CN211987537U - Pipeline convenient to assemble and install for waste gas treatment - Google Patents

Pipeline convenient to assemble and install for waste gas treatment Download PDF

Info

Publication number
CN211987537U
CN211987537U CN202020005697.2U CN202020005697U CN211987537U CN 211987537 U CN211987537 U CN 211987537U CN 202020005697 U CN202020005697 U CN 202020005697U CN 211987537 U CN211987537 U CN 211987537U
Authority
CN
China
Prior art keywords
wall
fixedly connected
gas treatment
mounting
processing pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020005697.2U
Other languages
Chinese (zh)
Inventor
陆永芬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Xinzhishuo Environmental Protection Engineering Co ltd
Original Assignee
Hangzhou Yuhang Environmental Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Yuhang Environmental Engineering Co ltd filed Critical Hangzhou Yuhang Environmental Engineering Co ltd
Priority to CN202020005697.2U priority Critical patent/CN211987537U/en
Application granted granted Critical
Publication of CN211987537U publication Critical patent/CN211987537U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model relates to a waste gas treatment technical field just discloses a waste gas treatment is with pipeline convenient to aggregate erection, including first processing pipe, the outer wall fixedly connected with fixed plate of first processing pipe, one side swing joint of fixed plate has fixing bolt, the spread groove has been seted up to the inner wall of first processing pipe, the inner wall swing joint of first processing pipe has the sealing washer, the inner wall fixedly connected with second processing pipe of sealing washer, the mounting groove has been seted up to the outer wall of second processing pipe, the first blotter of inner wall fixedly connected with of mounting groove. This exhaust-gas treatment is with pipeline convenient to aggregate erection can reach the purpose of the aggregate erection of being convenient for, has solved the problem that general pipeline erection is inefficient for exhaust-gas treatment for the staff can be rapid handle the pipe with first and the second and assemble, thereby has promoted staff's work efficiency, thereby has brought the facility for staff's use.

Description

Pipeline convenient to assemble and install for waste gas treatment
Technical Field
The utility model relates to an exhaust-gas treatment technical field specifically is a pipeline of being convenient for aggregate erection for exhaust-gas treatment.
Background
The waste gas purification mainly refers to the treatment work of industrial waste gas such as dust particles, smoke and dust, peculiar smell gas and toxic and harmful gas generated in industrial places. Common waste gas purification includes factory smoke waste gas purification, workshop dust waste gas purification, organic waste gas purification, waste gas peculiar smell purification, acid-base waste gas purification, chemical waste gas purification and the like. The waste gas discharged from industrial production often has harmful influence on environment and human health, and before being discharged into the atmosphere, the waste gas is treated by adopting a purification measure so as to meet the requirements of waste gas discharge standards, and the process is called waste gas purification. The commonly used exhaust gas purification methods include four methods, i.e., an absorption method, an adsorption method, a condensation method, and a combustion method. The pipeline for exhaust-gas treatment who uses in the existing market adopts bolt fixed connection mostly, and bolted connection's installation effectiveness is low for the staff needs longer time to install the pipeline for exhaust-gas treatment, thereby has reduced staff's work efficiency, thereby has brought the inconvenience for staff's use, thereby has reduced the practicality of pipeline for exhaust-gas treatment.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
The utility model provides a not enough to prior art, the utility model provides a waste gas treatment is with pipeline of being convenient for aggregate erection possesses advantages such as aggregate erection of being convenient for, has solved the problem that general waste gas treatment is with low in pipeline erection efficiency.
(II) technical scheme
For the purpose of realizing above-mentioned pipeline for exhaust-gas treatment be convenient for aggregate erection, the utility model provides a following technical scheme: a pipeline convenient for combined installation for waste gas treatment comprises a first treatment pipe, wherein the outer wall of the first treatment pipe is fixedly connected with a fixing plate, one side of the fixing plate is movably connected with a fixing bolt, the inner wall of the first treatment pipe is provided with a connecting groove, the inner wall of the first treatment pipe is movably connected with a sealing ring, the inner wall of the sealing ring is fixedly connected with a second treatment pipe, the outer wall of the second treatment pipe is provided with a mounting groove, the inner wall of the mounting groove is fixedly connected with a first cushion pad, the inner wall of the mounting groove is fixedly connected with a mounting spring, one end of the mounting spring is fixedly connected with a mounting block, the bottom of the mounting block is fixedly connected with a second cushion pad, the outer wall of the second treatment pipe is fixedly connected with a first mounting box, the inner wall of the second treatment pipe is movably connected with a filter element, and, one side of the connecting plate is fixedly connected with a second mounting box, the front face of the second mounting box is fixedly connected with an anti-slip pad, and the front face of the anti-slip pad is provided with an anti-slip groove.
Preferably, the number of the fixing plates is two, and the two fixing plates are symmetrically arranged by taking the horizontal central line of the first treatment pipe as a symmetry axis.
Preferably, the number of the installation grooves is two, and the two installation grooves are symmetrically arranged by taking the horizontal central line of the second treatment pipe as a symmetry axis.
Preferably, the inner wall of the second mounting box is movably connected with the outer wall of the first mounting box, and the inner wall of the second mounting box is provided with an internal thread.
Preferably, one end of the fixing bolt penetrates through one side of the fixing plate and extends to the other side of the fixing plate, and the fixing bolt is an alloy steel fixing bolt.
Preferably, the thickness of the first buffer pad is three millimeters, and the first buffer pad is a rubber buffer pad.
Preferably, the thickness of the non-slip mat is five millimeters, and the non-slip mat is a polyvinyl chloride non-slip mat.
(III) advantageous effects
Compared with the prior art, the utility model provides a waste gas treatment is with pipeline convenient to aggregate erection possesses following beneficial effect:
1. this pipeline of aggregate erection of being convenient for exhaust-gas treatment, through the first processing pipe that sets up, the spread groove, the sealing washer, the second is handled the pipe, the mounting groove, the installation spring, first blotter, installation piece and second blotter, can reach the purpose of aggregate erection of being convenient for, the problem of general pipeline erection inefficiency for exhaust-gas treatment has been solved, make that the staff can be rapid handle the pipe equipment with first processing pipe and second, thereby staff's work efficiency has been promoted, thereby brought the facility for staff's use.
2. This pipeline of aggregate erection is convenient for exhaust-gas treatment through first mounting box, connecting plate and the second mounting box that sets up, can reach the purpose of filter core convenient to detach and installation for the staff can be rapid dismantlement and installation filter core, thereby promoted staff's maintenance efficiency, thereby promoted this pipeline for exhaust-gas treatment's practicality.
3. This waste gas treatment is with pipeline convenient to aggregate erection through slipmat and the non-slip groove that sets up, can reach the effectual purpose of antiskid of second mounting box for the second mounting box can not be easy from staff's hand landing, thereby has promoted the life of filter core, thereby further provides convenience for staff's use.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the connection structure between the second processing tube and the first mounting box of the present invention;
fig. 3 is an enlarged view of a structure a in fig. 1 according to the present invention.
In the figure: 1. a first process tube; 2. a fixing plate; 3. fixing the bolt; 4. connecting grooves; 5. a seal ring; 6. a second process tube; 7. mounting grooves; 8. installing a spring; 9. a first cushion pad; 10. mounting blocks; 11. a second cushion pad; 12. a first mounting box; 13. a filter element; 14. a connecting plate; 15. a second mounting box; 16. a non-slip mat; 17. and (4) an anti-slip groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, a pipeline for waste gas treatment, which is convenient for assembly and installation, includes a first treatment pipe 1, the outer wall of the first treatment pipe 1 is fixedly connected with two fixing plates 2, the two fixing plates 2 are symmetrically arranged with the horizontal center line of the first treatment pipe 1 as a symmetry axis, one side of the fixing plate 2 is movably connected with a fixing bolt 3, one end of the fixing bolt 3 penetrates one side of the fixing plate 2 and extends to the other side of the fixing plate 2, the fixing bolt 3 is an alloy steel fixing bolt, the alloy steel fixing bolt has good wear resistance and high strength and toughness, the inner wall of the first treatment pipe 1 is provided with a connecting groove 4, the inner wall of the first treatment pipe 1 is movably connected with a sealing ring 5, the inner wall of the sealing ring 5 is fixedly connected with a second treatment pipe 6, the outer wall of the second treatment pipe 6 is provided with a mounting groove 7, and the number of the mounting grooves 7, the two mounting grooves 7 are symmetrically arranged by taking the horizontal center line of the second processing pipe 6 as a symmetry axis, the inner wall of each mounting groove 7 is fixedly connected with a first cushion pad 9, the thickness of each first cushion pad 9 is three millimeters, each first cushion pad 9 is a rubber cushion pad, the elasticity of each rubber cushion pad is good, the cost is low, the inner wall of each mounting groove 7 is fixedly connected with a mounting spring 8, one end of each mounting spring 8 is fixedly connected with a mounting block 10, the bottom of each mounting block 10 is fixedly connected with a second cushion pad 11, the purpose of convenient combination and installation can be achieved by arranging the first processing pipe 1, the connecting groove 4, the sealing ring 5, the second processing pipe 6, the mounting grooves 7, the mounting springs 8, the first cushion pads 9, the mounting blocks 10 and the second cushion pads 11, the problem of low installation efficiency of a common pipeline for waste gas processing is solved, and workers can rapidly assemble the first processing pipe 1 and the second processing pipe 6, thereby improving the working efficiency of workers and bringing convenience to the use of the workers, the outer wall of the second processing pipe 6 is fixedly connected with a first mounting box 12, the inner wall of the second processing pipe 6 is movably connected with a filter element 13, the top of the filter element 13 is fixedly connected with a connecting plate 14, one side of the connecting plate 14 is fixedly connected with a second mounting box 15, the purpose of convenient disassembly and assembly of the filter element 13 can be achieved through the arranged first mounting box 12, the connecting plate 14 and the second mounting box 15, so that the workers can rapidly disassemble and assemble the filter element 13, thereby improving the maintenance efficiency of the workers, thereby improving the practicability of the waste gas processing pipeline, the inner wall of the second mounting box 15 is movably connected with the outer wall of the first mounting box 12, the inner wall of the second mounting box 15 is provided with internal threads, the front side of the second mounting box 15 is fixedly connected with an anti-slip mat 16, the thickness of slipmat 16 is five millimeters, and slipmat 16 is the polyvinyl chloride slipmat, the skid resistance of polyvinyl chloride slipmat is good, and the wearability is good, non-slip groove 17 has been seted up in slipmat 16's front, through slipmat 16 and the non-slip groove 17 that sets up, can reach the effectual purpose of antiskid of second mounting box 15, make the second mounting box 15 can not be easy from staff's hand landing, thereby the life of filter core 13 has been promoted, thereby further facilitate for staff's use.
The electrical components presented in the document are all electrically connected with an external master controller and 220V mains, and the master controller can be a conventional known device controlled by a computer or the like.
When the exhaust gas treatment device is used, the first treatment pipe 1 is arranged on the exhaust gas treatment device through the fixing plate 2 and the fixing bolt 3, a worker holds the second treatment pipe 6, pushes the second treatment pipe 6 to the first treatment pipe 1, the installation block 10 moves, and the installation spring 8 compresses until the installation block 10 is clamped into the connection groove 4 formed in the first treatment pipe 1, so that the relative positions of the first treatment pipe 1 and the second treatment pipe 6 are fixed.
In conclusion, the pipeline convenient to assemble and install for the exhaust gas treatment can achieve the purpose of convenient assembly and installation, solves the problem of low installation efficiency of the general pipeline for the exhaust gas treatment, and enables a worker to rapidly assemble the first treatment pipe 1 and the second treatment pipe 6.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. A pipeline convenient for combined installation for exhaust gas treatment comprises a first treatment pipe (1), and is characterized in that: the outer wall of the first processing pipe (1) is fixedly connected with a fixing plate (2), one side of the fixing plate (2) is movably connected with a fixing bolt (3), the inner wall of the first processing pipe (1) is provided with a connecting groove (4), the inner wall of the first processing pipe (1) is movably connected with a sealing ring (5), the inner wall of the sealing ring (5) is fixedly connected with a second processing pipe (6), the outer wall of the second processing pipe (6) is provided with a mounting groove (7), the inner wall of the mounting groove (7) is fixedly connected with a first cushion pad (9), the inner wall of the mounting groove (7) is fixedly connected with a mounting spring (8), one end of the mounting spring (8) is fixedly connected with a mounting block (10), the bottom of the mounting block (10) is fixedly connected with a second cushion pad (11), the outer wall of the second processing pipe (6) is fixedly connected with a first mounting box (, the inner wall swing joint of pipe (6) is handled to the second has filter core (13), the top fixedly connected with connecting plate (14) of filter core (13), one side fixedly connected with second mounting box (15) of connecting plate (14), the positive fixedly connected with slipmat (16) of second mounting box (15), non-skid groove (17) have been seted up in the front of slipmat (16).
2. A duct for facilitating assembly installation for exhaust gas treatment according to claim 1, wherein: the number of the fixing plates (2) is two, and the two fixing plates (2) are symmetrically arranged by taking the horizontal central line of the first processing pipe (1) as a symmetry axis.
3. A duct for facilitating assembly installation for exhaust gas treatment according to claim 1, wherein: the number of the mounting grooves (7) is two, and the two mounting grooves (7) are symmetrically arranged by taking the horizontal central line of the second processing pipe (6) as a symmetry axis.
4. A duct for facilitating assembly installation for exhaust gas treatment according to claim 1, wherein: the inner wall of the second mounting box (15) is movably connected with the outer wall of the first mounting box (12), and the inner wall of the second mounting box (15) is provided with internal threads.
5. A duct for facilitating assembly installation for exhaust gas treatment according to claim 1, wherein: one end of the fixing bolt (3) penetrates through one side of the fixing plate (2) and extends to the other side of the fixing plate (2), and the fixing bolt (3) is an alloy steel fixing bolt.
6. A duct for facilitating assembly installation for exhaust gas treatment according to claim 1, wherein: the thickness of the first cushion pad (9) is three millimeters, and the first cushion pad (9) is a rubber cushion pad.
7. A duct for facilitating assembly installation for exhaust gas treatment according to claim 1, wherein: the thickness of the non-slip mat (16) is five millimeters, and the non-slip mat (16) is a polyvinyl chloride non-slip mat.
CN202020005697.2U 2020-01-03 2020-01-03 Pipeline convenient to assemble and install for waste gas treatment Expired - Fee Related CN211987537U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020005697.2U CN211987537U (en) 2020-01-03 2020-01-03 Pipeline convenient to assemble and install for waste gas treatment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020005697.2U CN211987537U (en) 2020-01-03 2020-01-03 Pipeline convenient to assemble and install for waste gas treatment

Publications (1)

Publication Number Publication Date
CN211987537U true CN211987537U (en) 2020-11-24

Family

ID=73428100

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020005697.2U Expired - Fee Related CN211987537U (en) 2020-01-03 2020-01-03 Pipeline convenient to assemble and install for waste gas treatment

Country Status (1)

Country Link
CN (1) CN211987537U (en)

Similar Documents

Publication Publication Date Title
CN211987537U (en) Pipeline convenient to assemble and install for waste gas treatment
CN212017142U (en) Combustion waste gas treatment device for coal equipment
CN206746315U (en) Photocatalysis treatment exhaust device
CN105464757A (en) Device used for purifying automobile exhaust
CN212296559U (en) Diesel engine tail gas particulate filter
CN211051122U (en) Air inlet unit for building engineering exhaust purification
CN213375629U (en) Based on municipal administration road bridge dust processing apparatus for tunnel construction
CN205570001U (en) Be applied to dust collector in tunnel
CN203043754U (en) Dust-removing system for waste tyre resource regeneration production line
CN207307525U (en) A kind of environment-protecting type exhaust air filtering and purifying of convenient connection
CN207271770U (en) A kind of chemical emission centralized recovery processing unit
CN204710032U (en) A kind of detachable sack cleaner
CN111120856A (en) Sewage collecting and treating device
CN206911030U (en) A kind of cyclone dust collectors
CN206386527U (en) A kind of large-scale pneumatic check valve
CN209840322U (en) Multipurpose household air purification equipment
CN216799159U (en) Waste gas treatment conveying device for environmental protection equipment
CN204619649U (en) A kind of complex type dust remover
CN210980159U (en) Industrial air purification equipment
CN215515249U (en) Stone material suspension clamp instrument
CN212283303U (en) Waste gas treatment conveying device for environment-friendly equipment
CN211553456U (en) Sampling probe for smoke on-line monitoring equipment
CN216987040U (en) Cigarette factory is with exhaust purification handles environmental protection discharging equipment
CN216137009U (en) Catalyst spray set for exhaust-gas treatment
CN207848040U (en) A kind of silencer applied to exhaust-gas treatment forced-and-induced draft fan

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220124

Address after: 430000 Zhashan street Conglin village, Caidian District, Wuhan City, Hubei Province (No. 9, floor 3, building B in the factory of Wuhan Aokang Hardware Manufacturing Co., Ltd.)

Patentee after: Wuhan xinzhishuo Environmental Protection Engineering Co.,Ltd.

Address before: 311115 No. 46, Zhuang village, group 1, Shengtang, Xi'an temple village, Pingyao Town, Yuhang District, Hangzhou City, Zhejiang Province

Patentee before: Hangzhou Yuhang Environmental Engineering Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201124