CN211977642U - Cooling tower for fluorine industry - Google Patents

Cooling tower for fluorine industry Download PDF

Info

Publication number
CN211977642U
CN211977642U CN201922466655.9U CN201922466655U CN211977642U CN 211977642 U CN211977642 U CN 211977642U CN 201922466655 U CN201922466655 U CN 201922466655U CN 211977642 U CN211977642 U CN 211977642U
Authority
CN
China
Prior art keywords
ring
cooling tower
pipe
water
water inlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922466655.9U
Other languages
Chinese (zh)
Inventor
张志君
陈爽
王博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Changlu Chemical New Material Co ltd
Original Assignee
Tianjin Changlu Chemical New Material Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Changlu Chemical New Material Co ltd filed Critical Tianjin Changlu Chemical New Material Co ltd
Priority to CN201922466655.9U priority Critical patent/CN211977642U/en
Application granted granted Critical
Publication of CN211977642U publication Critical patent/CN211977642U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

A cooling tower for fluorine chemical industry. The cooling tower endotheca, the bottom welding end ring of cooling tower endotheca, the top welding top ring of cooling tower endotheca, bottom ring with the top ring between the welding have the overcoat, the top ring open and to have a set of inlet opening, the inlet opening connect the inlet tube, the top of inlet tube pass through the ring union coupling, the bottom of inlet tube connect the shower nozzle, the shower nozzle be located the inboard of overcoat, the ring pipe open and to have into the water hole, into the water hole and connect the water pipe, water pipe connection force pump, the ring union coupling a set of solenoid valve, the solenoid valve connect the inlet tube. The utility model is used for fluorine industry cooling tower.

Description

Cooling tower for fluorine industry
The technical field is as follows:
the utility model relates to a fluoride industrial cooling tower.
Background art:
most of the existing cooling towers are cooled by natural or chemical medicines, but the speed of natural cooling is slower, the cooling cost of the chemical medicines is higher, pollution can be caused, and the using effects of the natural cooling tower and the chemical medicines are not ideal.
The invention content is as follows:
the utility model aims at providing a cooling tower for fluorine industry that cooling cost is low, cooling effect is good.
The above purpose is realized by the following technical scheme:
the cooling tower for the fluorine industry comprises a cooling tower inner sleeve, wherein a bottom ring is welded at the bottom of the cooling tower inner sleeve, a top ring is welded at the top of the cooling tower inner sleeve, an outer sleeve is welded between the bottom ring and the top ring, a group of water inlet holes are formed in the top ring and are connected with a water inlet pipe, the top of the water inlet pipe is connected with a circular pipe, a spray head is connected at the bottom of the water inlet pipe and is positioned on the inner side of the outer sleeve, a water inlet hole is formed in the circular pipe and is connected with a water supply pipe, the water supply pipe is connected with a pressure pump and is connected with a group of electromagnetic valves, and the electromagnetic valves are connected with the water inlet pipe.
A fluoride industrial cooling tower, end ring open and to have the apopore, the apopore connect the outlet pipe, play water piping connection end booster pump, go out water piping connection water storage tank, go out water piping connection circulation control valve, go out water piping connection return bend, the return bend connect the ring pipe.
A fluorine industrial cooling tower, water inlet hole welding end ring flange, end ring flange bonding end magnetic ring, end magnetic ring actuation top magnetic ring, top magnetic ring bonding top ring flange, top ring flange welding the running water pipe, end ring flange bottom magnetic ring top ring flange between fix through 2 bolts, end magnetic ring with the inboard of top magnetic ring be provided with the sealing washer.
The utility model provides a fluorine industrial cooling tower, the top of cooling tower endotheca feed port has, the bottom of cooling tower endotheca discharge opening has, the bottom connection support base of cooling tower endotheca, the overcoat connect the people's ladder, the overcoat open and to have the manhole, the manhole connect the circle sleeve pipe, circle sheathed tube connect the stopper stifled.
Has the advantages that:
1. the utility model discloses a water pipe cools off, and the running water can also cyclic utilization, and refrigerated is with low costs, and refrigerated is effectual.
The utility model discloses an inlet tube distributes round the cooling tower endotheca, can cool down for the cooling tower endotheca uniformly, and the refrigerated is even in the cooling, and the speed of cooling is fast, and the effect of cooling is good.
The utility model discloses a water storage tank can collect the water that has the temperature after the cooling, carries out natural cooling, then recycles, cools down once more and uses, can reduce use cost widely to still can not cause extravagant and pollution, excellent in use effect.
The utility model discloses a be connected through end ring flange, end magnetic ring, top ring flange between ring tube and the water pipe, the speed of equipment is fast, firmly has stably promptly after the equipment, fixes with 2 bolts, ensures that end ring flange is fixed more firmly with top ring flange, and the result of use is better.
Description of the drawings:
fig. 1 is a schematic structural diagram of the product.
Fig. 2 is an enlarged view of a portion of fig. 1.
The specific implementation mode is as follows:
the technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings of the present invention.
Example 1:
the cooling tower for the fluorine industry comprises a cooling tower inner sleeve 1, wherein a bottom ring 2 is welded at the bottom of the cooling tower inner sleeve, a top ring 3 is welded at the top of the cooling tower inner sleeve, an outer sleeve 4 is welded between the bottom ring and the top ring, the top ring is provided with a group of water inlet holes 5, the water inlet holes are connected with a water inlet pipe 6, the top of the water inlet pipe is connected through a ring pipe 7, the bottom of the water inlet pipe is connected with a spray head 8, tap water sprayed by the spray head is uniform, the spray head is positioned on the inner side of the outer sleeve, the ring pipe is provided with a tap water inlet hole 9, the tap water inlet hole is connected with a tap water pipe 10, the tap water pipe is connected with a pressure pump 11, the ring pipe is connected with a group of electromagnetic valves 12, and the electromagnetic valves are connected with the water inlet pipe.
The end ring open and to have apopore 13, the apopore connect outlet pipe 14, play water piping connection end booster pump 15, play water piping connection water storage tank 16, go out water piping connection circulation control valve 17, play water piping connection return bend 18, the return bend connect the ring pipe.
The water inlet hole is welded with a bottom flange 19, the bottom flange is adhered with a bottom magnetic ring 20, the bottom magnetic ring is attracted with a top magnetic ring 21, the top magnetic ring is adhered with a top flange 22, the top flange is welded with a tap water pipe, the bottom flange, the bottom magnetic ring, the top magnetic ring and the top flange are fixed through 2 bolts 23, and a sealing ring 24 is arranged on the inner side of the bottom magnetic ring and the inner side of the top magnetic ring.
The top of cooling tower endotheca feed port 25 has, the bottom of cooling tower endotheca discharge opening 26 has, the bottom of cooling tower endotheca connect and support base 27, the overcoat connect the ladder 28, the overcoat open and to have manhole 29, the manhole connect circular sleeve pipe 30, circular sleeve pipe connect stifled 31.
The working principle is as follows:
when the fluorinated product is guided into the cooling tower inner sleeve along the feed hole, the electromagnetic valve is opened, the pressure pump is started, tap water is added between the cooling tower inner sleeve and the cooling tower outer sleeve for cooling, and the cooled water is discharged into the water storage tank for recycling.

Claims (4)

1. The cooling tower for the fluorine industry comprises a cooling tower inner sleeve and is characterized in that a bottom ring is welded at the bottom of the cooling tower inner sleeve, a top ring is welded at the top of the cooling tower inner sleeve, an outer sleeve is welded between the bottom ring and the top ring, a group of water inlet holes are formed in the top ring and are connected with a water inlet pipe, the top of the water inlet pipe is connected with a circular pipe, the bottom of the water inlet pipe is connected with a spray head, the spray head is located on the inner side of the outer sleeve, a water inlet hole is formed in the circular pipe and is connected with a tap water pipe, the tap water pipe is connected with a pressure pump, the circular pipe is connected with a group of electromagnetic valves, and the electromagnetic valves are connected with the water inlet pipe.
2. The cooling tower for the fluorine chemical industry according to claim 1, wherein the bottom ring is provided with a water outlet hole, the water outlet hole is connected with a water outlet pipe, the water outlet pipe is connected with a bottom booster pump, the water outlet pipe is connected with a water storage tank, the water outlet pipe is connected with a circulation control valve, the water outlet pipe is connected with a bent pipe, and the bent pipe is connected with the ring pipe.
3. The cooling tower for the fluorine chemical industry according to claim 2, wherein a bottom flange plate is welded on the water inlet hole, a bottom magnetic ring is bonded on the bottom flange plate, a top magnetic ring is attracted on the bottom magnetic ring, a top flange plate is bonded on the top magnetic ring, the tap water pipe is welded on the top flange plate, the bottom magnetic ring, the top magnetic ring and the top flange plate are fixed through 2 bolts, and a sealing ring is arranged on the inner side of the bottom magnetic ring and the inner side of the top magnetic ring.
4. The cooling tower for the fluorine chemical industry according to claim 3, wherein a feeding hole is formed in the top of the inner sleeve of the cooling tower, a discharging hole is formed in the bottom of the inner sleeve of the cooling tower, the bottom of the inner sleeve of the cooling tower is connected with a supporting base, the outer sleeve is connected with a man ladder, a manhole is formed in the outer sleeve, the manhole is connected with a circular sleeve, and the circular sleeve is connected with a plug.
CN201922466655.9U 2019-12-31 2019-12-31 Cooling tower for fluorine industry Active CN211977642U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922466655.9U CN211977642U (en) 2019-12-31 2019-12-31 Cooling tower for fluorine industry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922466655.9U CN211977642U (en) 2019-12-31 2019-12-31 Cooling tower for fluorine industry

Publications (1)

Publication Number Publication Date
CN211977642U true CN211977642U (en) 2020-11-20

Family

ID=73369689

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922466655.9U Active CN211977642U (en) 2019-12-31 2019-12-31 Cooling tower for fluorine industry

Country Status (1)

Country Link
CN (1) CN211977642U (en)

Similar Documents

Publication Publication Date Title
CN211977642U (en) Cooling tower for fluorine industry
CN108178348B (en) Strong positive pressure spray aeration system
CN207654912U (en) A kind of spraying device of desulfurizing tower being conveniently replaceable
CN208543700U (en) Quickly cooling device is used in a kind of production of power pipe
CN106861475B (en) Gas-liquid mixed injection structure and method thereof
CN203802998U (en) Special fire-cooling protective device for spherical tank
CN210078873U (en) Double-effect concentrator with online heater flushing device
CN208642278U (en) A kind of emission-control equipment
CN214438009U (en) Steam ejector convenient for uniformly mixing steam and liquid
CN114717566A (en) Hydrodynamic stainless steel storage tank inner wall acid pickling passivation device and method
CN210463059U (en) Quench cooler suitable for high temperature flue gas
CN203061358U (en) Cooling atomizer
CN211099674U (en) Full-section spray head for tunnel watering maintenance
CN205518746U (en) High pressure hydrojet kettle
CN213363444U (en) Steam recycling device
CN219252952U (en) Simple spraying device
CN209166060U (en) A kind of polymer micro mist production precipitating drying kettle steam emptier
CN215674751U (en) Natural gas storage tank antistatic device
CN204973593U (en) Scrubbing tower with keep off and flow wall
CN208554667U (en) Two Fluid sprayers
CN213557807U (en) Water supplementing equipment for hydraulic engineering construction
CN215481086U (en) Water storage device for improving surface quality of steel strip
CN210711658U (en) Quenching cooling device for outer circular surface of large disc part
CN212776209U (en) Rapid cooling device for high-temperature heating surface of pipeline in power generation process
CN217267828U (en) A steady voltage water supply system for ball-milling workshop

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant