CN212026223U - Steel pipe pile of communication tower - Google Patents

Steel pipe pile of communication tower Download PDF

Info

Publication number
CN212026223U
CN212026223U CN202020602351.0U CN202020602351U CN212026223U CN 212026223 U CN212026223 U CN 212026223U CN 202020602351 U CN202020602351 U CN 202020602351U CN 212026223 U CN212026223 U CN 212026223U
Authority
CN
China
Prior art keywords
pipe
installation
installation pipe
groups
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020602351.0U
Other languages
Chinese (zh)
Inventor
黄炜炜
郑家乐
邱峰
程思远
赵鹏辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Tianyu Engineering Technology Co ltd
Original Assignee
Henan Tianyu Engineering Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Tianyu Engineering Technology Co ltd filed Critical Henan Tianyu Engineering Technology Co ltd
Priority to CN202020602351.0U priority Critical patent/CN212026223U/en
Application granted granted Critical
Publication of CN212026223U publication Critical patent/CN212026223U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a communication tower steel-pipe pile, including first installation pipe, second installation pipe, supporting mechanism and coupling mechanism, first installation pipe and second installation pipe pass through coupling mechanism and connect, first installation socle end is provided with the mount pad, the mount pad sets up to hollow structure, the welding of mount pad top has four group's arc pieces, four group arc piece equidistance distributes around the mount pad top, mount pad top intercommunication has spacing pipe, first installation socle end embedding is in the gap that forms between spacing pipe and four group's arc pieces, first installation pipe respectively with spacing pipe and four group's arc piece laminating welding, mount pad bottom intercommunication has the toper pipe, all be provided with supporting mechanism in first installation pipe and the second installation pipe. This communication tower steel-pipe pile, simple structure, the different regions of being convenient for use.

Description

Steel pipe pile of communication tower
Technical Field
The utility model belongs to the technical field of the steel-pipe pile, concretely relates to communication tower steel-pipe pile.
Background
The communication iron tower is composed of a tower body, a platform, a lightning rod, a ladder stand, an antenna support and other steel components, is subjected to hot galvanizing corrosion prevention treatment, and is mainly used for transmission and emission of microwave, ultrashort wave and wireless network signals;
the existing communication tower needs to sink the tower body of the communication tower into a foundation when a station is built, and steel pipe piles with different lengths are needed according to the use of different regions, so that the use requirements of users cannot be met.
Therefore, in order to meet the current situation, the design and production of the steel pipe pile of the communication tower are urgently needed to meet the requirement of practical use.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a communication tower steel-pipe pile to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a communication tower steel-pipe pile, includes first installation pipe, second installation pipe, supporting mechanism and coupling mechanism, first installation pipe and second installation pipe pass through coupling mechanism and connect, first installation socle end is provided with the mount pad, the mount pad sets up to hollow structure, the welding of mount pad top has four groups of arc pieces, four groups the arc piece equidistance distributes around the mount pad top, mount pad top intercommunication has spacing pipe, first installation socle end embedding is in the gap that forms between spacing pipe and four groups of arc pieces, first installation pipe respectively with spacing pipe and four groups of arc piece laminating welding, mount pad bottom intercommunication has the toper pipe, all be provided with supporting mechanism in first installation pipe and the second installation pipe.
Preferably, supporting mechanism includes fixed block, connecting plate and backup pad, all be provided with the fixed block in first installation pipe and the second installation pipe, the welding of fixed block periphery equidistance has three group's connecting plates, the welding of all laminating of the inside lateral wall of first installation pipe and second installation pipe has three group's backup pads, three groups the backup pad respectively with three group's connecting plate fixed weld.
Preferably, the connecting mechanism comprises a fixed pipe, a round pipe, an installation block and a reinforcing rib, the fixed pipe is arranged between the first installation pipe and the second installation pipe in a laminating manner, the round pipe is arranged on the inner side of the fixed pipe, the round pipe and the fixed pipe are arranged into an integral structure, the outer wall of the round pipe is respectively arranged in a laminating manner with the inner wall of the first installation pipe and the inner wall of the second installation pipe, and the round pipe is connected with the first installation pipe and the second installation pipe through a plurality of groups of bolts;
the fixed pipe top has two sets of installation pieces through multiunit bolt symmetric connection, and is two sets of the vertical outer wall of installation piece is the fixed welding of second installation pipe both sides outer wall respectively, the welding has the strengthening rib on the installation piece inside wall.
Preferably, four groups of clamping grooves are equidistantly formed in the periphery of the conical pipe, and clamping plates are clamped in each group of clamping grooves.
The utility model discloses a technological effect and advantage: according to the communication iron tower steel pipe pile, the fixing pipe and the round pipe are of an integral structure through the arranged connecting mechanism, the fixing pipe is clamped between the first installation pipe and the second installation pipe through the round pipe and connected through the plurality of groups of bolts, and meanwhile the installation block is matched and connected with the fixing pipe and the second installation pipe, so that the overall length is increased, and the communication iron tower steel pipe pile is convenient to use in different regions; through the arranged supporting mechanism, the fixing block, the three groups of connecting plates and the three groups of supporting plates are matched and connected, so that the circumferential degrees of the first mounting pipe and the second mounting pipe are supported, and the compressive strength of the whole body is improved; the steel pipe pile is not easy to shake after being positioned by clamping the plurality of clamping plates with the conical pipe; this communication tower steel-pipe pile, simple structure, the different regions of being convenient for use.
Drawings
Fig. 1 is a front view of the present invention;
fig. 2 is a partial cross-sectional view of a first mounting tube of the present invention;
fig. 3 is a top view of a first mounting tube of the present invention;
fig. 4 is a schematic structural diagram of the mounting base of the present invention.
In the figure: 1 first installation pipe, 2 second installation pipes, 3 mount pads, 4 conical tubes, 5 cardboard, 6 supporting mechanism, 61 fixed block, 62 connecting plates, 63 backup pads, 7 arc piece, 8 spacing pipes, 9 fixed pipes, 10 pipe, 11 installation pieces, 12 strengthening ribs, 13 coupling mechanism.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Unless defined otherwise, all references to up, down, left, right, front, back, inner and outer directions herein are to be interpreted as referring to up, down, left, right, front, back, inner and outer directions in the drawings to which the invention is applied, and all references are hereby incorporated herein by reference.
The utility model provides a communication tower steel pipe pile as shown in figures 1-4, which comprises a first installation pipe 1, a second installation pipe 2, a supporting mechanism 6 and a connecting mechanism 13, wherein the first installation pipe 1 and the second installation pipe 2 are connected through the connecting mechanism 13, the bottom end of the first installation pipe 1 is provided with an installation seat 3, the installation seat 3 is arranged into a hollow structure, four groups of arc-shaped blocks 7 are welded at the top end of the installation seat 3, the four groups of arc-shaped blocks 7 are equidistantly distributed around the top end of the installation seat 3, the top end of the installation seat 3 is communicated with a limiting pipe 8, the bottom end of the first installation pipe 1 is embedded into a gap formed between the limiting pipe 8 and the four groups of arc-shaped blocks 7, the first installation pipe 1 is respectively jointed and welded with the limiting pipe 8 and the four groups of arc-shaped blocks 7, which is convenient for the independent transportation of the first installation pipe 1 and the installation seat 3, and is convenient for the bottom end of the, and supporting mechanisms 6 are arranged in the first mounting pipe 1 and the second mounting pipe 2.
Specifically, supporting mechanism 6 includes fixed block 61, connecting plate 62 and backup pad 63, all be provided with fixed block 61 in first installation pipe 1 and the second installation pipe 2, fixed block 61 periphery equidistance welding has three group's connecting plates 62, the inside lateral wall of first installation pipe 1 and second installation pipe 2 all laminating welding has three group's backup pads 63, three groups backup pad 63 respectively with three group's connecting plates 62 fixed weld.
Specifically, the connecting mechanism 13 comprises a fixed pipe 9, a circular pipe 10, an installation block 11 and a reinforcing rib 12, the fixed pipe 9 is arranged between the first installation pipe 1 and the second installation pipe 2 in a laminating mode, the circular pipe 10 is arranged on the inner side of the fixed pipe 9, the circular pipe 10 and the fixed pipe 9 are arranged into an integral structure, the outer wall of the circular pipe 10 is respectively arranged in a laminating mode with the inner walls of the first installation pipe 1 and the second installation pipe 2, and the circular pipe 10 is connected with the first installation pipe 1 and the second installation pipe 2 through a plurality of groups of bolts;
fixed 9 tops of tubes have two sets of installation pieces 11, two sets of through multiunit bolt symmetric connection the vertical outer wall of installation piece 11 is the fixed welding of 2 both sides outer walls of second installation pipe respectively, utilizes fixed 9 of tubes to establish between first installation pipe 1 and second installation pipe 2 through pipe 10 card to connect it through the multiunit bolt, utilize installation piece 11 and fixed 9 of tubes and second installation pipe 2 to cooperate simultaneously and be connected, thereby increase this whole length, make things convenient for different regions to use, the welding has strengthening rib 12 on the 11 inside walls of installation piece, and strengthening rib 12 has improved installation piece 11 self intensity.
Specifically, four groups of clamping grooves are equidistantly formed in the periphery of the conical pipe 4, clamping plates 5 are clamped in each group of clamping grooves, and the clamping plates 5 are clamped with the conical pipe 4 through multiple groups of clamping plates, so that the steel pipe pile is not prone to shaking after being positioned.
Working principle, this communication tower steel-pipe pile, when using, mediate this whole length according to user's different needs, because solid fixed tube 9 and pipe 10 structure as an organic whole, utilize solid fixed tube 9 to establish between first installation pipe 1 and second installation pipe 2 through pipe 10 card, and connect it through the multiunit bolt, utilize erection block 11 to cooperate with solid fixed tube 9 and second installation pipe 2 to be connected simultaneously, then descend the stake, at the in-process of descending the stake, utilize fixed block 61, three group's connecting plates 62 and three group's backup pad 63 cooperation are connected, thereby make the circumference of first installation pipe 1 and second installation pipe 2 obtain supporting, improve this holistic compressive strength, at last through multiunit cardboard 5 and 4 joints of toper pipe, thereby guarantee to be difficult for rocking after the steel-pipe pile location.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.

Claims (4)

1. The utility model provides a communication tower steel-pipe pile, includes first installation pipe (1), second installation pipe (2), supporting mechanism (6) and coupling mechanism (13), its characterized in that: the first installation pipe (1) and the second installation pipe (2) are connected through a connecting mechanism (13), the bottom end of the first mounting pipe (1) is provided with a mounting seat (3), the mounting seat (3) is of a hollow structure, four groups of arc-shaped blocks (7) are welded at the top end of the mounting seat (3), the four groups of arc-shaped blocks (7) are distributed around the top end of the mounting seat (3) at equal intervals, the top end of the mounting seat (3) is communicated with a limiting pipe (8), the bottom end of the first mounting pipe (1) is embedded in a gap formed between the limiting pipe (8) and the four groups of arc-shaped blocks (7), the first mounting pipe (1) is respectively jointed and welded with the limiting pipe (8) and the four groups of arc blocks (7), the bottom end of the mounting seat (3) is communicated with a conical pipe (4), and a supporting mechanism (6) is arranged in each of the first mounting pipe (1) and the second mounting pipe (2).
2. The steel pipe pile of communication tower according to claim 1, characterized in that: supporting mechanism (6) are including fixed block (61), connecting plate (62) and backup pad (63), all be provided with fixed block (61) in first installation pipe (1) and the second installation pipe (2), fixed block (61) periphery equidistance welding has three group's connecting plate (62), first installation pipe (1) and second installation pipe (2) inside lateral wall all laminate the welding have three group's backup pad (63), three groups backup pad (63) respectively with three group's connecting plate (62) fixed weld.
3. The steel pipe pile of communication tower according to claim 1, characterized in that: the connecting mechanism (13) comprises a fixed pipe (9), a round pipe (10), an installation block (11) and a reinforcing rib (12), the fixed pipe (9) is arranged between the first installation pipe (1) and the second installation pipe (2) in a laminating mode, the round pipe (10) is arranged on the inner side of the fixed pipe (9), the round pipe (10) and the fixed pipe (9) are arranged into an integral structure, the outer wall of the round pipe (10) is arranged in a laminating mode with the inner walls of the first installation pipe (1) and the second installation pipe (2) respectively, and the round pipe (10) is connected with the first installation pipe (1) and the second installation pipe (2) through a plurality of groups of bolts;
fixed pipe (9) top has two sets of installation pieces (11), two sets of through multiunit bolt symmetric connection the vertical outer wall of installation piece (11) is second installation pipe (2) both sides outer wall fixed weld respectively, the welding has strengthening rib (12) on installation piece (11) inside wall.
4. The steel pipe pile of communication tower according to claim 1, characterized in that: four groups of clamping grooves are formed in the periphery of the conical pipe (4) at equal intervals, and clamping plates (5) are clamped in each group of clamping grooves.
CN202020602351.0U 2020-04-21 2020-04-21 Steel pipe pile of communication tower Expired - Fee Related CN212026223U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020602351.0U CN212026223U (en) 2020-04-21 2020-04-21 Steel pipe pile of communication tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020602351.0U CN212026223U (en) 2020-04-21 2020-04-21 Steel pipe pile of communication tower

Publications (1)

Publication Number Publication Date
CN212026223U true CN212026223U (en) 2020-11-27

Family

ID=73494765

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020602351.0U Expired - Fee Related CN212026223U (en) 2020-04-21 2020-04-21 Steel pipe pile of communication tower

Country Status (1)

Country Link
CN (1) CN212026223U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863316A (en) * 2021-09-30 2021-12-31 中铁第四勘察设计院集团有限公司 Double-steel-pipe concrete support pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863316A (en) * 2021-09-30 2021-12-31 中铁第四勘察设计院集团有限公司 Double-steel-pipe concrete support pile

Similar Documents

Publication Publication Date Title
CN212026223U (en) Steel pipe pile of communication tower
CN110900077A (en) Fixing platform for welding flange
CN209094820U (en) A kind of offshore wind farm tubular pole girth joint General welding platform
CN216341141U (en) Newly-increased encircling type steel column reinforcing device for single-tube communication tower
CN214738211U (en) Anti-seismic building pile for building
CN215859065U (en) Full-system turnover ultrahigh large-diameter inclined reinforced concrete cylindrical support
CN210684442U (en) Buckling restrained brace for bridge
CN211523530U (en) Node connection structure
CN215279280U (en) Pressure steel pipe mouth of pipe circumferential weld seam pressing device
CN211548280U (en) Light and stable mounting structure for curtain wall
CN211342038U (en) Communication tower base fixed equipment
CN106549628A (en) Solar tile and solar tile system
CN210317349U (en) A prevention of seepage water structure for colliery fault
CN212224426U (en) Pressure-resistant and pressure-resistant steel column structure
CN213898125U (en) Assembled auxiliary supporting structure
CN206306105U (en) A kind of novel portable support for depositing lightweight section bar
CN217678629U (en) Leaning tower stull base and leaning tower stull
CN215716087U (en) Bracing built-up connection structure for rack
CN218522208U (en) Novel support body bridging node
CN211974557U (en) Three-column steel pipe tower
CN212258365U (en) Hexagonal circular combined communication pipe with high compressive strength
CN213742160U (en) Scaffold for engineering
CN211924644U (en) Net-shaped connecting piece of sand pressing mechanism of building sand washer
CN219732853U (en) Protective structure
CN210967668U (en) Fixing platform for welding flange

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201127

CF01 Termination of patent right due to non-payment of annual fee