CN212002130U - Multi-upright-rod type scaffold for building construction - Google Patents

Multi-upright-rod type scaffold for building construction Download PDF

Info

Publication number
CN212002130U
CN212002130U CN202020474898.7U CN202020474898U CN212002130U CN 212002130 U CN212002130 U CN 212002130U CN 202020474898 U CN202020474898 U CN 202020474898U CN 212002130 U CN212002130 U CN 212002130U
Authority
CN
China
Prior art keywords
connecting piece
connector
scaffold
rod
building construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020474898.7U
Other languages
Chinese (zh)
Inventor
胡学军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yichang Boxin Construction Co Ltd
Original Assignee
Yichang Boxin Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yichang Boxin Construction Co Ltd filed Critical Yichang Boxin Construction Co Ltd
Priority to CN202020474898.7U priority Critical patent/CN212002130U/en
Application granted granted Critical
Publication of CN212002130U publication Critical patent/CN212002130U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a multi-vertical rod type scaffold for building construction, which comprises a connecting piece, a cross rod and a vertical rod, wherein the vertical rod is arranged at the top and the bottom of the connecting piece, the outer side of the connecting piece is provided with a connector, the inner side of the connector is provided with an internal thread, the top and the bottom of the connector are provided with through holes, the number of the connectors is 4, both ends of the cross rod are provided with a thread and a through hole, both ends of the cross rod are arranged inside the connector through threads, the outer side of the connecting piece of the multi-vertical rod type scaffold for building construction is provided with a connector, the cross rod is arranged in the connector through the thread, the connector is provided with a through hole, a fixed plate is arranged at the top of the connecting piece through a screw rod, the stability of the scaffold is increased, increasing the supporting force of the ground to the scaffold.

Description

Multi-upright-rod type scaffold for building construction
Technical Field
The utility model relates to a many building construction technical field specifically is a many pole setting formula scaffold frame for construction.
Background
The scaffold is used as a common tool for building construction, the basic form of the scaffold is single-row or double-row, the single-row scaffold is only provided with a row of upright rods at the outer side of the scaffold, one end of a transverse degree rod of the single-row scaffold is connected with a longitudinal degree rod in a penetrating way, the other end of the transverse degree rod is laid on a wall, the single-row scaffold is economical in materials, but the single-row scaffold is poor in stability and provided with hands and eyes on the wall, and the erection height and the utilization range of the single-; double pole scaffold all is equipped with the pole setting in the inboard of scaffold frame outside, stability is good, but take a lot of work and take the material than single scaffold frame, the mount of ordinary many pole setting formula scaffold frame is the welding mostly on the montant, pass through the fixed plate with other horizontal poles when using and connect fixedly, the long-time use of scaffold frame and the corrosion of rainwater or production are not up to standard, the fixed plate drops easily, cause the incident, and the base adoption of scaffold frame is directly placed subaerial or is put on the backing plate, the scaffold frame is unsettled easily, stability reduces.
Therefore, the utility model provides a construction is with many pole setting formula scaffold frame.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a not enough to prior art exists, the utility model aims at providing a many pole setting formula scaffold frame for construction to solve the problem that proposes in the above-mentioned background art, the utility model discloses a connecting piece outside is provided with the connector, passes through the horizontal pole and threaded mounting in the connector, is provided with the through-hole on the connector, and the fixed plate passes through the screw rod to be installed at the top of connecting piece, increases the stability of this scaffold frame, and can alleviate rainwater erosion, and the fixed plate is installed in the bottom of connecting piece, can regard as the base, increases the holding power of ground in the face of this scaffold frame.
In order to achieve the above purpose, the present invention is realized by the following technical solution: the utility model provides a construction is with many pole setting formula scaffold, includes connecting piece, horizontal pole and montant, the montant is all installed to the top and the bottom of connecting piece, the outside of connecting piece is provided with the connector, the inboard of connector is provided with the internal thread, the top and the bottom of connector are provided with the through-hole, the quantity of connector is 4, the both ends of horizontal pole all are provided with screw thread and through-hole, the both ends of horizontal pole are passed through the screw thread and are installed inside the connector, the fixed plate is installed at the top of connecting piece, one side of fixed plate is provided with the screw rod, be provided with the screw on the.
As a preferred embodiment of the present invention, the top and the bottom of the connecting member are both provided with external threads.
As a preferred embodiment of the present invention, the nut is installed at one end of the screw, and the number of the screws is 4.
As a preferred embodiment of the present invention, the fixing plate is provided with a screw hole, and the screw hole and the external thread have the same diameter.
As a preferred embodiment of the present invention, the vertical rod is screwed to the top and bottom of the connecting member through a screw.
The utility model has the advantages that: this use novel many pole setting formula scaffold's for construction connecting piece outside is provided with the connector, passes through the screw thread with the horizontal pole and installs in the connector, is provided with the through-hole on the connector, and the fixed plate passes through the screw rod and installs at the top of connecting piece, increases the stability of this scaffold to can alleviate rainwater erosion, the fixed plate is installed in the bottom of connecting piece, can regard as the base, increases the holding power of ground to this scaffold.
Drawings
FIG. 1 is a structural diagram of a multi-upright-rod scaffold for building construction;
FIG. 2 is a cross-sectional view of the multi-upright-rod scaffold for building construction of the present invention;
FIG. 3 is a structural view of the outer tube of the multi-vertical-rod scaffold for building construction;
FIG. 4 is a structural view of the inner tube of the multi-vertical-rod scaffold for building construction;
in the figure: 1-connecting piece, 2-fixing plate, 3-cross bar, 4-vertical bar, 5-connector, 6-internal thread, 7-screw rod, 8-nut, 9-external thread, 10-through hole and 11-screw hole.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
Referring to fig. 1 to 4, the present invention provides a technical solution: the utility model provides a construction is with many pole setting formula scaffold, includes connecting piece 1, horizontal pole 3 and montant 4, montant 4 is all installed to the top and the bottom of connecting piece 1, the outside of connecting piece 1 is provided with connector 5, the inboard of connector 5 is provided with internal thread 6, the top and the bottom of connector 5 are provided with through-hole 10, the quantity of connector 5 is 4, the both ends of horizontal pole 3 all are provided with screw thread and through-hole 10, threaded mounting is passed through at the both ends of horizontal pole 3 inside connector 5, fixed plate 2 is installed at the top of connecting piece 1, one side of fixed plate 2 is provided with screw rod 7, be provided with screw 11 on the fixed plate 2.
As a preferred embodiment of the utility model, the top and the bottom of connecting piece 1 all are provided with external screw thread 9, and the stability of this scaffold frame is improved to the convenient installation of fixed plate 2.
As a preferred embodiment of the utility model, nut 8 is installed to the one end of screw rod 7, the quantity of screw rod 7 is 4, conveniently fixes connecting piece 1 and horizontal pole 3 through screw rod 7, improves the stability of scaffold frame.
As a preferred embodiment of the present invention, the fixing plate 2 is provided with a screw hole 11, the screw hole 11 and the external thread 9 have the same diameter, so that the fixing plate 2 is conveniently installed at the top or the bottom of the connecting member 1.
As a preferred embodiment of the present invention, the vertical rod 4 is screwed on the top and bottom of the connecting member 1 through a screw, so that the stability of the scaffold can be increased.
The working principle is as follows: when the multi-upright-rod type scaffold for building construction is used, a cross rod 3 is arranged inside a connector 5 through an internal thread 6, a fixing plate 2 is arranged at the bottom of a first connecting piece 1 through an external thread 9, a screw rod 7 penetrates through a through hole 10, a nut 8 is arranged at the top of the screw rod 7 to fix the first connecting piece 1 and the cross rod 3, the first connecting piece 1 is placed on the ground, a vertical rod 4 is arranged at the top of the connecting piece 1, a second connecting piece 1 is arranged at the top of the vertical rod 3, the cross rods 3 are sequentially arranged in the connector 5 of the second connecting piece 1, the fixing plate 2 is arranged at the top of the second connecting piece 1 through the external thread 9, the screw rod 7 penetrates through the through hole 10 and fixes the second connecting piece 1 and the cross rods 3, scaffolds with different heights are built according to the steps, the connector 5 is arranged outside the, install horizontal pole 3 in connector 5 through internal thread 6, be provided with through-hole 10 on connector 5, fixed plate 2 passes through external thread 9 and installs the top at connecting piece 1, and screw rod 7 passes through-hole 10, increases the stability of this scaffold frame to can alleviate rain erosion, fixed plate 2 is installed in the bottom of connecting piece 1, can regard as the base, increases the holding power of ground to this scaffold frame.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (5)

1. The utility model provides a construction is with many pole setting formula scaffold, includes connecting piece (1), horizontal pole (3) and montant (4), its characterized in that, montant (4) are all installed to the top and the bottom of connecting piece (1), the outside of connecting piece (1) is provided with connector (5), the inboard of connector (5) is provided with internal thread (6), the top and the bottom of connector (5) are provided with through-hole (10), the quantity of connector (5) is 4, the both ends of horizontal pole (3) all are provided with screw thread and through-hole (10), the both ends of horizontal pole (3) are passed through the threaded mounting and are inside connector (5), fixed plate (2) are installed at the top of connecting piece (1), one side of fixed plate (2) is provided with screw rod (7).
2. The multi-upright-rod scaffold for building construction according to claim 1, wherein: the top and the bottom of the connecting piece (1) are both provided with external threads (9).
3. The multi-upright-rod scaffold for building construction according to claim 1, wherein: and nuts (8) are installed at one ends of the screw rods (7), and the number of the screw rods (7) is 4.
4. The multi-upright-rod scaffold for building construction according to claim 2, wherein: the fixing plate (2) is provided with a screw hole (11), and the diameter of the screw hole (11) is the same as that of the external thread (9).
5. The multi-upright-rod scaffold for building construction according to claim 1, wherein: the vertical rod (4) is screwed at the top and the bottom of the connecting piece (1) through threads.
CN202020474898.7U 2020-04-03 2020-04-03 Multi-upright-rod type scaffold for building construction Expired - Fee Related CN212002130U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020474898.7U CN212002130U (en) 2020-04-03 2020-04-03 Multi-upright-rod type scaffold for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020474898.7U CN212002130U (en) 2020-04-03 2020-04-03 Multi-upright-rod type scaffold for building construction

Publications (1)

Publication Number Publication Date
CN212002130U true CN212002130U (en) 2020-11-24

Family

ID=73403674

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020474898.7U Expired - Fee Related CN212002130U (en) 2020-04-03 2020-04-03 Multi-upright-rod type scaffold for building construction

Country Status (1)

Country Link
CN (1) CN212002130U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114046036A (en) * 2021-09-18 2022-02-15 湖南惠利建设工程有限公司 Scaffold device for construction
CN115059666A (en) * 2022-06-13 2022-09-16 保利长大工程有限公司 Connection structure and construction support for engineering construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114046036A (en) * 2021-09-18 2022-02-15 湖南惠利建设工程有限公司 Scaffold device for construction
CN115059666A (en) * 2022-06-13 2022-09-16 保利长大工程有限公司 Connection structure and construction support for engineering construction

Similar Documents

Publication Publication Date Title
CN212002130U (en) Multi-upright-rod type scaffold for building construction
CN201865195U (en) Novel movable board house
CN212153855U (en) Building curtain wall structure
CN211114981U (en) Assembled residential type sunlight room
CN209261320U (en) A kind of novel power transmission bird repellent electric pole
CN212104719U (en) Glass curtain wall connecting structure
CN220059125U (en) Awning rod
CN212201556U (en) Prefabricated fender that encloses of assembled
CN218375756U (en) Good and rail that can use night of stability
CN210092316U (en) Be used for fixed wire pole of radio station GPS basic station antenna
CN216042031U (en) Pull rod formula aluminium package steel construction large-span glass curtain wall
CN217847404U (en) Wind-resistant billboard for high-rise building
CN218019132U (en) Electrochemical anode device
CN218064679U (en) Wind-resistant solar street lamp
CN215519815U (en) Wind-resistant scaffold for building construction
CN218375659U (en) Assembled pylon
CN218815505U (en) Landscape garden is with long corridor of resing convenient to installation
CN216475751U (en) Cavity building module system with trip is fixed
CN209891517U (en) Factory building ceiling structure
CN214005993U (en) Modularization cold-formed thin-walled steel integrated house convenient to equipment
CN208633611U (en) A kind of light steel shading mill construction
CN214941433U (en) Connecting structure of corner connector and upright post of curtain wall embedded part
CN214091338U (en) Combined building safety enclosure
CN220822946U (en) Photovoltaic support pretreatment equipment
CN219409017U (en) Tower crane attaches wall device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201124

Termination date: 20210403

CF01 Termination of patent right due to non-payment of annual fee