CN212002429U - Building crack repair equipment - Google Patents

Building crack repair equipment Download PDF

Info

Publication number
CN212002429U
CN212002429U CN202020527120.8U CN202020527120U CN212002429U CN 212002429 U CN212002429 U CN 212002429U CN 202020527120 U CN202020527120 U CN 202020527120U CN 212002429 U CN212002429 U CN 212002429U
Authority
CN
China
Prior art keywords
vibration
box
vibrating
box body
rack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020527120.8U
Other languages
Chinese (zh)
Inventor
周盛光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Huakun Construction Group Co ltd
Original Assignee
Guangdong Huakun Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Huakun Construction Group Co ltd filed Critical Guangdong Huakun Construction Group Co ltd
Priority to CN202020527120.8U priority Critical patent/CN212002429U/en
Application granted granted Critical
Publication of CN212002429U publication Critical patent/CN212002429U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • Processing Of Stones Or Stones Resemblance Materials (AREA)

Abstract

The utility model provides a building crack repair equipment, including workbin, feed pump, groover, percussion drill, vibration discharging head and at least one vibrating device, the feed inlet of feed pump with the discharge gate of workbin is through first pipeline intercommunication, be equipped with the ooff valve on the first pipeline, the vibration discharging head includes first box, runs through the insert tube of first box, the discharge gate of feed pump with the one end of insert tube is through the hose intercommunication, first box internally mounted has a vibrating motor, the vibrations that first vibrating motor produced are through the drive of insert tube; the vibration device comprises a second box body and a rod body penetrating through the second box body, a second vibration motor is arranged in the second box body, and vibration generated by the second vibration motor is transmitted through the rod body; the filling material can flow in an acceleration way through vibration, so that the filling material can better permeate into gaps, and the repairing quality is improved.

Description

Building crack repair equipment
Technical Field
The utility model relates to a crack repair field, more specifically relates to a building crack repair equipment.
Background
With the continuous development of economic society of China and the continuous improvement of the living standard of people, the development of infrastructure is high, and particularly civil engineering is rapidly developed. In civil engineering and construction, concrete structures still dominate, and whatever the concrete structure is, cracks occur to various degrees for that reason. The crack generation will certainly destroy the building structure, so the crack problem of civil building concrete structure is receiving more and more attention.
The concrete structure is usually inevitably cracked in engineering application due to the large brittleness, and the cracking causes the water tightness reduction and leakage of the concrete structure, influences the service life of the engineering, and even can not be normally used, which is a common problem outside the building; most of the existing repairing modes are directly filled with repairing materials into gaps, but the repairing mode often cannot fill deep gaps better, and the repairing result is not ideal enough.
SUMMERY OF THE UTILITY MODEL
In order to overcome the defects of the prior art, the utility model aims to solve the technical problem of providing a building crack repair equipment, its accessible vibration is mobile and is made the better infiltration gap of filler material with higher speed, improves the repair quality.
To achieve the purpose, the utility model adopts the following technical proposal:
the utility model provides a building crack repair equipment, including workbin, feed pump, groover, percussion drill, vibration discharging head and at least one vibrating device, the feed inlet of feed pump with the discharge gate of workbin is through first pipeline intercommunication, be equipped with the ooff valve on the first pipeline, the vibration discharging head includes first box, runs through the insert tube of first box, the discharge gate of feed pump with the one end of insert tube is through the hose intercommunication, first box internally mounted has a vibrating motor, the vibrations that first vibrating motor produced are through the drive of insert tube; the vibrating device comprises a second box body and a rod body penetrating through the second box body, a second vibrating motor is arranged inside the second box body, and vibration generated by the second vibrating motor is transmitted through the rod body.
In the preferred technical solution of the present invention, a first rack is installed in the first box, the first rack includes a bottom plate and two oppositely disposed frame plates symmetrically disposed on one side of the bottom plate, each frame plate is provided with a threaded hole, the outer wall of the insert tube is provided with threads, the insert tube is in threaded connection with the threaded hole, and the first vibration motor is installed on the bottom plate; the side wall of the top end of the insertion pipe is provided with a first nut sleeve, and the hose is connected with the insertion pipe through a movable joint.
The utility model discloses in the technical scheme of preferred, install the second rack in the second box, the second rack with first rack structure is the same, the outer wall of the body of rod is equipped with the screw thread, the body of rod with the screw hole threaded connection cooperation of second rack, second vibrating motor installs on the second rack, the fixed second nut cover that is equipped with in top of the body of rod.
In the preferred technical scheme of the utility model, the material box and the material feeding pump are both arranged on the top surface of the cart, and the bottom of the cart is provided with universal wheels with self-locking function; the top surface of shallow installs the supporter, the groover the percussion drill the vibration stub bar reaches vibrating device all places on the supporter.
The utility model has the advantages that:
the utility model provides a building crack repair equipment, workbin, feed pump, groover, percussion drill, vibration play stub bar and vibrating device have been assembled and satisfied the required equipment in the whole repair work progress, are convenient for carry and construct; the vibrating discharge head can always keep vibrating in the feeding process, so that the discharge and the diffusion of materials are accelerated; and the setting of a plurality of vibrating devices can be better enlarge holistic vibration scope to make better flow of material, make things convenient for during the better infiltration gap of filling material, improve and repair the quality.
Drawings
Fig. 1 is a schematic structural diagram of a building crack repairing apparatus according to an embodiment of the present invention;
fig. 2 is a schematic view of an expanded structure of a crack repairing apparatus for a building according to an embodiment of the present invention;
fig. 3 is a schematic structural view of a vibrating discharge head provided in an embodiment of the present invention;
fig. 4 is a schematic structural diagram of a vibration device provided in an embodiment of the present invention.
In the figure:
100. a material box; 200. a feed pump; 210. a hose; 220. a movable joint; 300. a grooving machine; 400. percussion drilling; 500. vibrating the discharging head; 510. a first case; 520. an insertion tube; 521. a first nut sleeve; 530. a first vibration motor; 540. a first placing rack; 541. a base plate; 542. a frame plate; 600. a vibrating device; 610. a second case; 620. a rod body; 621. a second nut sleeve; 630. a second vibration motor; 640. a second rack; 710. an on-off valve; 800. pushing a cart; 810. a universal wheel; 820. a rack; 900. and a controller.
Detailed Description
The technical solution of the present invention is further explained by the following embodiments with reference to the accompanying drawings.
As shown in fig. 1 to 4, in an embodiment of the present invention, a building crack repairing apparatus is disclosed, including a material box 100, a feeding pump 200, a grooving machine 300, a percussion drill 400, a vibration discharging head 500 and at least one vibration device 600, a feeding port of the feeding pump 200 is communicated with a discharging port of the material box 100 through a first pipeline, the first pipeline is provided with a switch valve 710, the vibration discharging head 500 includes a first box 510 and an insertion tube 520 penetrating through the first box 510, the discharging port of the feeding pump 200 is communicated with one end of the insertion tube 520 through a hose 210, a first vibration motor 530 is installed inside the first box 510, and vibration generated by the first vibration motor 530 is transmitted through the insertion tube 520; the vibration device 600 includes a second box 610 and a rod 620 penetrating through the second box 610, a second vibration motor 630 is installed inside the second box 610, and vibration generated by the second vibration motor 630 is transmitted through the rod 620; the controller 900 is installed on the side wall of the material box 100, the feeding pump 200, the grooving machine 300, the impact drill 400, the first vibration motor 530 and the second vibration motor 630 are all electrically connected with the controller 900, and the controller 900 is connected with an external power supply.
The building crack repairing equipment comprises the material box 100, the feeding pump 200, the grooving machine 300, the impact drill 400, the vibration discharging head 500 and the vibration device 600, and integrates the equipment required in the whole repairing construction process, so that the equipment is convenient to carry and construct; the vibrating discharge head 500 can always keep vibrating in the feeding process, so that the discharge and the diffusion of materials are accelerated; and the setting of a plurality of vibrating device 600, holistic vibration range can be better enlarged to make better flow of material, make things convenient for during the better infiltration gap of filling material, improve and repair the quality.
More specifically, during construction, firstly, a grooving machine 300 is used for grooving along a crack, and ash removal treatment is carried out; the constructor selects the drilling point of the crack according to the trend of the crack, selects the higher position point of the crack and marks the higher position point; drilling the marked position by using a percussion drill 400; then, the inserting pipe 520 of the vibrating discharge head 500 is extended into the drill hole at the highest position, and the rod body 620 of the vibrating device 600 is inserted into the rest drill holes in an interval distribution mode; then, the switching valve 710 is opened, the first vibrator 530, the second vibrator 630 and the supply pump 200 are started, the slurry enters the insert pipe 520 along with the flexible pipe 210 and is injected into the crack, and the slurry flows along the crack along with vibration, thereby being filled; after a period of filling, the positions of the vibrating discharging head 500 and the vibrating device 600 are changed, and the number of the vibrating devices 600 is reduced; after the filling of the position is completed, the number of the vibrating devices 600 is further reduced, and the position of the vibrating discharging head 500 is replaced again; repeatedly replacing the position of the vibrating discharge head 500 and reducing the number of the vibrating devices 600 until the number of the vibrating devices 600 is less than 20% of the total number; taking out all the rest of the vibrating devices 600, and filling the rest of the drill holes by using the vibrating discharge head 500; and finally, filling and repairing the slots to finish the whole repair, wherein if 20% of the total number of the used vibration devices is not an integer, the whole is rounded up in a rounding mode.
Further, as shown in fig. 3, a first placing frame 540 is installed in the first box 510, the first placing frame 540 includes a bottom plate 541 and two frame plates 542 symmetrically arranged on one side of the bottom plate 541 and opposite to each other, each frame plate 542 is provided with a threaded hole, the outer wall of the insert tube 520 is provided with threads, the insert tube 520 is in threaded connection and matching with the threaded hole, and the first vibration motor 530 is installed on the bottom plate 541; the side wall of the top end of the insertion pipe 520 is provided with a first nut sleeve 521, and the hose 210 is connected with the insertion pipe 520 through a movable joint 220; the structural design can ensure that the first vibration motor 530 provides vibration for the insertion tube 520, and the adjustment of the extension length can be realized by rotating the insertion tube 520, so as to meet the depth requirement of drilling and facilitate installation; and the movable joint 220 is designed not to affect the normal rotation of the insertion tube 520 under the condition that the insertion tube 520 is kept communicated with the hose 210.
Further, as shown in fig. 4, a second rack 640 is installed in the second box 610, the second rack 640 has the same structure as the first rack 540, the outer wall of the rod 620 is provided with a thread, the rod 620 is in threaded connection and matching with the threaded hole of the second rack 640, the second vibration motor 630 is installed on the second rack 640, and a second nut sleeve 621 is fixedly installed at the top end of the rod 620; this structural design can ensure that second vibrating motor 630 provides the vibration for body of rod 620, and the accessible rotates body of rod 620 and realizes the adjustment of protrusion length to satisfy the degree of depth requirement of drilling, be convenient for install.
Further, the material box 100 and the feeding pump 200 are both mounted on the top surface of the cart 800, and the bottom of the cart 800 is provided with a universal wheel 810 with a self-locking function; a rack 820 is installed on the top surface of the cart 800, and the grooving machine 300, the impact drill 400, the vibrating discharge head 500 and the vibrating device 600 are all placed on the rack 820; the structural design facilitates the carrying and moving of all equipment, provides various equipment required by repair construction, and is convenient to operate.
While the invention has been described with reference to a preferred embodiment, it will be understood by those skilled in the art that various changes may be made and equivalents may be substituted for elements thereof without departing from the spirit and scope of the invention. The present invention is not to be limited by the specific embodiments disclosed herein, and other embodiments that fall within the scope of the claims of the present application are intended to be within the scope of the present invention.

Claims (4)

1. The utility model provides a building crack repair equipment which characterized in that:
the feeding device comprises a material box (100), a feeding pump (200), a grooving machine (300), a percussion drill (400), a vibration discharging head (500) and at least one vibration device (600), wherein a feeding hole of the feeding pump (200) is communicated with a discharging hole of the material box (100) through a first pipeline, a switch valve (710) is arranged on the first pipeline, the vibration discharging head (500) comprises a first box body (510) and an insertion pipe (520) penetrating through the first box body (510), the discharging hole of the feeding pump (200) is communicated with one end of the insertion pipe (520) through a hose (210), a first vibration motor (530) is arranged inside the first box body (510), and vibration generated by the first vibration motor (530) is transmitted through the insertion pipe (520);
the vibrating device (600) comprises a second box body (610) and a rod body (620) penetrating through the second box body (610), a second vibrating motor (630) is arranged inside the second box body (610), and vibration generated by the second vibrating motor (630) is transmitted through the rod body (620).
2. The apparatus for repairing construction cracks as claimed in claim 1, wherein:
a first placing frame (540) is installed in the first box body (510), the first placing frame (540) comprises a bottom plate (541) and two oppositely arranged frame plates (542) symmetrically arranged on one side of the bottom plate (541), each frame plate (542) is provided with a threaded hole, the outer wall of the inserting pipe (520) is provided with threads, the inserting pipe (520) is in threaded connection and matching with the threaded holes, and the first vibration motor (530) is installed on the bottom plate (541); the side wall of the top end of the insertion pipe (520) is provided with a first nut sleeve (521), and the hose (210) is connected with the insertion pipe (520) through a movable joint (220).
3. The apparatus for repairing construction cracks as claimed in claim 2, wherein:
install second rack (640) in second box (610), second rack (640) with first rack (540) structure is the same, the outer wall of the body of rod (620) is equipped with the screw thread, the body of rod (620) with the screw hole threaded connection cooperation of second rack (640), install second vibrating motor (630) on second rack (640), the fixed second nut cover (621) that is equipped with in top of the body of rod (620).
4. The apparatus for repairing construction cracks as claimed in claim 1, wherein:
the feed box (100) and the feed pump (200) are both arranged on the top surface of the trolley (800), and the bottom of the trolley (800) is provided with a universal wheel (810) with a self-locking function; an article shelf (820) is installed on the top surface of the cart (800), and the grooving machine (300), the impact drill (400), the vibrating discharge head (500) and the vibrating device (600) are all placed on the article shelf (820).
CN202020527120.8U 2020-04-10 2020-04-10 Building crack repair equipment Active CN212002429U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020527120.8U CN212002429U (en) 2020-04-10 2020-04-10 Building crack repair equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020527120.8U CN212002429U (en) 2020-04-10 2020-04-10 Building crack repair equipment

Publications (1)

Publication Number Publication Date
CN212002429U true CN212002429U (en) 2020-11-24

Family

ID=73414723

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020527120.8U Active CN212002429U (en) 2020-04-10 2020-04-10 Building crack repair equipment

Country Status (1)

Country Link
CN (1) CN212002429U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364797A (en) * 2020-04-10 2020-07-03 广东华坤建设集团有限公司 Building crack repairing equipment and using method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364797A (en) * 2020-04-10 2020-07-03 广东华坤建设集团有限公司 Building crack repairing equipment and using method thereof

Similar Documents

Publication Publication Date Title
CN213267890U (en) Foundation engineering slip casting device
CN212002429U (en) Building crack repair equipment
CN106738316A (en) A kind of manufacture of cement efficiency material mixing arrangement
CN110056361B (en) Reinforcing method for shield access hole of ultra-deep stratum
CN111364797A (en) Building crack repairing equipment and using method thereof
CN110761279A (en) Construction method and construction device for air-hardening cement mixing pile
CN112982387A (en) High-pressure grouting device for cement mixing pile construction
CN101403256A (en) Grouting apparatus and method for stand steel pipe
CN110952523A (en) Compaction vibration system of high-rise building foundation
CN213174829U (en) But angle regulation concrete vibrating device
CN211250758U (en) Concrete mixing device convenient to remove
CN211735367U (en) Construction device for air-hardening cement soil mixing pile
CN209989776U (en) Concrete slab cement caulking machine for water conservancy channel
CN113235379A (en) Concrete road surface construction patching device
CN209649115U (en) A kind of architectural engineering high-efficiency stirring concrete apparatus
CN215595472U (en) Bundling perfusion down-the-hole hammer drill
CN206720369U (en) Combined type blanking device
CN111255240A (en) Concrete pouring method for large-gradient inclined plane
CN220619739U (en) Grouting device for repairing concrete pavement
CN210086169U (en) Dry mortar joint filling device
CN212795395U (en) Building engineering construction material mixing arrangement
CN111997650A (en) A grouting device for high-efficient slip casting in mine tunnel
CN212978771U (en) Civil engineering construction compounding feeding device
CN220451491U (en) Injection device for filling concrete cracks
CN117888738B (en) Grouting device for engineering construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant