
TWM633485U (en) Building material board body connector
CN211714288U (en) A fast-installed curtain wall pendant
CN109914660B (en) Stone panel assembly installation structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201127

CF01 Termination of patent right due to non-payment of annual fee